26231 Ottawa Building - SIGMA Move to First Floor - Addendum 1.pdf
PDF 533 KB Posted
- Solicitation number
- RFQ 171 260000000470 3
- Issued by
- Michigan
About this file
This Addendum #1 is issued by the State of Michigan Department of Technology, Management and Budget (DTMB) for the Ottawa Building-SIGMA Move to First Floor renovation project (File No. 171/26231.ABG). The project involves comprehensive renovations to the west side of the first floor of the Ottawa Building located at 611 W Ottawa, Lansing, Michigan, including demolition of existing walls and doors and construction of new walls, doors, and transoms for offices and conference rooms. A mandatory pre-bid conference was conducted on October 7, 2026, with construction scheduled to commence in November 2026 and substantial completion required within 90 calendar days of Notice to Proceed. Bids are due by 2:00 pm on Wednesday, October 21, 2026, submitted electronically through Sigma-VSS. The addendum addresses nine specific questions raised during the pre-bid walkthrough, clarifying scope items including carpet tile and LVT flooring installation (to be performed by the State's flooring contractor), ceiling grid and tile work, lighting fixture replacement per drawing notes, controlled split receptacle installation with associated rewiring, HVAC controls integration per sheet M600, sprinkler head coverage responsibility, and compressible foam gasket installation at new wall terminations.
Key contractual requirements include a detailed schedule submission at project start, liquidated damages of $500 per day for delays beyond substantial completion and final completion, contractor responsibility for all permits and inspections, mandatory on-site supervision 100 percent of construction time, prevailing wage rate compliance per State of Michigan requirements, and comprehensive insurance coverage including workers' compensation, general liability, automobile liability, and builder's risk. The contractor must remove existing carpet and base materials and is responsible for addressing any deficiencies in existing sprinkler head coverage. A provisional allowance of $50,000 is included in the bid schedule. Working hours are restricted to 6:00 am to 6:00 pm, Monday through Friday, unless written permission is granted from MSHP for additional time. Written questions must be submitted to PSC no later than 2:00 pm on Wednesday, October 14, 2026, and an asbestos report will be provided to the winning bidder, with no known asbestos currently identified in the space.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Ottawa Building-SIGMA Move to First Floor| October 9, 2026 Page 1 | 2
Addendum #1
State of Michigan Department of Technology, Management and Budget Ottawa Building-SIGMA Move to First Floor File No:171/26231.ABG October 9, 2026
TO ALL PROSPECTIVE BIDDERS:
THE PURPOSE OF THIS MEMORANDUM IS TO ANSWER QUESTIONS RAISED DURING THE PRE-BID
WALK THROUGH CONDUCTED ON WEDNESDAY, OCTOBER 7, 2026:
GENERAL CLARIFICATIONS / RESPONSE TO BIDDER’S QUESTIONS
1. Question: Is the LVT and vinyl base replacement also being covered by the flooring contractor that will be hired by the State or only the carpet scope.
Answer: The carpet tile, LVT, and rubber base will be covered by the State and their contractor will be installing.
2. Question: The plans for demolition and replacement for ceiling tile and grid systems note more scope of work to be completed than what was noted at the walk through. Please advise the expected ceiling scope and provide any markups, if possible, for amendment to the plans.
Answer: Existing ceiling grid and tile is to remain in open areas. New rooms to receive new 2x4 grid and tile. Existing grid is to remain and tiles above new ceilings in new rooms are to be removed for access to mechanical.
3. Question: The plans call for only a few light fixtures to be replaced and that all others be serviced, but comments from the walkthrough imply an increase in the number of fixtures to be replaced. Please advise if the notes on the drawings are to be followed for pricing or if there is a revised scope for lighting to reflect otherwise.
Answer: Notes on the drawings are to be followed for pricing.
4. Question: Keynote P7 on Sheet E101 states that all existing receptacles are to be replaced with controlled split receptacles. This requires a complete rewire to accommodate the control of half of the new receptacles. Is split control wiring available at the existing outlet locations, or will additional wire pulling to panels and controls be required for the listed outlets.
Answer: As directed by the customer, controlled split receptacles shall be required. Additional wire pulling to panels and controls shall be required for the listed outlets.
5. Question: Please identify the existing building automation/DDC system manufacturer and the State’s current controls contractor for the Ottawa Building. Please confirm whether the HVAC controls work shown on M101/M401 is to be included in the contractor’s base bid or whether this work will be performed by the owner’s existing controls contractor.
Ottawa Building-SIGMA Move to First Floor| October 9, 2026 Page 2 | 2
Answer: HVAC controls are specifically addressed on sheet M600 for the new VAV boxes, with schematics and related sequences of operation. The scope of the project includes integration of these new VAV boxes into the existing DDC system that serves the building, and says so in the sequence. New and relocated temperature sensors are also indicated on the plans.
6. Question: Regarding the availability of an asbestos report for the Ottawa Building.
Answer: Report will be provided to the winning bidder. There is no known asbestos in the space.
