26081 Napaskiak Distribution Upgrade ITB Staking Sheets.pdf

PDF 112 KB Posted

Attached to
Napaskiak Distribution Upgrade Project Project
Solicitation number
26081
Issued by
Aleutians East Borough, Badger CDP, Alaska

About this file

This document is a staking sheet for the Napaskiak Distribution Upgrade Project, prepared by CRW Engineering Group, LLC, for construction to commence in May 2026. The project involves the renovation and upgrade of the existing overhead electrical power distribution system in Napaskiak, Alaska, funded through Denali Commission and State appropriations. The staking sheets detail specific construction work requirements across multiple pole locations, including transformer replacements, conductor installations, pole resets, guy and anchor installations, and secondary conductor connections. The document specifies work organized into base bid items and three alternative work packages (ALT 1, ALT 2, ALT 3, and ALT 4), with individual work assignments identified by pole numbers and construction unit codes. A non-mandatory pre-bid meeting was scheduled for May 28, 2026, at 10:00 AM, conducted telephonically via conference call (1-469-810-0642, Conference ID 214 800 089#), with no scheduled mandatory site visit prior to bid opening. The Contract Officer, Selwin C. Ray, provided contact information at (907) 771-3035 for additional project information.

The staking sheets identify detailed construction specifications including pole class designations, conductor sizes and types (#2 ACSR, #4 TRIPLEX, #1/0 TRIPLEX, and #2 TRIPLEX), transformer models (primarily 1-phase 120/240V and one 3-phase 208Y120V unit), guy and anchor quantities, and span measurements. Work is divided between existing pole modifications and new pole installations, with specific remarks documenting requirements such as transformer replacements, conductor connections, pole resets, guy re-tensioning, and miscellaneous tasks including salvaged light installations and telecom attachments. The document notes that construction units reference modified RUS (Rural Utility Service) standards and specifies that surge arresters shall not be installed on transformers, with guy leads standardized at 30 feet unless otherwise indicated.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NAPASKIAK

DISTRIBUTION UPGRADE PROJECT

STAKING SHEETS

ISSUED FOR CONSTRUCTION

MAY 2026

CRW ENGINEERING GROUP, LLC

3940 ARCTIC BLVD, SUITE 300

ANCHORAGE, ALASKA 99503

REV. NO. BY

0 TRK

SECONDARY CONDUCTOR

RIGHT

LOCATION Back Back OF

NUMBER No. SIZE/TYPE Span HEIGHT CLASS No. Units No. Units No. Units No. Units No. SIZE/TYPE Span No. SIZE/TYPE No. Units No. Units WAY

2 1 G1.4-10 2 EXISTING 1 H1.1 EXISTING POLE.

120/240V 1 N7.6 REPLACE XFMR.

1-PHASE PROVIDE NEW #2 ACSR JUMPERS.

CONNECT CONDUCTORS TO NEW XFMR.

4 1 G1.4-25 2 EXISTING 1 H1.1 EXISTING POLE.

120/240V 1 N7.6 RESET POLE AND RE-TENSION GUY.

1-PHASE REPLACE XFMR.

PROVIDE #2 ACSR JUMPERS.

CONNECT CONDUCTORS TO NEW XFMR.

4B 2 EXISTING 1 J3.1 EXISTING POLE.

CONNECT NEW TO EXISTING SECONDARY.

4C 1 E1.1La 1 F3.10 1 #4 TRIPLEX 140 1 #4 TRIPLEX 2 J3.1 EXISTING POLE.

RESET POLE.

INSTALL NEW GUY AND ANCHOR.

5-1 1 G1.4-15 1 H1.1 EXISTING POLE.

120/240V 1 N7.6 REPLACE XFMR.

1-PHASE PROVIDE NEW #2 ACSR JUMPERS.

CONNECT CONDUCTORS TO NEW XFMR.

5-2 EXISTING POLE.

RESET POLE AND RE-TENSION GUY.

5-3 1 G1.4-15 2 EXISTING 1 H1.1 EXISTING POLE.

120/240V 1 N7.6 RESET POLE AND RE-TENSION GUYS.

1-PHASE REPLACE XFMR.

PROVIDE #2 ACSR JUMPERS.

