25RE0XX_ROM.xlsx
XLSX spreadsheet 25 KB Posted
- Solicitation number
- HE125425R_KOREAOBVSS
- Issued by
-
Department of Defense Education Activity
About this file
This is a Request for Information (RFI) spreadsheet for a Department of Defense Education Activity (DoDEA) On-Board Vehicle Surveillance System (OBVSS) contract in South Korea. The contract covers bus surveillance services for military locations including Camp Humphreys, Daegu, and Osan Air Base, spanning a base year and four option periods from August 1, 2025 to January 31, 2031. The scope includes initial installation of surveillance systems on 45-passenger buses, involving digital video recorders (DVRs) and seven cameras per bus, along with bi-annual preventative maintenance, unscheduled corrective maintenance, and transition period camera removal services.
The contract structure anticipates potential student population growth, with a 3.5% inflation adjustment applied to the first option period. While the estimated unit prices and total contract value are currently listed as $0, the document indicates a phased approach with consistent service requirements across base and option years. The RFI is part of market research to identify potential sources capable of providing these bus surveillance services, with the goal of understanding market capabilities before formal solicitation. The procurement is being conducted by the DoDEA Procurement Office for the Pacific West Region, and respondents are advised that this RFI does not constitute a binding solicitation or guarantee future contract award.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFI Q and A.docx | DOCX document | |
| 25RE0XX_RFI.pdf | ||
| 25RE0XX_Attachment 1.pdf | ||
| 25RE0XX_Attachment 2.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Summary
| RFI - ROM | |
| DoDEA Pacific West South Korea | |
| OBVSS Contract | |
| Summary Base plus Option Periods | |
| Korea OBVSS Services | Projected Cost |
| Base Year | 0.00 |
| Option Period Year 1 | 0.00 |
| Option Period Year 2 | 0.00 |
| Option Period Year 3 | 0.00 |
| Option Period Year 4 | 0.00 |
| FAR 52.217-8 | 0.00 |
| Total | 0.00 |
2025 OBVSS Contract-Korea
| Please complete all yellow highlighted cells | |||||
| Korea OBVSS Contract: ROM | |||||
| Contract Line Item | POP/Supplies/Services | Estimated Unit Price | Qty. | Estimated Total Cost | Remark |
| Base Year | 8/1/2025 - 7/31/2026 | ||||
| CLIN 0001 | Initial Installation | ||||
| SLIN 0001AA | Initial Installation on 45-Pax buses | 42 | $0 | DVR + (7cameras/bus) + Installation | |
| CLIN 0002 | Maintenance | ||||
| SLIN 0002AA | Bi-annual preventative maintenance | 42 | $0 | ||
| SLIN 0002AB | Unscheduled corrective maintenance | 12 | $0 | ||
| SLIN 0002AC | Materials (additional/replacement hard drives, cables, & cameras) | 21 | $0 | ||
| CLIN 0003 | Transition Period | ||||
| SLIN 0003AA | Camera Removal | 42 | $0 | ||
| Total | $0 |
| 1st Option Period | 8/1/2026 - 7/31/2027 | |||
| CLIN 1001 | Initial Installation (3.5% inflation adjustment applied) | |||
| SLIN 1001AA | Initial Installation on 45-pax buses | 5 | $0 | Increase due to student population growth (longer military tours) |
| CLIN 1002 | Maintenance (3.5% inflation adjustment applied) | |||
| SLIN 1002AA | Bi-annual preventative maintenance | 42 | $0 | |
| SLIN 1002AB | Unscheduled corrective maintenance | 21 | $0 | |
| SLIN 1002AC | Materials (additional/replacement hard drives, cables, & cameras) | 21 | $0 | |
| CLIN 1003 | Transition Period | |||
| SLIN 1003AA | Camera Removal | 42 | $0 | |
| Total | $0 |
| 2nd Option Period | 8/1/2027 - 7/31/2028 | |||
| CLIN 2001 | Initial Installation | |||
| SLIN 2001AA | Initial Installation on 45-pax buses | 5 | $0 | Increase due to student population growth (longer military tours) |
| CLIN 2002 | Maintenance | |||
| SLIN 2002AA | Bi-annual preventative maintenance | 42 | $0 | |
| SLIN 2002AB | Unscheduled corrective maintenance | 21 | $0 | |
| SLIN 2002AC | Materials (additional/replacement hard drives, cables, & cameras) | 21 | $0 | |
| CLIN 2003 | Transition Period | |||
| SLIN 2003AA | Camera Removal | 42 | $0 | |
| Total | $0 |
| 3rd Option Period | 8/1/2028 - 7/31/2029 | |||
| CLIN 3001 | Initial Installation | |||
| SLIN 3001AA | Initial Installation on 45-pax buses | 5 | $0 | Increase due to student population growth (longer military tours) |
| CLIN 3002 | Maintenance | |||
| SLIN 3002AA | Bi-annual preventative maintenance | 42 | $0 | |
| SLIN 3002AB | Unscheduled corrective maintenance | 21 | $0 | |
| SLIN 3002AC | Materials (additional/replacement hard drives, cables, & cameras) | 21 | $0 | |
| CLIN 3003 | Transition Period | |||
| SLIN 3003AA | Camera Removal | 42 | $0 | |
| Total | $0 |
| 4th Option Period | 8/1/2029 - 7/31/2030 | |||
| CLIN 4001 | Initial Installation | |||
| SLIN 4001AA | Initial Installation on 45-pax buses | 5 | $0 | Increase due to student population growth (longer military tours) |
| CLIN 4002 | Maintenance | |||
| SLIN 4002AA | Bi-annual preventative maintenance | 42 | $0 | |
| SLIN 4002AB | Unscheduled corrective maintenance | 21 | $0 | |
| SLIN 4002AC | Materials (additional/replacement hard drives, cables, & cameras) | 21 | $0 | |
| CLIN 4003 | Transition Period | |||
| SLIN 4003AA | Camera Removal | 42 | $0 | |
| Total | $0 |
| FAR 52.217-8 | 8/1/2030 - 1/31/2031 | |||
| CLIN 4001 | Initial Installation | |||
| SLIN 4001AA | Initial Installation on 45-pax buses | 2 | $0 | Increase due to student population growth (longer military tours) |
| CLIN 4002 | Maintenance | |||
| SLIN 4002AA | Bi-annual preventative maintenance | 21 | $0 | |
| SLIN 4002AB | Unscheduled corrective maintenance | 11 | $0 | |
| SLIN 4002AC | Materials (additional/replacement hard drives, cables, & cameras) | 11 | $0 | |
| CLIN 4003 | Transition Period | |||
| SLIN 4003AA | Camera Removal | 42 | $0 | |
| Total | $0 | |||
| Total Contract | $0 |