Statement of Work Summary

This is a Design-Build Statement of Work for Project QUUG 25-1008 prepared by KBR Services LLC for the Department of the Air Force at Morón Air Base, Spain. The project encompasses the replacement of outdated permanent emergency generators and Automatic Transfer Switches (ATS) at the Base Power Plant (Building #212) and the Sewage Treatment Plant (Building #1215). The total performance period is 730 calendar days, including design, preconstruction, construction, and finishing activities, with phased design reviews at 35%, 65%, 95%, and 100% completion milestones.

The scope of work includes design and construction of two permanent diesel engine-generator sets with ATS and bypass/isolation switches, new electrical distribution systems, and related infrastructure. For Building #212, the contractor must provide a new EPA-compliant generator rated at minimum 200 kW, new 4-pole ATS, main distribution panel replacement, grounding systems, and exterior flashing beacon installation. For Building #1215, the work includes a new 100 kW generator, high-voltage switchgear, transformer, low-voltage panelboard housed in a pre-manufactured concrete utility vault, underground high-voltage distribution system (replacing overhead lines), new ductbanks and manholes, and LED lighting for the vault. The project requires compliance with Spanish, US, and NATO regulations; incorporation of environmental protections including stormwater pollution prevention planning; training of government personnel in equipment operation and maintenance; and delivery of comprehensive as-built drawings and spatial data. All design must be performed by a certified A-E firm, with detailed specifications, calculations, and cost estimates provided at each design review stage. Generators are specified as Cummins Power Generation models (C200D6D for Building #212 and C100D6C for Building #1215) due to sole-source requirements, and ATS units must be Cummins Power Generation OTECC or higher-capacity equivalent models, also on a sole-source basis.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PREPARED FOR

DEPARTMENT OF THE AIR FORCE

BY

KBR SERVICES LLC SUCURSAL EN ESPAÑA

496TH AIR BASE SQUADRON

ENGINEERING DESIGN SECTION

MORÓN AIR BASE, SPAIN

DESIGN-BUILD STATEMENT OF WORK (SOW) FOR:

PROJECT QUUG 25-1008, RPR SEWER AND POWER PLANT GENSET & ATS, MULTI

Prepared by: __________________________________________________________________

Reviewed by: _________________________________________________________________

Approved by: _________________________________________________________________

PAGE INTENTIONALLY LEFT BLANK

INDEX OF CONTENTS

PART 1 GENERAL PROJECT DESCRIPTION

PART 2 PROJECT OBJECTIVES

PART 3 SCOPE

PART 4 DESIGN REQUIREMENTS

PART 5 PERFORMANCE TECHNICAL SPECIFICATIONS

PART 6 CONCEPT AND RECORD DRAWINGS (Separate file)

PART 7 PHOTOS

PART 8 SCHEDULE OF MATERIAL SUBMITTALS (Separate file)

PART 9 LIST OF SPECIFIC DESIGN CRITERIA

PART 10 SPECIAL CONDITIONS

PART 11 GENERAL CONDITIONS

PART 12 SMALL PROJECT DESIGN-BUILD PROGRESS SCHEDULES

ATTACHMENT A INTEGRATED NATURAL RESOURCES MANAGEMENT PLAN FOR

MORÓN AIR BASE

ATTACHMENT B FINAL GOVERNING STANDARDS FOR SPAIN, MAY 2014

ATTACHMENT C ARCHITECTURAL COMPATIBILITY PLAN

PART 1 - GENERAL PROJECT DESCRIPTION

1. This project is intended to replace the outdated permanent emergency generators and Automatic Transfer Switches (ATS) at the Base Power Plant (Bldg #212) and the Sewage Treatment Plant (bldg. #1215) of Morón AB (Spain).

2. Building #212 is located in the central area of the base, with main entrance in C Av, and located between B Av, C Av and 4th St.

3. Building #1215 is located in the North area of the base, with main entrance in Sewage Treatment Plant Access Rd.

4. Building #212 was constructed in 1,956, and the emergency generator was installed around 2,014 under Work Order #12187.

5. Building #1215 was constructed in 1,956, and the emergency generator was installed around 2,000, under Work order #98103.

