This Request for Proposals (RFP) document is issued by the Jones County School District (JCSD) in Gray, Georgia, seeking Construction Professional (CP) services for the Jones County High School Renovations project. The RFP solicits proposals from qualified construction professionals and firms interested in providing CP services for the comprehensive renovation of Jones County High School. The document outlines instructions and requirements for all respondents, who are required to thoroughly review the entire RFP and comply with all specified instructions. The JCSD reserves the right to reject any proposals and to waive technicalities and informalities at its discretion.

The RFP document establishes the framework for evaluating proposals and selecting qualified construction professionals to manage the renovation project. Specific details regarding proposal due dates, site visit requirements, bidder conferences, evaluation criteria, pricing structures, and contract terms are contained within the full RFP documentation. Respondents are advised to carefully review all sections of the RFP to understand the complete scope of services required, evaluation methodology, and submission requirements necessary to be considered for this construction professional engagement.

View the file

Other files

File Type Posted
Contractor Affidavit.pdf PDF
36_36 GENERAL INFORMATION WORKSHEET.doc DOC document
JCSS STANDARD TERMS AND CONDITIONS.pdf PDF
26_36 MANDATORY RESPONSE CHECKLIST.xls XLS spreadsheet
Tax Compliance Form.doc DOC document
Certificate of NonCollusion.pdf PDF
DEPARTMENT OF AUDITS IMMIGRATION AND SECURITY.pdf PDF
W_9.pdf PDF
District Certifications Form.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1 Jones County School District - Construction Professional Services RFP

Request for Proposal (RFP) Request for Proposal (RFP) to provide

Jones

For

Jones County School District

Jones County High School Additions and Improvements

The eRFP is available on BidNet Direct and the Georgia Procurement Registry.

OWNER:

Jones County School District

125 Stewart Ave.

Gray, Georgia 31032-5201

The Jones County School District reserves the right to reject any and all proposals and to waive technicalities.

Solicitation Issue Date: November 24, 2025

Proposal Packages Due: December 31, 2025

2 Jones County School District - Construction Professional Services RFP

TABLE OF CONTENTS

1. GENERAL PROJECT INFORMATION

2. CONSTRUCTION PROFESSIONAL SERVICES REQUIREMENTS

3. CONTRACT INFORMATION

4. SELECTION PROCESS

5. SCHEDULE OF EVENTS

6. MANDATORY PRE-SUBMITTAL CONFERENCE

7. SUBMITTAL OF QUESTIONS AND REQUESTS FOR CLARIFICATION

8. SUBMITTAL REVIEW PROCESS

9. INSTRUCTIONS FOR PREPARING SUBMITTAL

10. SUBMITTAL OF FEE PROPOSALS

11. SUBMITTAL OF PROPOSAL AND FEE PROPOSALS

12. STEP II: INTERVIEW AND FEE NEGOTIATION PROCESS (for Finalists only).

13. PRESENTATION/ INTERVIEW INFORMATION

14. FINAL EVALUATION AND SELECTION

15. ADDITIONAL TERMS AND CONDITIONS

16. EXHIBIT "A" – GENERAL SCOPE OF WORK

17. EXHIBIT "B" –ATTACHMENT ‘A' - I. PRECONSTRUCTION COSTS AND

EXPENSES BREAKDOWN ATTACHMENT ‘B' - II.

CONSTRUCTION COSTS OVERHEAD BREAKDOWN

3 Jones County School District - Construction Professional Services RFP

REQUEST FOR PROPOSAL

Jones County High School Renovations

Gray, Georgia 31032

The Jones County School District (JCSD) (Owner), is soliciting proposals from Construction

Professionals/firms interested in providing Construction Professional (CP) services for the Jones

County High School Renovations, Gray, Georgia. This Request for Proposals (RFP) seeks to identify potential providers of the above-mentioned services. All respondents to this RFP are subject to instructions communicated in this document and are cautioned to completely review the entire RFP and follow instructions carefully. The Owner reserves the right to reject any proposals, and to waive technicalities and informalities at their discretion.

1. GENERAL PROJECT INFORMATION

Project Description: Refer to Exhibit A for the "Project Description/Scope of Work".

Project Budget

The preliminary Stated Cost of Limitation (SCL) shall be $_3,000,000___. The final budget/SCL will be determined by the prioritization of the Work, and the available funding. The Scope of

Work may be revised by the Owner due to programmatic requirements, funding availability, or other circumstances.

Project Schedule

2. CONSTRUCTION PROFESSIONAL SERVICES REQUIREMENTS

The CP will be expected to work collaboratively with the Design Professional (if any) to provide preconstruction services which may include, without limitation, technical review, cost verification, cost evaluation, value engineering, schedule development, and schedule evaluation, in addition to management of the construction. In addition, the CP will be responsible for methods of construction, safety, and the scheduling and coordination of the work of all construction and miscellaneous contracts required for completion of the project within its predetermined budget and schedule. The successful CP will be required to work collaboratively with the Owner's consultants (if any).

