This document comprises special terms and conditions for the Orange County, Florida Construction Manager at Risk Services for the Orange County Convention Center (OCCC) West Building BAS and HVAC Upgrades project (RFP #Y26-813). The project involves the upgrade of Building Automation Systems (BAS) and HVAC equipment at an occupied, operational convention center facility with an estimated design cost of $4,652,763.34 and estimated construction cost of $51,839,337.00. Sealed responses were required to be submitted electronically via the OpenGov e-Procurement Platform by 4:00 PM EST on Tuesday, September 15, 2026. Work is anticipated to be performed seven days per week during hours from 6:00 PM to 6:00 AM to accommodate ongoing convention center operations, with any deviations requiring 48-hour advance approval from the OCCC Project Manager. The contractor must coordinate work schedules around show events and Orange County holidays, requiring detailed daily reporting and progress documentation within 48 hours of completion.
Key operational requirements include mandatory employee background checks in accordance with Florida Statute 435.03(2) and badge protocols; submission of all project submittals through the e-Builder platform at an approximate annual cost of $2,050 per license; provision of 24/7 fire watch services with trained security personnel during any fire suppression system work; compliance with OCCC fire protection and sprinkler system protocols; and responsibility for temporary power coordination, utility relocations, and construction waste disposal. Additional constraints include restrictions on personal transport devices and motorized vehicles in designated areas, use of non-marking or protected tires in carpeted areas, prohibition of gasoline-powered vehicles in certain facility zones, and acceptance of owner-provided equipment with contractor responsibility for receiving, storage, security, and final condition. The contractor must maintain detailed daily construction reports documenting activities, manpower, safety incidents, materials, photographic documentation, and equipment decommissioning per OCCC Maximo system requirements, with monthly reports submitted by the first of each month, all filed within the e-Builder system for Owner Project Team review.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NOTICE OF REQUEST FOR PROPOSALS
FOR
CONSTRUCTION MANAGER AT RISK SERVICES FOR THE ORANGE COUNTY
CONVENTION CENTER WEST BUILDING BAS AND HVAC UPGRADES
RFP # Y26-813-CC
PART C: SPECIAL TERMS
1. SECURITY AND IDENTIFICATION:
A. Badges for Working On Site
The Prime Contractor shall require a badge issued by OCCC for each individual working on site. The criteria to receive a badge shall be in accordance with Florida Statute 435.03(2) and the “OCCC Capital Planning Badge Protocols Acknowledgement Form” that will be issued to the awarded Contractor. The Prime Contractor is responsible for submitting badge requests for all personnel, inclusive of subcontractors. The form includes the following:
1. Process FDLE Background Check
2. Ensure background checks are at no cost to the OCCC.
3. Confirm the background checks shall be dated no earlier than ninety
(90) days prior to the contract state date.
4. Approve each employee’s background check prior to submi�ng employee names for badges.
5. Ensure background checks are performed and updated for each employee on an annual basis.
6. Submit a list of approved employees to work on site to the OCCC Capital
Planning Project Manager and designees.
7. Return badges by the comple�on of the project to the Capital Planning office. The cost associated with each stolen, lost, or unreturned badges is $35.00.
The form must be submitted, signed, notarized, and returned to the OCCC Capital Planning Project Manager. The form only needs to be submitted one time for acknowledgement to adhere to during the contract duration. In the subject line of all e-mails, please include the project name, subunit and date.
B. If the Contractor and/or Subcontractor staff u�lize the Electronic Key FOB to access OCCC facili�es they are required to return it to the key box at the end of the work shi� to the place it was checked out. The cost associated with stolen, lost, or unreturned Electronic Key FOBs is $200.00 for each.
C. The Contractor shall also request OCCC parking hang tags for Contractor’s staff to park on OCCC designated parking lots during construc�on work hours. The Contractor shall submit the required forms given by the OCCC Project Manager for the issuance of hang tags. All hang tags must be returned at the end of the project. The cost associated with lost, stolen, or unreturned parking hang tags is $35.00.
2. CONTRACTORS SUBMITTALS: The Contractor shall submit all submitals, product data, shop drawings, mockups and samples documenta�on and other submitals via e-Builder to the A/E Design Team. All submitals will be returned to the Contractor and all responses shall also be (filed) in the e-Builder. All approved submitals shall bear the A/E Design Team’s stamp. The Owner Project Team will manage and monitor at all �mes the Submital log in conjunc�on with the A/E Design Team. The status of the log will be reviewed by the Owner Project Team as a part of each Construc�on Progress Mee�ng.