7. Question: Who is doing floor prep for new carpet and flooring?
Answer: Winning contractor shall be required to remove the existing carpet and base and dispose of
it. The State of Michigan flooring contractor will prep the floor and install new flooring and base.
8. Question: Question was raised regarding existing sprinkler head layout(s).
Answer: Winning contractor shall be responsible for addressing any deficiencies and lack of coverage that may be present with the existing sprinkler heads.
9. Question: Question was raised as to how to treat the top of new walls that will be butting up to the existing ceiling tile(s).
Answer: Provide continuous compressible closed-cell foam gasket at top of new non-rated metal stud partition where it terminates at underside of existing acoustical ceiling system.
TO THE SPECIFICATIONS
N/A
TO THE DRAWINGS
N/A
Attachments:
Pre-Bid Meeting Agenda Prospective Bidder(s) Sign In Sheet(s)
Mandatory Pre-Bid Meeting Agenda
Project: DTMB – SIGMA move to first floor Ottawa Building File No.: 171/26231.ABG Date: October 7, 2026, 1:00 pm – On Site, Ottawa Bldg, 611 W Ottawa, Lansing, MI
A. Introductions
1. Owner’s Representatives – DTMB
2. PSC’s Representatives – Colliers Engineering
B. Sign-in Sheet – Please sign for evidence of attendance. Note: You must sign in under the same name as the company submitting the bid. An individual is only permitted to represent one bidder at a mandatory Pre-Bid Conference.
C. “Any answers provided at this meeting are considered clarifications of the bidding documents and are not intended to change them. If a point or concern raised during this meeting is deemed by the PSC and Owner to require a change to the bidding documents, such change will be reflected by the issuance of an addendum.”
D. Project description – Provide all material, equipment, labor and services required for renovations to the west side of the first floor of the Ottawa Building including removal of existing walls and doors and new walls, doors and transoms for new offices and conference rooms, per drawings and specifications dated September 18, 2026.
E. Bid due date – Wednesday, October 21, 2026 at 2:00 pm, delivery location –
Electronic bid submittal on Sigma-VSS. Bid must be received on or before 2:00 pm to be accepted.
F. Bid Contents: (MICHSPEC)
1. Forms required for all bids:
a. Bid Summary Form
i. Submit Bid Summary Form with bidder information filled in and signed by an Officer of the Company
ii. Fill base proposal amount.
iii. Acknowledge addenda issued.
b. Bid Schedule - Fill out form in the specifications.
i. Include provisionary allowance of $50,000.00
c. Schedule of Alternates – Not applicable
d. Schedule of Unit Prices – Not applicable
G. Michigan Preferences
1. All contractors and suppliers are encouraged to use Michigan products and recycled and/or environmentally friendly products whenever possible where price, quality and performance are equal to, or superior to non-Michigan products.
2. Certification of Michigan based business – Fill out form in the specifications.
H. Contract Time
1. A detailed schedule is required from the Contractor at the start of the work.
2. Construction to start November, 2026.
3. Time of substantial completion: work must be substantially complete within 90 calendar days of Notice to Proceed.
4. Liquidated Damages. $500/day after substantial completion, $500/day after final completion.
I. Permits –
1. The contractor is responsible for obtaining and paying for all permits required by DLARA, or any other agency as required.
2. The Contractor is responsible for scheduling all inspections.
J. Contractor Supervision – The Contractor is responsible for managing and supervising the work and must be on site 100% of time.
K. Insurance Requirements – Must be submitted by contractor after notification of award of contract.
1. Workers’ Compensation and Employer’s Liability
2. Commercial General Liability
3. Commercial Automobile Liability
4. Excess Liability and any other designated in Supplementary conditions.
5. Builder’s Risk – Contractor provides.
L. Testing – See Section 014000 Quality Control for tests paid by the Contractor:
1. Earthwork compaction and density
2. Cast-in-Place Concrete compression testing
M. Special Working Conditions – Working on State owned property. Working hours shall be between 6 AM and 6 PM, Monday through Friday or per special working conditions by Agency (Appendix I). Additional weekday hours or work on State Holidays, Saturdays or Sundays is not allowed unless written permission is granted from MSHP.
N. Special Project Procedures– See Appendix II –
1. Soil Erosion and Sedimentation Control
2. Demolition/Remodeling Project Procedures
3. Hazardous Materials Project Procedures
4. Asbestos Abatement Project Procedures
5. Lead Abatement Project Procedures
O. Wage Rates – SOM Prevailing wage rates ARE reqd. See Appendix III in specs
P. Project Meetings
1. Pre-Construction Meeting – Scheduled after contract is executed.
2. Progress Meetings – Bi-weekly to be determined at Pre-Construction Meeting.
Q. Questions. In writing to PSC no later than 2:00pm on Wednesday, October 14, 2025.
| 171-26231-ABG SIGMA move Pre-BidMtgAgenda |
| 171-26231.ABG Ottawa Building - SIGMA Move to First Floor_Pre Bid Walk Through Sign In Sheet_2026_10-08 |
File details come from the government source that posted it. Updated .