This is a Project Description document outlining contractor responsibilities for interior renovation work. The contractor is responsible for prepping, painting, and replacing flooring systems in buildings specified in the project area descriptions, with all measurements to be field-verified on-site. The point of contact for building access will be provided in the project area descriptions section.
The facility will remain operational throughout the construction period, requiring the contractor to minimize interference with normal operations. The contractor is responsible for moving furniture and other room contents as necessary. Regarding project supervision, a single qualified individual may serve in the combined roles of Superintendent, Quality Control Manager, and Safety & Health Officer, provided they meet all qualification requirements as defined in the project specification.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJECT DESCRIPTION
The responsibility of the contractor is to prep, paint, and replace the flooring systems in the following buildings listed in the project area description / title according to the general requirements. All measurements are for reference only and are to be field verified by contractor. The point of contact for access to the building is listed below in the project area descriptions.
SPECIAL SCHEDULING
The facility/activity will remain in operation during the entire construction period. The Contractor shall conduct his operations so as to cause the least possible interference with normal operations of the facility/ activity. The furniture and other objects in the room are to be moved by the contractor.
SUPERVISION
One person may fill the roles of Superintendent, Quality Control Manager, and Safety & Health Officer, if duly qualified for all three positions as defined in the project specification.