260583-RIB-Wiring Connections-12-24-2025.pdf

PDF 58 KB Posted

Attached to
CBI GJ HVAC/Lighting Upgrade Project
Solicitation number
IFB1 REAA 2027000005 1
Issued by
Denver County, Denver City, Colorado

About this file

This is a specification document (Section 260583 - Wiring Connections) for the 25-388 CBI HVAC and Lighting Upgrade project. The specification establishes requirements for electrical connections to equipment as part of a broader HVAC and lighting upgrade initiative. The document outlines technical standards and procedures for wiring connections but does not include project timelines, bid deadlines, site visit schedules, bidders' conferences, award dates, or contract term information. The scope encompasses flexible conduit connections, cord and plug connections (NEMA 6-20R configuration), and field-installed disconnect switches for equipment installations.

The specification mandates compliance with NFPA 70 (National Electrical Code) and NEMA standards (WD 1 and WD 6) for all wiring devices and connections. Materials must include Type SO multiconductor flexible cord suitable for damp locations, with proper color coding and sizing appropriate for connected loads and branch circuit overcurrent protection. All electrical connections must follow equipment manufacturer's instructions, with provisions for strain-relief clamps, terminal block jumpers, and interconnecting conduit between devices. The document does not address pricing, funding sources, set-asides, incumbent contractors, or other procurement-related terms, as it functions solely as a technical specification for project execution.

View the file

Other files

File Type Posted
230529-RIB-Hangers and Supports for HVAC Piping and Equipment-12-24-2025.pdf PDF
221005-RIB-Plumbing Piping-12-24-2025.pdf PDF
235216-RIB-Condensing Boilers-12-24-2025.pdf PDF
260519-RIB-Low-Voltage Electrical Power Conductors and Cables-12-24-2025.pdf PDF
230719-RIB-HVAC Piping Insulation-12-24-2025.pdf PDF
221006-RIB-Plumbing Piping Specialties-12-24-2025.pdf PDF
265140-LUT-Luminaires-12-24-2025.pdf PDF
TYPE IU Sure-Lites-SLX-Surface-Mount-LED.pdf PDF
235100-RIB-Breechings, Chimneys, and Stacks-12-24-2025.pdf PDF
230923 Alerton Direct Digital Control System for HVAC.pdf PDF
TYPE P2 Metalux-Cruze-Linear-Bay-spec-sheet.pdf PDF
Bid Questions - BCE Response - 05012026.pdf PDF
230553-RIB-Identification for HVAC Piping and Equipment-12-24-2025.pdf PDF
265600-RIB-Exterior Lighting-12-24-2025.pdf PDF
230593-RIB-Testing, Adjusting, and Balancing for HVAC-12-24-2025.pdf PDF
260553-RIB-Identification for Electrical Systems-12-24-2025.pdf PDF
230513-RIB-Common Motor Requirements for HVAC Equipment-12-24-2025.pdf PDF
220553-RIB-Identification for Plumbing Piping and Equipment-12-24-2025.pdf PDF
233100-RIB-HVAC Ducts and Casings-12-24-2025.pdf PDF
233423-RIB-HVAC Power Ventilators-12-24-2025.pdf PDF
265100-RIB-Interior Lighting-12-24-2025.pdf PDF
237413-RIB-Packaged Outdoor Central-Station Air-Handling Units-12-24-2025.pdf PDF
TYPE EMX CMB-ISOLITE-Specification.pdf PDF
230523-RIB-General-Duty Valves for HVAC Piping-12-24-2025.pdf PDF
25388-CBI 100% CD w Add1.pdf PDF
232113-RIB-Hydronic Piping-12-24-2025.pdf PDF
TYPE S1 iO-CoviO-Spec-Sheet.pdf PDF
232123-RIB-Hydronic Pumps-12-24-2025.pdf PDF
262726-RIB-Wiring Devices-12-24-2025.pdf PDF
260923-RIB-Lighting Control Devices-12-24-2025.pdf PDF
TYPE P1 Corelite-Iridium-i3-Suspended-specification-sheet.pdf PDF
238126.13-RIB-Small-Capacity Split-System Air Conditioners-12-24-2025.pdf PDF
220529-RIB-Hangers and Supports for Plumbing Piping and Equipment-12-24-2025.pdf PDF
231123-RIB-Facility Natural-Gas Piping-12-24-2025.pdf PDF
232114-RIB-Hydronic Specialties-12-24-2025.pdf PDF
230913-RIB-Instrumentation and Control Devices for HVAC-12-24-2025.pdf PDF
260505-RIB-Selective Demolition for Electrical-12-24-2025.pdf PDF
CBI GJ Project Manual_VSS_R2.pdf PDF
230800-RIB-Commissioning of HVAC-12-24-2025.pdf PDF
TYPE D3 PrentaLux-CYL6-6-Sustainable-LED-Cylinder-Luminaire-Spec-Sheet.pdf PDF
Show all 40

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

25-388 CBI HVAC and Lighting Upgrade 260583 - 1 Wiring Connections

SECTION 260583

WIRING CONNECTIONS

PART 1 GENERAL

1.01 SECTION INCLUDES

A. Electrical connections to equipment.

1.02 RELATED REQUIREMENTS

A. Section 260519 - Low-Voltage Electrical Power Conductors and Cables.

B. Section 260533.13 - Conduit for Electrical Systems.

C. Section 260533.16 - Boxes for Electrical Systems.

D. Section 262726 - Wiring Devices.

E. Section 262816.16 - Enclosed Switches.

F. Section 262913 - Enclosed Controllers.

1.03 REFERENCE STANDARDS

A. NEMA WD 1 - General Color Requirements for Wiring Devices; 1999 (Reaffirmed 2020).

B. NEMA WD 6 - Wiring Devices - Dimensional Specifications; 2021.

C. NFPA 70 - National Electrical Code; Most Recent Edition Adopted by Authority Having

Jurisdiction, Including All Applicable Amendments and Supplements.

1.04 ADMINISTRATIVE REQUIREMENTS

A. Coordination:

1. Obtain and review shop drawings, product data, manufacturer's wiring diagrams, and manufacturer's instructions for equipment furnished under other sections.

2. Determine connection locations and requirements.

1.05 SUBMITTALS

A. See Section 013000 - Administrative Requirements, for submittal procedures.

B. Product Data: Provide wiring device manufacturer’s catalog information showing dimensions, configurations, and construction.

1.06 QUALITY ASSURANCE

A. Comply with requirements of NFPA 70.

PART 2 PRODUCTS

2.01 MATERIALS

A. Cords and Caps: NEMA WD 6; match receptacle configuration at outlet provided for equipment.

1. Colors: Comply with NEMA WD 1.

2. Cord Construction: NFPA 70, Type SO, multiconductor flexible cord with identified equipment grounding conductor, suitable for use in damp locations.

3. Size: Suitable for connected load of equipment, length of cord, and rating of branch circuit overcurrent protection.

B. Disconnect Switches: As specified in Section 262816.16 and in individual equipment sections.

C. Wiring Devices: As specified in Section 262726.

D. Flexible Conduit: As specified in Section 260533.13.

E. Wire and Cable: As specified in Section 260519.

F. Boxes: As specified in Section 260533.16.

2.02 EQUIPMENT CONNECTIONS

A.

25-388 CBI HVAC and Lighting Upgrade 260583 - 2 Wiring Connections

1. Electrical Connection: Flexible conduit.

2. Electrical Connection: Cord and plug (NEMA 6-20R).

3. Provide field-installed disconnect switch.

PART 3 EXECUTION

3.01 EXAMINATION

A. Verify that equipment is ready for electrical connection, wiring, and energization.

3.02 ELECTRICAL CONNECTIONS

A. Make electrical connections in accordance with equipment manufacturer's instructions.

B. Make conduit connections to equipment using flexible conduit. Use liquidtight flexible conduit with watertight connectors in damp or wet locations.

C. Connect heat producing equipment using wire and cable with insulation suitable for temperatures encountered.

D. Provide receptacle outlet to accommodate connection with attachment plug.

E. Provide cord and cap where field-supplied attachment plug is required.

F. Install suitable strain-relief clamps and fittings for cord connections at outlet boxes and equipment connection boxes.

G. Install disconnect switches, controllers, control stations, and control devices to complete equipment wiring requirements.

H. Install terminal block jumpers to complete equipment wiring requirements.

I. Install interconnecting conduit and wiring between devices and equipment to complete equipment wiring requirements.

END OF SECTION