25-8421_Exhibit_M_-_EOR_R.E._Brylanski_S&S.pdf

PDF 87 MB Posted

Attached to
BIG CYPRESS GOLF AND COUNTRY CLUB ESTATES OF NAPLES SECONDARY DRAINAGE IMPROVEMENTS AND WATER MAIN REPLACEMENT
Solicitation number
25-8421
Issued by
Collier County, Florida

About this file

This is an Engineer's Opinion and Recommendation (EOR) document from R.E. Brylanski supporting a sealed bid solicitation by Collier County, Florida for Bid No. 25-8421, covering secondary drainage improvements and water main replacement in the Big Cypress Golf & Country Club residential areas and the adjacent Country Club of Naples golf course. The project encompasses infrastructure work across a 170.50-acre area, including removal and replacement of existing driveways, culverts, roadside swales, cross drains, outfall piping, and roadway asphalt overlay, along with construction of a new water main with associated components such as valves, fire hydrants, water services, and meter boxes. The existing water main consists of asbestos cement (AC) pipe requiring special handling and disposal procedures. Sealed bids are due electronically by October 7, 2025, at 3:00 p.m., with a non-mandatory pre-bid meeting scheduled for September 11, 2025, at 10:00 a.m. at the Collier County Procurement Services Conference Room. The project timeline requires substantial completion within 270 calendar days and final completion within 300 calendar days from the Notice to Proceed, with work hours restricted to 7:00 a.m. to 7:00 p.m., Monday through Friday.

The project budget is established at $8,000,000.00, with the county assessing liquidated damages of $3,813 per calendar day for failure to achieve substantial completion within the specified timeframe. Bidders must provide a 5% bid bond and performance and payment bonds for 100% of the contract amount, along with comprehensive insurance coverage and demonstration of E-Verify compliance and appropriate Florida professional licensing. No specific set-aside designations for disadvantaged enterprises are identified in the documentation. Contractors will be responsible for coordinating with multiple agencies, including the South Florida Water Management District and City of Naples Utilities, and must adhere to strict environmental, health, and safety requirements. Prospective bidders must register on the Collier County online procurement portal at https://procurement.opengov.com/portal/collier-county-fl to access the complete bid documents.

View the file

Other files

File Type Posted
Construction_Bid_Instructions_Version_1.pdf PDF
25-8421_Bid_Schedule_R2.xlsx XLSX spreadsheet
25-8421_Solicitation_R1.pdf PDF
Water_Meter_Application.pdf PDF
25-8421_Interlocal_Agreement.pdf PDF
Construction_Services_Agreement_2025_Template_ver_3_with_Exhibits.pdf PDF
Construction_Bid_Instructions_Version_1.pdf PDF
25-8421_Bid_Schedule_R1.xlsx XLSX spreadsheet
25-8421_Solicitation_R1.pdf PDF
25-8421_Exhibit_M_-1_-_EOR_R.E._Brylanski_S&S.pdf PDF
PO_Terms_and_Conditions_Rev.3.pdf PDF
25-8421_Exhibit_N_-_EHS_Contractor_Requirements_Master_2021_rev.pdf PDF
25-8421_Exhibit_J_-_Technical_Specifications_S&S_10.7.pdf PDF
25-8421_Exhibit_M_-1_-_EOR_R.E._Brylanski_S&S.pdf PDF
25-8421_Exhibit_M_-_EOR_R.E._Brylanski_S&S.pdf PDF
25-8421_Exhibit_N_-_EHS_Contractor_Requirements_Master_2021_rev.pdf PDF
PO_Terms_and_Conditions_Rev.3.pdf PDF
25-8421_Solicitation_R1.pdf PDF
Construction_Bid_Instructions_Version_1.pdf PDF
Construction_Services_Agreement_2025_ver._3.pdf PDF
25-8421_Exhibit_N_-_EHS_Contractor_Requirements_Master_2021_rev.pdf PDF
25-8421_Exhibit_M_-_EOR_R.E._Brylanski_S&S.pdf PDF
25-8421_Exhibit_M_-1_-_EOR_R.E._Brylanski_S&S.pdf PDF
25-8421_Exhibit_J.pdf PDF
25-8421_Bid_Schedule.xlsx XLSX spreadsheet
25-8421_Authorization_to_Advertise_Final.pdf PDF
PO_Terms_and_Conditions_Rev.3.pdf PDF
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .