261113 - TSC VCR - Cx RFQ - Addendum 01 - FINAL.pdf
PDF 195 KB Posted
- Attached to
- TSC DQ2027000156
- Solicitation number
- DQ1 GJMA 2027000156 3
- Issued by
- Larimer County, Colorado
About this file
This document is Addendum #1 to a Documented Quote Request (DQ) issued by NV5 on behalf of Trinidad State College for commissioning services on the Valley Campus Main Building Renovation project located in Alamosa, Colorado. The project encompasses mechanical, electrical, plumbing, and controls systems commissioning for a renovation that includes a 16,064 gross square feet addition and major roof work targeting high-performance building standards. The scope is specifically limited to MEP systems, DDC (direct digital controls), lighting controls, and plumbing systems, excluding building envelope commissioning. The addendum clarifies that construction will be executed under a single general contractor with no phased commissioning requirements, and proposers should assume a single integrated functional testing effort at the end of the project rather than phase-by-phase turnover. There is no minimum requirement for on-site visits; proposers must determine appropriate visit frequency based on construction milestones and their professional expertise. The contract will be structured as a fixed not-to-exceed price professional services agreement under the State Consultant Agreement template with a 4-year term, though post-occupancy support is limited to a 10-month warranty period including seasonal testing.
Pricing shall be submitted in a format as specified in Section D of the DQ, with proposers able to establish rates for re-testing and travel expenses as part of their proposal for potential add services. The Building Automation System will be installed by Long under the general contractor, and the BAS contractor is required to provide trend logging and remote read-only access to the commissioning agent during construction and functional testing. Proposers may include alternative approaches such as BalanceCx software integration as an optional add-on, though base scope should assume traditional on-site testing. A bid bond is not required for professional services. The commissioning agent is responsible for creating missing specification sections (01 9113, 23 0800, and 23 0995) as these do not appear in the project manual. The project will occur in an occupied building during renovation, and standard working hours should be assumed for proposals, though the College will remain flexible in accommodating ongoing construction work.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Trinidad State College – Valley Campus Main Building Renovation
Commissioning Services Documented Quote Request (Cx DQ) – Addendum #1
DATE: November 13, 2026
TO: ALL POTENTIAL CANDIDATES
FROM: NV5
RE: TSC Valley Campus Main Building Renovation Commissioning - Addendum #1
Documents issued to date:
o DQ for Commissioning (Cx), dated November 2, 2026
Documents included with this addendum:
• Addendum #1 (this document)
• 261005 – CD Phasing Plan
• Pre-Submittal Conference Agenda – November 6, 2026
Addendum #01
• Questions received by the deadline listed in the DQ:
1. Phasing & Proposal Pricing Format
• Reference: Exhibit B — Scope of Work / Capital Construction Requests ($6.34M Phase 1 /
$13.06M Phase 2)
• Question: The capital budget references Phase 1 ($6.34M) and Phase 2 ($13.06M). Will construction be executed under a single continuous contract with one General Contractor, or bid separately? Should the CxA fee proposal break out hours and pricing separately by Phase 1 and
Phase 2? Additionally, please confirm the format which pricing should be submitted in general or if a proposal document within the packet on company letterhead will be acceptable.
• Answer: That phasing information is outdated, and not included as part of the DQ. This project was bought out under a single general contractor. The CxA is not expected to work across any phases.
No additional formatting requirements for pricing beyond what is listed in Section D: Quote Format.
2. Building Envelope Commissioning (BECx) Scope
• Reference: Exhibit B — High Performance Building Standards (16,064 GSF Addition & Roof Scope)
• Question: The project includes a 16,064 GSF addition and major envelope/roof work targeting High
Performance Building standards. Is Building Envelope Commissioning (BECx)—including air barrier testing, thermography, and window water testing—required as a mandatory base scope under
DQ2027000156, or is the scope strictly limited to MEP, DDC, lighting, and plumbing systems?
• Answer: This scope is limited to MEP DDC, lighting, and plumbing systems.
3. Building Automation System (BAS) / Controls Headend
• Reference: Exhibit B — DDC System Commissioning
• Question: What is the preferred or existing campus DDC/BAS front-end platform or platforms at
Trinidad State College (e.g., Tridium Niagara, Automated Logic, JCI, Siemens)? Will the BAS contractor be required to provide trend logging and remote read-only access to the CxA during construction and functional testing?
• Answer: There is currently not a modern BAS system. As part of the project Long has been contracted under the General Contractor to install a BAS. Yes, contractor will be required to provide trend logging and remote read-only access.
4. Contractor Re-Testing & Not-To-Exceed Price Protections
• Reference: Form Agreement SC-5.3 / Fee Structure
• Question: Since this Documented Quote requires a fixed Not-To-Exceed (NTE) price, if functional testing is delayed or requires repeat site visits due to contractor unreadiness or uncorrected initial deficiencies, how will re-testing labor and travel expenses be handled and compensated?
• Answer: Any work beyond what is included in the base contract will need to be proposed as a
Supplement (add service) to the agreement if the need arises. Proposers may establish rates for re-testing, travel, etc as part of their proposal.