CONNECT CONDUCTORS TO NEW XFMR.

5-3-1 1 EXISTING EXISTING POLE.

RESET POLE.

CONNECT NEW TO EXISTING SECONDARY.

5-3-2 2 E1.1La 2 F3.10 1 G1.4-25 2 EXISTING 175 1 #1/0 TRIPLEX 3 J3.1 1 H1.1 EXISTING POLE.

120/240V 1 N7.6 RESET POLE, REMOVE GUYS/ANCHORS.

1-PHASE INSTALL NEW GUYS AND ANCHORS.

REPLACE XFMR.

PROVIDE #2 ACSR JUMPERS.

CONNECT CONDUCTORS TO NEW XFMR.

BASE BID WORK

DATE DESCRIPTION DESIGNER DATE

5/18/26 ISSUED FOR CONSTRUCTION CRW ENGINEERING GROUP, LLC TRK May 18, 2026 NAPASKIAK DISTRIBUTION

3940 ARCTIC BLVD, SUITE 300 CHECKER DATE UPGRADES PROJECT

ANCHORAGE, ALASKA 99503 TRK May 18, 2026

(907) 562-3252 DIST. ENG. DATE

TRK MAY 18, 20206

STAKING SHEETS SHOW ONLY LOCATION WHERE NEW WORK IS REQUIRED.

MISCELLANEOUS

LINE CONDUCTOR PRIMARY SERVICE

STATION (DEG) REMARKS/COMMENTS/NOTES

BACKFEED SECONDARY CONSTRUCTION

ANGLE POLE SERVICE UNITSASSEMBLY GUYS ANCHORS XFMRS

RAMPART RPSU PAGE 1 OF 6

SECONDARY CONDUCTOR

RIGHT

LOCATION Back Back OF

NUMBER No. SIZE/TYPE Span HEIGHT CLASS No. Units No. Units No. Units No. Units No. SIZE/TYPE Span No. SIZE/TYPE No. Units No. Units WAY

MISCELLANEOUS

LINE CONDUCTOR PRIMARY SERVICE

STATION (DEG) REMARKS/COMMENTS/NOTES

BACKFEED SECONDARY CONSTRUCTION

ANGLE POLE SERVICE UNITSASSEMBLY GUYS ANCHORS XFMRS

5-3-4 1 G1.4-15 1 EXISTING 1 J3.1 1 H1.1 EXISTING POLE.

120/240V 1 N7.6 REPLACE XFMR.

1-PHASE PROVIDE NEW #2 ACSR JUMPERS.

CONNECT CONDUCTORS TO NEW XFMR.

5-3-4A 141 1 #1/0 TRIPLEX 2 J3.1 EXISTING POLE.

5-3-4B 40 4 1 E1.1La 1 F3.10 132 1 #1/0 TRIPLEX 2 J3.1 NEW POLE

5-3-4C 40 4 1 E1.1La 1 F3.10 1 #4 TRIPLEX 116 1 #1/0 TRIPLEX 2 J3.1 NEW POLE

INSTALL SALVAGED LIGHT ON NEW POLE

18 1 G1.4-25 1 EXISTING 1 H1.1 EXISTING POLE.

120/240V 1 N7.6 REPLACE XFMR.

1-PHASE PROVIDE #2 ACSR JUMPERS.

CONNECT CONDUCTORS TO NEW XFMR.

22 1 E1.1La 1 F3.10 1 J3.1 EXISTING POLE.

INSTALL NEW GUY AND ANCHOR.

CONNECT NEW TO EXISTING SECONDARY.

22A 35 4 2 E1.1La 2 F3.10 1 #4 TRIPLEX 120 1 #1/0 TRIPLEX 3 J3.1 NEW POLE

1 #1/0 TRIPLEX INSTALL SALVAGED LIGHT ON NEW POLE

24 1 G1.4-25 1 EXISTING 1 J3.1 1 H1.1 EXISTING POLE.

120/240V 1 N7.6 RESET POLE AND RE-TENSION GUY.

1-PHASE REPLACE XFMR.

PROVIDE #2 ACSR JUMPERS.

CONNECT CONDUCTORS TO NEW XFMR.

24A 35 4 1 #4 TRIPLEX 75 1 #2 TRIPLEX 2 J3.1 NEW POLE

25 1 E1.1La 1 F3.10 1 EXISTING EXISTING POLE.

INSTALL NEW GUY AND ANCHOR.

CONNECT NEW TO EXISTING SECONDARY.

25A 1 E1.1La 1 F3.10 130 1 #2 TRIPLEX 2 J3.1 EXISTING POLE.

RESET POLE AND RE-TENSION GUY.

INSTALL NEW GUY AND ANCHOR.

25B 35 4 1 #4 TRIPLEX 70 1 #2 TRIPLEX 2 J3.1 NEW POLE

ATTACH TELECOM TO NEW POLE.

BASE BID WORK

RAMPART RPSU PAGE 2 OF 6

LOCATION Back Back OF

NUMBER No. SIZE/TYPE Span HEIGHT CLASS No. Units No. Units No. Units No. Units No. SIZE/TYPE Span No. SIZE/TYPE No. Units No. Units WAY

MISCELLANEOUS

LINE CONDUCTOR PRIMARY SERVICE

STATION (DEG) REMARKS/COMMENTS/NOTES

BACKFEED SECONDARY CONSTRUCTION

ANGLE POLE SERVICE UNITSASSEMBLY GUYS ANCHORS XFMRS

27 2 E1.1La 2 F3.10 EXISTING POLE.

RESET POLE AND RE-TENSION GUYS.

INSTALL NEW GUYS AND ANCHORS.

29 1 G1.4-25 1 EXISTING 1 H1.1 EXISTING POLE.

120/240V 1 N7.6 RESET POLE AND RE-TENSION GUY.

1-PHASE REPLACE XFMR.

PROVIDE #2 ACSR JUMPERS.

CONNECT CONDUCTORS TO NEW XFMR.

CONNECT TO OVERHEAD GUY.

29A 45 4 1 E1.4L 1 F3.10 NEW POLE.

1 E1.1La INSTALL OVERHEAD GUY

5A 1 E1.1La 1 F3.10 1 G1.4-15 2 EXISTING 1 H1.1 EXISTING POLE.

120/240V 1 #4 TRIPLEX 1 N7.6 REPLACE XFMR.

1-PHASE PROVIDE NEW #2 ACSR JUMPERS.

INSTALL NEW GUY AND ANCHOR.

CONNECT CONDUCTORS TO NEW XFMR.

5B 1 EXISTING EXISTING POLE.

RESET POLE AND RE-TENSION GUY.

5-2-1 1 G1.4-25 1 EXISTING 1 H1.1 EXISTING POLE.

120/240V 1 N7.6 REPLACE XFMR.

1-PHASE PROVIDE NEW #2 ACSR JUMPERS.

CONNECT CONDUCTORS TO NEW XFMR.

5-4 1 EXISTING EXISTING POLE.

RESET POLE AND RE-TENSION GUYS.

5-5 EXISTING POLE.

RESET POLE AND RE-TENSION GUY.

5-6 2 EXISTING EXISTING POLE.

RESET POLE AND RE-TENSION GUY.

5-7 1 EXISTING EXISTING POLE.

RESET POLE AND RE-TENSION GUYS.

REMOVE (1) GUY/ANCHOR PER PLANS.

CONNECT NEW OVERHEAD GUY.

ADD ALT 1 WORK

BASE BID WORK

RAMPART RPSU PAGE 3 OF 6

LOCATION Back Back OF

NUMBER No. SIZE/TYPE Span HEIGHT CLASS No. Units No. Units No. Units No. Units No. SIZE/TYPE Span No. SIZE/TYPE No. Units No. Units WAY

MISCELLANEOUS

LINE CONDUCTOR PRIMARY SERVICE

STATION (DEG) REMARKS/COMMENTS/NOTES

BACKFEED SECONDARY CONSTRUCTION

ANGLE POLE SERVICE UNITSASSEMBLY GUYS ANCHORS XFMRS

5-7A 45 4 1 E1.4L 1 F3.10 NEW POLE

1 E1.1La INSTALL OVERHEAD GUY

5-8 1 G1.4-25 4 EXISTING 1 H1.1 EXISTING POLE.

