25-8421_Bid_Schedule.xlsx

XLSX spreadsheet 18 KB Posted

Attached to
BIG CYPRESS GOLF AND COUNTRY CLUB ESTATES OF NAPLES SECONDARY DRAINAGE IMPROVEMENTS AND WATER MAIN REPLACEMENT
Solicitation number
25-8421
Issued by
Collier County, Florida

About this file

The document is a Bid Schedule for Bid No. 25-8421, issued by Collier County, Florida, for secondary drainage system improvements and water main replacement at Big Cypress Golf & Country Club Estates and Country Club of Naples. The project covers a 170.50-acre area and includes multiple infrastructure elements such as removing and replacing driveways, culverts, roadside swales, cross drains, outfall piping, and roadway asphalt overlay. The bid schedule details 11 line items in Category No. 1 (Common Items), including mobilization, maintenance of traffic, sedimentation barriers, clearing and grubbing, and concrete removal. The non-mandatory pre-bid meeting is scheduled for September 11, 2025, at 10:00 a.m., with sealed bids due electronically by October 7, 2025, at 3:00 p.m. The project timeline requires substantial completion within 270 calendar days and final completion within 300 calendar days from the Notice to Proceed.

The anticipated project budget is $8,000,000.00, with liquidated damages of $3,813 per calendar day for failing to meet completion timelines. The project requires a 5% bid bond and comprehensive insurance coverage, with contractors responsible for coordinating with agencies like the South Florida Water Management District and City of Naples Utilities. The existing water main, consisting of asbestos cement (AC) pipe, will be replaced, necessitating special handling and disposal procedures. Work is restricted to 7:00 a.m. to 7:00 p.m., Monday through Friday, and the county will require performance and payment bonds for 100% of the contract amount. Bidders must comply with E-Verify requirements, immigration laws, and possess appropriate professional licensing for construction work in Florida.

View the file

Other files

File Type Posted
Construction_Bid_Instructions_Version_1.pdf PDF
25-8421_Bid_Schedule_R2.xlsx XLSX spreadsheet
25-8421_Solicitation_R1.pdf PDF
Water_Meter_Application.pdf PDF
25-8421_Interlocal_Agreement.pdf PDF
Construction_Services_Agreement_2025_Template_ver_3_with_Exhibits.pdf PDF
Construction_Bid_Instructions_Version_1.pdf PDF
25-8421_Bid_Schedule_R1.xlsx XLSX spreadsheet
25-8421_Solicitation_R1.pdf PDF
25-8421_Exhibit_M_-1_-_EOR_R.E._Brylanski_S&S.pdf PDF
PO_Terms_and_Conditions_Rev.3.pdf PDF
25-8421_Exhibit_N_-_EHS_Contractor_Requirements_Master_2021_rev.pdf PDF
25-8421_Exhibit_J_-_Technical_Specifications_S&S_10.7.pdf PDF
25-8421_Exhibit_M_-1_-_EOR_R.E._Brylanski_S&S.pdf PDF
25-8421_Exhibit_M_-_EOR_R.E._Brylanski_S&S.pdf PDF
25-8421_Exhibit_N_-_EHS_Contractor_Requirements_Master_2021_rev.pdf PDF
PO_Terms_and_Conditions_Rev.3.pdf PDF
25-8421_Exhibit_M_-_EOR_R.E._Brylanski_S&S.pdf PDF
25-8421_Solicitation_R1.pdf PDF
Construction_Bid_Instructions_Version_1.pdf PDF
Construction_Services_Agreement_2025_ver._3.pdf PDF
25-8421_Exhibit_N_-_EHS_Contractor_Requirements_Master_2021_rev.pdf PDF
25-8421_Exhibit_M_-_EOR_R.E._Brylanski_S&S.pdf PDF
25-8421_Exhibit_M_-1_-_EOR_R.E._Brylanski_S&S.pdf PDF
25-8421_Exhibit_J.pdf PDF
25-8421_Bid_Schedule.xlsx XLSX spreadsheet
25-8421_Authorization_to_Advertise_Final.pdf PDF
PO_Terms_and_Conditions_Rev.3.pdf PDF
Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Bid Form

Big Cypress Golf & Country Club Estates and Country Club of Naples
Secondary Drainage System Improvements and Water Main Replacement
BID SCHEDULE - AUGUST 2025
Item No.DescriptionUnitBid QuantityUnit PriceTotal Price
CATEGORY NO. 1 - COMMON ITEMS
101-1Mobilization/DemobilizationLS1$ - 0
102-1Maintenance of TrafficLS1$ - 0
102-99Portable Changeable Message SignEA2$ - 0
104-10-3Sedimentation BarrierLF1,200$ - 0
104-18Inlet Protection SystemEA26$ - 0
110-1-1Clearing & GrubbingAC7.73$ - 0
110-4-10Removal of Existing ConcreteSY3,169$ - 0
SP-1Pre and Post Construction VideoLS1$ - 0
SP-2Project SignEA2$ - 0
SP-3Record SurveyLS1$ - 0
Category No. 1 - Common Items Subtotal$ - 0
CATEGORY NO. 2 - DRAINAGE
425-1-521FDOT Type C Inlet, <10'EA4$ - 0
425-1-551FDOT Type E Inlet, <10'EA12$ - 0
425-3-61Junction Box, J-7, <10'EA5$ - 0
430-175-124Pipe Culvert, Optional Material, Round (24" RCP)LF98$ - 0
430-175-136Pipe Culvert, Optional Material, Round (36" RCP)LF38$ - 0
430-175-136APipe Culvert, Optional Material, Round (36" HDPE)LF330$ - 0
430-175-215Pipe Culvert, Optional Material, Ellip. (15" ERCP) 12x18LF2,710$ - 0
430-175-218Pipe Culvert, Optional Material, Ellip. (18" ERCP) 14x23LF854$ - 0
430-175-224Pipe Culvert,Optional Material, Ellip. (24" ERCP) 19x30LF1,182$ - 0
430-175-236Pipe Culvert, Optional Material, Ellip. (36" ECP) 29x45LF64$ - 0
430-536-100Straight Concrete Endwall, 36" Single, 0 Deg. RoundEA1$ - 0
430-536-202Straight Concrete Endwall, 36" Double, 0 Deg. Ellip.EA2$ - 0
430-601-123U-Type Concrete Endwall (12"x18")EA179$ - 0
430-601-125U-Type Concrete Endwall (14"x23")EA50$ - 0
430-601-129U-Type Concrete Endwall (19"x30")EA66$ - 0
SP-4Swale Regrading (Inclduing Cut & Fill)SY23,600$ - 0
SP-5Golf Course Interconnect, Site Work (Sheet 13)LS1$ - 0
SP-6Golf Course Interconnect, Site Work (Sheet 13A)LS1$ - 0
Category No. 2 - Drainage Subtotal$ - 0
CATEGORY NO. 3 - RESTORATION
110-7-1Mailbox, F&I SingleEA127$ - 0
121-70Flowable FillCY56$ - 0
210-2Limerock, New Material for Reworking Base (18")SY360$ - 0
334-1-12Superpave Asphaltic Concrete (SP-9.5)TN1,030$ - 0
334-1-13Superpave Asphaltic Concrete (SP-12.5)TN40$ - 0
522-2Concrete Sidewalk & Driveway, 6" ThickSY3,169$ - 0
530-3-4Riprap, Rubble, F&I, Ditch LiningTN54$ - 0
570-1-2Performance Turf, SodSY23,426$ - 0
SP-7Remove and Reset Paver DrivewaySY3,379$ - 0
Category No. 3 - Restoration Subtotal$ - 0
CATEGORY NO. 4 - SIGNAGE AND PAVEMENT MARKINGS
700-1-500Single Column Ground Sign Assembly, RelocateEA9$ - 0
711-11-125Thermoplactic, STD, White, Solid, 24"LF208$ - 0
711-11-123Thermoplactic, STD, White, Solid, 12"LF148$ - 0
711-15-201Thermoplactic, STD, Yellow, Solid 6"LF0.0947$ - 0
Category No. 4 - Signage and Pavement Markings Subtotal$ - 0
CATEGORY NO. 5 - WATER MAIN REPLACEMENT
16" PVC, DR-18, C900LF58
28" PVC, DR-14, C900LF146$ - 0
38" PVC, DR-18, C900LF2,848$ - 0
410" PVC, DR-14, C900LF84$ - 0
510" PVC, DR-18, C900LF5,132$ - 01
66" Gate Valve w/BoxEA2$ - 0
78" Gate Valve w/BoxEA12$ - 0
810" Gate Valve w/BoxEA9$ - 0
98x8x8 Cut In Tee w/ReducersEA2$ - 0
10Fire Hydrant Assembly w/6" Gate ValveEA15$ - 0
11Water Main ARVEA7$ - 0
126" & 8" Pipe RemovalLF765$ - 0
136" & 8" Pipe Grout and AbandonmentLF7,503$ - 0
14Miscellaneous Water Main AbandonmentLS1$ - 0
15Temporary Water Main Jumper/Final Connection
a. Burning Tree/Solana (Ph. 1)EA1$ - 0
b. Burning Tree/Cypress Point (Ph. 2)EA1$ - 0
c. Burning Tree/Cypress Point (Ph. 3)EA1$ - 0
d. North Gate/Mel Jen (Ph. 4)EA1$ - 0
16Flushing Port/TBSV/Final Connection
a. Burning Tree/Cypress Point (Ph. 1)EA1$ - 0
b. Burning Tree/Cypress Point (Ph. 2)EA1$ - 0
c. North Gate/Burning Tree (Ph. 3)EA1$ - 0
d. Burning Tree/Mel Jen (Ph. 4)EA1$ - 0
17Single Water Service (Short)EA55$ - 0
18Single Water Service (Long)EA52$ - 0
19Double Water Service (Short)EA14$ - 0
20Double Water Service (Long)EA16$ - 0
21Meter BoxesEA137$ - 0
22Additional 8" Water Main DeflectionEA4$ - 0
23Additional 10" Water Main DeflectionEA4$ - 0
24Relocate Existing Sewer LateralLS1$ - 0
25Exist. Sewer Service AdjustmentsEA6$ - 0
26Additional Sewer Clean Out AssemblyEA3$ - 0
27Additional Sewer Lateral PipingLF100$ - 0
Category No. 5 - Water Main Replacement Subtotal$ - 0
BID SUMMARY
Category No. 1 - Common Items Subtotal$ - 0
Category No. 2 - Drainage Subtotal$ - 0
Category No. 3 - Restoration Subtotal$ - 0
Category No. 4 - Signage and Pavement Markings Subtotal$ - 0
Category No. 5 - Water Main Replacement Subtotal$ - 0
Total Bid Amount$ - 0
County Staff has allocated a total of 10% in Owner's Allowance for Owner's Use as Directed. This Allowance will be used only at the Owner's direction to accomplish work due to unforeseen conditions and/or as directed by the Owner. Inclusion of the Allowance as part of the Contract Price is not a guarantee that the Contractor will be paid any portion or the full amount of the Allowance. Expenditures of Owner's Allowance will be made through Change Order with proper documentation of Time and Materials supporting the change.