About this file
This is a Proposal Section Bid Submission Checklist document for Yardley Borough in Bucks County, Pennsylvania, establishing requirements for sealed electronic bidding on the N. Main Street & University Drive Stormwater Improvements - Phase 1 project. The project involves replacement of deteriorated stormwater infrastructure within a Borough-owned storm sewer easement in a shared commercial parking lot, including installation of new 36-inch Reinforced Concrete Pipe (RCP), connections to existing storm infrastructure, a new Type D cast-in-place concrete endwall, pavement and landscaping restoration, concrete sidewalk restoration, and televising and cleaning of existing storm infrastructure. Sealed bids must be submitted electronically through PennBid prior to April 27, 2026, at 11:40 AM EST, with public bid opening at Yardley Borough Hall, 56 South Main Street, Yardley, PA 19067. A non-mandatory pre-bid meeting is scheduled for April 15, 2026, at 10:40 AM EST at the project site. The contract term requires substantial completion within 120 calendar days of receiving a Notice to Proceed, with a 2-year maintenance bond required upon project completion.
All bidders must submit bid security equal to 10 percent of the total bid amount in the form of a certified check or bid bond from a Pennsylvania-licensed surety company, along with completed proposal documents including Statement of Corporate Ownership, Nondiscrimination Requirements affidavit, Non-Collusion Affidavit, Consent of Surety, Background Questionnaire, Subcontractor Declaration, Certificate of Bidder Showing Ability to Perform Contract, Acknowledgement of Receipt of Changes to Bid Documents Form, and Public Works Employment Verification Form demonstrating E-Verify participation. The successful bidder must furnish Performance and Labor and Materials Payment Bonds, each equal to 100 percent of the awarded contract value. The project is subject to Pennsylvania Prevailing Wage Act requirements with rates established for various trade classifications effective from January 2023 through January 2026. Liquidated damages are assessed at $500 per day for days one through fifteen beyond deadline, $1,000 per day for days sixteen through thirty, and $2,000 per day for delays exceeding thirty days. Retainage of 10 percent is withheld for contracts valued at $100,000 or less, or 5 percent for contracts exceeding $100,000. The project is fully funded through FEMA's Severe Repetitive Loss Program administered by the Pennsylvania Emergency Management Agency, with the successful bidder responsible for a PennBid fee calculated at one-third percent (0.0033) of the initial contract award amount with a minimum fee of $100.00 and maximum cap of $5,000.00. No set-aside designations or disadvantaged enterprise restrictions are specified, and no incumbent vendors are identified.
View the file
Other files
Show all 22
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
P-1
PROPOSAL SECTION
BID SUBMISSION CHECKLIST
Name of Local Contracting Agency: Yardley Borough
Project Title: N. Main Street & University Drive Stormwater Improvements – Phase 1
RVE File Number: PA091593T004
A. Bid Submission Checklist. The following documents must be submitted to the Local Contracting
Agency via PennBid prior to the advertised bid opening. Failure to submit a bid guarantee will result in rejection of the bid. Failure to submit any other documents listed on this Bid Submission Checklist may result in rejection of the bid.
1. Bid Pricing Section Form (completed online through PennBid).
2. Bid Security.
3. Consent of Surety.
4. Proposal Section. The Proposal Section includes the following documents which must be completed and submitted:
a) Bid Submission Checklist (P-1)
b) Statement of Corporate Ownership (P-3).
c) Nondiscrimination Requirements (P-5).
d) Non-collusion Affidavit (P-7).
e) Bid Security (P-10).
f) Consent of Surety (P-11).
g) Background Questionnaire (P-12).
h) Subcontractor Declaration (P-14).
i) Certificate of Bidder Showing Ability to Perform Contract (P-17).
j) Acknowledgement of Receipt of Changes to Bid Documents Form (P-19).
5. Public Works Employment Verification Form
6. (Intentionally left blank)
P-2
B. SIGNATURE: The undersigned does hereby acknowledge all of the documents listed above.
Furthermore, the undersigned does hereby certify that all of the documents have been completed and have been submitted to the Local Contracting Agency via PennBid prior to the advertised bid opening.
Name of Bidder
Street Address
City State Zip
Telephone Number E-mail Address
By Authorized Representative of Bidder:
Signature Date
Print Name and Title
Commonwealth of Pennsylvania )
) S.S.
County of _________________ )
On this, the _____ day of _______________, 20_____, before me a notary public, the undersigned officer, personally appeared ____________________, known to me (or satisfactorily proven) to be the person whose name is subscribed to the within instrument, and acknowledge that they executed the same for the purposes therein contained.
In witness hereof, I hereunto set my hand and official seal.
Notary Public
P-3
STATEMENT OF CORPORATE OWNERSHIP
Check the appropriate box:
Corporation Limited Liability Company Partnership Sole Proprietor
A. No corporation or partnership shall be awarded any contract by the state, county, municipality or school district, or any subsidiary or agency thereof, unless prior to the receipt of the bid of the corporation or partnership, there is submitted to the Local Contracting Agency a statement setting forth the names of all individuals who own 10% or more of stock or interest in the corporation or partnership.
1. If the bidder is a partnership, then the statement shall set forth the names and addresses of all partners who own a 10% or greater interest in the partnership.
2. If the bidder is a corporation, then the statement shall set forth the names and addresses of all stockholders in the corporation who own 10% or more of its stock in any class.
3. If a corporation owns all or part of the stock of the corporation or partnership submitting the bid, then the statement shall include a list of the stockholders who own 10% or more of the stock of any class of that corporation.
4. If the bidder is other than a corporation or partnership, the bidder shall indicate the form of corporate ownership as listed below.
B. Bidder must complete one of the following statements:
1. Stockholders or Partners owning 10% or more of the company submitting a bid:
a) NAME: ___________________________________________________________________
ADDRESS: ________________________________________________________________
b) NAME: ___________________________________________________________________
ADDRESS: ________________________________________________________________
c) NAME: ___________________________________________________________________
ADDRESS: ________________________________________________________________
2. No Stockholder or Partner owns 10% or more of the company submitting the bid:
P-4
3. Bid is being submitted by an individual who operates as a sole proprietorship:
4. Bid is being submitted by a corporation or partnership that operates as a (check one of the following):
Limited Partnership Limited Liability Corporation
Limited Liability Partnership Subchapter S Corporation
Stockholders or Partners owning 10% or more of the form of corporation or partnership checked above shall provide the following information:
a) NAME: ___________________________________________________________________
ADDRESS: ________________________________________________________________
b) NAME: ___________________________________________________________________
ADDRESS: ________________________________________________________________
c) NAME: ___________________________________________________________________
ADDRESS: ________________________________________________________________
d) NAME: ___________________________________________________________________
ADDRESS: ________________________________________________________________
e) NAME: ___________________________________________________________________
ADDRESS: ________________________________________________________________
P-5
NONDISCRIMINATION REQUIREMENTS
A. Bidders are required to comply with the requirements of Title 16, Pennsylvania Code, Section 49.101, which includes the following nondiscrimination clause:
1. Contractor shall not discriminate against any employee, applicant for employment, independent contractor, or any other person because of race, color, religious creed, ancestry, national origin, age, or sex. Contractor shall take affirmative action to ensure that applicants are employed, and that employees or agents are treated during employment, without regard to their race, color, religious creed, ancestry, national origin, age, or sex. Such affirmative action shall include, but is not limited to, the following: Employment, upgrading, demotion, or transfer; recruitment or recruitment advertising; layoff or termination; rates of pay or other forms of compensation; and selection for training. Contractor shall post in conspicuous places, available to employees, agents, applicants for employment and other persons, a notice to be provided by the contracting agency setting forth the provisions of this nondiscrimination clause.
2. Contractor shall in advertisements or requests for employment placed by it or on its behalf state all qualified applicants will receive consideration for employment without regard to race, color, religious creed, ancestry, national origin, age, or sex.
3. Contractor shall send each labor union or workers’ representative with which it has a collective bargaining agreement or other contract or understanding, a notice advising said labor union or workers’ representative of its commitment to this nondiscrimination clause. Similar notice shall be sent to every other source of recruitment regularly utilized by Contractor.
4. It shall be no defense to a finding of a noncompliance with Contract Compliance Regulations issued by the Pennsylvania Human Relations Commission or this nondiscrimination clause that Contractor had delegated some of its employment practices to any union, training program, or other source of recruitment which prevents it from meeting its obligations. However, if the evidence indicates that the Contractor was not on notice of the third-party discrimination or made a good faith effort to correct it, such factor shall be considered in mitigation in determining appropriate sanctions.
5. Where the practices of a union or any training program or other source of recruitment will result in the exclusion of minority group persons, so that Contractor will be unable to meet its obligations under the Contract Compliance Regulations issued by the Pennsylvania Human Relations
Commission or this nondiscrimination clause, Contractor shall then employ and fill vacancies through other nondiscriminatory employment procedures.
P-6
6. Contractor shall comply with the Contract Compliance Regulations of the Pennsylvania Human
Relations Commission, 16 Pa. Code Chapter 49 and with all laws prohibiting discrimination in hiring or employment opportunities. In the event of Contractor’s noncompliance with the nondiscrimination clause of this contract or with any such laws, this contract may, after hearing and adjudication, be terminated or suspended, in whole or in part, and Contractor may be declared temporarily ineligible for further Commonwealth contracts, and such other sanctions may be imposed and remedies invoked as provided by the Contract Compliance Regulations.
7. Contractor shall furnish all necessary employment documents and records to, and permit access to its books, records and accounts by, the contracting agency and the Human Relations Commission, for purposes of investigation to ascertain compliance with the provisions of the Contract
Compliance Regulations, pursuant to § 49.35 (relating to information concerning compliance by contractors). If Contractor does not possess documents or records reflecting the necessary information requested, it shall furnish such information on reporting forms supplied by the contracting agency or the Commission.
8. Contractor shall actively recruit minority subcontractors or subcontractors with substantial minority representation among their employees.
9. Contractor shall include the provisions of this nondiscrimination clause in every subcontract, so that such provisions will be binding upon each Subcontractor.
10. The terms used in this nondiscrimination clause shall have the same meaning as in the Contract
Compliance Regulations issued by the Pennsylvania Human Relations Commission, 16 Pa. Code
Chapter 49.
11. Contractor obligations under this clause are limited to the Contractor’s facilities within
Pennsylvania, or, where the contract is for purchase of goods manufactured outside of
Pennsylvania, the facilities at which such goods are actually produced.
B. The undersigned further understands that their bid must be rejected as non-responsive if the requirements of Title 16, Pennsylvania Code, Section 49.101 are not complied with.
P-7
INSTRUCTIONS FOR NON-COLLUSION AFFIDAVIT
A. This Non-Collusion Affidavit is material to any contract awarded pursuant to this bid. According to the Antibid-Rigging Act, Title 62, Pennsylvania Code, Section 4507, governmental agencies may require Non-Collusion Affidavits to be submitted together with bids.