120/240V 1 N7.6 REPLACE XFMR.

1-PHASE PROVIDE NEW #2 ACSR JUMPERS.

CONNECT CONDUCTORS TO NEW XFMR.

5-9 1 G1.4-15 3 EXISTING 1 H1.1 EXISTING POLE.

120/240V 1 N7.6 REPLACE XFMR.

1-PHASE PROVIDE NEW #2 ACSR JUMPERS.

CONNECT CONDUCTORS TO NEW XFMR.

6 2 E1.1La 2 F3.10 3 #4 TRIPLEX 120 1 #1/0 TRIPLEX 3 J3.1 EXISITING POLE

CONNECT NEW TO EXISTING SECONDARY.

6A 35 4 2 E1.1La 2 F3.10 3 #4 TRIPLEX 120 1 #1/0 TRIPLEX 3 J3.1 NEW POLE

7A 1 E1.1La 1 F3.10 2 EXISTING 115 1 #1/0 TRIPLEX 1 J3.1 EXISITING POLE

CONNECT NEW TO EXISTING SECONDARY.

18B 1 E1.1La 1 F3.10 1 EXISTING EXISTING POLE.

RESET POLE.

INSTALL NEW GUYS AND ANCHORS.

20 1 G1.4-25 1 EXISTING 1 H1.1 EXISTING POLE.

120/240V 1 N7.6 REPLACE XFMR.

1-PHASE PROVIDE #2 ACSR JUMPERS.

CONNECT CONDUCTORS TO NEW XFMR.

20B 1 E1.1La 1 F3.10 2 EXISTING EXISTING POLE.

RESET POLE, REMOVE GUY/ANCHOR.

INSTALL NEW GUY AND ANCHOR.

21 1 E1.1La 1 F3.10 1 G1.4-25 1 H1.1 EXISTING POLE.

120/240V 1 N7.6 RESET POLE.

1-PHASE INSTALL NEW GUY AND ANCHOR.

REPLACE XFMR.

PROVIDE #2 ACSR JUMPERS.

CONNECT CONDUCTORS TO NEW XFMR.

ADD ALT 2 WORK

ADD ALT 1 WORK

RAMPART RPSU PAGE 4 OF 6

LOCATION Back Back OF

NUMBER No. SIZE/TYPE Span HEIGHT CLASS No. Units No. Units No. Units No. Units No. SIZE/TYPE Span No. SIZE/TYPE No. Units No. Units WAY

MISCELLANEOUS

LINE CONDUCTOR PRIMARY SERVICE

STATION (DEG) REMARKS/COMMENTS/NOTES

BACKFEED SECONDARY CONSTRUCTION

ANGLE POLE SERVICE UNITSASSEMBLY GUYS ANCHORS XFMRS

24-3 1 G1.4-15 2 EXISTING 1 H1.1 EXISTING POLE.

120/240V 1 N7.6 REPLACE XFMR.

1-PHASE PROVIDE #2 ACSR JUMPERS.

CONNECT CONDUCTORS TO NEW XFMR.

24-6 1 A5.1 1 E1.1La 1 F3.10 1 G1.4-10 1 J3.1 1 H1.1 EXISTING POLE.

120/240V 1 N7.6 RESET POLE AND RE-TENSION GUYS.

1-PHASE INSTALL NEW GUY AND ANCHOR.

REPLACE XFMR.

PROVIDE #2 ACSR JUMPERS.

CONNECT NEW TO EXISTING PRIMARY.

24-7 2 #2 ACSR 175 45 4 1 A1.1 1 #4 TRIPLEX 110 1 #1/0 TRIPLEX 3 J3.1 NEW POLE.

24-8 2 #2 ACSR 110 45 4 1 A2.1 1 E1.1La 1 F3.10 1 #4 TRIPLEX 115 1 #1/0 TRIPLEX 2 J3.1 NEW POLE.

24-9 2 #2 ACSR 115 45 4 1 A5.1 2 E1.1La 2 F3.10 1 G1.4-15 115 1 #1/0 TRIPLEX 1 J3.1 1 H1.1 NEW POLE.

