3-004110 - Bid Form Unit Price x.pdf
PDF 74 KB Posted
- Solicitation number
- US.256229
- Issued by
- Lancaster County, Pennsylvania
About this file
This is a bid form for a general construction project submitted to the Upper Leacock Township Municipal Authority in Pennsylvania. The New Holland Pike Low-Pressure Force Main Replacement Project (Contract No. 2026-04, RETTEW Project No. 0571404139) involves the installation of low-pressure force main sewers, gravity sewer lines, forcemain valves, lateral connections, and surface restoration across improved and unimproved areas. The project scope includes multiple line sizes ranging from 1.5 inches to 12 inches in diameter, with estimated quantities including 8,351 linear feet of 12-inch HDPE force main in improved areas, 1,250 linear feet of 1.5-inch HDPE service laterals, 180 lateral reconnections, and miscellaneous items such as valve installations, manhole work, and contingent utility repairs. Bids were due by 10:00 AM on November 5, 2026, submitted electronically through the PennBID website. A voluntary pre-bid meeting was scheduled for October 29, 2026, at 1:00 PM at the owner's office. The successful bidder must substantially complete the work within 315 calendar days from the date the contract time commences and be ready for final payment within 14 days of substantial completion.
Bid security in the amount of 10% of the total bid price, submitted as a certified check or bid bond from a surety licensed in Pennsylvania, is required with the bid submission. The successful bidder must furnish performance and payment bonds in the amount of 100% of the contract price. Bids remain open for 60 days from the bid opening date, or 120 days if award is delayed by governmental agency approval, bond sales, or grant awards. Bidders must complete a minimum of 50% of the work with their own forces. The contract is subject to the Pennsylvania Prevailing Wage Act, Federal OSHA requirements, Pennsylvania Act 229 of 2002, the Pennsylvania One Call Act (Underground Utility Line Protection Law), and the Pennsylvania Human Relations Act. All bidders must bid on all items listed on the bid form, with pricing entered into the electronic bid form on the PennBID website. Supporting documentation required at bid submission includes bid security, bid form certification, non-collusion affidavit, workers' compensation affidavit, public works employment verification, CFA non-discrimination and sexual harassment affidavit, and an experience questionnaire.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BID FORM 004110 - 1
RETTEW Project No.: 0571404139 Contract No. 2026-04
BID FORM
Project Identification: Contract No. 2026-04 – General Construction New Holland Pike Low-Pressure Force Main Replacement Project RETTEW Project No.: 0571404139
Name of Bidder:
This Bid is submitted to: Upper Leacock Township Municipal Authority 161 Newport Road Leola, PA 17540
1. The undersigned Bidder proposes and agrees, if this Bid is accepted, to enter into an
Agreement with OWNER in the form included in the Contract Documents to perform and furnish all Work as specified or indicated in the Contract Documents for the Bid price and within the Bid Times indicated in this Bid and in accordance with the other terms and conditions of the Contract Documents.
2. Bidder accepts all of the terms and conditions of the Invitation to Bid and Instructions to Bidders, including without limitation those dealing with the disposition of Bid Security.
This Bid will remain subject to acceptance for 60 days after the day of Bid opening unless award is delayed by a required approval of another government agency, the sale of bonds, or the award of a grant or grants, in which case this Bid shall remain subject to acceptance for 120 days after the bid opening date as provided by the Act of November 26, 1978 (P.L.
1309, No. 317), as amended by the Act of December 12, 1994 (P.L. 1042, No. 142). Bidder will sign and deliver the required number of counterparts of the Agreement with the Bonds and other documents required by the Bidding Requirements within 15 days after the date of OWNER'S Notice of Award.
3. In submitting this Bid, Bidder represents, as more fully set forth in the Agreement, that:
a. Bidder has examined and carefully studied the Contract Documents and the following Addenda receipt of all which is hereby acknowledged:
b. Bidder has visited the site and become familiar with and is satisfied as to the general, local and site conditions that may affect cost, progress, performance and furnishing of the Work.
c. Bidder is familiar with and is satisfied as to all federal, state and local laws and regulations that may affect cost, progress, performance and furnishing of the Work.
d. If applicable, Bidder has carefully studied all reports of explorations and tests of subsurface conditions at or contiguous to the site and all drawings of physical conditions in or relating to existing surface or subsurface structures at or contiguous to the site (except underground facilities) that have been identified in the Supplementary Conditions as referenced in Article 4 of the General Conditions.