B. This Non-Collusion Affidavit must be executed by the member, officer or employee of the bidder who makes the final decision on prices and the amount quoted in the bid.
C. Bid rigging and other efforts to restrain competition, and the making of false sworn statements in connection with the submission of bids are unlawful and may be subject to criminal prosecution. The person who signs the affidavit should examine it carefully before signing and assure himself or herself that each statement is true and accurate, making diligent inquiry, as necessary, of all other persons employed by or associated with the bidder with responsibilities for the preparation, approval or submission of the bid.
D. In the case of a bid submitted by a joint venture, each party to the venture must be identified in the bid documents and an affidavit must be submitted separately on behalf of each party.
E. The term “complementary bid” as used in the affidavit has the meaning commonly associated with that term in the bidding process, and includes the knowing submission of bids higher than the bid of another firm, any intentionally high or noncompetitive bid, and any other form of bid submitted for the purpose of giving a false appearance of competition.
F. Failure to submit an affidavit with the bid in compliance with these instructions may result in disqualification of the bid.
P-8
NON-COLLUSION AFFIDAVIT
Title of Project: N. Main Street & University Drive Stormwater Improvements – Phase 1
Local Contracting Agency: Yardley Borough
Commonwealth of Pennsylvania )
I state that I am the ____________________ (Title) of ____________________ (Name of Firm) and that I am authorized to make this affidavit on behalf of my firm, and its owners, directors, and officers. I am the person responsible in my firm for the price(s) and the amount of this bid.
I state that:
1. The price(s) and amount of this bid have been arrived at independently and without consultation, communication or agreement with any other contractor, bidder or potential bidder.
2. Neither the price(s) nor the amount of this bid, and neither the approximate price(s) nor approximate amount of this bid, have been disclosed to any other firm or person who is a bidder or potential bidder, and they will not be disclosed before the bid opening.
3. No attempt has been made or will be made to induce any firm or person to refrain from bidding on this contract, or to submit a bid higher than this bid, or to submit any intentionally high or noncompetitive bid or other form of complementary bid.
4. The bid of my firm is made in good faith and not pursuant to any agreement or discussion with, or inducement from, any firm or person to submit a complementary or other noncompetitive bid.
5. _____________________________ (Name of Firm), its affiliates, subsidiaries, officers, directors, and employees are not currently under investigation by any governmental agency and have not in the last four years been convicted or found liable for any act prohibited by state or federal law in any jurisdiction, involving conspiracy or collusion with respect to proposing and/or bidding on any public contract, except as follows:
I state that _________________________ (Name of Firm) understands and acknowledges that the above representations are material and important, and will be relied upon by the Local Contracting Agency in awarding the contract(s) for which this bid is submitted. I understand and my firm understands that any
P-9 misstatement in this affidavit is and shall be treated as fraudulent concealment from the Local Contracting
Agency of the true facts relating to the submission of bids for this contract.
On this, the _____ day of _______________, 20_____, before me a notary public, the undersigned officer, personally appeared ____________________, known to me (or satisfactorily proven) to be the person whose name is subscribed to the within instrument, and acknowledge that they executed the same for the purposes therein contained.
In witness hereof, I hereunto set my hand and official seal.
P-10
BID SECURITY
Title of Project: N. Main Street & University Drive Stormwater Improvements – Phase 1
Local Contracting Agency: Yardley Borough
A. Bid security in the form of either a bid bond in the amount of 10% of the total amount bid or a cashier's check in the amount of 10% of the total amount bid is to be submitted to the Local Contracting Agency via PennBid prior to the bid opening time. Bid bonds may be provided in the form of AIA Document
A310 or an equivalent. Bid security must be made payable to the Local Contracting Agency.
B. All bidders must have an original copy of their bid security in their own possession prior to the advertised bid opening and must be able to deliver an original copy of their bid security to the Local
Contracting Agency within three (3) business days of receipt of a written request from the Local
Contracting Agency. Failure to deliver an original copy of bid security to the Local Contracting Agency within three (3) business days will result in rejection of the bid.
C. If the successful bidder has posted a bid bond, cashier's check, or any other form of security and refuses to accept a contract when tendered, they will be required to forfeit such bid security and shall be otherwise liable for the full amount secured by the Bid Security in the event that the Surety refuses to release the entire amount and/or the full amount is not provided to the Local Contracting Agency for any other reason.
D. Any payment made to the Local Contracting Agency by reason of default of the bidder shall not be construed as a penalty, but as liquidated damages for breach of contract.
P-11
CONSENT OF SURETY
A. Attach a Consent of Surety from a Surety Company, meeting the requirements described herein, stating that if the bidder is awarded the contract that the Surety Company will supply the bonds for the contract.
1. Consent of Surety must be an irrevocable, unconditional commitment by the Surety Company to issue on behalf of the bidder the bond or bonds upon award of the project in the full amount specified.
2. Consent of Surety must include all bonds required by the contract documents (i.e. performance, labor and material payment, maintenance, environmental, etc.).
3. Consent (Certificate) of Surety is not waivable and will be considered a material defect resulting in rejection of bid if omitted from bid package.
4. Consent of Surety must not contain any provision that would serve to limit the Surety Company's liability to "spread the second" bidder in the event the bidder fails to enter into a contract upon award.