3. CONSTRUCTION SCHEDULE WITH EVENTS: The Conven�on Center is an occupied and ac�ve space that is opera�onal at all �mes. On-Site work availability is limited due to Conven�on Center scheduled show events and Orange County holidays. The project site is an�cipated to be available to the contractor seven (7) days per week. Contractor work hours are an�cipated to be from 6:00 PM to 6:00 AM. Any noise generated ac�vity off hours and/or any excep�ons to the agreed upon work hours must be approved in advance by the OCCC Project Manager, unless approved otherwise by the OCCC Project Manager at least 48 hours in advance for work outside those hours. Work shall be sequenced to accommodate the OCCC events/shows during the project dura�on.
Any permissible work activities during the non-workdays will be determined at the OCCC Project Manager’s discretion. With the advanced approval of the OCCC Project Manager, specific dates may be coordinated with the Contractor for their work schedule. Work is required to be scheduled around show activity.
4. COMMUNICATION AND GENERAL OVERSIGHT: The Contractor shall communicate with all the project participants during all phases of pre-construction, construction, project close out and other project activities to include the following:
A. Communicate daily or periodically with the OCCC Project Manager and its Project Team as needed. The Contractor shall submit a report daily on concerns related to design and construction efforts, activities, costs, scope, and schedule.
B. The Contractor shall have a Supervisor/qualified person present onsite for the entire duration when performing their own work or any of their sub-contractors, suppliers or any other project team members.
C. The Contractor shall include in its bid a minimum of one (1) license in order to utilize the
County’s adopted e-BuilderTM program for all communications with the A/E Design Team, and other members of Owner Project Team. This is to include but not limited to: changes orders, RFI’s, submittals, daily reports or any other correspondence deemed to be necessary by the county project management team. The cost of a single license is approximately $2,050 per year. The Contractor is responsible for the costs of their e-Builder licenses and renewals throughout the duration of construction and closeout phases.
D. The Contractor shall conduct the project progress meetings and any other workshops with the OCCC Capital Planning Team and the Architect/Engineer of Record including preparation of the agenda, record meeting minutes, and distributing the meeting minutes to the attendees and uploaded to the E-Builder under Daily Reports Process within three (3) business days from the date of the meeting. The project progress meeting minutes shall include at the minimum following items as applicable:
1. Deliveries
2. Off-site Fabrica�on challenges/updates
3. Site Access Protocols
4. Hours of work
5. Hazards and risks
6. Housekeeping
7. Payment Requests Status
8. Submitals Status
9. Correc�on of Deficient Items
10. Request for Informa�on (RFI’s) Status
11. Project Schedule
12. Pending Change Orders, Claims and Disputes Status
5. CONSTRUCTION REPORTS: The Contractor shall submit and File in e-Builder Daily Construction
Reports within 48 hours. These reports shall contain information on construction activities, manpower, equipment, materials, deliveries, safety, and other pertinent information. Each construction daily report shall include:
A. The date, �me on and off site, weather condi�ons and temperature B. General discussion of the daily work and progress, including a description of the activities completed and started and an assessment of the work accomplished by location.
C. Project accidents, deficiencies, changes or corrective action to maintain schedule.
D. Damage to existing facilities E. Project delays, reason for delay and corrective action to maintain schedule.
F. Record when Contractor is on site, number of workers by craft and list of equipment items by type G. Construction testing activities, results, and observations H. Where possible and appropriate, the quantities of work should be put into place.
I. Description of potential disputes between the Contractor and Orange County and/or A/E Design
Team J. Description of any direction or corrective action given to the Contractor K. Description of non-conforming work L. Detailed record of materials, equipment and number of works by craft used in connection with extra work, or in situations where there is reason to suspect a request for a change order or claim may be submitted by the Contractor.
M. Photographic documentation and associated log with description. These photographs should be capturing daily project progress, overall site conditions, job accidents, deficiencies noted, deviations or changes from drawings or technical specifications, items that could cause delays (i.e., weather conditions, unforeseen conditions) and staged materials/equipment.
N. The Contractor is responsible for completing the Maximo equipment decommissioning and replacement documentation in accordance with the OCCC Facilities Maximo system requirements. The County Project Manager will be responsible for documentation of the Asset Tags for New Capital Equipment installed as part of the project.
O. Incident Reports (if applicable)
Monthly reports shall be submitted to the Owner Project Team by the first of every month, detailing construction progress during the month, costs, safety remarks, schedule milestones, manpower and upcoming events. Each monthly report shall be Filed in e-Builder.
6. WORK RESTRICTIONS: The Contractor shall be responsible for covering exposed work areas. The work areas shall be covered to prevent visible exposure.
The Contractor is responsible prior to demolition of ceilings to survey the above ceiling and ensure existing wiring is not damaged during demolition.
The Contractor is responsible for providing their own equipment and method of construction waste disposal. The Contractor shall have a designated location for their waste disposal containers. The Contractor shall be responsible for ensuring these containers are used for disposal of project specific debris. The Contractor is also responsible for securing the waste disposal containers from unauthorized use.