Bidder accepts the determination set forth in Paragraph SC-4.02 of the
BID FORM 004110 - 2
Supplementary Conditions of the extent of the "technical data" contained in such reports and drawings upon which Bidder is entitled to rely as provided in Article 4 of the General Conditions. Bidder acknowledges that such reports and drawings are not Contract Documents and may not be complete for Bidder's purposes. Bidder acknowledges that OWNER and ENGINEER do not assume responsibility for the accuracy or completeness of information and data shown or indicated in the Contract Documents with respect to underground facilities at or contiguous to the site. Bidder has obtained and carefully studied (or assumes responsibility for having done so) all such additional or supplementary examinations, investigations, explorations, tests, studies and data concerning conditions (surface, subsurface and underground facilities) at or contiguous to the site or otherwise that may affect cost, progress, performance or furnishing of the Work or that may relate to any aspect of the means, methods, techniques, sequences and procedures of construction to be employed by Bidder and safety precautions and programs incident thereto. Bidder does not consider that any additional examinations, investigations, explorations, tests, studies or data are necessary for the determination of this Bid for performance and furnishing of the Work in accordance with the times, price and other terms and conditions of the Contract Documents.
e. Bidder is aware of the general nature of the Work to be performed by OWNER and others at the site that relates to work for which this Bid is submitted as indicated in the Contract Documents.
f. Bidder has correlated the information known to Bidder, information and observations obtained from visits to the site, reports and drawings identified in the Contract Documents and all additional examinations, investigations, explorations, tests, studies and data with the Contract Documents.
g. Bidder has given ENGINEER written notice of all conflicts, errors, ambiguities or discrepancies that Bidder has discovered in the Contract Documents and the written resolution thereof by ENGINEER is acceptable to Bidder, and the Contract Documents are generally sufficient to indicate and convey understanding of all terms and conditions for performing and furnishing the Work for which this Bid is submitted.
h. This Bid is genuine and not made in the interest of or on the behalf of any undisclosed person, firm or corporation and is not submitted in conformity with any agreement or rules of any group, association, organization or corporation; Bidder has not directly or indirectly induced or solicited any other Bidder to submit a false or sham Bid; Bidder has not solicited or induced any person, firm or corporation to refrain from bidding; and Bidder has not sought by collusion to obtain for itself any advantage over any other Bidder or over OWNER. Bidder is aware that they must complete a minimum of fifty (50) percent of the work on the project with its own forces.
4. Bidder will complete the Work in accordance with the Contract documents for the prices entered into the electronic Bid Form on the PennBID website, which is located under the “Bid” tab. (The electronic Bid Form may be downloaded and printed for the Bidder’s use.)
