25-8409_Bid_Schedule.xlsx
XLSX spreadsheet 14 KB Posted
- Attached to
- South County Water Reclamation Facility Preliminary Treatment Influent Screens Replacement
- Solicitation number
- 25-8409
- Issued by
- Collier County, Florida
About this file
The document is a Bid Schedule for Collier County Public Utilities' South County Water Reclamation Facility (SCWRF) Preliminary Treatment Screen Replacement project in Naples, Florida. The bid covers a comprehensive infrastructure upgrade involving the complete replacement of existing influent screens, with work divided into five sections: General Conditions, Demolition, Influent Screens Installation, Gate/Stop Log/Actuator Installation, and New Decking Installation. The project requires electronic bid submission by October 17, 2025, at 3:00 P.M. local time, with a non-mandatory pre-bid conference and site visit scheduled for September 17, 2025. The total project scope includes demolishing existing screens, installing new Multi-Rake Bar Screens and Wash and Press units, replacing channel gates, modifying electrical systems, and performing associated structural modifications.
The anticipated project budget is $3,214,000, with contractors required to complete substantial work within 600 calendar days and final completion within 30 calendar days after punch list delivery. Liquidated damages of $1,071.33 per calendar day will be assessed for timeline delays. Bidders must possess a Florida Underground Utility or General Contractor license and a Florida Licensed Electrical Contractor certification. An additional 10% Owner's Allowance is included for unforeseen conditions, which can be utilized through documented change orders. The project requires integration with the facility's existing SCADA system, PLC controls, and fiber optic communications, necessitating careful coordination with Collier County Water-Sewer District staff to minimize disruption to ongoing wastewater treatment processes.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BID TAB
| COLLIER COUNTY PUBIC UTILITIES | |||||
| SCWRF - PRELIMINARY TREATMENT SCREEN REPLACEMENT | |||||
| BID TABULATION | |||||
| SECTION 1 - GENERAL CONDITIONS | |||||
| ITEM NO. | DESCRIPTION | QUANTITY | UNIT | UNIT PRICE | EXTENDED PRICE |
| 1 | Mobilization/Demobilization | 1 | LS | $0.00 | |
| 2 | Preconstruction Audio/Video Recording | 1 | LS | $0.00 | |
| 3 | Survey Layout and Record Survey | 1 | LS | $0.00 | |
| 4 | Flow Bypass | 1 | LS | $0.00 | |
| SECTION 1 SUBTOTAL | $0.00 | ||||
| SECTION 2 - DEMOLITION | |||||
| ITEM NO. | DESCRIPTION | QUANTITY | UNIT | UNIT PRICE | EXTENDED PRICE |
| 5 | Existing Influent Screen Demolition | 1 | LS | $0.00 | |
| 6 | Existing Electrical Component Demolition | 1 | LS | $0.00 | |
| 7 | Existing Gate and Actuator Demolition | 1 | LS | $0.00 | |
| 8 | Existing Aluminum Decking Demolition | 1 | LS | $0.00 | |
| SECTION 2 - SUBTOTAL | $0.00 | ||||
| SECTION 3 - INFLUENT SCREENS INSTALLATION | |||||
| ITEM NO. | DESCRIPTION | QUANTITY | UNIT | UNIT PRICE | EXTENDED PRICE |
| 9 | Furnish and Install Influent Screens, Electrical Panels and Wash Presses | 1 | LS | $0.00 | |
| 10 | Furnish and Install Drop Chutes | 1 | LS | $0.00 | |
| 11 | Furnish and Install Level Sensors | 1 | LS | $0.00 | |
| 12 | Furnish and Install New Electrical Components | 1 | LS | $0.00 | |
| 13 | Screens Startup and Testing | 1 | LS | $0.00 | |
| 14 | Screens Electrical and Telemetry Startup and Testing | 1 | LS | $0.00 | |
| SECTION 3 - SUBTOTAL | $0.00 | ||||
| SECTION 4 - GATE, STOP LOG & ACTUATOR INSTALLATION | |||||
| ITEM NO. | DESCRIPTION | QUANTITY | UNIT | UNIT PRICE | EXTENDED PRICE |
| 15 | Furnish and Install New Channel Mounted Slide Gates | 1 | LS | $0.00 | |
| 16 | Furnish and Install New Actuators | 1 | LS | $0.00 | |
| 17 | Gate and Actuator Startup and Testing | 1 | LS | $0.00 | |
| 18 | Furnish and Install New Stainless Steel Stop Logs | 1 | LS | $0.00 | |
| SECTION 4 - SUBTOTAL | $0.00 | ||||
| SECTION 5 - NEW DECKING INSTALLATION | |||||
| ITEM NO. | DESCRIPTION | QUANTITY | UNIT | UNIT PRICE | EXTENDED PRICE |
| 19 | Furnish and Install New Aluminum Decking and Modifications | 950 | SF | $0.00 | |
| SECTION 5 - SUBTOTAL | $0.00 | ||||
| COST SUMMARY | |||||
| SECTION 1 - GENERAL CONDITIONS | $0.00 | ||||
| SECTION 2 - DEMOLITION | $0.00 | ||||
| SECTION 3 - INFLUENT SCREENS INSTALLATION | $0.00 | ||||
| SECTION 4 - GATE, STOP LOG & ACTUATOR INSTALLATION | $0.00 | ||||
| SECTION 5 - NEW DECKING INSTALLATION | $0.00 | ||||
| CONSTRUCTION TOTAL | $0.00 |
20 *Owners Allowance T&M 1 $0 $0
* Staff has allocated ten percent (10%) of the total items 1-19 in Owner’s Allowance – for Owners Use as Directed. This Allowance will be used only at the Owner’s direction to accomplish work due to unforeseen conditions and/or by the Owner. Inclusion of the Allowance as part of the Contract Price is not a guarantee that the Contractor will be paid any portion or the full amount of the Allowance. Expenditures of Owners Allowance will be made through Change Order with proper documentation of Time and Materials supporting the change.