3. CONTRACT INFORMATION

The contract format will be a stipulated sum not to exceed the SCL Agreement. The contract may have liquidated damages.

Form of Agreement

The agreement between the Owner and the CP shall be a modified "AIA Document A101-2017-current edition - Standard Form of Agreement Between Owner and Contractor where the basis of payment is a stipulated sum, along with the Owner's modifications. The General Conditions for the project shall be as described in a modified "AIA Document A201-2017 - General Conditions of the Contract for Construction", along with the Owner's modifications and Supplementary

Conditions (if any). The General Requirements of the CP contract and general conditions are not open for negotiation.

Please see the timeline below.

4 Jones County School District - Construction Professional Services RFP

4. SELECTION PROCESS

Selection of the CP will be a qualification/fee proposal evaluation process. Selection of the CP will be a two-step process. The first step will be a qualification-based process, which will result in two (2) to five (5) firms being selected for the second step. The second step will be an interview and negotiation-based process beginning with the top ranked firm.

5. SCHEDULE OF EVENTS

The following Schedule of Events represents the Owner's best estimate of the schedule that will be followed. All times indicated will be current standard time in Gray, Georgia. The Owner reserves the right to adjust the schedule as the Owner deems necessary.

RFP Estimated Timeline:

A. Owner issues public/website advertisement of RFP November 24, 2025 B. Deadline for written questions/requests for clarification (see Section 7) December 12, 2025 C. Mandatory Pre-Bid Submittal Meeting December 17, 2025 D. Deadline for submission of Proposal by 4PM December 31, 2025 E. Owner completes evaluation, and issues notification to finalist firms on or before January 9, 2026

F. Committee interviews finalist firm’s the week of January 12, 2026 G. Recommendation/ Board Approval of CM 7 days after meeting

6. MANDATORY PRE-SUBMITTAL CONFERENCE

A pre-submittal conference will be conducted by the Owner, and attendance is mandatory. The pre-bid conference will be held in the Jones County High School Gym located at 339 Railroad

Street, Gray, GA 31032 on December 17, 2025 @ 1:00 PM.

The Owner reserves the right to disqualify a proposer from the selection process due to a failure by a proposer to arrive for the conference by the scheduled start time. Failure to attend a mandatory conference will automatically result in disqualification from the selection process.

7. SUBMITTAL OF QUESTIONS AND REQUESTS FOR CLARIFICATION

It is the responsibility of each respondent to examine the entire RFP, seek clarification in writing, and review its submittal for accuracy before submitting the document. Questions about any aspect of the RFP, or the project, shall be submitted in writing to: Mr. Raymond Braziel:

raymond.braziel@jones.k12.ga.us or post on BidNet Direct.

The deadlines for submission of questions relating to the RFP are the times and dates shown in the

(Schedule of Events- Section 5). All relevant questions and requests for clarification received by the Owner and the corresponding responses will be posted on the BidNet Direct or

Georgia Procurement Registry only. From the issue date of this solicitation until a successful proposer is selected and the selection is announced, respondents are not allowed to communicate for any reason with any members or employees of the Owner except for submission of questions as instructed in the RFP, or during the proposer's conference (if applicable), or as provided by any existing work agreement(s). For violation of this provision, the Owner shall reserve the right to reject the proposal of the offending proposer.

mailto:raymond.braziel@jones.k12.ga.us

5 Jones County School District - Construction Professional Services RFP

8. STEP 1: SUBMITTAL REVIEW PROCESS

Proposal Review

This RFP is issued for the purpose of acquiring Proposals from prospective CPs. A selection will be made by a Selection Committee consisting of representatives of the Owner. The Selection

Committee will receive, and review Proposals submitted in response to this RFP. To be deemed eligible for evaluation, firms must meet the following minimum qualifications:

Minimum Qualifications Required (evaluated on a pass/fail basis by the selection committee)

• The firm or its principals are not currently ineligible, debarred, suspended, or otherwise excluded from bidding or contracting by any state or federal agency, department, or authority.

• Firm must provide performance and payment bonding capacity, as required by Georgia law.

• Firm must have a current Contractor's Public Liability Insurance policy and must be insurable in at least the following amounts: Bodily injury, including death- limits of $1,000,000 for each accident. Property damage- limits of $2,000,000 for each accident and $10,000,000 for the aggregate of operations. (The Owner reserves the right to require additional limits and/or coverage for actual contract.) Provide your current insurance certificate.

• Firms must have all necessary, valid and current licenses to do business in the State of

Georgia. Provide a copy of your GC license, business license and Georgia Certificate of

Existence.

• Firm must demonstrate sufficient cash flow to undertake the project as evidenced by a current ratio (current assets/current liabilities) of 1.0 or higher.

• The firm must demonstrate a commitment to safety with regard to Worker's

Compensation by having an Experience Modification Rate (EMR) over the past three years of 1.2 or less.

• The firm or its principals have not been terminated for cause or currently in default on any public works contract.