5. Site Visit Frequency & Travel Logistics
• Reference: Exhibit B — Construction Phase Field Observation (Alamosa, CO)
• Question: Given the site location in Alamosa, CO, does the Owner or OSA require a specific minimum count of on-site construction observation visits, or should the CxA define site visit frequency aligned with major construction milestones in their proposal?
• Answer: There is not a minimum requirements for on-site visits. The proposers shall use their expertise to determine the appropriate number of on-site visits.
6. Post-Occupancy Scope & 4-Year Term Horizon
• Reference: Form Agreement SC-5.3 — Contract Term
• Question: The State Consultant Agreement template spans a 4-year term. Can the State confirm that post-occupancy commissioning scope is limited to the 10-month warranty walkthrough and seasonal testing, or are there additional ongoing support requirements beyond Month 12?
• Answer: Confirmed, there are not ongoing support requirements beyond Month 12 of the warranty.
7. Deficiency Tracking / Commissioning Software
• Reference: Exhibit B — Deliverables & Deficiency Logging
• Question: EEI preferred tool is the enterprise cloud based CxAlloy for issues tracking in conjunction with BalanceCx for system performance tracking. Would the State consider allowing BalanceCx software to be integrated to building management systems as a cost saving mechanism in lieu of additional onsite testing time? Additionally, can the State confirm the utilization of CxAlloy as an acceptable tracking tool for all parties during the commissioning process?
• Answer: Additional information on how the BalanceCx software would need to be integrated would be needed to make a determination on this. Proposers may include this as an alternate. For base scope, assume traditional on site testing.
8. Information Technology / Addendum 1 Applicable Terms
• Reference: Form Agreement SC-5.3 — Addendum 1 IT Provisions
• Question: Can the State confirm that Addendum 1 Information Technology security/compliance provisions are not applicable to independent CxA engineering consulting services, as defined under
C.R.S. IT definitions?
• Answer: Confirmed.
9. Facility Occupancy & Work Hours
• Reference: Scope of Work / Site Operations
• Question: Will construction and commissioning functional testing be performed in an occupied or unoccupied building, and will standard working hours apply, or will after-hours / off-peak testing be required for specific operational systems or Allied Health spaces?
• Answer: Because this is an occupied renovation, assume that commissioning functional testing will be performed in an occupied building. That said, the College has been and will continue to be flexible in accommodating the ongoing work. For proposals, assume standard working hours.
10. Question: Section F.5 requires a 5% bid bond for bids of $50,000 or more. Does that apply to a professional services quote?
• Answer: Bid bond is not required for professional services.
11. Question: G-101 through G-107 show five or more construction phases. Please provide the construction start and end dates for each phase. Should the CxA plan separate functional testing and turnover documentation for each phase, or does the project team anticipate a single testing effort near the end of the project?
• Answer: Proposers can assume a single testing effort at the end of the project. That way, the entire integrated system is testing at once. See attached document “261005 – CD Phasing Plan” for phase start and end dates as of 10/5/26.
12. Question: Specification sections 22 0500, 23 0500, 23 0593 and 23 0923 reference commissioning sections 01 9113 and 23 0800, which do not appear in the project manual. Should the CxA plan to create these specifications? Would they be issued by addendum?
• Answer: The CxA should plan to create these specifications.
13. Question: Exhibit B limits scope to HVAC and HVAC controls. However, the electrical plans show new lighting and lighting controls. Should the quote include lighting controls? IECC 2024 requires commissioning of lighting controls.
• Answer: Yes, include all applicable commissioning required per code, including lighting.
14. Question: Does the Owner have required sampling rates for functional testing of terminal units and for
TAB field verification?
• Answer: No, the Owner looks to the proposer’s expertise to decide what is appropriate.
15. Question: Exhibit B limits the commissioned systems to HVAC and controls. However, the Electrical
Commissioning General Notes on Sheet E-002 require commissioning of the electrical and lighting systems per IECC Section C408. Mechanical General Note 19 on Sheet M-000 requires functional testing of service water heating controls, with service hot water findings reported in their own section of the commissioning reports. Are electrical, lighting control, and plumbing (service water heating) systems included in the CxA scope?
• Answer: Yes, electrical, lighting control, and plumbing is included in CxA scope.
16. Question: Specification Sections 22 0500, 23 0500, 23 0593, and 23 0923 refer to Section 01 9113
(General Commissioning Requirements), Section 23 0800 (Commissioning), and Section 23 0995
(Metering, Trending and Remote Data Acquisition for M&V). None of these sections appear in the
Project Manual. Will they be issued by addendum, or is the CxA expected to write them?
• Answer: The CxA should plan to create these specifications.
17. Question: The temporary egress plans (Sheets G-101 through G-106) show construction phases 1A, 1B, 2, 3, 4, and 5 while the building remains occupied. Will HVAC systems be turned over phase by phase, and has a schedule been developed?
• Answer: See response to Question 11.
--End of Addendum #1--
| Trinidad State College – Valley Campus Main Building Renovation |
| Commissioning Services Documented Quote Request (Cx DQ) – Addendum #1 |
| FROM: NV5 |
| Addendum #01 |