B. Sample wording for Consent of Surety is shown below:
CONSENT OF SURETY
KNOW ALL MEN BY THESE PRESENTS, that for and consideration of the sum $ ________.____, lawful money of the United States of America, the receipt whereof is hereby acknowledged, paid the undersigned, and for other valuable consideration, the ___________________________ (Insurance
Company Name), ______________________________ (Insurance Company Address), existing under the laws of the Commonwealth of Pennsylvania and licensed to do business in the same, certifies and agrees that if the contract for ____________________ (Contracting Agency) for
____________________ (Project Title) is awarded to ____________________ (Bidder), the undersigned will execute the bond or bonds required of the contract documents and will become Surety in the full amount set forth in the contract documents for the faithful performance of all obligations of the Bidder, provided however, that this commitment shall expire sixty (60) calendar days from the bid opening, unless agreed upon by Bidder, Owner and Surety to be extended.
Signed, sealed and dated this _____ day of _______________, 20_____.
__________________________________________ (Insurance Company Name)
By __________________________________________ (Attorney-in-Fact)
(To be accompanied by an Affidavit authorizing the Attorney-in-Fact to sign the Consent of Surety and
Bid Bond.)
P-12
Background Questionaire
A. In accordance with the paragraph entitled "Qualifications of Bidders" of the Information for Bidders, provide the following information:
1. Date of Organization of Company: _______________
2. Name and Address of Officers (provide physical address):
a) President: _________________________________________________________________
b) Vice President: _____________________________________________________________
c) Secretary: _________________________________________________________________
d) Treasurer: _________________________________________________________________
3. Experience:
a) How many years has your organization been in business under your present business name?
b) How many years of experience does your organization have with the type of construction work involved in this contract? __________________
c) What are the latest projects (within the last 5 years) that your organization has completed?
(Attach additional pages if necessary)
# Project Name Contract
Amount
Date of
Completion Contracting Agency
d) References for projects listed above:
# Project Name Contact Name Telephone Number
P-13
4. Have you ever failed to complete any work awarded to you (within the last 10 years)? _______
a) If so, where and why? _______________________________________________________
5. Have you or has any officer or your organization ever been an officer or partner of some other contracting organization that failed to complete any work (within the last 10 years)? _________
a) If so, state the name of the individual, position and the name of the other organization:
b) Did this other contracting agency ever fail to complete any work awarded to it (within the last
10 years)? ____________
(1) If so, where and why? ____________________________________________________
6. Provide a listing of all uncompleted contracts presently held by your organization:
# Name of Contract Contracting Agency Contract Amount
7. State approximately the largest amount of work that your organization has completed within any calendar year (within the last 5 years) or similar nature to the work being bid on. ____________
8. List the equipment presently available for the performance of the work under the proposed contract
(attach additional pages if necessary). _______________________________________
P-14
9. For any contract which includes more than 500 square yards or 50 tons of asphalt paving work, list the make and model of the following paving equipment to be used (attach additional pages if necessary).
a) Milling Machine: ____________________________________________________________
b) Roller: _____________________________________________________________________
c) Bituminous Tack Distributor: ___________________________________________________
d) Bituminous Paver: ___________________________________________________________
Note: Failure by a bidder to list equipment which meets the requirements of the specifications of this contract shall not invalidate the bid nor absolve the bidder of their responsibility to secure and use equipment which meets the requirements of the specifications.
P-15
SUBCONTRACTOR DECLARATION
A. Each bidder shall set forth in their bid the names, addresses and license numbers (where required) of each subcontractor for the furnishing of plumbing and gas fitting, and kindred work, and of the steam and hot water heating and ventilating apparatus, steam power plants and kindred work, and electrical work, structural steel and ornamental iron work, if any, for the construction, alteration or repair of public buildings.
B. A general contractor that intends to utilize a specific subcontractor to perform work in one or more of the specialty trade categories shall provide the required information with regard to that subcontractor in the appropriate space for each specialty trade category applicable to the contract.
C. There shall be submitted proof that each subcontractor is qualified in accordance with the rules and regulations of the state in which the project is located, when such rules and regulations exist.
D. A general contractor that intends to perform work in one or more specialty trade categories either through the use of its own employees or the general contractor themselves, rather than through the utilization of a subcontractor, shall write the word "IN-HOUSE" next to each applicable category and then insert the name and license number (where required), of each such employee of the general contractor or the general contractor themselves in the appropriate spaces provided for each specialty trade category applicable to the contract. If the contract does not involve any of the specialty trade categories below, insert the word "NONE" in the appropriate spaces provided. (Attach additional pages if necessary)
1. Plumbing.
Name: Telephone:
Address:
License #:
2. Heating, Ventilating and Air Conditioning.
Name: Telephone:
P-16
3. Electrical.
Name: Telephone:
4. Other: ____________________
5. Other: ____________________
6. Other: ____________________
7. Other: ____________________
8. Other: ____________________
9. Other: ____________________
P-17
CERTIFICATE OF BIDDER SHOWING ABILITY TO PERFORM CONTRACT
Title of Project: N. Main Street & University Drive Stormwater Improvements – Phase 1
Local Contracting Agency: Yardley Borough
AFFIDAVIT
Commonwealth of Pennsylvania )
Before me, the undersigned notary public, this day, personally appeared ____________________ known to me (or satisfactorily proven), who being sworn according to law, deposes the following:
I, ____________________ of the (City, Town, Township, Borough, etc.) of ____________________ in the County of ____________________ and the State of ____________________ of full age, being duly sworn according to law on my oath depose and say that:
A. I am a(n) owner, partner, shareholder or officer of the company set forth below and am duly authorized to execute this affidavit on its behalf.