The firms must provide a sworn statement attesting to compliance with the minimum criteria listed above and provide supporting documentation as requested further in the process in accordance with deliverable (A) A-1 below in this RFP.

The Selection Committee will then evaluate the submittals which have met the above minimum qualifications. Criteria for the evaluation are listed below:

Criteria for Evaluation of Submittal

15% Factor: Stability of the firm, including the firm's corporate history, resources, form of ownership, litigation history, financials, etc.

20% Factor: Firm's relevant project Experience and Qualifications, including the demonstrated ability of firm in effective management of construction of facilities comparable in complexity and function, for public owners.

20% Factor: Firm's Suitability to provide services for project, including the firm's apparent fit to the project type, delivery method, any unique qualifications for the project, current and projected workloads, describe your firms plan for competitively selecting subcontractors. Additional factors for a firm's suitability will include the construction manager's office location/proximity to the project, and current/recent project workload.

6 Jones County School District - Construction Professional Services RFP

20% Factor: Proposed Project Team's Relevant Experience and Qualifications: Experience of the project manager and superintendent on completed projects of similar type, and complexity; Assigned team's experience with effective budget and schedule control plans for this project; Provide information regarding percentage of the primary team member's time will be committed to this project.

15% Factor: Quality of Proposed Construction Plan: The firm's cost and schedule management plans; Firm's approach for managing changes within the stated cost and schedule limitations; The firm's quality assurance program and plan; The firm's close-out plan; The firm's work force plan; The firm's safety plan and site logistics plan for proposed project.

10% Factor: Evaluation of the submitted Fee Proposal, as submitted on Exhibit B with attachments A & B, attached herein.

9. INSTRUCTIONS FOR PREPARING SUBMITTAL

Each submittal shall be identical and include a transmittal letter. Submittals must be typed on standard (8- 1/2" x 11") paper. The pages must be numbered. A table of contents, with corresponding tabs, must be included to identify each section. Responses are limited to forty (40) double-sided pages or less using a minimum of an 11-point font. Any exhibits, affidavits or other enclosure information called for may be included in an appendix and will not count toward the limit. Tab sheets also do not count toward limit. Each submittal shall be prepared simply and economically, providing straightforward, concise delineation of respondent's capabilities.

Emphasis must be on completeness, relevance, and clarity to content.

To expedite the review of submittals, it is essential that respondents follow the format and instructions outlined below. The content of all Proposals must be categorized and numbered as outlined below and be responsive to all requested information:

PROPOSAL

A. Stability

A1- Provide basic company information: Company name, address, name of primary contact, telephone number, fax number, e-mail address, and company website (if available). If the firm has multiple offices, include information about the parent company and branch office separately. Identify the office from which project will be managed and proximity to the project site. Provide form of ownership, including state of residency or incorporation, and number of years in business. For joint venture entities that have not undertaken at least two projects together, each firm should submit its proposal separately. Joint submittals are Subject to the same submittal page limit.

A2- Briefly describe the history of your firm(s). Provide general information about the firm's establishment, personnel resources, including disciplines and numbers and classifications of employees, and locations and staffing of offices that will be directly involved with this

Project.

A3- Please disclose whether or not the firm has been involved in any litigation with an Owner or

Architects during the past five (5) years. List any active or pending litigation and provide a thorough explanation of its scope. List any claims against your firm or against Owners where your firm is named.

7 Jones County School District - Construction Professional Services RFP

A4- List the firm's annual average gross revenue for each of the past 5 years. Supply main financial and banking references.

A5- Please provide information as to whether or not your firm has ever been removed from a contract for cause OR failed to complete a contract as awarded?

A6- The firm, in order to be deemed eligible for further evaluation, will issue the following statement asserting that the firm meets the minimum qualifications required for this project

(supporting information is requested and can be included as an Appendix in the Proposal).

The SIGNED statement shall read as follows:

a. We certify our firm, or its principals are not currently ineligible, debarred, suspended, or otherwise excluded from bidding or contracting by any state or federal agency, department, or authority.

b. We certify that our firm has sufficient bonding capacity for anticipated total cost of work. Provide a letter or other supporting documentation from a bonding company indicating the firm's capacity to bond the project.

c. We certify our firm has a current Contractor's Public Liability Insurance policy, and our firm is insurable in the following amounts: Bodily injury, including death limits of $1,000,000 for each accident. Property damage- limits of $2,000,000 for each accident and $10,000,000 for the aggregate of operations. (The Owner reserves the right to require additional limits and/or coverage for actual contract.) Provide your current insurance certificate.

8 Jones County School District - Construction Professional Services RFP

d. We certify our firms has all necessary, valid and current licenses to do business in the State of Georgia. Provide a copy of your GC license, business license and

Georgia Certificate of Existence.

e. We certify we have sufficient cash flow to undertake the project as evidenced by a current ratio (current assets/current liabilities) of 1.0 or higher.

f. We certify a commitment to safety with regard to Worker's Compensation by having an Experience Modification Rate (EMR) over the past three years of 1.2 or less. Firm must provide a letter or other supporting documentation.

g. We certify the firm, or its principals have not been terminated for cause or are currently in default on any public works contract.