PART 2 - PROJECT OBJECTIVES

1. Provide a complete and fully operational facility/ies for the base needs in compliance with all applicable US, Spanish and NATO codes.

2. Incorporate in the project all the measures that can be foreseen to minimize the total power outage/s time required for project execution.

3. Provide an installation that incorporates maintainability and sustainable design principles.

4. Energy efficiency shall be incorporated into the design principles.

5. Provide a completed project with coordinated systems (structural, mechanical, civil and other applicable disciplines, if required).

6. Provide a complete project considering the ecological, physical and visual features of the site.

7. Project shall incorporate all necessary safety precautions in accordance with applicable safety standards.

8. Include proper training of Government personnel in the Operation and Maintenance (O&M) of new equipment installed, and provide fully developed O&M packages.

9. Low maintenance and non-use of hazardous substances are of primary importance.

10. Project shall incorporate a Stormwater Pollution Prevention Plan (SWPPP) describing all the construction site operator’s activities to prevent stormwater contamination, control sedimentation and erosion, and comply with the legally binding requirements.

PART 3 - SCOPE

1. GENERAL: The work covered by this Statement of Work (SOW) consists in the design and build of the project, performing all necessary travels and furnishing all professional services, facilities, labor, equipment, materials, plants, transportation, specifications, detailed drawings and cost estimates that enable the Contractor to construct a complete and usable facility under a firm fixed price contract. The Contractor shall investigate site conditions, perform topographic surveys (geographic information system) at each facility and utilize manufacturer’s standard installation plans, specifications and drawings to the maximum extent feasible in developing the final design documentation necessary for obtaining Government approval. Any design change suggested by the Contractor to the SOW requires the approval of the Contracting Officer before its acceptance is given. The Contractor shall be responsible for the temporary markings, signs, markers and lights at the area affected by the construction and, if required, shall provide the flagmen, escorts and foreign object debris controllers during the work hours.

2. WORK DESCRIPTION: The construction works consist of, but are not limited to, the items indicated below, including the testing to be performed by independent laboratories for quality control. All items do not limit or reduce the Contractor’s responsibility to design and build all works as required by the project in order to provide a complete, operational and low-maintenance facility.

2.1. The project consists only of a basic package that includes the design and construction works to install an emergency generator with ATS and BP/IS to provide emergency power supply to the Base Power Plant located in Bldg #212, and to install an emergency generator with ATS and BP/IS enclosed in a new transformer vault to provide emergency power supply to the Sewage Treatment Plant located in Bldg #1215.

2.2. BUILDING #212 (Base Power Plant):

2.2.1. Electrical Works:

2.2.1.1. Provide a new permanent emergency generator with Automatic Transfer Switch (ATS) to provide emergency power to whole Building #212.

2.2.1.2. Remove electrical connections of existing permanent emergency generator and assist/co-ordinate with shops with removal/temporary genset connection if needed.

2.2.1.3. Provide and install new EPA-compliant electrical generator rated and located as indicated in project drawings and specifications. If needed, existing concrete slab for future generator shall be expanded or a new one constructed in a different location apart from the existing one.

2.2.1.4. Provide and install new 4-pole automatic transfer switch for automatic change-over from the electrical network to generator operation, that shall be located within existing electrical room of Base Power Plant building.

2.2.1.5. Provide and install new by-pass/isolation switch where required for by-pass maintenance capability, that shall be located within existing electrical room of Base Power Plant building.

2.2.1.6. Provide and install new service line, as well as ductbanks/manholes for connection of generator to building interior electrical installation.

2.2.1.7. Provide and install new Main Distribution Panel in power plant to replace existing combined Manual Transfer Switch + Main Distribution Panel.

2.2.1.8. Perform all necessary connections.

2.2.1.9. Provide adequate grounding to new generator.

2.2.1.10. Provide a red flashing beacon in exterior façade of Bldg #212 to indicate that the emergency power generation is on in the building.

2.2.1.11. Commissioning and final testing on all new equipment.

2.3. BUILDING #1215 (Sewage Treatment Plant):

2.3.1. Electrical Works:

2.3.1.1. Provide a new permanent emergency generator with Automatic Transfer Switch (ATS) to provide emergency power to whole Building #1215.

2.3.1.2. Remove electrical connections of existing permanent emergency generator and assist/co-ordinate with shops with removal/temporary genset connection if needed..

2.3.1.3. Provide and install new high-voltage switchgear, new transformer, new low-voltage panelboard and accessories in a new concrete pre-manufactured utility vault.

2.3.1.4. Provide and install new EPA-compliant electrical generator rated and located as indicated in project drawings and specifications. If needed, existing concrete slab for future generator shall be expanded or a new one constructed in a different location apart from the existing one.

2.3.1.5. Provide and install new 4-pole automatic transfer switch for automatic change-over from the electrical network to generator operation, that shall be located within the new utility vault.

2.3.1.6. Provide and install new by-pass/isolation switch where required for by-pass maintenance capability, that shall be located within the new utility vault.

2.3.1.7. Provide and install new service line, as well as ductbanks/manholes for connection of generator to building interior electrical installation.

2.3.1.8. Perform all necessary connections.

2.3.1.9. Provide adequate grounding to new generator.

2.3.1.10. Provide a red flashing beacon in exterior façade of the new utility vault to indicate that the emergency power generation is on in the building.

2.3.1.11. Provide and install new underground high voltage distribution system to replace all existing overhead high voltage distribution system sections in the area, as well as ductbanks/manholes and splices for connection with existing sections of underground electrical distribution system.

2.3.1.12. Commissioning and final testing on all new equipment.

2.4. Miscellaneous.

2.5. Testing and Commissioning.

2.6. Delivery of As-built drawings.

2.7. Delivery of Spatial Data.

Note: Verify existing utility locations indicated on contract drawings, within area of work. Scan the construction site with Ground Penetrating Radar (GPR), electromagnetic, or sonic equipment, and mark the surface of the ground or paved surface where there are existing underground utilities. Verify the elevations of existing piping, utilities, and any type of underground obstruction not indicated, or specified to be removed, that is indicated or discovered during scanning, in locations to be traversed by piping, ducts, and other work to be conducted or installed. Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.

3. SITE AVAILABILITY:

3.1. The Contractor shall coordinate with the Contracting Officer or authorized representative for site visits with a minimum of ten (10) working days in advance. The attendance to the site visit prior to the design phase commencement is mandatory.

3.2. The Contractor is responsible to investigate the site as needed to complete the project.

The Contractor shall follow all instructions to comply with the base access requirements and restrictions in Bldgs #212 & #1215 areas.

4. PROJECT PHASING: The Contractor shall plan and execute all works in strict adherence to phase completion requirements provided by the Government below. The two general phases of the project shall be the Design Phase and the Construction Phase. A unique notice to proceed (NTP) for both the design and for the construction phases will be issued, which will be the contract award. The design and construction phases below can be balanced, i.e.: if the Contractor completes the design faster, the remaining time can be used for construction; on the contrary, if the Contractor design is delayed, the construction period shall be shortened accordingly, so the overall project performance period shall be maintained at no extra cost to the Government in case that the Contractor needs to increase resources to accomplish the overall contract. The construction phase shall consider the phasing plan required to perform works with minimum interferences to Base operations and security, including a Construction Phasing Plan, if needed. The estimated project phases (not to exceed days) will be as follows (see next page):

Milestones Periods Contract Award (CA) – Notice To Proceed (NTP).

Kick-off meeting Any time within NTP+25 calendar days.

35% Design Review Submittal Preparation CA + 30 calendar days.

35% Design Review and Approval CA + 60 calendar days.

65% Design Review Submittal Preparation CA + 85 calendar days.

65% Design Review and Approval CA + 115 calendar days.

95% Design Review Submittal Preparation CA + 150 calendar days.

95% Design Review and Approval CA + 180 calendar days.

100% Design Review Submittal Preparation CA + 200 calendar days.

100% Design Review and Approval CA + 230 calendar days.

Construction Completion Date CA + 730 calendar days.

4.1 The total performance period proposed for this project is 730 calendar days, including the design, the preconstruction, construction and finish activities and average inclement weather days.

The start of construction can be requested by the contractor before the design phase is completed. In this case, the Contractor should request an updated AF103 from the Contracting Officer when preparing to mobilize for construction, the updated AF103 can be requested before design has been finalized and construction shall not start until receiving the AF103 from Contracting Officer..

5. The Government design review continues through the 100% design to provide direction, as pertaining, to the quality and content of the documents.

PART 4 - DESIGN REQUIREMENTS

1. PROJECT DESIGN:

1.1. The project design shall be performed by a certified A-E firm hired for this project by the Contractor, regularly engaged in projects of similar size and type, whose design meets Spanish, US and NATO regulations. The A-E shall provide a comprehensive description of the project to be designed under this contract. The description of the project shall be prepared in sufficient detail to clearly describe all functional requirements and minimize design changes. During the progress of the work, the A-E may expect minor changes in criteria within the general scope of the project and shall make necessary adjustments accordingly. The 35% design submission is intended to clarify and establish specific requirements of project.

1.2. The project submitted by the A-E Firm shall represent the best engineering solution possible providing a complete and usable installation. All work must be in accordance with current criteria, guides and specifications established by the Spanish, US and NATO regulations.

2. ENVIRONMENTAL CRITERIA: The Integrated Natural Resources Management Plan for Morón Air Base and the Final Governing Standards (FGS) for Spain shall be followed to assure final design meets all environmental requirements.

3. SERVICES. The services to be performed and project documents to be provided to the Government shall include the following:

1. Design analysis.

2. Technical specifications.

3. Drawings.

4. Cost estimates.

5. Design conferences, site inspections and investigations (to include minutes of all meetings).

6. GIS/topographic/GPR survey of the areas affected by new installation in the project, especially concerning underground utilities.

4. KICK-OFF MEETING: Before beginning the design and within 25 days of contract award, the Contractor shall review current criteria, guides and specifications, make a thorough study of conditions at the site and the requirements of the project. A kick-off meeting shall be held by the Contractor with the members of the Base and Government representatives to clarify the functional requirements to be met and the scope of the work. Any conflict shall be brought to the attention of the Contracting Officer. The expected outcomes of this meeting are:

1. Integrate the Contractor and all Base and Government representatives into the project team.

2. Achieve consensus from the project team on any issues and concerns with the Contractor's technical proposal and the User's functional requirements.

Confirm the design is within the project budget.

3. Establish and explain policies and procedures for completion of a successful project.

4. Establish clear lines of communication and points of contact for Government and Contractor team members.

5. Establish project design schedule, design submittal packaging, and preliminary construction schedule including the main activities related to the construction of this project foreseen at this stage.

6. Discuss design milestones and events.

7. Establish clear expectations and schedules for facility turnover, providing asset management records, O & M submittals, and training of Government maintenance personnel.

8. Establish procedure for design packages reviews, Contractor's resolution to comments, and Government's role in review of packages.

5. DELIVERABLES: The submission requirements at the different design review milestones shall be as indicated below.

5.1. First Submittal: This submission to the Contracting Officer or authorized representative shall be at approximately the 35 percent stage of completion (see requirements in table below). The Contracting Office or its authorized representative shall furnish the A-E with the comments and corrections from the 35% review package to be incorporated in the subsequent submission.

5.2. Second Submittal: This submission to the Contracting Officer or authorized representative shall be at approximately the 65 percent stage of completion. The documents in the table below shall be provided as deemed necessary to convey the design intention in a construction contract. Likewise, comments and corrections shall be provided, after revising the package, to be included in the third submission.

5.3. Third Submittal (Pre-Final). This submission (95 percent) shall be essentially complete from A-E viewpoint and shall include information in sufficient detail of all phases of the work to provide a complete technical submittal. The intent of this submission is to prevent premature time-consuming reviews of incomplete drawings and specifications. All submittal data, including plans and specifications, shall be date stamped with the date of submittal. An incomplete submittal shall not be accepted. Engineering calculations shall be legible, neatly arranged, bound and indexed.

The A-E's name and the project title shall be shown, as well as Contractor’s name. Design data shall be clearly stated, and where unconventional design methods or formulas are employed, reference sources shall be cited. Specifications for the third submission (95%) shall be complete, with all elements thoroughly checked and coordinated with the drawings and with sufficient detailed information to permit accurate construction of the project. The third submission shall incorporate all comments of the previous submission. Particular emphasis shall be placed on coordination of the different disciplines where parts of the design are subcontracted. The Contracting Office or its authorized representative shall furnish the A-E with the comments and corrections to be included in the final submission following the review of the third submittal.

5.4. Final Submittal Project Design. The final submission (100%) shall incorporate the corrections and clarifications noted on the third submission or an explanation provided for not doing so.

5.5. Table of Deliverables:

Document Description Number Required

35% Design Submission Basis of Design/Design Analysis

Description of design criteria, principles and codes applied and results of calculations, tests and other information pertinent to the design of the project organized and detailed sufficiently to permit easy selection of the appropriate guide specifications.

2 bound copies and 1 electronic copy

Outline Specifications Draft specifications at this level. The outline specifications shall list all basic construction items and specific types of materials. The outline specification shall describe any special conditions of service and site conditions inherent in the project.

1 electronic copy

Drawings Sketches/plans including site plan, perspective, floor plans, and elevations required for the project. Results from GIS/topographic/GPR survey shall be included.

2 sets (A3 size), 1 set (full size) and 1 electronic copy

Preliminary cost estimate (rough order of magnitude)

A cost analysis of various structural, mechanical and electrical systems shall be included.

1 electronic copy

Design review meeting minutes

Minutes of the design review meeting shall be distributed within 5 workdays after each meeting.

1 electronic copy

GIS/topographic/GPR survey

Full and complete report on existing conditions. It might be included in an annex to the Basis of Design/Design Analysis.

2 bound copies and 1 electronic copy

65% Design Submission Basis of Design/Design Analysis

Further development of previous up to this stage of design. All major design concepts to be captured, at minimum partially designed.

2 bound copies and 1 electronic copy

Specifications Preliminary specifications in sufficient detail to permit a thorough review, English version only.

2 bound copies and 1 electronic copy

Drawings Cover sheet - project location maps, drawing index, site plans. Civil, Architectural, Mechanical, Electrical and Communication drawings: Telephone/data lines, external conduits and cables, manholes/handholes, and other utilities drawings (lighting, fire hydrant piping, etc.) affecting works.

2 sets (A3 size), 1 set (full size) and 1 electronic copy

Cost estimate Itemized cost estimate shall be provided summarized by the major work categories.

1 bound copy and 1 electronic copy

Comments on 35% submission

Annotated prints and comments on the 35% submission shall be returned with this submission. This can be included in the basis of design/design analysis as an attachment.

1 electronic copy

Design review meeting minutes

Minutes of the design review meeting shall be distributed within 5 workdays of each meeting.

1 electronic copy

Generator Authorization and Design Approval Request

Completed form with information from the project design as required per DAFMAN 32-1062 and supporting documentation/attachments for submission to AFCEC

1 electronic copy

Catalog Cuts Catalog information, installation instructions, manufacturer recommendations of every material listed in the Schedule of Material Submittals for easy reference of materials selected and market research performed shall be included in an annex to the Basis of Design/Design Analysis.

1 bound copy and 1 electronic copy

95% Design Submission

Basis of Design/Design Analysis

Further development of previous up to this stage of design, including all civil, structural, mechanical and electrical calculations, including short circuit calculation, load calculations, and lighting calculations if needed, hydraulic, among others. Engineering calculations shall be legible, neatly arranged and indexed.

2 bound copies and 1 electronic copy

Specifications Full specifications including Spanish translations. The content of each translated page shall be the same as each page of the English version of the specification.

Separate volumes by language.

2 bound copies and 1 electronic copy

Drawings Drawings, at this stage, shall include Spanish translations.

2 sets (A3), 1 set (full size) and 1 electronic copy

Cost estimate Itemized cost estimate shall be provided summarized in the form named Construction Cost Estimate Breakdown

1 bound copy and 1 electronic copy

Comments on 65% submission

Annotated prints and comments on the 65% submission shall be returned with this submission. This can be included in the basis of design/design analysis as an attachment.

1 electronic copy

Design review meeting minutes

Minutes of the design review meeting shall be distributed within 5 workdays of each meeting.

1 electronic copy

Catalog Cuts Catalog information, installation instructions, manufacturer recommendations of every material listed in the Schedule of Material Submittals for easy reference of materials selected and market research performed shall be included in an annex to the Basis of Design/Design Analisys.