120/240V 1 N7.6

1-PHASE

24-9A 55 1 #1/0 TRIPLEX 1 J3.1 EXISTING POLE.

CONNECT NEW TO EXISTING SECONDARY.

24-9B EXISTING POLE.

RESET POLE AND RE-TENSION GUY.

29-3 1 E1.1La 1 F3.10 1 G1.4-25 1 EXISTING 1 H1.1 EXISTING POLE.

120/240V 1 N7.6 RESET POLE AND RE-TENSION GUY.

1-PHASE INSTALL NEW GUY AND ANCHOR.

REPLACE XFMR.

PROVIDE #2 ACSR JUMPERS.

CONNECT CONDUCTORS TO NEW XFMR.

29-4 1 G1.4-15 2 EXISTING 1 H1.1 EXISTING POLE.

120/240V 1 N7.6 REPLACE XFMR.

1-PHASE PROVIDE #2 ACSR JUMPERS.

CONNECT CONDUCTORS TO NEW XFMR.

ADD ALT 3 WORK

RAMPART RPSU PAGE 5 OF 6

LOCATION Back Back OF

NUMBER No. SIZE/TYPE Span HEIGHT CLASS No. Units No. Units No. Units No. Units No. SIZE/TYPE Span No. SIZE/TYPE No. Units No. Units WAY

MISCELLANEOUS

LINE CONDUCTOR PRIMARY SERVICE

STATION (DEG) REMARKS/COMMENTS/NOTES

BACKFEED SECONDARY CONSTRUCTION

ANGLE POLE SERVICE UNITSASSEMBLY GUYS ANCHORS XFMRS

30A 1 E1.1La 1 F3.10 2 EXISTING EXISTING POLE.

INSTALL NEW GUY AND ANCHOR.

31 1 G1.4-25 1 EXISTING 1 H1.1 EXISTING POLE.

120/240V 1 N7.6 REPLACE XFMR.

1-PHASE PROVIDE #2 ACSR JUMPERS.

CONNECT CONDUCTORS TO NEW XFMR.

31B 2 E1.1La 2 F3.10 2 EXISTING EXISTING POLE.

RESET POLE.

INSTALL NEW GUYS AND ANCHORS.

32 1 G3.3-15 1 H1.1 EXISTING POLE.

208Y120V REPLACE XFMRS.

3-PHASE PROVIDE #2 ACSR JUMPERS.

CONNECT CONDUCTORS TO NEW XFMR.

34 1 G1.4-25 1 EXISTING 1 H1.1 EXISTING POLE.

120/240V 1 N7.6 REPLACE XFMR.

1-PHASE PROVIDE #2 ACSR JUMPERS.

CONNECT CONDUCTORS TO NEW XFMR.

35 1 G1.4-25 1 H1.1 EXISTING POLE.

120/240V 1 N7.6 REPLACE XFMR.

1-PHASE PROVIDE #2 ACSR JUMPERS.

CONNECT CONDUCTORS TO NEW XFMR.

36 3 EXISTING 1 J3.1 EXISTING POLE.

CONNECT NEW TO EXISTING SECONDARY.

37 2 EXISTING 140 1 #1/0 TRIPLEX 1 J3.1 EXISTING POLE.

CONNECT NEW TO EXISTING SECONDARY.

38 1 G1.4-25 1 EXISTING 1 H1.1 EXISTING POLE.

120/240V 1 N7.6 REPLACE XFMR.

1-PHASE PROVIDE #2 ACSR JUMPERS.

CONNECT CONDUCTORS TO NEW XFMR.11 67

ADD ALT 4 WORK

STAKING SHEET NOTES:

1. SEE PROJECT DETAIL DRAWINGS FOR MODIFIED RUS CONSTRUCTION UNITS. UNLESS OTHERWISE INDICATED, GUY LEADS SHALL BE 30 FEET.

2. ON THE RUS CONSTRUCTION UNIT G1.4 AND G1.5 AN ARMOR ROD IS INDICATED AT THE CONNECTION TO THE LINE WITH A HOT LINE CLAMP. DO NOT INSTALL SURGE ARRESTERS ON TRANSFORMERS.

RAMPART RPSU PAGE 6 OF 6

File details come from the government source that posted it. Updated .