The document is a Bid Schedule for Bid No. 25-8378, issued by Collier County, Florida, for the Sun-N-Fun Interactive Water Features Renovations project. The solicitation seeks sealed bids for a comprehensive renovation of existing interactive water features, with a non-mandatory pre-bid meeting scheduled for May 28, 2025, at 11:00 a.m. at Sun-N-Fun Lagoon in Naples, FL. The bid response deadline is June 26, 2025, at 3:00 p.m. local time. The project scope includes demolition of existing infrastructure, installation of new concrete slabs, collector tanks, pumps, UV units, flow meters, autofill systems, and electrical components. The bid schedule outlines 17 base bid items and one alternate item (Life Floor tile installation), with work to be completed as a lump sum (LS) for each specified task.
The bid schedule indicates an owner's allowance of $83,000 for unforeseen conditions or owner-directed work, which will be distributed through change orders with proper documentation. Prospective bidders are required to register on the Collier County procurement portal to access complete bidding documents. The bid schedule shows all line items currently priced at $0, suggesting that bidders will need to fill in their specific pricing. Electrical work, including bonding, grounding, and powering new equipment, is integrated into the project scope. The project appears to be a comprehensive renovation of existing interactive water features, with a focus on infrastructure upgrades, equipment replacement, and electrical system improvements.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Sun-N-Fun Interactive Water Features Renovations | |||||
| Construction ITB No. 25-8378 | |||||
| Bid Schedule | |||||
| Item No. | Description | QTY | Unit | Unit Cost | Total Cost |
| 1 | Mobilization/Aquatic Supervision/General Conditions | 1 | LS | $ - 0 | $ - 0 |
| 2 | Demo of 2 existing fiberglass collector tanks and partial pipe demo | 1 | LS | $ - 0 | $ - 0 |
| 3 | Selective demo of existing IWF slab for new features | 1 | LS | $ - 0 | $ - 0 |
| 4 | Demo of 2 existing pumps, plus strainer and pipe/pipe fitting removal | 2 | LS | $ - 0 | $ - 0 |
| 5 | Supply of new features from vendor | 1 | LS | $ - 0 | $ - 0 |
| 6 | Installation of new concrete slab for IWF | 1 | LS | $ - 0 | $ - 0 |
| 7 | Broom finish new concrete to match existing finish | 1 | LS | $ - 0 | $ - 0 |
| 8 | Installation of new concrete collector tank | 1 | LS | $ - 0 | $ - 0 |
| 9 | Reinstall piping as detailed to new collector tank | 1 | LS | $ - 0 | $ - 0 |
| 10 | Furnish/installation of 2 new pumps and all piping, reducers, and strainers | 2 | LS | $ - 0 | $ - 0 |
| 11 | Furnish/installation of new UV unit, control panel, and piping | 1 | LS | $ - 0 | $ - 0 |
| 12 | Furnish/installation of new flow meters, display, and power supply | 1 | LS | $ - 0 | $ - 0 |
| 13 | Furnish/installation of new autofill system | 1 | LS | $ - 0 | $ - 0 |
| 14 | Disconnect bonding to existing features/collector tanks as noted (Electrical) | 1 | LS | $ - 0 | $ - 0 |
| 15 | Bond/ground new collector tank, pool concrete, and features (Electrical) | 1 | LS | $ - 0 | $ - 0 |
| 16 | Furnish/installation of new VFD's for pumps P1E & P2E (Electrical) | 2 | LS | $ - 0 | $ - 0 |
| 17 | Power all new pool equipment, plus bonding/grounding | 1 | LS | $ - 0 | $ - 0 |
| PROJECT BASE BID - SUBTOTAL COST | $ - 0 | ||||
| 18 | Supply & installation of 3/8" thick Life Floor tiles - ALTERNATE | 1 | LS | $ - 0 | $ - 0 |
| ALTERNATE LIFE FLOOR - SUBTOTAL COST | $ - 0 |
PROJECT BASE BID + ALTERNATE- SUBTOTAL ALL TRADES $ - 0
Staff has allocated $83,000 in Owner's Allowance - for Owners Use as Directed. This Allowance will be used only at the Owner's direction to accomplish work due to unforeseen conditions and/or as directed by the Owner. Inclusion of the Allowance as part of the Contract Price is not a guarantee that the Contractor will be paid any portion or the full amount of the Allowance. Expenditures of Owners Allowance will be made through Change Order with proper documentation of Time and Materials supporting the change.