This document is a startup meeting minutes record for Project 26-103 BMS HVAC Upgrades Design Services, involving the School Board of Marion County, Florida. The meeting was conducted on March 3, 2026, at 9:00 AM at the Purchasing Department Conference Room in Ocala, Florida, and was led by Garrett McCallum, Purchasing Specialist. The project involves procuring architectural and engineering design services for a campus-wide HVAC system replacement at Belleview Middle School, transitioning from an existing water-to-air package heat pump system to a modern, energy-efficient chilled water system. Key project milestones outlined during the meeting include the Submittal Review Final Meeting scheduled for March 13, 2026, at 9:00 AM (open to the public); shortlist notification on March 13, 2026; shortlist interviews on April 1, 2026, at 9:00 AM (not open to the public but recorded in compliance with Florida Statutes); a shortlist tabulation meeting on April 1, 2026, at 2:00 PM (open to the public); and finalist notification on April 2, 2026. The mandatory pre-bid meeting had been held on February 12, 2026, with qualifications submittals due by 2:00 p.m. EST on February 26, 2026, and bid opening on February 27, 2026.
The evaluation process utilizes a two-phase scoring methodology totaling 205 points. The initial submittal review phase evaluates firms based on related project experience (30 points), project team qualifications (10 points), professional and technical office staff (20 points), staff adequacy (10 points), Florida public school systems experience (20 points), other project experience (10 points), office location (5 points), and minority/woman-owned or small business status (5 points). The shortlist interview phase evaluates the top-ranked firms on project team composition (25 points), approach and methodology (25 points), timeline and quality control (15 points), cost controls and value engineering (15 points), and knowledge of site and local conditions (20 points). Nine firms submitted qualifications, with DDC Engineering, Inc. ultimately selected as the highest-ranking firm. Required qualifications include current Florida licensure, General Liability and Auto Insurance of at least $1,000,000 each, statutory Workers' Compensation Insurance, and professional reference letters for at least three school projects.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project 26-103 Design Services BMS HVAC Upgrades – Startup Meeting Minutes
Startup Meeting Minutes
Project: 26-103 BMS HVAC Upgrades Design Services
Date: March 3rd, 2026 @ 9:00 AM
Location: Purchasing Department Conference Room, 2091 NE 35th St. Ocala, FL 34479
Meeting Minutes
I. Opening Remarks
Meeting was called to order at 9:00 AM by Garrett McCallum, Purchasing Specialist for the School Board of Marion County, Florida. Mr. McCallum went over the current date and time, project title, and meeting location.
Mr. McCallum introduced himself. Everyone in attendance also introduced themselves.
Mr. McCallum also stated that meeting was being recorded and that he would be taking meeting minutes. He then asked everyone in the room to ensure they signed in on the sign in sheet.
II. Project Scope
At approximately 9:01 AM, Mr. McCallum provided an overview of the project scope.
III. Scoring Criteria
At approximately 9:02 AM, Mr. McCallum provided information on the scoring criteria contained in Form 1 of the 2026 Marion County Public Schools Design Services Manual.
Project 26-103 Design Services BMS HVAC Upgrades – Startup Meeting Minutes
IV. VendorLink Instructions
At approximately 9:07 AM, Mr. McCallum and Ms. Ivonne Bumbach demonstrated how to use the VendorLink system to input scores for each submitting firm. Mr. McCallum requested that no committee members submit their scores in the system until the Submittal Review Final Meeting, and to save their scores as a draft until then. Mr. Mccallum and Ms. Bumbach then assisted members of the committee as-needed to ensure they could access VendorLink properly. Mr. McCallum also reviewed the Cone of Silence during this time.
V. Remaining RFQ Milestones
At approximately 9:15 AM, Mr. McCallum then reminded everyone of the deadlines of this RFQ:
o Submittal Review Final Meeting March 13th, 2026 @ 9:00AM Open to the Public.
o Shortlist Notification March 13th, 2026 o Shortlist Interviews April 1st, 2026 @ 9:00AM
NOT open to the Public. Will be recorded in compliance with F.S.
286.0113.
o Shortlist Tabulation Meeting April 1st, 2026 @ 2:00PM Open to the Public o Finalist Notification April 2nd, 2026
VI. Closing Remarks
Mr. McCallum and Ms. Bumbach then thanked everyone for attending and adjourned the meeting at approximately 9:17 AM.