1 bound copy and 1 electronic copy

100% Design Submission Basis of Design/Design Analysis

Further development of previous up to this stage of design, including all civil, structural, mechanical and electrical calculations, including short circuit calculation, load calculations, and lighting calculations if needed, hydraulic, among others. Engineering calculations shall be legible, neatly arranged and indexed.

1 bound copy

Specifications Final specifications including Spanish translations. The content of each translated page shall be the same as each page of the English version of the specification

1 bound copy

Drawings Drawings shall include proper signatures. 2 sets (full size), 2 sets (A3 size), 1 set (full size in mylar for as-built)

Cost estimate Signed original of final cost estimate (Construction Cost Estimate Breakdown)

Signed original

Comments on 95% submission

Annotated prints and comments on the 35%, 65% and 95% submissions shall be returned with this submission. This can be included in the basis of design/design analysis as an attachment.

1 bound copy

Catalog Cuts Catalog information, installation instructions, manufacturer recommendations of every material listed in the Schedule of Material Submittals for easy reference of materials selected and market research performed shall be included in an annex to the Basis of Design/Design Analisys.

1 bound copy and 1 electronic copy

Electronic copies All drawings, specifications and other project documents shall additionally be on a CD-ROM or DVD-ROM utilizing Adobe PDF, MS WORD 2016 and AUTOCAD 2015 or higher. Drawings shall be on a separate CD-ROM or DVD-ROM than the rest of the documents and in both AUTOCAD and Adobe PDF formats. All other documents shall be provided in both the original format and in Adobe PDF. Final CD-ROM or DVD-ROM for drawings and specifications must be labeled as follows:

Project name and location Date Project Number A-E Firm Contractor's Name Drawing numbers Virus scanner person’s name

1 copy

Other All computations, studies and other significant material shall be bound in book form for the final submittal.

The annotated prints and comments on pre-final submission.

1 bound copy and 1 electronic copy

5.6. Appropriate Signatures. Each final drawing shall be signed by the Designer of Record (DOR). The project shall be validated by the organizations of Morón Air Base involved on the project with a signature on the cover sheet. To expedite this process the A-E shall send the original drawing of the cover sheet on polyester with the third submission and it shall be returned to the A-E prior to the final submission with the required signatures.

5.7. Project Drawings Final Submission. Project drawings shall be final and complete with all elements thoroughly checked and coordinated. All elements of the work shall be properly coordinated to insure that there are no conflicts between all portions of the work. Particular emphasis shall be placed on this coordination when certain elements of the design are performed under sub-contract to the A-E contract. Drawings shall be prepared in order to avoid errors, omissions, inadequacies or conflicts with the specifications. Applicable parts of the following design data shall be shown on the drawings.

5.8. Format for Drawings:

5.8.1. AUTOCAD Requirements: All designs shall be accomplished in AUTOCAD 2015 or higher and shall be submitted on CD ROM and in one set of Mylar reproducible.

5.8.2. Size of Drawings: The A-E shall use drawing size DIN A-1 841 mm x 594 mm in all cases unless specifically directed to use another size.

5.8.3. Lettering and Shading: The minimum size lettering on all project drawings shall be

2.5 mm high. Make minimum gap between lines equal to one-half the letter height. Shading is not acceptable.

5.8.4. Scales: Locate it directly under the title of each plan, elevation, section and detail and shall be an indication of the scale of the object drawn (example: SCALE 1:100) on the metric system unless otherwise approved. In addition to the conventional scales, and directly to the left of the title block, shall be a series of graphic scales, which shall include every scale used on the sheet. Scales shall be placed in sequence according to size with the smallest uppermost. If it is not sufficient to place all scales on one sheet, each sheet must be treated independently, as the drawings used usually are reduced in size and not always at scaled. For these reasons, it is imperative that graphic scales be shown.

5.8.5. Title Blocks: Sample of title block is available at Morón Air Base, Bldg. 202, Design Section.

5.8.6. Arrangement of Drawings: Drawings shall be arranged and comply with the A/E/C CAD Standard – Release 5.0, prepared by the CAD/BIN Technology Center.