B. Select the appropriate statement:
I own, lease or control the necessary equipment required by the plans, specifications, and advertisement under which bids are asked for.
I do not own, lease or control the necessary equipment required by the plans, specifications, and advertisements under which bids are asked for.
C. If the bidder does not own, lease or control all of the necessary equipment, provide the source from which the equipment will be obtained: (Attach additional pages if necessary.) _________________
1. Attach certification from the owner, lessee or person in control of the equipment definitely granting to the bidder the control of the equipment required during such time as may be necessary for the completion of that portion of the contract for which it is necessary.
P-18
Subscribed and sworn to before me this _____ day of _______________, 20_____.
P-19
ACKNOWLEDGEMENT OF RECEIPT OF CHANGES TO BID DOCUMENTS FORM
A. By listing and initialing next to each notice, revision or addenda to the bid advertisement, specifications or bid documents, the undersigned bidder hereby acknowledges their receipt. In lieu of listing addenda hereon, bidders may acknowledge receipt of addenda by including a signed copy of the addenda with the bidder’s electronic bid. (Attach additional pages if necessary)
Local Contracting Agency Designation Date
Received
Bidder's
Initials Notice, Revision or
Addenda Number Title or Description
B. The undersigned bidder hereby acknowledges receipt of all questions and answers submitted or distributed through PennBid.
C. The undersigned bidder hereby certifies that the submitted bid takes into account the provisions of all notices, revisions, or addenda, including any changes to the bid advertisement, specifications or bid documents. Failure by a bidder to include all such provisions may result in rejection of their bid.
D. The Local Contracting Agency's record of distribution for questions, answers, notices, revisions, or addenda shall take precedence.
Acknowledged by Bidder:
P-20
PUBLIC WORKS EMPLOYMENT VERIFICATION
A. In accordance with the Public Works Employment Verification Act (Act No. 127 of 2012), a public works contractor or subcontractor shall participate in the E-Verify Program and shall, subject to the requirements of Federal law governing the use of the E-Verify Program, use the E-Verify Program to verify employment eligibility of each new employee.
B. In conducting the verification required by the Public Works Employment Verification Act, a public works contractor or subcontractor shall not discriminate against an employee on the basis of race, ethnicity, color or national origin.
C. As a precondition of being awarded a contract for a public work, prior to the execution of the contract, a public works contractor shall provide the public body with a completed Public Works Employment
Verification Form, provided herein, acknowledging its responsibilities under and its compliance with the Public Works Employment Verification Act. Contracts between a public works contractor and its subcontractors shall contain information about the requirements of the Public Works Employment
Verification Act.
D. Prior to commencing work on a public works project, a subcontractor shall provide the public body with a completed Public Works Employment Verification Form, provided herein, acknowledging its responsibilities under and its compliance with the Public Works Employment Verification Act.
Contracts between an subcontractor and its subcontractors shall contain information about the requirements of the Public Works Employment Verification Act.
Nondiscrimination/Sexual Harassment Provisions:
The Grantee agrees:
1. In the hiring of any employee(s) for the manufacture of supplies, performance of work, or any other activity required under the grant agreement or any subgrant agreement, contract, or subcontract, the Grantee, a subgrantee, a contractor, a subcontractor, or any person acting on behalf of the Grantee shall not discriminate by reason of race, gender, creed, color, sexual orientation, gender identity or expression, or in violation of the Pennsylvania Human Relations Act (PHRA) and applicable federal laws, against any citizen of this Commonwealth who is qualified and available to perform the work to which the employment relates.
2. The Grantee, any subgrantee, contractor or any subcontractor or any person on their behalf shall not in any manner discriminate by reason of race, gender, creed, color, sexual orientation, gender identity or expression, or in violation of the PHRA and applicable federal laws, against or intimidate any of its employees.
3. Neither the Grantee nor any subgrantee nor any contractor nor any subcontractor nor any person on their behalf shall in any manner discriminate by reason of race, gender, creed, color, sexual orientation, gender identity or expression, or in violation of the PHRA and applicable federal laws, in the provision of services under the grant agreement, subgrant agreement, contract or subcontract.
4. Neither the Grantee nor any subgrantee nor any contractor nor any subcontractor nor any person on their behalf shall in any manner discriminate against employees by reason of participation in or decision to refrain from participating in labor activities protected under the Public Employee Relations Act, Pennsylvania Labor Relations Act or National Labor Relations Act, as applicable and to the extent determined by entities charged with such Acts’ enforcement, and shall comply with any provision of law establishing organizations as employees’ exclusive representatives.
5. The Grantee, any subgrantee, contractor or any subcontractor shall establish and maintain a written nondiscrimination and sexual harassment policy and shall inform their employees in writing of the policy. The policy must contain a provision that sexual harassment will not be tolerated and employees who practice it will be disciplined. Posting this Nondiscrimination/Sexual Harassment Clause conspicuously in easily-accessible and well-lighted places customarily frequented by employees and at or near where the grant services are performed shall satisfy this requirement for employees with an established work site.
6. The Grantee, any subgrantee, contractor or any subcontractor shall not discriminate by reason of race, gender, creed, color, sexual orientation, gender identity or expression, or in violation of the PHRA and applicable federal laws, against any subgrantee, contractor, subcontractor or supplier who is qualified to perform the work to which the grant relates.