Battery operated lifts shall have gel cell batteries. Accessibility for equipment such as scissor lifts or electric powered maintenance carts shall be permitted with limited access areas, as coordinated, and approved with the OCCC Project Manager.
Availability of space for staging/lay down area will determine whether County will permit the
Contractor to set up a staging area. The OCCC Project Manager will make reasonable staging/storage accommodations on property. The Contractor staging area on site will depend on availability of space; however, relocation of staging area may be required during project.
The OCCC facilities’ designated restrooms can be used by the Contractor with previous coordination and approval of the OCCC Project Manager. If deemed necessary by the OCCC Project Manager, the Contractor will be required to provide their own restroom facilities at no additional cost.
After completion of the work, the Contractor shall replace or restore to the original condition all affected areas within the project limits. The Contractor is required to provide all materials for patching and painting.
7. FIRE PROTECTION SYSTEM INSTALLATION PROTOCOL: The Contractor and their Sub-Contractors are responsible for reviewing and following the atached Fire Protec�on Protocol for Installing, Downloading the Program, Pretes�ng, and Final Tes�ng. Any devia�ons from the atached protocol will need writen authoriza�on from the OCCC Project Manager.
8. FIRE WATCH: The Contractor shall provide a 24/7 fire watch for all inac�ve areas during the construc�on phase. The fire watch is the ac�on of an onsite person whose sole duty is to watch for the occurrence of fire the en�re �me the fire sprinkler system and/or fire alarm system (includes but is not limited to smoke detectors, duct detectors, sprinkler risers, etc.) is disabled. Fire watch personnel shall be a fire watch trained security guard, they must be competent, equipped with a cell phone to contact OCCC Security (OCCC Security line 407-685-9828), have a thorough understanding of the purpose and responsibili�es of their assignment, and shall know the loca�on and opera�on of all portable fire ex�nguishers onsite. Fire watch personnel shall conduct con�nuous hourly rounds by walking throughout the affected area, looking for evidence of smoke, fire or any abnormal condi�ons. The specific route shall be laid out so that the fire watch person is required to pass through the en�re area to be covered. A separate log iden�fying each building, or area, under the fire watch by name and address shall be kept. Log entries shall be made hourly at the comple�on of each round. Log entries shall consist of the date, the �me the round was completed, a summary of what was observed, and the name and signature of the individual conduc�ng the fire watch. The fire watch log shall be kept readily accessible for review by the Fire Marshal and submited daily through the E- Builder system. The personnel must be a fire watch trained security guard. The onsite OCCC Fire Inspector will check to ensure that the fire watch security guards are properly trained.
9. OCCC FIRE SPRINKLER SYSTEM DRAINING AND REFILL PROTOCOL: The Contractor and their Sub- Contractors are responsible for reviewing and following the atached Fire Sprinkler System Draining and Refill Protocol. This process is required for all fire suppression work. Any devia�ons from the atached protocol will need writen authoriza�on from the OCCC Project Manager.
10. OCCC SAFETY PROTOCOL: For any life threatening or medical emergencies, the Contractor should immediately call 911. The Contractor shall report any safety incidents (examples: damage to building;
injury to personnel; impact to building opera�ons) or equipment failures to OCCC Security and the County Project Manager immediately.
11. TRANSPORT DEVICES: With the excep�on of ADA-approved mobility devices, personal transport equipment such as Segways®, Scooters (electric or manual), Bicycles, Rollerblades, Skates, Skateboards, and Hoverboards are prohibited inside the OCCC. The Contractor is responsible for obtaining prior writen approval from the OCCC Execu�ve Director or designee for ADA approved mobility devices prior to use.
The Contractor shall obtain approval prior written approval from the OCCC Executive Director or designee to operate golf/utility carts on the OCCC campus. If electric motor vehicles, including golf/utility carts, must be operated in the OCCC’s exhibit halls, the Contractor shall also obtain prior written approval from the OCCC Project Manager. If approved, non-gasoline powered motorized vehicles may be operated on the show floor during move-in and move-out days only. All vehicles must be operated in a safe manner and in accordance with all applicable OCCC policies.
Motorized vehicles, such as personnel carts, forklifts, pallet jacks, and other related motorized vehicles with steel and/or hard metallic wheels are not permitted on the OCCC’s Concourses, Lobbies, and Registration areas. Lifts (scissors or boom) or other wheeled vehicles approved for use in carpeted areas shall have non-marking tires, or tires that are covered with carpet tape or heavy-duty polyethylene sheeting. Carpeted areas shall be protected by Rhino board or similar products in concourse/high traffic areas. The use of Masonite is not permitted in concourse/high traffic areas.