B. Experience and Qualifications

B1- Provide information on the firm's experience on projects of similar function, and complexity

(similar type of construction). Describe 3-5 projects, in order of most relevant to least relevant, which demonstrate the firm's capabilities to perform the project. For each project, provide the following information:

a. Project name, location and dates during which services were performed.

b. Brief description of project and physical description (delivery method, cost, square footage, number of stories, type of foundation, structural system, envelope, site area).

c. Services performed by your firm.

d. Provide any Owner-written letters of reference/recommendation about the firm's performance on the project.

e. Owner/Architect contact information.

f. Explanation as to how the highlighted project relates to the current Project being considered. If the firm has multiple offices, indicate the office responsible for each highlighted project

C. Statement of Suitability

C1- Provide any information that may serve to differentiate your firm from other firms regarding suitability for the project. Suitability may include, but is not limited to, the firm's fit to the project and/or needs of the Owner, any special or unique qualifications for the project, current and projected workloads, the proximity of main office to project location, and any techniques or methodologies offered by the firm that may be particularly suitable for this project type.

C2- Provide information on any special services, such as BIM capabilities, LEED Certification, and Georgia Peach Green Certification, offered by the firm that may be relevant and available for this project.

D. Qualifications and Experience of Proposed Project Team

D1- Describe your firm's proposed organization for the construction team including, project executive, project director, project manager, superintendent, cost estimator, etc., who will manage the project. Please designate the specific individuals to fill the following key roles on your team:

a. Superintendent(s)

b. Project Manager

c. Project Executive / Project Director

d. Cost Estimator

e. Other (please describe, if applicable)

9 Jones County School District - Construction Professional Services RFP

D2- Please provide, for each of the above personnel, current resume listing relevant project experience, percentage of the person's time to be committed to this project, current and projected workloads, and his/her office location in relation to project location.

D3- Please identify the individual who, from project start to finish, will be the leader of your construction team and the principal point of contact between your firm and the Owner, the Architect, and other consultants. Provide detailed information on the qualifications of this individual and the direction, authority, and management tools that will be provided to the individual by the firm. Provide information on his/her current and projected workloads, and his/her office location in relation to project location. This individual's competence, his/her leadership, location, and his/her ability to achieve customer satisfaction will be heavily considered in the selection of a construction management firm.

10 Jones County School District - Construction Professional Services RFP

D4- Provide an organizational chart showing the lines of responsibility and accountability for your team and proposed sub-consultants. If a joint venture, identify responsibility relationships, where there may be past experience at such relationships, and levels of experience.

D5- Provide examples of your recent experience as CP in constructing facilities similar to this project, including the following information:

a. Provide photographs of similar projects your firm/team completed in the past five

(5) years.

b. Provide a written reference from the Architect/Owner (with current contact information) familiar with your performance on each of the above projects.

Provide a Program Manager reference (if applicable).

c. List the individuals who served as the Project Executive/Director, Project Manager, Superintendent, and Cost Estimator on the projects. Please note whether these individuals are still employed with your firm.

d. Indicate those projects where an architect, engineering consultant, and CP served a corporate or public client as a team.

e. Provide information about the two most recent similar projects your firm has completed. Include the total quantity of change orders and net total cost increase of change orders to the project. Summarize the actual schedule performance relative to the initial project schedule. For each project, provide the name of an

Owner's representative (with a current phone number) who is most familiar with your performance on the project.

E. Management Plan E1- With regard to your firm's expected role in the project, please provide:

• a statement of your definition of the role,

• your anticipated level of management responsibility and accountability for project concerns.

E1.1 Describe your process for efficiently resolving issues and maintaining the project commitments while working collaboratively with the Architect, Owner, and other stakeholders as applicable.

E1.2 Describe your procedures for routine solving of complex project issues without compromising your team commitments.

E1.3 Provide your proposed methods and plans of communication.

E2- Describe your firm's approach to providing pre-construction services on this project.

E3- Provide your cost management plan for controlling costs on this project within the GMP during construction. Describe your systems and procedures for controlling costs during construction.

E4- Provide your change order management plan for managing cost and schedule exposures within the stated limitations.

E5- Provide your procurement and workforce plan including details on your plan to assure local CP opportunity. Describe how your firm intends to arrange the construction into bid packages in order to maintain The Owner's schedule and budget objectives.

11 Jones County School District - Construction Professional Services RFP

E6- Provide your schedule management plan for this project during construction. Describe systems and procedures your firm uses to manage the project schedule. Describe alternatives that may be explored to shorten the schedule.

E7- Provide your closeout management plan for this project. Describe your systems and procedures for your closeout plan.

E8- Provide your quality assurance plan for this project. Describe your firm's approach for validating compliance with the construction documents. Explain your process for ensuring quality workmanship.

E9- Provide your safety and site logistics plan for this project. Describe your plan for working around existing operations and for site access. Provide your accident incident rate for the past three (3) years, using the following formula: Incident Rate = # of Injuries x

(200,000) / # Total Man Hours.

E10- Provide your plan for applying any services not specifically mentioned herein. Explain the relevance of these services to this project and how they benefit the project.

10. SUBMITTAL OF PROPOSAL AND FEE PROPOSALS

Proposers will upload a copy of their proposal via BidNet Direct as one document. The Fee

Proposal must also be uploaded to BidNet Direct separately. Firms must use the attached

"Fee Proposal" forms (Exhibit B, attachment A, & B) for their fee proposal. Understand that this proposal constitutes a starting point for negotiation toward an eventual agreement on fees.

The submitted fees will be evaluated concurrently with the Proposal.

It is the sole responsibility of the Proposers to assure proposals are uploaded by the specified deadlines. No Proposal submittals will be accepted after the time stipulated above.

Proposal submittals will not be accepted via facsimile or e-mail.

It is the responsibility of the Proposers to examine the entire Request, seek clarification in writing, and review their proposal for accuracy before submitting a response. Once the deadline has passed, all submittals will be final.

All expenses for preparing and submitting responses are the sole cost of the party submitting the response. The Owner is not obligated to any party to reimburse such expenses. All submittals upon receipt become the property of the Owner. Labeling information provided in submittals

"proprietary" or "confidential" or any other designation of restricted use will not protect the information from public view. Subject to the provisions of the Open Records Act, the details of the proposal documents will remain confidential until final award.

11. STEP II: INTERVIEW AND FEE NEGOTIATION PROCESS (for Finalists only).

Step II- CP Selection, will be initiated by invitation to the qualified finalists by the Selection

Committee (determined in Step I from evaluation of Proposal) for interviews to be conducted by the Owner. The successful CP will be determined from the interview evaluation and a successful fee negotiation process.

12 Jones County School District - Construction Professional Services RFP

12. PRESENTATION/ INTERVIEW INFORMATION

Interview Format

Firms selected to make presentations shall be notified by the Invitation to Interview letter issued by the Selection Committee or Architect. The Invitation to Interview letter shall designate a place and time for the interview session. The Invitation letter will specify the manner in which the presentations will be conducted.

Electronic presentations, such as PowerPoint presentations, are allowed but may not comprise more than 20 minutes of the 30-minute presentation. The Owner will have a screen available in the interview room. Nevertheless, presenters must be prepared with their own projector and computer. The presentation may include flip charts, boards, or any other media the CP may need to communicate their abilities, along with the oral presentation.

The interviews may be conducted by the members of the Jones County School District, the

Superintendent, and invited attendees of the District’s discretion. Each interviewer will grade and judge the firms to determine the top ranked firm. Firms are encouraged to briefly describe their general company history and any other information that is relevant to the presentation. All key personnel should be present at the interview, including at a minimum, the project superintendent, project manager and project executive.

Interview Requirements

The primary intent of the formal interview process is to provide the School District with in-depth and clarifying information about the firm. Information provided should assist the School District in making an informed decision as to the proposer best suited for the work.

Firms should focus their presentations on:

Describing their detailed plan for managing the construction, cost, schedule, and quality on the project; and Unique characteristics or services the firm offers; and, Firm's concepts or plans for the division of the project into separate packages for award.

13. FINAL EVALUATION AND SELECTION

Upon completion of the evaluation of RFP submittal, proposers will be ranked in descending order of recommendation. In the event a satisfactory fee cannot be reached with the highest-ranking firm, the Owner will formally terminate the negotiations in writing and begin negotiation with the second highest-ranking firm, and so on until a mutually agreed upon fee is established.

Once the successful CP and the agreed upon fee have been determined, a CP services contract will be awarded by the Owner.

14. ADDITIONAL TERMS AND

CONDITIONS

Deadlines

The deadline for submission of questions relative to the RFP is the time and date shown in the

Schedule of Events (Section 5). All relevant and significant questions that have been submitted in writing prior to the deadline will be compiled and answered in writing and issued directly to all proposers via BidNet Direct and Georgia Procurement Registry. Any proposer exceptions to the

RFP requirements or requests for deadline extensions must also be communicated to the Owner by the deadline to be properly considered. Any requests for proposal deadline extensions must include the

13 Jones County School District - Construction Professional Services RFP reason(s) for such a request. The Owner reserves the right to approve or reject such requests as the

Owner deems necessary.

Confidentiality

Labeling information provided in submittals "proprietary" or "confidential", or any other designation of restricted use will not protect the information from public view. Subject to the provisions of the Open Records Act, the details of the proposal documents will remain confidential until final award.

Award Conditions

• This request is not an offer to contract or a solicitation of bids. This request and any proposal submitted in response, regardless of whether the proposal is determined to be the best proposal, is not binding upon the Owner and does not obligate the Owner to procure or contract for any services. Neither the Owner nor any party submitting a response will be bound unless and until a written contract mutually accepted by both parties is negotiated as to its terms and conditions and is signed by the

14 Jones County School District - Construction Professional Services RFP

Owner and a party containing such terms and conditions as are negotiated between those parties. The

Owner reserves the right to waive non-compliance with any requirements of this Request for

Proposal and to reject any or all proposals submitted in responses. Upon receipt and review of responses, the Owner will determine the party(s) and proposal that in the sole judgment of the

Owner is in the best interest of the Owner (if any is so determined), with respect to the evaluation criteria stated herein. The Owner then intends to conduct negotiations with such party(s) to determine if a mutually acceptable contract may be reached.

• Any contract awarded will include the required provision of O.C.G.A. 20-2-506. In addition, a termination for convenience provision will be included.

• The requirements of this RFP and proposal submitted in response, as agreed to by the Jones

County School District, shall be incorporated into the contract for services.

• Respondents to this RFP agree to waive any claims they have or may have against the

Owner, its employees, agents, members, representatives and legal counsel, arising out of or in connection with the: (1) administration, evaluation, recommendation or selection of any proposal; (2) waiver of any representations under the proposal or documents; (3) approval or rejection of any proposal; and (4) award of a contract.

Reciprocal Preference Law Pursuant to O.C.G.A. 13-10-3, for the purpose of determining residency, a Georgia resident business shall include:

(1) Any business that regularly maintains a place from which business is physically conducted in Georgia for at least one year prior to any bid or proposal

(2) (or) a new business that is domiciled in Georgia which regularly maintains a place from which business is physically conducted in Georgia (provided) that a place of business shall not include a post office box, site trailer or temporary structure.

Whenever the state contracts for public works construction, materialmen, CPs, builders, architects, engineers and laborers resident in the State of Georgia are to be granted the same preference over materialmen, CPs, builders, architects, engineers and laborers resident in another state in the same manner, on the same basis, and to the same extent that preference is granted in awarding bids for the same goods or services by such other states.

Joint-Venture Proposals

The Owner does not desire to enter into "joint-venture" agreements with multiple firms. In the event two or more firms desire to "team up" it is strongly recommended that one incorporated firm propose and maintain status as the contracted lead firm with the remaining firms participating as major consultants to the lead firm.

Immigration Reform Compliance Requirement.

The successful Proposer will be required to certify compliance with the

Immigration Reform and Control Act of 1986 (IRCA), D.L. 99-603 and the

Georgia Security and Immigration Compliance Act OCGA 13-10-90 et.seq., by meeting or having complied with one of the (2) following provisions and by executing any affidavits required by the rules and regulations issued by the

Georgia Department of Labor set forth at Rule 300-10-1-.01:

1) The CP warrants that CP has complied with the Immigration Reform and Control

Act of 1986 and the Georgia Security and Immigration Compliance Act by registering at https://www.vis-dhs.com/EmployerRegistration and verifying information of all new employees.

2) The successful proposer shall comply with the stipulations cited in Security and

Immigration Compliance Act OCGA 13-10-91. with respect to the proper federal authorizations regarding the right to work for subcontractors and CPs.

http://www.vis-dhs.com/EmployerRegistration

15 Jones County School District - Construction Professional Services RFP

E-Verify: CP Affidavit under O.C.G.A. § 13-10-91(b)(1)

The successful Proposer will be required to submit an Affidavit verifying its compliance with

O.C.G.A. § 13-10-91, stating affirmatively that the firm or corporation which is engaged in the performance of services on behalf of the Jones County School District has registered with, is authorized to use and uses the federal work authorization program commonly known as E-Verify, in accordance with the applicable provisions and deadlines established in O.C.G.A. § 13-10-91.

Furthermore, the CP will continue to use the federal work authorization program throughout the contract period and will contract for the physical performance of services in satisfactory of such contract only with subcontractors who present an affidavit to the CP with the information required by O.C.G.A. § 13-10-91(b). The affidavit shall include the CP's Federal Work

Authorization User Identification Number and date of authorization.

Statement of Agreement

With submission of a proposal, the Proposer agrees that he/she has carefully examined the Request for Proposal (RFP), and the Proposer agrees that it is the Proposer's responsibility to request clarification on any issues in any section of the RFP with which the Proposer disagrees or needs clarified. The Proposer also understands that failure to mention these items in the proposal will be interpreted to mean that the Proposer is in full agreement with the terms, conditions, specifications and requirements in the therein.

16 Jones County School District - Construction Professional Services RFP

EXHIBIT "A" – GENERAL SCOPE OF WORK

Project may include, but not limited to (all information herein subject to change):

1. Jones Co. High School - New Ag Mechanics Lab

2. Jones Co. High School - New Small Animal Science Barn

3. Jones Co. High School - Kitchen Epoxy Flooring

4. Jones Co. High School – Cross Country Fence Improvement

5. Jones Co. High School – Cross Country Water Well and Well House (Includes testing and power)

6. Jones Co. High School – Floor Replacement in weight room

Scope of work is subject to change, as the budget dictates.