7. The Grantee and each subgrantee, contractor and subcontractor represents that it is presently in compliance with and will maintain compliance with all applicable federal, state, and local laws and regulations relating to nondiscrimination and sexual harassment. The Grantee and each subgrantee, contractor and subcontractor further represents that it has filed a Standard Form 100 Employer Information Report (“EEO-1”) with the U.S. Equal Employment Opportunity Commission (“EEOC”) and shall file an annual EEO-1 report with the EEOC as required for employers’ subject to Title VII of the Civil Rights Act of 1964, as amended, that have 100 or more employees and employers that have federal government contracts or first-tier subcontracts and have 50 or more employees. The Grantee, any subgrantee, any contractor or any subcontractor shall, upon request and within the time periods requested by the Commonwealth, furnish all necessary employment documents and records, including EEO-1 reports, and permit access to their books, records, and accounts by the granting agency and the Bureau of Diversity, Inclusion and Small Business Opportunities for the purpose of ascertaining compliance with the provisions of this Nondiscrimination/Sexual Harassment Clause.
8. The Grantee, any subgrantee, contractor or any subcontractor shall include the provisions of this Nondiscrimination/Sexual Harassment Clause in every subgrant agreement, contract or subcontract so that those provisions applicable to subgrantees, contractors or subcontractors will be binding upon each subgrantee, contractor or subcontractor.
9. The Grantee’s and each subgrantee’s, contractor’s and subcontractor’s obligations pursuant to these provisions are ongoing from and after the effective date of the grant agreement through the termination date thereof. Accordingly, the Grantee and each subgrantee, contractor and subcontractor shall have an obligation to inform the Commonwealth if, at any time during the term of the grant agreement, it becomes aware of any actions or occurrences that would result in violation of these provisions.
10. The Commonwealth may cancel or terminate the grant agreement and all money due or to become due under the grant agreement may be forfeited for a violation of the terms and conditions of this Nondiscrimination/Sexual Harassment Clause. In addition, the granting agency may proceed with debarment or suspension and may place the Grantee, subgrantee, contractor, or subcontractor in the Contractor Responsibility File.
Signature Date
Print twilliams Typewritten Text
| PROPOSAL SECTION |
| BID SUBMISSION CHECKLIST |
| STATEMENT OF CORPORATE OWNERSHIP |
| NONDISCRIMINATION REQUIREMENTS |
| Instructions for non-collusion affidavit |
| NON-COLLUSION AFFIDAVIT |
| BID SECURITY |
| consent of surety |
| SUBCONTRACTOR DECLARATION |
| Certificate of Bidder Showing Ability to Perform Contract |
| Acknowledgement of Receipt of Changes to Bid Documents Form |
| Public works employment verification |
| Table of Contents |
| 1.0 General. |
| 1.01 Project Information: |
| A. Project Title: N. Main Street & University Drive Stormwater Improvements – Phase 1 |
| B. Project County: Bucks County |
| C. Local Contracting Agency: Yardley Borough |
| 56 South Main Street |
| Yardley, PA 19067 |
| D. Design Professional: Remington & Vernick Engineers (RVE) |
| 1010 Stony Hill Road, Suite 175 |
| Yardley, PA 19067 |
| 2.0 Electronic Bidding Information. |
| 2.01 Electronic Bidding Statement. |
| A. In accordance with Title 62, Pennsylvania Code, Section 4603, local government units in the Commonwealth of Pennsylvania are allowed to utilize electronic bidding. |
| B. The Local Contracting Agency is utilizing the PennBid electronic procurement program ("PennBid") to solicit bids for this project. Any alternate forms of bid submission will not be permitted for this project. Any bids received by means other than... |
| 2.02 Use of PennBid. |
| A. PennBid can be accessed by visiting the following website URL on the internet: https://pennbid.bonfirehub.com/ |
| B. Interested bidders are required to register on PennBid. There is no cost associated with registering on PennBid. Once registered and logged into PennBid, bidders view a complete listing of all currently available solicitations from every agency u... |
| C. PennBid is a sealed bidding system and has the electronic capability to maintain the confidentiality of the bid until the bid opening time. |
| D. Only the successful bidder for a contract will be responsible for payment of a fee to PennBid and for bearing the cost thereof. The amount of the fee due to PennBid is either 1/3% (0.0033) of the initial contract award amount for fixed fee contrac... |
| 2.03 Obtaining Bid Documents. |
| A. Bidders can access all bid documents during the bidding period by visiting the project solicitation on PennBid and then selecting the "Supporting Documents” section of the “Project Details” tab within the project solicitation. |
| B. All bid documents, including plans and specifications, can be downloaded from PennBid at no cost to the bidder. Once downloaded from PennBid, bidders may print any of the bid documents and may forward them to subcontractors or suppliers. Bidders ... |
| 2.04 Questions During the Bidding Period. |
| A. All questions during the bidding period must be submitted through PennBid. Answers to any questions received during the bidding period will be distributed to all bidders through PennBid. Any questions received by means other than through PennBid ... |
| B. Bidders can submit questions by visiting the project solicitation on PennBid and selecting the "Ask A Question" button from within the project solicitation. Questions may be submitted until the question cutoff time that is established on the "Proj... |
| 2.05 Submission of Bids. |
| A. Bidders must submit their bid by visiting the bid tab on PennBid and selecting the "Submissions" section from within the project solicitation. Bidders shall follow the guidelines from the PennBid Bonfire Vendor Support webpage for “Creating a Subm... |
| B. An electronic copy of all required documents must be submitted to PennBid along with the bidder's electronic bid. Prior to submitting required documents to PennBid, the bidder must complete the documents, including any signatures and notarizations... |
| C. After completing the electronic bid form and uploading all required documents to PennBid, the bidder must click the "Submit & Finalize My Submission" button at the bottom of the electronic bid form to submit their bid. |
| D. Verifying Bid Submission. If the bid was submitted properly on PennBid, the bidder will receive a “Submission Receipt” appearing in the middle of their screen stating "Submission Complete!". |
| E. Bid Withdrawal Prior to Bid Opening Time. A bidder may withdraw their own bid at any time prior to the bid opening time. In order to withdraw their bid, the bidder must click the "Withdraw Bid" button at the bottom of the electronic bid form. |
