260427 SOW.pdf
PDF 129 KB Posted
- Attached to
- Building 217 Visitor Area Security Upgrade
- Solicitation number
- N4008526R9046
About this file
This is a Statement of Objectives (SOO) for a construction project at Marine Corps Base Camp Lejeune, North Carolina. Project Number 26M015MZ involves a Building 217 Visitor Area Security Upgrade with a project date of 05/27/2026, MACC 26-0427, and MAXIMO 5584705.
The contractor shall execute four primary task categories: (1) construct approximately 20 linear feet of steel-framed security partition in Waiting Room 101 extending from floor to structural ceiling, consisting of commercial-grade steel framing with sound attenuation insulation and drywall layers (5/8" GWB base and face layers on both controlled and uncontrolled sides) finished to Level 4 standard; (2) install one 38-inch solid wood door with commercial-grade hollow metal steel frame and a commercial-grade cipher lock system integrated with base security protocols; (3) repair and restore the suspended ceiling grid to accommodate the new partition, install matching Acoustic Ceiling Tiles, and install a new 4' x 8' rubber tile area in the specified location; and (4) prepare approximately 4,500 square feet of wall surfaces in the Processing Room (111), Observation Room (110), Waiting Area (101), Corridor (106), and six Exam Rooms (102, 103, 104, 105, 107, 109) by cleaning, patching, and sanding, then apply one coat of primer and two finish coats of commercial-grade interior acrylic/latex paint with colors and finishes matching existing spaces or as directed by the Contracting Officer. The contractor must furnish all qualified personnel, supervision, materials, equipment, and transportation, with all measurements to be field-verified prior to procurement or construction. The Command Point of Contact is Dawn Gilmore at (847) 393-3286.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amend0003 260427.pdf | ||
| 217 Security Upgrade Floor Plan.pdf | ||
| 217 SOW.pdf | ||
| Amend0002 260427.pdf | ||
| Amend 0001 260427.pdf | ||
| 260427 PD.pdf | ||
| 260427 SR.pdf | ||
| RFP 26-0427.pdf | ||
| 260427 Combined DIV 01 spec.pdf | ||
| 260427 Contractor Environmental Guide.pdf | ||
| 260427 FP.pdf | ||
| 260427 WS.pdf |
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DISTRIBUTION: DoW COMMUNITY ONLY
PROJECT DATA
Date 05/27/2026
Project Number 26M015MZ
MACC 26-0427
MAXIMO 5584705
Project Title Building 217 Visitor Area Security Upgrade
Location Building 217, Marine Corps Base (MCB) Camp Lejeune, NC
Attachments 1. Drawings for wall and adjacent rooms (217 Project Area)
2. 2. Wall Assembly Detail (217 Wall Spec.)
A. OBJECTIVE
The objective of this project is to enhance physical security and improve facility conditions within the Building 217 Visitor Area. The Contractor shall install a new security partition and access-controlled door, and perform comprehensive repairs and painting of adjacent rooms, including the Processing Room (111), Observation Room (110), Waiting Area (101), and Corridor (106). All work shall be executed in strict accordance with the drawings provided and specifications.
B. DETAILED SCOPE OF WORK
The Contractor shall furnish all qualified personnel, supervision, materials, equipment, and transportation to execute the following tasks. All measurements are approximate and must be field verified by the Contractor prior to procurement or construction.
• 1. Security Partition Construction (Waiting Room 101):
• Construct approximately 20 linear feet of steel-framed partition as indicated on the drawings provided. The wall must extend from the floor slab to the original structural ceiling.
• The wall assembly, as detailed in 217 Wall Spec.png, shall consist of:
• Farming: Commercial-grade steel framing members.
• Insulation: Sound Attenuation Material installed within the wall cavity.
• Controlled Side (Corridor 106 side): One base layer of 5/8" GWB and one face layer of
5/8" GWB.
• Uncontrolled Side (Waiting Room 101 side): One base layer of 5/8" GWB and one face layer of 5/8" GWB.
• Finish all new drywall surfaces to a Level 4 standard, ready for primer and paint.
• 2. Door and Access Control Installation:
• Install one (1) 38-inch solid wood door with a commercial-grade hollow metal steel frame within the new partition.
• Install and test a commercial-grade "cypher lock" system, ensuring full integration and functionality with existing base security protocols.
• 3. Ceiling and Finishes Restoration:
• Carefully cut, remove, and re-support the existing suspended ceiling grid as necessary to accommodate the new partition.
• Repair and restore the ceiling grid and install new Acoustic Ceiling Tiles (ACT) to exactly match the existing ceiling system. Finish the grid cleanly against the new wall.
• Install a new 4' x 8' area of rubber tile in the location specified on the 217 Project Area.png drawing.
• 4. Surface Preparation & Painting (Adjacent Areas):
DISTRIBUTION: DoW COMMUNITY ONLY
• Prepare approximately 4,500 sq. ft. of wall surfaces in the Processing Room (111), Observation Room (110), Waiting Area (101), Corridor (106), and the six (6) Exam Rooms (102, 103, 104, 105, 107, 109) highlighted on the drawing.
• Preparation includes cleaning, patching minor holes/cracks, and sanding.
• Apply one (1) coat of primer and two (2) finish coats of commercial-grade interior acrylic/latex paint to all designated surfaces. Colors and finishes shall match existing spaces or as directed by the Contracting Officer.