17 Jones County School District - Construction Professional Services RFP

The forms must be completed in their entirety and submitted along with the bid.

It is the vendor ‘s responsibility to read each form carefully and to ask for clarification if needed.

If the required forms are not completed correctly or submitted with the bid, it will be rejected.

The REQUIRED forms and documents listed below must be included in your Technical Proposal at the end.

• Certificate of non-collusion

• Department of Audits Immigration and Security Form (Please complete all forms included and if any of the forms do not apply to you, please write NA at the top.)

• District Certification Form

• JCSS Standards Terms and Conditions:(Return the last page only of this document)

• Request of Quote/General Information Sheet

• Information Document

• Tax Compliance Form

• W9

Additional Instructions:

• If you have any questions, please do not hesitate to reach out to the BidNet Direct

Support Team by email at 800-835-4603 or support@bidnet.com. They will be happy to help.

• Vendors should submit a Technical Proposal and Cost Proposal only.

• DO NOT upload one document at a time if you do, the bid will be rejected.

• If vendors do not follow the directions as outlined in the eRFP as well as meet the requirements listed in the Information Document, the bid will be rejected. NO

EXCEPTIONS.

• Do not include this eRFP as a part of the documents that you submit.

mailto:support@bidnet.com

EXHIBIT B - ATTACHMENT "A"

I. PRECONSTRUCTION COSTS AND EXPENSES BREAKDOWN

Description

Qty

Unit

Labor*

Mat'l**

Sub

Labor

Subtotal

Mat'l

Subtotal

Subtotal

Total

Notes

A. Preconstruction - Supervision & Management:

1 Senior Project Mgr. mos $0 $0 $0 $0

2 Project Mgr. mos $0 $0 $0 $0

3 Preconstruction Manager mos $0 $0 $0 $0

4 Project Supt. mos $0 $0 $0 $0

5 Cost Control mos $0 $0 $0 $0

6 Scheduling mos $0 $0 $0 $0

7 Secretary mos $0 $0 $0 $0

8 Consultant mos $0 $0 $0 $0

9 Other (Identify) mos $0 $0 $0 $0

Subtotal $0

B. Preconstruction - Miscellaneous

10 Office Supplies mos $0 $0 $0 $0

11 Postage & Shipping mos $0 $0 $0 $0

12 Blueprint/Photostat. ls $0 $0 $0 $0

13 Phone Charges mos $0 $0 $0 $0

14 Phone Charges-Long Dist. mos $0 $0 $0 $0

15 Courier Service mos $0 $0 $0 $0

16 Travel Expenses mos $0 $0 $0 $0

17 Other (Identify) mos $0 $0 $0 $0

TOTAL ALL PRECONSTRUCTION COST AND EXPENSES $0

5/5/2017 10:47 AM 1

EXHIBIT B - ATTACHMENT "B"

II. CONSTRUCTION OVERHEAD COST BREAKDOWN

Subtotal

Mat'l

Subtotal

Site Supervision & Management:

1 Senior Project Mgr. mos $0 $0 $0 $0

2 Project Mgr. mos $0 $0 $0 $0

3 Project Supt. mos $0 $0 $0 $0

4 Project Supt. mos $0 $0 $0 $0

5 Area Supt. mos $0 $0 $0 $0

6 Secretary mos $0 $0 $0 $0

7 Project Engineer mos $0 $0 $0 $0

8 Project Engineer mos $0 $0 $0 $0

9 Office Engineer mos $0 $0 $0 $0

10 Engineer or Eng. Company mos $0 $0 $0 $0

11 Rodman mos $0 $0 $0 $0

12 Cost Control mos $0 $0 $0 $0

13 Safety Engineer mos $0 $0 $0 $0

14 Scheduling mos $0 $0 $0 $0

15 Purchasing mos $0 $0 $0 $0

16 Project Accountant mos $0 $0 $0 $0

17 Other (Identify) mos $0 $0 $0 $0

18 Other (Identify) mos $0 $0 $0 $0

Site Office Expense:

19 Job Office Trailer Rent mos $0 $0 $0 $0

20 Office Jobsite Build Out ls $0 $0 $0 $0

21 Office Jobsite Set-up ls $0 $0 $0 $0

22 Temp. Const. Trailer/Storage ea $0 $0 $0 $0

23 Office Furniture ls $0 $0 $0 $0

24 Office Machines/Equip. mos $0 $0 $0 $0

25 Copy Machines/Maintenance mos $0 $0 $0 $0

26 Office Supplies mos $0 $0 $0 $0

27 Janitor/San. Supplies mos $0 $0 $0 $0

28 Postage & Shipping mos $0 $0 $0 $0

29 First Aid/Med. Treat. mos $0 $0 $0 $0

30 Job Signs ea $0 $0 $0 $0

31 Progress Photos mos $0 $0 $0 $0

32 Extra Plans & Specs. allow $0 $0 $0 $0

33 Blueprint/Photostat. ls $0 $0 $0 $0

34 Telephone System ls $0 $0 $0 $0

35 Phone Installation ls $0 $0 $0 $0

Subtotal

Mat'l

Subtotal

36 Phone Charges mos $0 $0 $0 $0

37 Phone Charges-Long Dist. mos $0 $0 $0 $0

38 Radio Communications ea $0 $0 $0 $0

39 Radio Maintenance ls $0 $0 $0 $0

40 Other (Identify) ls $0 $0 $0 $0

Safety & Security:

41 Safety Incentives ls $0 $0 $0 $0

42 Sidewalk Barricades ls $0 $0 $0 $0

43 Safety Railings lf $0 $0 $0 $0

44 Opening Closures lf $0 $0 $0 $0

45 Weather Protection mos $0 $0 $0 $0

46 Ladders & Stairs ea $0 $0 $0 $0

47 Watchman/Guard Ser. mos $0 $0 $0 $0

48 Fences & Gates ls $0 $0 $0 $0

49 Traffic Control wks $0 $0 $0 $0

Fire Protection, Extinguishers, Barrels ea

$0

51 Safety Equipment mos $0 $0 $0 $0

52 Rainwear/Hardhats, etc. ls $0 $0 $0 $0

53 Other (Identify) ls $0 $0 $0 $0

Cleaning:

54 Daily Cleaning mos $0 $0 $0 $0

55 Final Cleanup-Building sf $0 $0 $0 $0

56 Window/Skylight Cleaning sf $0 $0 $0 $0

57 Trash Bin Rent/Haul mos $0 $0 $0 $0

58 Trash Chutes/Hoppers ea $0 $0 $0 $0

59 Dump Fees/Hauling mos $0 $0 $0 $0

60 Dust Barricades sf $0 $0 $0 $0

61 Other (Identify) sf $0 $0 $0 $0

Temporary Utilities/Misc.

62 Temp. Electric-Office mos $0 $0 $0 $0

63 Security-Office mos $0 $0 $0 $0

64 Temp. Electric -Building mos $0 $0 $0 $0

65 Water - Field Office mos $0 $0 $0 $0

Subtotal

Mat'l

Subtotal

66 Water - Coolers ls $0 $0 $0 $0

67 Water Barrels ls $0 $0 $0 $0

68 Ice Machine mos $0 $0 $0 $0

69 Ice and/or Cups mos $0 $0 $0 $0

70 Temporary Toilets Install ea $0 $0 $0 $0

71 Temporary Toilets mos $0 $0 $0 $0

72 Cold Weather Protection mos $0 $0 $0 $0

73 Temp. Heat for Bldg. mos $0 $0 $0 $0

74 Drug Testing ls $0 $0 $0 $0

75 Computer-PCS allow $0 $0 $0 $0

76 Computers ls $0 $0 $0 $0

77 Software ls $0 $0 $0 $0

78 MIS Charges ls $0 $0 $0 $0

79 Off-Site Parking ls $0 $0 $0 $0

80 Living Expenses mos $0 $0 $0 $0

81 Executive Travel ls $0 $0 $0 $0

82 Air Fare trips $0 $0 $0 $0

83 Car Rental trips $0 $0 $0 $0

84 Hotel trips $0 $0 $0 $0

85 Meals days $0 $0 $0 $0

86 Ceremony Expense ls $0 $0 $0 $0

87 Other (Identify) ls $0 $0 $0 $0

General Equipment:

88 Automobiles mos $0 $0 $0 $0

89 Pickup Trucks mos $0 $0 $0 $0

90 Temporary Parking mos $0 $0 $0 $0

91 Small Tools/Expendables ls $0 $0 $0 $0

92 Survey Equipment mos $0 $0 $0 $0

93 Hoist/Operator mos $0 $0 $0 $0

94 Hoist Service mos $0 $0 $0 $0

95 Erect/Dismantle Hoist ls $0 $0 $0 $0

96 Tower Crane Service ls $0 $0 $0 $0

97 Erect/Dismantle Crane ls $0 $0 $0 $0

98 Crane Rental/Operator mos $0 $0 $0 $0

99 Temp. Elev. & Operator mos $0 $0 $0 $0

100 Repair Cab/Temp. Elev. ls $0 $0 $0 $0

101 Protect Perm. Elevator ls $0 $0 $0 $0

102 Fuel/Oil/Grease mos $0 $0 $0 $0

103 Vehicle Repairs/Maintenance ls $0 $0 $0 $0

104 Other (Identify) ls $0 $0 $0 $0

Subtotal

Mat'l

Subtotal

Bonds & Insurance:

105 Perform. & Payment Bonds ls $0 $0 $0 $0

106 Workers Comp. Insurance ls $0 $0 $0 $0

107 Builders Risk Insurance ls $0 $0 $0 $0

108 Liability Insurance ls $0 $0 $0 $0

109 Other (Identify) ls $0 $0 $0 $0

TOTAL ALL CONSTRUCTION OVERHEAD COSTS: $0