Gasoline or propane motorized vehicles are not permitted on the OCCC’s Concourses, Lobbies, Tunnels, and Registration areas. The Contractor is responsible for directing their sub-contractors and vendors to ensure these requirements are met.
The on-site staging areas shall be coordinated with and approved by the OCCC Project Manager. Any vehicle or equipment that requires charging of lead acid or similar battery type, shall be done outside of the exterior of the building.
Contractor vehicle parking is in a specific parking lot and shall be coordinated with OCCC Project Manager.
12. OWNER PROVIDED EQUIPMENT / CONTRACTOR INSTALLED: If the Contractor is provided with owner equipment/material, Contractor shall be responsible for costs associated with receiving the material from the shipper, storing material in designated loca�on, provide security for the stored material, relocate the material from staging area to jobsite, and to install, connect, erect, use, clean and condi�on, as required, in accordance with the instruc�ons of the applicable manufacturer instruc�ons/warranty. Contractor shall schedule and coordinate with the OCCC Project Manager the inspec�ons and reloca�on to the jobsite of equipment/material. Any request for access to materials stored by OCCC managed loca�ons outside of normal business hours would need to be approved by the OCCC Project Manager at least forty-eight (48) hours in advance. The contractor shall inspect the equipment/material prior to accep�ng it from the OCCC Warehouse or other OCCC managed loca�ons. A�er acceptance, Contractor shall be responsible for the condi�on of the equipment/material un�l final acceptance of the project. Any delivered equipment/material found to be damaged shall be reported to OCCC Project Manager within 48 hours (via email with pictures and serial number and descrip�on of damages). The owner will be responsible for contac�ng suppliers regarding any warranty issues.
13. UTILITY COORDINATION: The Contractor shall coordinate any u�lity improvements and / or reloca�ons for this project. The Contractor shall not use u�lity delays as a basis for addi�onal compensa�on. The Contractor shall be responsible for all coordina�on with u�li�es and the OCCC Project Manager and shall cooperate fully with u�lity companies in the reloca�on of their u�li�es.
14. TEMPORARY POWER: Where possible, the owner can provide temporary power with minimum of 48 hours no�ce request to the County Project Manager. The Contractor is responsible for connec�on to the owner provided power and also arrange for temporary power in the event of any Emergency events when the OCCC power system is not available (e.g., Storm Events).
15. WORK INVOLVING ELECTRICAL HAZARDS: When possible, OCCC will endeavor to accommodate the electrical system(s) shutdown request(s). Requests need to be submited in wri�ng 2 weeks prior to actual shutdown and shall clearly indicate shutdown start �mes and end �mes. Pre-shutdown mee�ngs will be required to determine poten�al impacts to exis�ng Electrical and Ligh�ng system and the usage of OCCC facili�es. The Contractor shall design the installa�on of electrical system work to minimize the need to shut down electrical systems. If OCCC Capital Planning determines the Contractor must perform work without a panel shutdown due to equipment design or opera�onal limita�ons, the Contractor shall be responsible for providing workers with proper personal protec�on equipment to complete the scope of work at no addi�onal cost to owner. This would be the case for working around any energized equipment or circuits within the OCCC campus. The Contractor is also responsible for complying with the requirements outlined in the latest versions of the applicable electrical codes and licensing requirements pertaining to the project, including required field verifica�on of exis�ng electrical panels power configura�on within the project limits.
16. LICENSES/PERMITS/FEES: Refer to “Invita�on for Bids”, Item 2 “COUNTY PAID LICENSES/PERMITS
AND FEES”.
The Contractor is responsible for cost associated with permit lapse renewal. The Contractor is also responsible for cost associated with failed inspections and expired permits.
The Orange County Building Division has assigned the following Building Permit Numbers:
North South Bldg. B24903806
17. REQUEST FOR ADDITIONAL INFORMATION (RFI): The County will require a reasonable amount of
�me, no more than 5 (five) business days, to respond to any RFI submited by the Contractor. Any delays in responding to the RFI shall not be the basis for reimbursement of any addi�onal compensa�on, including delay claims. The Contractor shall submit all Requests for Informa�on (RFI) through the e-Builder to request technical interpreta�on of the plans/drawings and specifica�ons.
The A/E Team will evaluate requested devia�on from the approved design or specifica�on; will review and respond to RFIs. Any supplementary sketches will be provided using e-builder for clarifica�on of construc�on plans and assist in resolving actual field condi�ons encountered e-Builder. The Owner Project Team will monitor and manage at all �mes an RFI log of all RFI’s submited by the Contractor in conjunc�on with the A/E Design Team. The status of RFI log will be reviewed as part of each Project Progress Mee�ng.
Attachment:
1. OCCC Fire Protec�on System Protocol for Capital Planning Projects - Version 1 Dated 08/19/2024