5.8.7. Register number: All drawing sheet shall be incorporated in its title box the register number record provided by Morón Air Base Civil Engineering specific for each project.

5.8.8. Drawing Orientation: The orientation of drawings shall be arranged with North toward the top (or left edge, if better suited) of the plotted sheet and perpendicular to the sheet borderline. On individual sheets, if the shape of the area dictates, the North symbol can be oriented between these directions to accommodate the site. For example, on drawings having excessive longitudinal but limited lateral dimensions, such as those for roads and railroads, the North symbol can be oriented obliquely to make the best use of available space. All drawings of the same discipline shall be consistent in orientation in so far as practicable.

5.8.9. GIS Master Plan: Coordinate with Geobase office for requirements on GIS drawings and obtaining initial site plans for GIS survey.

5.9. Requirements for Project Specifications:

5.9.1. Project Specifications Preparation. The project specifications form a part of the contract documents. Project specifications shall be as brief as possible, definite, and free of ambiguities and omissions, which might result in controversies and subcontractors' claims for additional compensation. For construction projects, which involve interruptions of existing facilities operations or major utility usage, it is the Contractor's responsibility to discuss the required outages and interruptions with the Contracting Officer or authorized representative and operations personnel to establish a construction schedule for these interruptions in the contract specifications. In order to provide conformity in reproduction of specifications, it is requested that all sketches, which are to be bound as a page in the specifications, be drawn on a sheet of A4 page size with 1.25 mm margin on all sides.

5.9.2. Standard Specifications. The guideline for the specifications shall the Unified Facilities Guide Specifications (UFGS). Maximum use shall be made of standard specifications, materials and methods of construction available in Spain (for example, UNE, CÓDIGO TÉCNICO DE LA EDIFICACIÓN, PLIEGOS DE CONDICIONES DEL MOPU, among others). Federal and Military Specifications and other standards such as ASTM, ASME, AASHO shall not be used if the products or the methods described are not available in Spain or are not common practice in the local construction industry, unless there is a requirement for use of such product or method (ie; U.S.

standard electrical devices). In general, the materials shall meet all necessary requirements and be specified briefly in the project specifications.

5.9.3. Spanish Translation of Specifications: It is a requirement to submit a Spanish translation of project specifications. Project drawings shall contain both the English and Spanish versions.

5.10. Cost Estimate Requirements: It shall provide a detailed breakdown of all items required for the construction project based on this design. The Construction Cost Estimate Breakdown shall be developed, at least, in accordance with the divisions of the UFGS, and marked "For Official Use Only", and itemized in such a manner that effective construction management invoicing can be executed by Construction Management department. In addition, a cost estimate itemized in Uniformat II classification, can be requested by Civil Engineering Design section at no additional cost/time for the Government. Cost estimates shall be prepared separately for each funding source category. Summary sheets of not more than 4 pages shall be provided.

5.11. Correspondence: The Contractor shall forward all correspondence pertaining to this contract to the Morón Air Base Contracting Officer or authorized representative including submittal packages, minutes of meeting and all pertinent documents. The only exception to this requirement is the 100% submittal, which shall be delivered directly to Civil Engineering of Moron Air Base.

5.12. Minutes. The Contractor is responsible for recording, typing, and preparing the meeting minutes of all pre-design and design review conferences for their distribution.

6. COORDINATION The Contracting Officer or authorized representative, in coordination with his technical representative, shall establish liaison between the Contractor and all U.S. Government agencies for general and detailed technical information necessary to completing the terms of the contract. The Contracting Officer or authorized representative, in conjunction with the technical representative, shall assist the Contractor to gain access to Base and facilities necessary to complete the terms of the contract.

7. MATERIALS TO BE MADE AVAILABLE BY THE GOVERNMENT PRIOR TO

DESIGN START: The Government shall provide access to the Contractor to the following materials prior to design start:

1. Existing record drawings.

2. Government publications and criteria shall be available for review, during normal duty hours, at the Base Civil Engineering Office, Bldg 202, of Moron Air Base, Spain.

3. One copy of the facility as-built drawings necessary for design.

4. Project, project register number, title block and drawing frame to be used for final contract drawings in AutoCAD 2015 file.