| 2.06 PennBid Support. |
| A. There are several Help Guides and Frequently Asked Questions (FAQs) available on the PennBid website. |
| B. If additional technical support is needed in relation to PennBid, bidders should call PennBid at (610) 693-4769. |
| 3.0 Bid Preparation. |
| 3.01 Examination & Responsibility. |
| A. Bidders are directed to examine for themselves the drawings, specifications, estimated quantities and the location of the proposed work. They shall exercise their own judgment as to the scope and nature of the work, the difficulties to be encounte... |
| 3.02 Condition of Work. |
| A. Each bidder must inform themselves fully of the conditions relative to the construction under which the work is now being or will be performed. Failure to do so will not relieve a successful bidder of their obligation to furnish all materials and ... |
| 3.03 Obligations of Bidders. |
| A. At the time of the opening of bids, each bidder will be presumed to have inspected the site and to have read and to be thoroughly familiar with the drawings and contract documents (including all addenda). The failure or omission of a bidder to rec... |
| 3.04 Addenda, Bid Specification Challenges and Interpretations. |
| A. The Table of Contents for the technical specifications provides an index of each of the individual technical specification sections for this project and each of the individual technical specification sections include page numbering. If any bidder ... |
| B. Failure by a bidder to receive or acknowledge receipt of any notice, revision or addenda to the bid advertisement, specifications or bid documents, which have been duly issued and distributed, shall not relieve the bidder from any obligations intro... |
| C. All notices, revisions or addenda shall be acknowledged by the bidder by completing the “Acknowledgement of Receipt of Changes to Bid Documents Form,” which is provided in the Proposal Section of the bid documents. In lieu of listing addenda on th... |
| D. Failure by a bidder to include the provisions of all answers, notices, revisions and addenda, including any changes, in their bid may result in rejection of the bid. |
| E. All addenda which have been duly issued and distributed shall become part of the contract documents. |
| F. Any bidder who wishes to challenge a bid specification shall file such challenges in writing by submitting a question on PennBid on or before the established question cutoff time. Challenges may not be filed after the question cutoff time and any ... |
| G. No interpretations of the meaning of the drawings, specifications or other contract documents will be made to any bidder orally. Every request for such interpretations should be made by submitting a question on PennBid on or before the established... |
| 3.05 Qualifications of Bidders. |
| A. The Local Contracting Unit may make such investigation as is necessary to determine the responsibility of the bidder and/or the ability of the bidder to perform the work. The bidder shall furnish the Local Contracting Unit all such information and... |
| B. Conditional bids will not be accepted. |
| C. Bids which are incomplete or obscure may be rejected at the option of the Local Contracting Unit. |
| 3.06 Disclosure Statement. |
| A. No corporation or partnership shall be awarded any contract nor shall any agreements be entered into for the performance of any work or the furnishing of any materials or supplies, the cost of which is to be paid with any public funds, by the State... |
| 3.07 Manufactured Articles. |
| A. In the specifications and on the accompanying drawings, there are specified and shown certain pieces of equipment and materials to be rented, purchased or delivered in place which have been deemed most suitable for the service anticipated and are h... |
| B. Equivalency Claims will not be accepted unless specifically allowed by the specifications or on the project drawings for a specific piece of equipment or material. Subject to the requirements of the contract General Conditions, substitutions may b... |
| C. If the specifications or project drawings specifically allow an Equivalency Claim to be submitted for a specific piece of equipment or material, then any bidder desiring to submit an Equivalency Claim for that specific piece of equipment or materia... |
| (1) Bidders must submit their Equivalency Claim to the Local Contracting Unit in the form of a question on PennBid no less than fourteen (14) days prior to the bid opening time. Along with the submission of any Equivalency Claim, bidders must provide... |
| (2) The Local Contracting Unit, along with their Design Professional for the project, will review the information and data submitted by bidders and make a determination for or against acceptance of the bidder's Equivalency Claim. The results of any s... |
| (a) If the Local Contracting Unit accepts a bidder's Equivalency Claim, then any bidder may submit their bid based on the provisions of the accepted Equivalency Claim. |
| (b) In the event that the Local Contracting Unit denies a bidder's Equivalency Claim or does not make a determination for or against an Equivalency Claim prior to the bid opening time for any reason, then the bidder must submit their bid based on the ... |
| 3.08 Bid Security & Consent of Surety. |
| A. Each bid shall be accompanied by bid security in the form of either a bid bond, in an amount equal to 10% of the total amount bid, or a Cashier's Check, in an amount equal to 10% of the total amount bid, duly executed by the bidder as principal mad... |
| (1) Any bid bond provided as bid security shall be issued by a Surety Company licensed to transact such business in the Commonwealth of Pennsylvania and shall be without endorsement or conditions. Bid bonds may be provided in the form of AIA Document... |
| (2) Bidders must have an original copy of their bid security in their own possession prior to the advertised bid opening and must be able to deliver an original copy of their bid security to the Local Contracting Agency within three (3) business days ... |
| (3) Such bid security will be returned to all bidders, with the exception of the three (3) apparent lowest responsible bidders, within fifteen (15) days after the bid opening time. Bid security will be returned to the remaining unsuccessful bidders ... |
| (4) Subject to the provisions of the Public Contract Bid Withdrawal Law, Title 72, Pennsylvania Code, Section 1601, any bid security shall be forfeited by the bidder and shall become the possession of the Local Contracting Unit if the bidder whose bid... |
B. Each bid shall be accompanied by a certificate letter from a Surety Company licensed to transact such business in the Commonwealth of Pennsylvania certifying that it will provide the bidder with the required performance bond and labor and material ...
| 4.0 Submission of Bids. |
| 4.01 General. |
| A. The Local Contracting Unit is utilizing the PennBid electronic procurement program ("PennBid") to solicit bids for this project. Any alternate forms of bid submission will not be permitted for this project. Any bids received by means other than t... |
| B. Any bid may be submitted or withdrawn prior to the bid opening time, or authorized postponement thereof. |
| C. Bids will not be accepted or opened if submitted after the bid opening time that is indicated in the advertised Notice to Bidders, or authorized postponement thereof. |
| D. Subject to the provisions of the Public Contract Bid Withdrawal Law, Title 72, Pennsylvania Code, Section 1601, once the actual bid opening takes place, no bid may be withdrawn for a period of sixty (60) days. |
| E. Bidders should refer to the "Electronic Bidding Information" section of the Information for Bidders for more information. |
| 4.02 Price to Include. |
| A. The bid submitted must cover the entire cost of the contemplated construction and installation, as illustrated on the drawings and in the manner and detail described in the specifications. The price bid for each line item shall cover the entire co... |
| B. If there are minimum unit prices included in the bid form, those unit prices shall be the minimum acceptable unit prices for the corresponding line items of the work. If the bidder fails to propose a unit cost in their bid that is equal to or grea... |
| 4.03 Rejection of Bids. |
| A. The Local Contracting Unit reserves the right to reject all bids, to reject any bid or bids not complying with the specifications, and to waive any informality in any bid or bids if such waiver be deemed by the Local Contracting Unit to be in the b... |
| B. Each bidder is instructed to be present in person or by representative at the time and place fixed for the opening of bids and at every subsequent meeting of the Local Contracting Unit at which the bidder is advised, or it has been publicly announc... |
| C. Any of following reasons, either considered independently or in combination with factors, may be considered, in the judgment of the Local Contracting Unit sufficient reasons for bidder disqualification and rejection of the bid(s): |
| (1) Submittal of more than one bid for the same work from an individual, a firm, a partnership, an association, a subsidiary, an affiliate, or a corporation under the same or different name. |
| (2) Evidence of collusion among bidders. Any participation in such collusion will receive no recognition as a bidder for future work from the Local Contracting Unit until the participant has been reinstated as a qualified bidder. |
| (3) Lack of competency, adequate machinery, plant, or of other equipment. |
| (4) Inability, in the judgment of the Local Contracting Unit to promptly complete the project, because of uncompleted work. |
| (5) Failure to pay, or satisfactorily settle, all bills due for material furnished, for labor supplied or performed, for rental of equipment used, and for services rendered by public utilities. |
| (6) Failure to comply with any prequalification requirements which may be established by the Local Contracting Unit. |
| (7) Contractor currently debarred by Federal or State Authority. |
| (8) Material or intentional failure to comply with contract, drawings, or specifications, or material or intentional failure to adequately maintain and control traffic during construction on a previous contract. |
| (9) Failure to properly sign the bid, the required affidavits, or certificate, or any other required documents, said documents being listed in the Proposal Section. |
| (10) Failure to include a price for each item on the pricing response form, except in the case of alternate bidding; in alternate bidding, failure to include a price for one of the required alternate bid items on the pricing response form. |
| (11) The inclusion of conditions or qualifications not provided for in the proposal. |
| (12) The bid contains omission(s) or alteration(s), addition(s) not specified, or deviation(s) of any other kind. |
| (13) The bid is materially unbalanced. A bid is materially unbalanced when, despite an acceptable total bid price, the price of one or more line items is significantly overstated or understated. A bid ay be rejected if the lack of balance poses an u... |
| (14) Failure by the bidder to satisfy any of the other requirements included with the contract, specifications or plans, including, but not limited to, those requirements listed within the Proposal Section and Information for Bidders section. |
| 4.04 Award of Bid. |
| A. The award of the contract will be made, subject to necessary monies to do the work being provided by the Local Contracting Unit either by resolution or ordinance or another lawful manner. The contract to be executed by the successful bidder will p... |
| 5.0 Contracts. |
| 5.01 Drawings and Specifications to be Furnished. |
| A. The Local Contracting Unit shall furnish, at no additional cost to the successful bidder, one (1) executed set of the contract documents and two (2) additional copies of the project drawings and specifications. All additional copies of the project... |
| 5.02 Performance, Payment and Maintenance Bonds. |
| A. The bidder who's bid is accepted shall furnish to the Local Contracting Unit the required performance bond and labor and material payment bond, each in the amount of one hundred percent (100%) of the awarded contract price and, at the completion of... |
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .