25-3-12 Time Line Deliverable.docx

DOCX document 28 KB Posted

Attached to
Deburring System Federal contract opportunity
Solicitation number
W519TC25QA010
Issued by
Department of the Army Materiel Command Contracting Command Rock Island Arsenal

About this file

The document is a timeline deliverable for a federal contract opportunity at Rock Island Arsenal, detailing a project (RIPD E4000-25-3-12) for acquiring a Deburring Machine and Metallographic Cut Saw for a laboratory. The timeline outlines key milestones from contract award, including equipment delivery within 210 days, manual submission within 30 days, installation within 14 days after delivery, training within 14 days of installation, and final acceptance within 7 days of training. The total maximum time from contract award to acceptance is 245 days, with the solicitation (W519TC25QA010) specifically targeting small businesses for procurement of deburring machines in support of the Rock Island Arsenal Joint Manufacturing and Technology Center (RIA-JMTC). The Army Contracting Command - Rock Island (ACC-RI) maintains discretion to award or not award the contract based on responses received.

View the file

Other files for this federal contract opportunity

Other files attached to Deburring System, newest first.
File Type Posted
Contractor Questions and Government Answers v5.xlsx XLSX spreadsheet
Contractor Questions and Government Answers v4.xlsx XLSX spreadsheet
B08 Contract Questions and Government Answers v2 and v3.xlsx XLSX spreadsheet
Contractor Questions and Government Answers.xlsx XLSX spreadsheet
25-3-12 CDRL- Deburring System.docx DOCX document
25-3-12 Evaluation Criteria.docx DOCX document
RIPD E4000-25-3-12 Deburring System rev2.docx DOCX document
Solicitation - W519TC25QA010.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ROCK ISLAND ARSENAL DATE: 22 April 2025

PROJECT: RIPD E4000-25-3-12

TIMELINE OF DELIVERIES

Deburring Machine(s)

The following proposed timeline for Project RIPD E4000-25-3-12 is based upon the contract award date and the number of calendar days between events. Time allocations are maximums for each stage. It is acceptable to complete a stage in fewer days than shown on the timeline and move on to the next stage.

The timeline for this project is as follows:

· Contract AwardContract Award
· Equipment DeliveryContract Award + 210 Days
· ManualsContract Award + 30 Days
· Equipment InstallationEquipment Delivery + 14 Days
· Training (Operator, Maintenance)Equipment Installation + 14 Days
· Final AcceptanceTraining + 7 Days

Total Maximum Time from Award to Acceptance Contract Award + 245-days

Metallographic Cut Saw for Lab in support of AM