the unit price summation is identified as:
BID FORM 004110 - 3
CONTRACT NO. 2026-04
Item
Estimated Quantity
Unit
Unit Price
Total Price
GENERAL CONDITIONS
1 Mobilization/Demobilization and Closeout 1 LS 2 Erosion and Sedimentation Control 1 LS 3 Maintenance and Protection of Traffic 1 LS
DEMOLITION
4 Small Tree/Shrub Removal 5 EA 5 Demolition of Existing Valve Vaults/Manholes 7 EA
HDPE LOW-PRESSURE SEWER LINE (OPEN CUT)
6A 3” HDPE DR-17 Force Main (Improved Area) 53 LF 6B 4” HDPE DR-17 Force Main (Improved Area) 18 LF 6C 6” HDPE DR-17 Force Main (Improved Area) 489 LF 6D 8” HDPE DR-17 Force Main (Improved Area) 68 LF 6E 8” HDPE DR-17 Force Main (Unimproved Area) 126 LF 6F 10” HDPE DR-17 Force Main (Improved Area) 1472 LF 6G 12” HDPE DR-17 Force Main (Improved Area) 8351 LF 6H 12” HDPE DR-17 Force Main (Unimproved Area) 760 LF 6I 1.5” HDPE DR-11 Service Lateral 1250 LF
PVC LOW-PRESSURE SEWER LINE (OPEN CUT)
7A 2” PVC SDR-21 Force Main (Improved Area) 26 LF 7B 2.5” PVC SDR-21 Force Main (Improved Area) 5 LF
PVC GRAVITY SEWER (OPEN CUT)
8 12” PVC SDR-35 Gravity Sewer Line (Improved Area, 0’-8’
Deep)
23 LF
9 4’ Pre-Cast Sanitary Sewer Manhole 8 VF 10 4’ Doghouse Sanitary Sewer Manhole 8 VF 11 Standard Manhole Frame and Cover 2 EA
FORCEMAIN VALVES
12A 3” Plug Valve & Box 1 EA 12B 4” Plug Valve & Box 4 EA 12C 6” Plug Valve & Box 2 EA 12D 8” Plug Valve & Box 1 EA 12E 12” Plug Valve & Box 5 EA 13A 2” Ball Valve & Box 4 EA 13B 2.5” Ball Valve & Box 1 EA 14 4” Insertion Valve 1 EA 15 3” Combination Air Release Valve & Vault 5 EA
MAINLINE CONNECTIONS
16 Mainline Interconnections 12 EA 17 Dart Interconnection & South Maple Vault Rehab 1 LS
LATERAL CONNECTIONS
18 Lateral Reconnection (Short Side) 98 EA 19 Lateral Reconnection (Long Side) 82 EA
MISCELLANEOUS
20 Unclassified Excavation (Contingent) 100 CY
BID FORM 004110 - 4
Item
Estimated Quantity
Unit
Unit Price
Total Price
21A Unmarked Utility Repair (Contingent) - Telecom 3 EA 21B Unmarked Utility Repair (Contingent) – 6” Waterline 3 EA 21C Unmarked Utility Repair (Contingent) – 8” Waterline 3 EA 21D Unmarked Utility Repair (Contingent) – Water Lateral 3 EA 21E Unmarked Utility Repair (Contingent) – Gas Main 3 EA 21F Unmarked Utility Repair (Contingent) – Gas Lateral 3 EA 21G Unmarked Utility Repair (Contingent) – Sanitary Sewer
Lateral
3 EA
22A Line Stops/Mech Plugs (Additional, Contingent) – 2” 2 EA 22B Line Stops/Mech Plugs (Additional, Contingent) – 2.5” 2 EA 22C Line Stops/Mech Plugs (Additional, Contingent) – 3” 2 EA 22D Line Stops/Mech Plugs (Additional, Contingent) – 4” 2 EA
SURFACE RESTORATION
23 Unimproved Surface - Lawns/Field 1003 LF 24 Improved Surface - Gravel 150 LF 25 Improved Surface – Asphalt Driveway 50 LF 26 Improved Surface – Municipal Road 430 LF 27 Improved Surface – Concrete Sidewalk 420 LF 28 Improved Surface – Full Depth State Road Restoration 10744 LF 29 Improved Surface – Temporary Road Restoration (State &
Municipal)
11174 LF
30 Improved Surface – Concrete curb 250 LF
TOTAL UNIT PRICE BASE BID SUMMATION: (figures) Dollars and Cents (written)
5. Bidder agrees that the Work will be substantially complete within 315 calendar days after the date when the contract time commences to run as provided in Paragraph 2.03 of the General Conditions, and completed and ready for final payment within 14 calendar days after the date of Substantial Completion. Bidder accepts the provisions of the Agreement as to liquidated damages in the event of failure to complete the Work within the times specified in the Agreement.
6. The following shall be submitted with the BID on the PennBID website: Bid Security, Bid Form Certification, Non Collusion Affidavit, Workers Comp Affidavit, Public Works Employment Verification, CFA Non Discrimination Sexual Harassment Affidavit, Experience Questionnaire
7. Communications concerning this Bid shall be addressed to the address of Bidder indicated below or the following address:
8. The terms used in this Bid that are defined in the General Conditions or Instructions will have the meanings assigned to them in the General Conditions or Instructions.
BID FORM 004110 - 5
SUBMITTED on .
If Bidder is:
An Individual
By: (SEAL)
(INDIVIDUAL’S NAME)
doing business as Business Address:
Phone No.:
A Partnership
By: (SEAL)
(FIRM’S NAME)
(GENERAL PARTNER)
Business Address:
Phone No.:
A Corporation
By: (SEAL)
(CORPORATION’S NAME)
(STATE OF INCORPORATION)
By: (SEAL)
(NAME OF PERSON AUTHORIZED TO SIGN)
(TITLE)
(Corporate Seal)
Attest:
(SECRETARY)
Business Address:
Phone No.:
BID FORM 004110 - 6
A Joint Venture
By: (SEAL)
(NAME)
(ADDRESS)
By: (SEAL)
(NAME)
(ADDRESS)
Phone Number and Address for Receipt of Official Communications.
(Each joint venturer must sign. The manner of signing for each individual, partnership and corporation that is a party to the joint venture should be in the manner indicated above.)
| 1. The undersigned Bidder proposes and agrees, if this Bid is accepted, to enter into an Agreement with OWNER in the form included in the Contract Documents to perform and furnish all Work as specified or indicated in the Contract Documents for the Bi... |
| 2. Bidder accepts all of the terms and conditions of the Invitation to Bid and Instructions to Bidders, including without limitation those dealing with the disposition of Bid Security. This Bid will remain subject to acceptance for 60 days after the ... |
| 3. In submitting this Bid, Bidder represents, as more fully set forth in the Agreement, that: |
| a. Bidder has examined and carefully studied the Contract Documents and the following Addenda receipt of all which is hereby acknowledged: |
| b. Bidder has visited the site and become familiar with and is satisfied as to the general, local and site conditions that may affect cost, progress, performance and furnishing of the Work. |
| c. Bidder is familiar with and is satisfied as to all federal, state and local laws and regulations that may affect cost, progress, performance and furnishing of the Work. |
| d. If applicable, Bidder has carefully studied all reports of explorations and tests of subsurface conditions at or contiguous to the site and all drawings of physical conditions in or relating to existing surface or subsurface structures at or contig... |
| e. Bidder is aware of the general nature of the Work to be performed by OWNER and others at the site that relates to work for which this Bid is submitted as indicated in the Contract Documents. |
| f. Bidder has correlated the information known to Bidder, information and observations obtained from visits to the site, reports and drawings identified in the Contract Documents and all additional examinations, investigations, explorations, tests, st... |
| g. Bidder has given ENGINEER written notice of all conflicts, errors, ambiguities or discrepancies that Bidder has discovered in the Contract Documents and the written resolution thereof by ENGINEER is acceptable to Bidder, and the Contract Documents ... |
| h. This Bid is genuine and not made in the interest of or on the behalf of any undisclosed person, firm or corporation and is not submitted in conformity with any agreement or rules of any group, association, organization or corporation; Bidder has no... |
| 4. Bidder will complete the Work in accordance with the Contract documents for the prices entered into the electronic Bid Form on the PennBID website, which is located under the “Bid” tab. (The electronic Bid Form may be downloaded and printed for the... |
| CONTRACT NO. 2026-04 |
| 5. Bidder agrees that the Work will be substantially complete within 315 calendar days after the date when the contract time commences to run as provided in Paragraph 2.03 of the General Conditions, and completed and ready for final payment within 14 ... |
| 6. The following shall be submitted with the BID on the PennBID website: Bid Security, Bid Form Certification, Non Collusion Affidavit, Workers Comp Affidavit, Public Works Employment Verification, CFA Non Discrimination Sexual Harassment Affidavit, E... |
| 7. Communications concerning this Bid shall be addressed to the address of Bidder indicated below or the following address: |
| 8. The terms used in this Bid that are defined in the General Conditions or Instructions will have the meanings assigned to them in the General Conditions or Instructions. |
File details come from the government source that posted it. Updated .