25BA011 - Solicitation TechSpec.pdf
PDF 2 MB Posted
- Solicitation number
- W912EF25BA011
About this file
This is a solicitation for the Ice Harbor Dam Charbonneau Park Septic System Upgrades project, Contract Number W912EF25BA011, issued by the U.S. Army Corps of Engineers Walla Walla District. The project involves comprehensive upgrades to the septic system at Charbonneau Park, including installation of new precast concrete septic tanks, MicroFAST 3.0 treatment units, submersible pumps, electrical systems, and associated infrastructure. Key components include two 3,000-gallon surge tanks, one 3,000-gallon feed tank, multiple submersible pumps for marina, feed tank, and drain field, regenerative blowers, an alarm radio system, and electrical controls.
The solicitation covers detailed technical specifications for excavation, concrete work, piping, electrical systems, and installation requirements. The project mandates strict compliance with Washington State Department of Health regulations for large on-site sewage systems, requires licensed septic system contractors, and includes comprehensive testing and commissioning protocols. The work is to be performed during off-season recreational periods, with specific requirements for site access, environmental protection, safety procedures, and quality control. Contractors must provide extensive documentation, including operation and maintenance manuals, warranty information, and as-built drawings upon project completion.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
HLD - Charbonneau Park Septic System Upgrades W912EF25BA011
HLD518536CPSSUP
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00.00 28 GENERAL REQUIREMENTS
01 11 01.00 28 SUPPLEMENTARY REQUIREMENTS
01 14 00.10 28 PROJECT SITE RESTRICTIONS
01 14 00.90 28 INTEGRATING ANTITERRORISM (AT) AND OPERATIONS SECURITY
(OPSEC)
01 22 00.00 28 MEASUREMENT AND PAYMENT
01 32 16.00 28 SMALL PROJECT CONSTRUCTION PROGRESS SCHEDULES
01 33 00 SUBMITTAL PROCEDURES
01 35 29.10 28 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 01.00 28 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)
01 45 04.00 28 CONTRACTOR QUALITY CONTROL
01 51 00.00 28 TEMPORARY UTILITIES
01 55 10.00 28 CONTRACTOR WORK, ACCESS AND STORAGE AREAS
01 57 20.00 28 ENVIRONMENTAL PROTECTION
01 78 00.00 28 CLOSEOUT SUBMITTALS
01 78 23.00 28 OPERATION AND MAINTENANCE (O&M) DATA
01 91 00.00 28 SYSTEMS TESTING AND COMMISSIONING
DIVISION 03 - CONCRETE
03 50 00.00 28 MISCELLANEOUS CONCRETE
DIVISION 05 - METALS
05 05 20.00 28 POST-INSTALLED ANCHORS IN CONCRETE
DIVISION 22 - PLUMBING
22 13 29.00 28 SANITARY SEWERAGE PUMPS
DIVISION 25 - INTEGRATED AUTOMATION
25 05 11.00 28 CYBERSECURITY
DIVISION 26 - ELECTRICAL
26 05 19.00 28 INSULATED WIRE AND CABLE
26 08 00.00 28 APPARATUS INSPECTION AND TESTING
26 20 00.00 28 ELECTRICAL DISTRIBUTION SYSTEM
DIVISION 31 - EARTHWORK
31 23 00.00 28 EXCAVATION AND FILL
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 92 19.00 28 SEEDING
DIVISION 33 - UTILITIES
33 30 00.00 28 SANITARY SEWERAGE
-- End of Project Table of Contents --
Page 1PROJECT TABLE OF CONTENTS
THIS PAGE INTENTIONALLY LEFT BLANK
Page 2PROJECT TABLE OF CONTENTS
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 00 00.00 28
GENERAL REQUIREMENTS
PART 1 GENERAL
1.1 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS
CONTRACTS
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
-- End of Section Table of Contents --
SECTION 01 00 00.00 28 Page 1
SECTION 01 00 00.00 28 Page 2
SECTION 01 00 00.00 28
GENERAL REQUIREMENTS
PART 1 GENERAL
1.1 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS CONTRACTS
In addition to complying with the requirements outlined in FAR Part 22.13, FAR Provision 52.222-38, FAR Clause 52.222-35, FAR Clause 52.222-37, DFARS
222.13 and Department of Labor regulations, U.S. Army Corps of Engineers (USACE) contractors and subcontractors at all tiers are encouraged to promote the training and employment of U.S. veterans while performing under a USACE contract. While no set-aside, evaluation preference, or incentive applies to the solicitation or performance under the resultant contract, USACE contractors are encouraged to seek out highly qualified veterans to perform services under this contract. The following resources are available to assist USACE contractors in their outreach efforts:
Federal Veteran Employment Information https://www.opm.gov/fedshirevets/
Department of Labor Veterans Employment Assistance https://www.dol.gov/agencies/vets
Department of Veterans Affairs-VOW to Hire Heroes Act https://benefits.va.gov/vow/
Army Recovery Care Program -ht t ps: / / myar mybenef i t s. us. ar my. mi l / Benef i t - Li br ar y/ Feder al - Benef i t s/ Ar my- Recover y- Car e- Pr ogr am- ( ARCP) - ( f or mer l y- known- as- War r i or - Car e- and- Tr ansi t i on- Pr ogr am)
U.S. Chamber of Commerce Foundation-Hiring Our Heroes https://www.hiringourheroes.org/
Guide to Hiring Veterans - Reference Material https://www.dol.gov/sites/dolgov/files/VETS/files/Employer-Guide-to-Hiring-Veterans-20231101.pdf
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
-- End of Section --
SECTION 01 00 00.00 28 Page 3
SECTION 01 00 00.00 28 Page 4
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 11 01.00 28
SUPPLEMENTARY REQUIREMENTS
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.3 DEFINITIONS
1.4 DOCUMENT SUBMITTALS
1.5 FIELD VERIFICATION OF SITE CONDITIONS
1.6 Preconstruction ON-SITE INSPECTION
1.7 SUPPLEMENTAL DRAWINGS
1.8 REGULAR CLEANUP AND DEBRIS DISPOSAL
1.9 EQUIPMENT LIST
1.10 TESTING OF EQUIPMENT
1.11 DISPOSITION OF REMOVED MATERIALS AND EQUIPMENT
1.12 PROTECTION AND RESTORATION OF EXISTING FACILITIES
1.13 INSTALLATION SUPERVISOR
1.14 PROJECT OPERATORS' TRAINING
1.15 PROJECT TECHNICAL SUPPORT
1.16 PROJECT SUPERINTENDENT
1.17 KEY PERSONNEL SUBSTITUTION
1.18 POST AWARD MEETINGS
1.18.1 Pre-Work Meeting
1.18.2 Preconstruction Meeting
1.18.2.1 Minutes
1.18.2.2 Demobilizing And Remobilizing
1.18.3 RMS Orientation Meeting
1.19 WEEKLY PRODUCTION MEETINGS
1.19.1 Production Briefings
1.19.2 Construction Progress Photos
1.19.3 Minutes
1.20 ADDITIONAL MEETINGS
1.21 PARTNERING
1.21.1 General
1.21.2 Partnering Meetings
1.22 RED ZONE MEETING
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
ATTACHMENTS:
Weekly Meeting Agenda
SECTION 01 11 01.00 28 Page 1
SECTION 01 11 01.00 28 Page 2
SECTION 01 11 01.00 28
SUPPLEMENTARY REQUIREMENTS
PART 1 GENERAL
The work covered by this section of the specifications consists of work common to more than one section of these TECHNICAL SPECIFICATIONS.
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 Safety and Occupational Health Requirements
Comply with the current edition and all changes posted on the web as of the effective date of this solicitation.
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals having an "I" designation are for information only.
Designation following the "G" or "I" designation identifies the office that will review the submittal for the Government. Submit in accordance with SECTION 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Equipment List ; I, C
Preconstruction On-Site Inspection report ; I, C
Project Superintendent ; I, C
SD-07 Certificates
Installation Supervisor ; G, C
Key Personnel Substitution ; G, C
1.3 DEFINITIONS
a. Qualified Person.
As defined in EM 385-1-1 ; "DEFINITIONS", unless otherwise specified.
1.4 DOCUMENT SUBMITTALS
In addition to other specified submittal requirements, a copy of all documents submitted as part of work on this contract, shall be e-mailed to the Contracting Officer and submitted in Resident Management System
SECTION 01 11 01.00 28 Page 3
Contractor Mode (RMS CM). Include project contract number, title, and e-mail topic in all e-mail subject lines.
1.5 FIELD VERIFICATION OF SITE CONDITIONS
Field verify all elevations, dimensions, and coordinates of existing features indicated on the contract drawings that affect new construction.
Any variations must be updated as per SECTION 01 78 00.00 28 , CLOSEOUT SUBMITTALS, paragraphs WORKING AS-BUILT DRAWINGS.
1.6 Preconstruction ON-SITE INSPECTION
Prepare a Preconstruction On-Site Inspection report of existing conditions, prior to start of on-site work, with the Contracting Officer.
Document existing site conditions prior to Construction by digital photographs, and/or videos along with descriptive narrative report to the Contracting Officer within five (5) business days after completion of the inspection.
1.7 SUPPLEMENTAL DRAWINGS
a) A “Supplemental Drawings” packet is provided as part of this contract for information only and is not part of Contract work. These drawings are not available in CAD. These drawings depict the best estimate of existing components and equipment. The Government does not guarantee the accuracy of Supplemental Drawings.
b) Contractor shall verify accuracy of these drawings prior to use. Any errors or deficiencies arising from use of these drawings shall be the responsibility of the Contractor and corrected at no additional cost to the Government.
1.8 REGULAR CLEANUP AND DEBRIS DISPOSAL
With the exception of materials specifically indicated or specified to be salvaged for reuse in construction, or turned over to the Government, all wastes and demolished materials becomes the property of the Contractor and must be removed from the job site daily in accordance with Federal, State, and local regulations. The Contractor shall furnish waste containers. All small waste containers provided by the contractor must be emptied daily, large bin containers must be emptied when full or once a week.
1.9 EQUIPMENT LIST
Furnish a complete list of all equipment to be used on the Project 30 days prior to commencement of on-site work. Submit a revised list in the event of change of equipment. Lists shall include rented equipment as well as lease-purchase or sale-leaseback equipment. The initial list and the revised lists shall indicate dates equipment is assigned to or removed from the Project and adequate identification or description of each item of equipment including manufacturer's name (abbreviated), model number, manufacturer's serial number, year of manufacture, and Contractor's assigned serial or record number.
1.10 TESTING OF EQUIPMENT
Before any machinery or mechanized equipment is put to use on the job, it must be inspected and tested by a qualified person and determined to be in safe operating condition. Cranes or derricks must be tested by the
SECTION 01 11 01.00 28 Page 4
Contractor or a qualified testing agency in accordance with EM 385-1-1 .
Equipment must be large enough to safely handle proposed picks or tasks without exceeding the crane rating established by these tests.
1.11 DISPOSITION OF REMOVED MATERIALS AND EQUIPMENT
Unless otherwise specified in other sections of the specifications, all existing equipment removed and not reinstalled becomes the property of the Contractor, removed from the Project site, and disposed of in a legal manner. Materials that cannot be removed daily may be temporarily stored on-site at an approved area. Salvaged materials shall not be sold on the project site.
1.12 PROTECTION AND RESTORATION OF EXISTING FACILITIES
Reference FAR 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements (Apr 1984).
1.13 INSTALLATION SUPERVISOR
A representative of the Contractor who is technically qualified to supervise the installation, preparation, and testing of the septic system. The Installation Supervisor, or approved substitute, must be available at all times and is experienced in installing septic systems.
Approved substitute must have the same qualifications as the Installation Supervisor. The representative must report immediately in writing to the Contracting Officer any work not in accordance with the manufacturer's recommendation or any special conditions which may result in an unsatisfactory job. The representative must have supervised the installation of a septic system within the past 5 years. Installation supervisor's, and potential substitute's resumes must be submitted to the Contracting Officer.
1.14 PROJECT OPERATORS' TRAINING
Provide the services of one or more authorized individuals for Project Operators' training. Contractor personnel must be experienced in the operational requirements of all newly installed equipment, and control features. Provide a recommended maintenance job plan with step by step training to complete the job plan for each type of equipment. Contractor personnel must be present at the project and available for assistance for two (2), four hour work shifts immediately following Government acceptance of newly installed features. Required work shifts must be coordinated with the Contracting Officer.
1.15 PROJECT TECHNICAL SUPPORT
a. Provide 20 hours of project technical support after Government acceptance of the completed project. One or more Contractor personnel experienced in the operational requirements of all newly installed equipment, and control features must be available for Technical Support during normal Government Work Schedule hours. See paragraph "Government's Work Schedule" in SECTION 01 14 00.10 28 PROJECT SITE
RESTRICTIONS.
b. Support includes site visits by Contractor personnel. Contractor personnel must be available at the project within 48 hours, or the next normal Government Work Schedule day following notification by the Government - whichever is later. Technical support must be available
SECTION 01 11 01.00 28 Page 5 for 60 days following Government acceptance of the newly installed septic system, or until final Operation and Maintenance Manuals and Parts Catalogs have been approved and received by the Government -whichever is later. See SECTIONS 01 78 00.00 28 CLOSEOUT SUBMITTALS.
c. Technical Support shall include all contractor Supervision, Safety and QC personnel required to maintain proper control of work in accordance with contract requirements.
1.16 PROJECT SUPERINTENDENT
The Contractor's Project Superintendent must be on the worksite during performance of work on this contract. The Project Superintendent is required on the worksite, at all times work is being performed, until work on this contract is completed and accepted. Assign a competent superintendent as per FAR Clause 52.236-6 "Superintendence by the Contractor". Submit Superintendent name and contact information prior to start of on-site construction. The Project Superintendent may also be the Installation Supervisor as long as the Project Superintendent also meets the qualifications for the Installation Supervisor.
1.17 KEY PERSONNEL SUBSTITUTION
If the Contractor plans on replacing any Key personnel (Project Superintendent, Installation Supervisor, CQC System Manager, or CQC staff Members) they must have the approval of the Contracting Officer.
Personnel shall possess the qualifications that meet or exceed those stated in this contract for the position of the individual they are replacing. Submit qualifications of new personnel at least 15 calendar days in advance of date of replacement.
1.18 POST AWARD MEETINGS
1.18.1 Pre-Work Meeting
Within thirty (30) calendar days after receipt of Notice to Proceed , attend a Pre-Work Meeting. Senior Level members of the Contractor's staff involved with this contract shall participate in this meeting to discuss the overall contract requirements. The Government will lead this meeting and take the meeting minutes.
1.18.2 Preconstruction Meeting
Coordinate with the Contracting Officer and establish the date of the Preconstruction Meeting. The meeting will be held at the Project site at least one (1) week prior to mobilizing to the job site. The Contractor shall lead the Preconstruction Meeting discussing the Contractor's plan on executing the work at the project site, schedule, required clearances and timeframe for them, and plan for implementing safety and quality control.
The Government will have key members from the Project staff to discuss environmental and clearance issues. Key members of the contractor staff shall attend this meeting including the Quality Control (QC) System Manager, Site Safety and Health Officer (SSHO) and any other members determined by the Government to be required.
1.18.2.1 Minutes
Contractor is responsible for taking the meeting minutes and shall send them electronically within 48 hours of the meeting to the Government's
SECTION 01 11 01.00 28 Page 6
Project Engineer, Quality Assurance Representative, and Resident Engineer. Include project name and meeting topic in e-mail subject line.
1.18.2.2 Demobilizing And Remobilizing
Anytime the Contractor demobilizes from the site and remobilizes at a later date, another Preconstruction Meeting must be held following the requirements listed above.
1.18.3 RMS Orientation Meeting
a. Upon the Contractor's request, an RMS (Resident Management System) Orientation Meeting will be held within fifteen (15) calendar days after receipt of Notice to Proceed . See SECTION 01 45 01.00 28 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM) for additional information. The Orientation Meeting will be held at NWW District Headquarters, and may occur in conjunction with, but not at the same time as, the Pre-Work Meeting. The Orientation Meeting can also occur via video conference. Coordinate meeting date and time with the Contracting Officer a minimum of 7 calendar days prior to the meeting.
b. At a minimum, the Contractor's RMS-CM Administrator and QC system manager shall attend the RMS Orientation meeting. A Government Representative will lead the orientation. Anticipate the following at the meeting:
1. Allow for a maximum 4 hour duration.
2. Cover the following topics, at a minimum, in RMS Contractor Mode (CM):
i. Contractor use of RMS (CM) system.
ii. Contractor Data.
iii. Quality Control Reports.
iv. Submittals.
v. RFIs.
vi. Payment.
3. Receive a follow-up handout/guide for reference on the above items.
c. Contractor employees shall bring a computer with Wi-Fi capability (to gain access to the Internet), with RMS pre-loaded.
d. The RMS Orientation Meeting is required for Contractors with no prior RMS experience. The RMS Orientation Meeting, is optional, but may be requested, for all other Contractors.
e. The purpose of the RMS Orientation Meeting is to facilitate Contractor's use of RMS (CM). It does not relieve the Contractor of the requirement to use RMS (CM) in accordance with the Contract. See
SECTION 01 45 01.00 28 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE
(RMS CM), paragraph RMS SOFTWARE for information related to required download and installation deadlines.
SECTION 01 11 01.00 28 Page 7
1.19 WEEKLY PRODUCTION MEETINGS
1.19.1 Production Briefings
During all onsite construction work, hold a weekly production meeting to brief the Government on the status of the project.
a. Use the attached "Weekly Meeting Agenda" and discuss all elements of this agenda.
b. Provide a three (3) week 'look ahead'.
1. Describe all planned construction activities, on-site and off-site over the next three (3) weeks.
2. ENSURE these activities align to the overall Construction Schedule submitted under SECTION 01 32 16.00 28 SMALL PROJECT
CONSTRUCTION PROGRESS SCHEDULES.
3. RECORD any changes to the Project Schedule AND INCLUDE IN the next scheduled update.
c. Key members of the Contractor's staff including the Quality Control System Manager and the SITE SAFETY AND HEALTH OFFICER shall attend.
d. The Quality Control System Manager shall discuss all QC aspects outlined in SECTION 01 45 04.00 28 CONTRACTOR QUALITY CONTROL.
e. The Government reserves the right to require any person from the Contractor's staff such as the Project Manager, Engineer, Scheduler or Key Subcontractor Personnel to attend the meeting.
1.19.2 Construction Progress Photos
a. During on site construction activities record construction progress using weekly progress photographs. Submit digital photographs weekly for use at the WEEKLY PRODUCTION MEETING. Photographs provided are for unrestricted use by the Government.
1. Submit photos at the end of each work week.
2. Furnish digital photographs, Utilize JPEG file format for all photograph and image files.
3. Provide full-color photos with photo resolution of not less than 4 megapixels and not more than 12 megapixels. Photos shall show the sequence and progress of work.
4. Take a minimum of 20 digital photographs each week throughout the entire project.
b. Ensure that the photographs are digitally dated. A log must be furnished for each photograph that records the following information:
1. Photograph number (the specific format should be tied to the filename of the digital photograph).
2. Date the photograph was taken.
SECTION 01 11 01.00 28 Page 8
3. A brief description of the location, what the photograph depicts, and the orientation of the view.
1.19.3 Minutes
The Contractor is responsible for taking the meeting minutes and shall send them electronically within 24 hours of the meeting to the Government's Project Engineer, Quality Assurance Representative, and Resident Engineer. Include project name and meeting topic in e-mail subject line.
1.20 ADDITIONAL MEETINGS
Record the minutes of all meetings, including all conference calls, that occur between the Contractor and Government. Send minutes electronically within 24 hours of the meeting to the Contracting Officer for concurrence.
Include in the e-mail subject line the project: name, number and meeting topic, as noted in SECTION 01 33 00 SUBMITTAL PROCEDURES, paragraph
DIGITAL COPIES.
1.21 PARTNERING
1.21.1 General
The Government intends to encourage the foundation of a cohesive partnership with the Contractor and its subcontractors by informally partnering this contract. This partnership will be structured to draw on the strengths of each organization to identify and achieve reciprocal goals. The objectives are effective and efficient contract performance with the intent to achieve a safe completion of the work - within budget, on schedule, and in accordance with plans and specifications. This partnership would be bilateral in makeup and participation will be totally voluntary. If Partnering is pursued, meetings would be held as identified in the following paragraph.
1.21.2 Partnering Meetings
Within 30 calendar days of receipt of Notice to Proceed, the initial partnering meeting is scheduled if the meeting is requested by the Contractor. The Contractor's key personnel will attend a face-to-face partnering meeting (typically one day in duration) together with key Government personnel, to discuss project goals and communication.
Follow-up meetings will be held periodically, as required, throughout the duration of the contract, as agreed to by the Contractor and the Government. The Government will facilitate the meeting.
1.22 RED ZONE MEETING
Within one (1) month of completing the project or when the project is 80 percent completed, the Contractor shall set up and lead a Red Zone meeting. The Contractor shall contact the Contracting Officer to Schedule this meeting. The Government’s representative will include the Contracting Officer, key personnel from the Project, Project Engineer, Quality Assurance Representative, and Resident Engineer. The key people from the Contractor must be, at a minimum, the Project Superintendent, Quality Control System Manager, Scheduler, key subcontractors personnel, and Project Manager.
SECTION 01 11 01.00 28 Page 9
The purpose of this meeting is to develop an overall schedule for all activities required by both the Government and Contractor and to complete the project through commissioning and final acceptance. The Government will come prepared with all their activities, key dates, and durations for all work required by the Government to complete the project. The Contractor shall provide the same information for all of their activities. The Contractor’s scheduler shall input all of this information into the Contractor’s project schedule during the meeting.
This schedule must be updated weekly, or as needed, based on the information from the weekly production meetings for both the Government and Contractor activities.
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
SECTION 01 11 01.00 28 Page 10
Weekly Meeting agenda template
Schedule - Work scheduled over the next week Three week look ahead Overall Schedule Review
Submittals Review- Submittal Register Submittals approved by QC Outstanding Submittals RFI’s Letters
Coordination - Clearances required over the next week, include the following:
A description of the work to be performed under the Clearance.
Determine the correct energy isolation points needed to perform the work safely.
Physical barriers, protective grounds, piping blanks, or bulkheads that shall be used, including locations.
Determine the procedure and method of testing for stored energy if applicable.
The date and time the Clearance shall be required.
The estimated length of time the system or equipment shall be out of service and the time to return the system or equipment to service in an emergency.
Coordination issues
Safety- Review of AHA’s for ongoing work Pending AHA’s
Required for new work Status of Gov’t approval
Safety issues
QC -
Preparatory meetings Held over last week- status of meeting minutes
Required over the next week Initial meetings over the next week Follow up over the next week Rework list Review Deficiency tracking log
SECTION 01 11 01.00 28 Page 12
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 14 00.10 28
PROJECT SITE RESTRICTIONS
PART 1 GENERAL
1.1 REFERENCES
1.2 SITE CONDITIONS AND OPERATIONAL RESTRICTIONS
1.3 PROJECT SECURITY
1.3.1 Contractor Vehicle Access
1.3.2 Identification of Employees
1.4 DELIVERY OF EQUIPMENT
1.5 FACILITY OCCUPANCY CLOSURE
1.6 WORK SCHEDULES
1.6.1 Contractor's Work Schedule
1.6.2 Government's Work Schedule
1.7 USE OF WALLA WALLA DISTRICT PARKS
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
SECTION 01 14 00.10 28 Page 1
SECTION 01 14 00.10 28 Page 2
SECTION 01 14 00.10 28
PROJECT SITE RESTRICTIONS
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 Safety and Occupational Health Requirements
Comply with the current edition and all changes posted on the web as of the effective date of this solicitation.
1.2 SITE CONDITIONS AND OPERATIONAL RESTRICTIONS
A key, or combination will be provided to the Contractor to access the construction area within the park. Construction in the park is restricted to off-season recreational timeframes of the year. Coordinate with the Project personnel on access and work schedules.
1.3 PROJECT SECURITY
The project site location is in Charbonneau Park, which has a locked security gate and requires a key to access the work area during off-season times of the year.
1.3.1 Contractor Vehicle Access
Project site access road is on the south side of the Snake River.
Charbonneau Drive is the only road available to access the project site, and is open to the public during daylight hours. Only Contractor's work vehicles and equipment essential to the conduct of the work are allowed in the work areas. Display suitable permanent or temporary identification on all Contractor vehicles.
1.3.2 Identification of Employees
Every Contractor employee (prime or subcontractor) is required to have a hard hat meeting the requirements of EM 385-1-1 , and display the Prime Contractor's name, subcontractor's name, and the employee's name.
Contractor employee hard hats can not be white with red markings. It is the Project Superintendent's responsibility to enforce this requirement.
1.4 DELIVERY OF EQUIPMENT
The Contractor is responsible for delivery and receipt of all materials and equipment. Government personnel are not available to assist the Contractor with these activities.
SECTION 01 14 00.10 28 Page 3
1.5 FACILITY OCCUPANCY CLOSURE
Streets, walks, and other facilities occupied and used by the Government cannot be closed or obstructed without written permission from the Contracting Officer.
1.6 WORK SCHEDULES
1.6.1 Contractor's Work Schedule
At the Pre-Work Meeting, furnish a schedule of number of working days per week, shifts per day, and hours per shift for contract work. Furnish notification of any change of schedule of regular work hours, overtime work hours, and shifts of work crews and personnel at the site. Provide this notification a minimum of 48 hours prior to any schedule change to allow suitable scheduling of Government personnel and inspection.
Exception to this requirement may be allowed in case of schedule change due to emergency conditions.
1.6.2 Government's Work Schedule
a. The maintenance crews at the Park work from 6:30 a.m. to 5:00 p.m., Monday through Thursday. Crews and staff do not work on weekends and Federal holidays. If a Federal holiday falls on a Friday, the crews and staff do not work on the preceding Thursday.
b. If the Contractor requires Government support or assistance outside of normal work hours, the Contractor must make a formal written request to the Contracting Officer at least one week prior to the date that support/assistance is needed. The Government will review this request, but there is no guarantee that Government support or assistance can be provided.
1.7 USE OF WALLA WALLA DISTRICT PARKS
Special consideration for the use of the Walla Walla District Camping Grounds will not be given to the Contractor if camping at these sites.
The Contractor's crew may not use Government parking lots near Charbonneau Park for RV parking.
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
SECTION 01 14 00.10 28 Page 4
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 14 00.90 28
INTEGRATING ANTITERRORISM (AT) AND OPERATIONS SECURITY (OPSEC)
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.3 RESOURCES
1.4 GENERAL SECURITY REQUIREMENTS AND GUIDANCE
1.5 PHYSICAL SECURITY AND ACCESS CONTROL REQUIREMENTS
1.6 SUSPICIOUS ACTIVITY REPORTING TRAINING (e.g. iWATCH, CorpsWatch, or See Something, Say Something)
1.7 PRE-SCREEN CANDIDATES USING E-VERIFY PROGRAM
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
SECTION 01 14 00.90 28 Page 1
SECTION 01 14 00.90 28 Page 2
SECTION 01 14 00.90 28
INTEGRATING ANTITERRORISM (AT) AND OPERATIONS SECURITY (OPSEC)
PART 1 GENERAL
The work covered by this section of the specifications consists of work common to more than one section of these TECHNICAL SPECIFICATIONS. This contract does not require access to or handling of classified material.
This contract requires access to a restricted area during the off-season, but does not require access to sensitive information, or equipment.
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
FEDERAL ACQUISITION REGULATIONS (FAR)
FAR 52.222-54 Employment Eligibility Verification
FAR 22.18 Employment Eligibility Verification
Website for Federal Acquisition Regulation Supplement:
https://www.acquisition.gov/browse/index/far
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals having an "I" designation are for information only. The designation following the "G" or "I" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with SECTION 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Suspicious Activity Reporting ; G, C
Pre-Screen Candidates Using E-Verify Program ; G, C
1.3 RESOURCES
The following resources are accessible from the Walla Walla District (NWW) Public Website:
https://www.nww.usace.army.mil/Business-With-Us/Contracting/AT-OPSEC-for-Contractors/
a. Suspicious Activity Reporting Training (e.g. iWATCH, CorpsWatch, or See Something, Say Something).
b. E-Verify Program.
1.4 GENERAL SECURITY REQUIREMENTS AND GUIDANCE
a. The security requirements described in this SECTION apply to all
SECTION 01 14 00.90 28 Page 3 contractor personnel supporting the performance requirements of this contract. Contractor personnel includes employees of the prime Contractor ("Contractor") and all subcontractor employees. The Contractor is responsible for compliance with these security requirements. Questions regarding security matters shall be addressed to the Contracting Officer (KO).
b. The Department of Defense (DoD) and Army security training requirements specified in this SECTION, are performance requirements.
All contractor personnel shall complete initial training within 30 calendar days of contract Notice to Proceed , or the date new contractor personnel begin performance on the contract. Within five business days from the completion of training, the Contractor shall submit written documentation of completed training to the KO. The documentation shall include the names of contractor personnel trained, and which training they completed. The Contractor shall maintain training records as part of their contract files and be prepared to provide copies of training certificates to the KO.
c. Contractor personnel and vehicles are subject to search when entering federal installations. Additionally, all contractor personnel shall comply with Force Protection Condition (FPCON) measures, Random Antiterrorism Measures (commonly referred to as "RAMs"), and Health Protection Condition (HPCON) measures.
d. The Contractor is responsible for meeting performance requirements during elevated FPCON and/or HPCON levels in accordance with applicable Walla Walla District (NWW) plans and procedures. This includes identifying mission essential and non-mission essential personnel.
e. In addition to the changes otherwise authorized by the changes clause of this contract, should the FPCON or HPCON levels at any individual facility or installation change, the Government may implement security changes that affect contractor personnel. The Contractor shall ensure all contractor personnel are aware of their security responsibilities, including any site-specific requirements identified in local policies or procedures.
1.5 PHYSICAL SECURITY AND ACCESS CONTROL REQUIREMENTS
a. All contractor personnel requiring physical access to a federal installation or facility shall comply with the access control procedures of that location.
b. Contractor personnel requiring unescorted access to meet contract performance requirements on a DoD installation in the US shall be vetted by the installation/facility Provost Marshal/Directorate of Emergency Services/ Security Office using the National Crime Information Center-Interstate Identification Index (commonly referred to as "NCIC-III") and Terrorist Screening Database (commonly referred to as "TSDB"). Contractor personnel shall comply with all personal identity verification requirements specified in installation/facility policies and procedures.
c. Contractor personnel who do not meet requirements for unescorted access to USACE facilities shall coordinate escorted access with the KO, as needed. Coordinate escorted access with the KO a minimum of 14 calendar days prior to date of needed escort. Government escorts are
SECTION 01 14 00.90 28 Page 4 dependent upon availability of personnel. The Government is not responsible for impacts to Contractor work due to unavailability of Government escorts.
d. Contractor personnel who receive keys, access cards, or lock combinations that provide access to government-owned property shall comply with key and lock control procedures of NWW.
1.6 SUSPICIOUS ACTIVITY REPORTING TRAINING (e.g. iWATCH, CorpsWatch, or See Something, Say Something)
All onsite contractor personnel shall receive initial and annual refresher training on the local suspicious activity reporting program. This locally developed training provides contractor personnel with general information on suspicious behavior, and guidance on reporting suspicious activity to the project manager, security representative or law enforcement entity.
See paragraph RESOURCES for link to training.
1.7 PRE-SCREEN CANDIDATES USING E-VERIFY PROGRAM
a. Contractors shall comply with the requirements set forth in FAR 52.222-54 Employment Eligibility Verification and FAR 22.18 in using the E-Verify Program to meet the contract employment eligibility requirements. Contractors are encouraged to cooperate with Federal and State agencies responsible for enforcing labor requirements to include eligibility for employment under United States immigration laws in accordance with FAR 22.102-1(i). See paragraph RESOURCES for link to the E-Verify website.
b. An initial list of verified/eligible candidates shall be provided to the KO no later than three business days after receipt of Notice to Proceed . Submit pre-screening results to the KO via email as a password protected pdf file.
c. Submit updates to list of verified/eligible candidates within three business days of new verifications. The Contractor shall maintain a current list of verified/eligible employees as part of their contract files and provide copies to the KO upon request.
d. When contracts are with individuals, the individuals will be required to complete a Form I-9 , Employment Eligibility Verification, and submit it to the Contracting Officer to become part of the official contract file.
e. Contractors are encouraged to cooperate with federal and State agencies responsible for enforcing labor retirements to include eligibility for employment under United States Immigration laws in accordance with FAR 22.102-1 (i).
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
SECTION 01 14 00.90 28 Page 5
SECTION 01 14 00.90 28 Page 6
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 22 00.00 28
MEASUREMENT AND PAYMENT
PART 1 GENERAL
1.1 RETAINAGE OF PAYMENT
1.2 CLIN 0001 - CHARBONNEAU PARK SEPTIC SYSTEM UPGRADE
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
SECTION 01 22 00.00 28 Page 1
SECTION 01 22 00.00 28 Page 2
SECTION 01 22 00.00 28
MEASUREMENT AND PAYMENT
PART 1 GENERAL
In each instance, the contract price for an item shall constitute full compensation for furnishing all plant, labor, equipment, and materials, and for performing all operations required to complete the work included in the item as herein specified, or as otherwise approved.
1.1 RETAINAGE OF PAYMENT
Retainage in the amount of 10 percent of original contract award amount will be withheld until the final submittals, listed below, have been approved by the Government. The 10 percent retainage for final submittals will start once the Contractor has earned 90 percent of the original contract value. See SECTION 01 78 00.00 28 "CLOSEOUT SUBMITTALS" for additional information.
FINAL SUBMITTALS
a. Final Shop Drawings.
b. Final As-built Drawings.
c. Final Record Drawings.
d. Return of Government Issued Items.
e. Final Operation and Maintenance Manuals and Parts Catalogs.
f. Final Spare Parts submission (if applicable).
g. Complete all required training.
1.2 CLIN 0001 - CHARBONNEAU PARK SEPTIC SYSTEM UPGRADE
Charbonneau Park septic system upgrade is measured for payment as a complete pay item (JOB). Payment is made at the lump sum price for CLIN No. 0001, "CHARBONNEAU PARK SEPTIC SYSTEM UPGRADE," which price and payment is full compensation for all work required for the construction on the Septic system, complete, as specified and approved. Features included with this item includes, but not be limited to the following:
1. All material needed to construct the septic system per plans & specs.
2. All labor to install the septic system.
3. All machinery to install the septic system.
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
SECTION 01 22 00.00 28 Page 3
SECTION 01 22 00.00 28 Page 4
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 32 16.00 28
SMALL PROJECT CONSTRUCTION PROGRESS SCHEDULES
PART 1 GENERAL
1.1 SUBMITTALS
1.2 ACCEPTANCE
1.3 SCHEDULE FORMAT
1.3.1 Network Analysis Schedule (NAS)
1.3.1.1 Primavera P6 Settings and Parameters
1.3.1.2 Microsoft Project 2016 Settings and Parameters
1.3.1.3 Cost Loading Microsoft Project 2016 Schedules
1.3.2 Schedule Submittals and Procedures
1.4 SCHEDULE MONTHLY UPDATES
1.5 CONTRACT MODIFICATION
1.6 3-WEEK LOOK AHEAD SCHEDULE
1.7 CORRESPONDENCE AND TEST REPORTS:
1.8 ADDITIONAL SCHEDULING REQUIREMENTS
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
SECTION 01 32 16.00 28 Page 1
SECTION 01 32 16.00 28 Page 2
SECTION 01 32 16.00 28
SMALL PROJECT CONSTRUCTION PROGRESS SCHEDULES
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals having an "I" designation are for information only.
Designation following the "G" or "I" designation identifies the office that will review the submittal for the Government. Submit in accordance with SECTION 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Construction Schedule ; G, C
SD-07 Certificates
Monthly Updates ; G, C
1.2 ACCEPTANCE
a. Prior to the start of work, prepare and submit a Baseline construction schedule for acceptance. Schedule shall be in the form of a Network Analysis Schedule (NAS) in accordance with the terms in Contract Clause "FAR 52.236-15, Schedules for Construction Contracts," except as modified in this contract.
b. The Baseline Construction Schedule must be accepted prior to any of the following:
1. The Contractor starting work on the demolition or construction stage(s) of the contract.
2. Processing Contractor's invoice(s) for construction activities/items of work.
3. Review of any schedule updates.
c. Submittal of the Baseline Schedule, and subsequent schedule updates, is understood to be the Contractor's certification that the submitted schedule meets all of the requirements of the Contract Documents, represents the Contractor's plan on how the work will be accomplished, and accurately reflects the work that has been accomplished and how it was sequenced (as-built logic).
d. All Construction Schedules must be cost loaded. Cost load material, labor and equipment costs to their respective Construction Activities. Evenly disperse overhead and profit to each activity over the duration of the project. Cost loading must total to 100 percent of the value of the contract, and is required to process Contractor's invoice(s)
SECTION 01 32 16.00 28 Page 3
1.3 SCHEDULE FORMAT
1.3.1 Network Analysis Schedule (NAS)
Use the critical path method (CPM) to schedule and control project activities. Prepare and maintain project schedules using Primavera P6 or Microsoft Project 2016 . Importing data into the scheduling program using data conversion techniques or third party software is cause for rejection of the submitted schedule. Build the schedule as follows:
a. Show preconstruction submittals, Government review periods, material/equipment delivery, utility outages, all on-site construction, inspection, testing, and closeout activities. Government and Contractor on-site work activities must be driven by calendars that reflect Saturdays, Sundays and all Federal Holidays as non-work days.
b. With the exception of the Contract Award and End Contract milestone activities, no activities shall be open-ended. Each activity shall have predecessor and successor ties. No activity is to have open start, or open finish (dangling) logic. Minimize redundant logic ties. Once an activity exists on the schedule it is not to be deleted, or renamed to change the scope of the activity, and must not be removed from the schedule logic without approval from the Contracting Officer. While an activity cannot be deleted, where said activity is no longer applicable to the schedule but must remain within the logic stream for historical record, it can be changed to a milestone. Document any such change in the milestone's "Notebook", including a date and explanation for the change. The ID number for a deleted activity must not be re-used for another activity.
c. Each activity is to be assigned an appropriate Responsibility Code indicating responsibility to accomplish the work indicated by the activity, Phase Code and Work Location Code.
d. Date/time constraint(s) and/or lags, other than those required by the contract, are not allowed unless accepted by the Contracting Officer.
Include as the last activity in the contract schedule, a milestone activity named "Contract Completion Date".
1.3.1.1 Primavera P6 Settings and Parameters
Use the following Primavera P6 settings and parameters in preparing the Baseline Schedule. Deviation from these settings and parameters, without prior consent of the Contracting Officer, is cause for rejection of schedule submission.
a. General: Define or establish Calendars and Activity Codes at the "Project" level, not the "Global" level.
b. Admin Drop-Down Menu, Admin Preferences, Time Periods Tab:
(1) Set time periods for P6 to 8.0 Hours/Day, 40.0 Hours/Week, 172.0 Hours/Month and 2000.0 Hours/Year.
(2) Use assigned calendar to specify the number of work hours for each time period: Must be checked.
c. Project Level, Dates Tab:
SECTION 01 32 16.00 28 Page 4
(1) Set "Must Finish By" date to "Contract Completion Date".
d. Project Level, Defaults Tab:
(1) Duration Type: Set to "Fixed Duration & Units".
(2) Percent Complete Type: Set to "Physical".
(3) Activity Type: Set to "Task Dependent".
(4) Calendar: Set to "Standard 5 Day Workweek". Calendar must reflect Saturday, Sunday and all Federal holidays as non-work days.
Alternative calendars may be used with Contracting Officer approval.
e. Project Level, Calculations Tab:
(1) Activity percent complete based on activity steps: Must be Checked.
(2) Reset Remaining Duration and Units to Original: Must be Checked.
(3) Subtract Actual from At Completion: Must be Checked.
(4) Recalculate Actual units and Cost when duration percent(%) complete changes: Must be Checked.
(5) Link Actual to Date and Actual This Period Units and Cost: Must be Checked.
f. Project Level, Settings Tab:
(1) Define Critical Activities: Check "Total Float is less than or equal to" and add "0d".
g. No on-site construction activity may have durations in excess of 10 working days.
1.3.1.2 Microsoft Project 2016 Settings and Parameters
The Network must have a minimum of 30 construction activities. No on-site construction activity may have durations in excess of 10 working days.
1.3.1.3 Cost Loading Microsoft Project 2016 Schedules
Assign material, labor and equipment costs to their respective Construction Activities. Material and equipment costs for which payment will be requested in advance of installation must be assigned to their respective procurement activity (i.e. the material/equipment on-site activity). See paragraph ACCEPTANCE in this SECTION for additional Cost Loading requirements.
a. Submit an Earned Value Report with each schedule update showing activity budget, cost percent complete, earned amount and cost to complete as directed by the Contracting Officer.
b. With each schedule submission, provide a Schedule Variance control (SVC) diagram showing:
SECTION 01 32 16.00 28 Page 5
(1) Cash Flow S-Curves indicating planned project cost based on projected early and late activity finish dates.
(2) Earned Value to-date. Revise Cash Flow S-Curves when the contract is modified, or as directed by the Contracting Officer.
1.3.2 Schedule Submittals and Procedures
Submit Network Analysis Schedules (NAS) and updates in hard copy and on electronic media that is acceptable to the Contracting Officer. Submit an electronic back-up of the project schedule in an import format compatible with the Government's scheduling program.
1.4 SCHEDULE MONTHLY UPDATES
Update the Construction Schedule at monthly intervals, and when the schedule has been revised. The updated schedule must be kept current, reflecting actual activity progress and plan for completing the remaining work. Submit copies of purchase orders and confirmation of delivery dates as directed by the Contracting Officer.
a. Narrative Report: Provide with schedule updates. Identify and justify;
(1) Progress made in each area of the project
(2) Critical Path
(3) Date/time constraint(s), other than those required by the contract
(4) Changes in the following; added or deleted activities, original and remaining durations for activities that have not started, logic, milestones, planned sequence of operations, and critical path
(5) Status of Contract Completion Date and interim milestones;
(6) Current and anticipated delays (describe cause of delay and corrective actions(s) and mitigation measures to minimize);
(7) Description of current and future schedule problem areas.
Each entry in the narrative report must cite the respective Activity ID and Activity Description, the date and reason for the change, and description of the change.
1.5 CONTRACT MODIFICATION
Submit a Time Impact Analysis (TIA) with each cost and time proposal for a proposed change. TIA must illustrate the influence of each change or delay on the Contract Completion Date or milestones. No time extensions will be granted nor delay damages paid unless a delay occurs which consumes all available Project Float, and extends the Projected Finish beyond the Contract Completion Date.
a. Each TIA must be in both narrative and schedule form. The narrative must define the scope and conditions of the change; provide start and finish dates of impact, successor and predecessor activity to impact period, responsible party, describe how it originated, and how it impacts the schedule. The schedule submission must consist of three
SECTION 01 32 16.00 28 Page 6 native files:
(1) Fragnet used to define the scope of the changed condition
(2) Most recent accepted schedule update as of the time of the proposal or claim submission that has been updated to show all activity progress as of the time of the impact start date.
(3) The impacted schedule that has the fragnet inserted in the updated schedule and the schedule "run" so that the new completion date is determined.
b. For claimed as-built project delay, the inserted fragnet TIA method must be modified to account for as-built events known to occur after the data date of schedule update used.
c. All TIAs must include any mitigation, and must determine the apportionment of the overall delay assignable to each individual delay. The associated narrative must clearly describe the findings in a chronological listing beginning with the earliest delay event.
(1) Identify types of delays as follows:
(a) Excusable Delay: Force-Majeure (e.g. weather) - Contractor may receive time extension, but time will not be compensable.
(b) Inexcusable Delay: Contractor Responsibility - Contractor will not receive time extension.
(c) Compensable Delay: Government Responsibility - Contractor may receive compensable time extension.
(2) If a combination of any of the delay types outlined above occurs, it is considered a Concurrent Delay, which will require an analysis of the facts to determine compensability and entitlement to any time extension under the applicable contract clauses.
d. Submit Data disks containing the narrative and native schedule files.
e. Unless the Contracting Officer requests otherwise, only add conformed contract modifications into the Project NAS.
1.6 3-WEEK LOOK AHEAD SCHEDULE
Prepare and issue a 3-Week Look Ahead schedule to provide a more detailed day-to-day plan of upcoming work identified on the Construction Schedule.
Key the work plans to activity…