5. Key Map of Spain, Vicinity Plan, Base Map, Reference Key, logos, drawing schedule table and project coordination table for the cover sheet in AutoCAD .2015 file.

6. AutoCAD seed files, color table, font resource files used for the creation of AutoCAD design files.

7. A sample of Cover Sheet and Second Sheet. These samples are to be strictly adhered to when formatting the cover and second sheets for each project. The Contractor shall be required to edit the list of abbreviations.

8. Vicinity, Location and Base information for the project location in ESRI (Environmental Systems Research Institute) Geodatabase, as well as reference control points in UTM WGS84 coordinates system.

9. Submittal Sheet for project design packages.

10. Standard specification cover sheet.

11. Files of existing site and facilities’ plans, details and utility plan files shall be made available to the Contractor. The Contractor shall research the files of all applicable drawings and generate a list of any document that is deemed necessary. The Government shall provide copies of the drawings within 72 working hours of the Contractor's request. All provided drawings in either hard copy or digital drawing file formats are record drawings and not as-built drawings. Air Force record drawings are from past construction projects that may not reflect the true as-built condition. The Air Force shall provide one full size copy of each drawing required. Any additional copies of any one particular drawing shall be at a reduced scale, normally half size.

PART 5 - PERFORMANCE TECHNICAL SPECIFICATIONS

1. ELECTRICAL WORKS

1.1. General system description

1.1.1. This project requires two (2 ea) new permanent emergency generators with ATS and BP/IS located in an existing concrete slab (or a new slab, if needed), new underground distribution system and modifications to interior electrical distribution systems in Base Power Plant and Sewage Treatment Plant buildings, installation of a new utility vault in Sewage Treatment Plant, as well as the upgrades to electrical installations indicated in Part 3 of this SOW. All systems shall be complete and operational.

1.1.2. Electrical distribution system in Morón Air Base is 12,47 kV primary, three phase, four wire, 60 Hz, and 208/120 volts or 480/277 volts secondary, three phase, four wire, unless otherwise indicated.

1.1.3. Demolitions required under this project shall be performed as indicated in the architectural works paragraph, and incorporating specific requirements for lighting devices under category 5 of the R.D. 208/2005.

1.1.4. Provide an electrical system complete in place, tested and approved, as specified throughout this SOW, as needed for a complete, usable and proper installation. All equipment shall be installed per the criteria of PTS, applicable codes and manufacturer’s recommendations. Where the word “should” is used in the manufacturer’s recommendations, substitute with the word “shall”.

All electrical raceways under this project shall be installed, to the maximum extent feasible, concealed in walls, above false ceilings or below raised floors, following applicable installation criteria in regulations. The only exception to the installation of concealed raceways is where this would lead to structural damage.

1.2. Interior Distribution System

1.2.1. Conduits and fitting. The number of conductors permitted in conduit, shall conform to the applicable provisions of the National Electrical Code for the conduit of the equivalent internal diameter. In no case conductors area shall exceed 40 percent of conduit cross sectional area. Conduit sizes in drawings refer to interior free diameters. Conduits and fittings shall conform to the following:

a. Rigid Steel Conduit (Zinc): ANSI C80.1. Galvanized steel. To be installed where exposed to weather, where subject to physical damage, where exposed on exterior of buildings, in mechanical rooms and where so indicated in project drawings.

b. Electrical, Zinc-Coated Steel Metallic Tubing (EMT): ANSI C.80.3. Hot zinc-galvanized steel.

To be installed in branch circuits and feeders above suspended ceilings or exposed where not subject to physical damage and where so indicated in project drawings.

c. Flexible Metal Conduit: UL 1, UNE-EN 50086-1 or UNE-EN 61386-23, for recessed and semi-recessed lighting fixtures; for equipment subject to vibration; and for motors other than pumps.

Limited to 6 ft (1.80m) length. They shall be armored with exterior PVC insulation; minimum compressive strength of 1,250N with a 25% maximum deformation, medium impact resistance, operating temperature range from -5ºC to +60ºC, flame propagation resistant, tensile strength greater than 250N. The connections shall be watertight.

d. Surface Metal Raceway: UNE 50085-1. Anodized aluminum, RAL 9006 color, totally enclosed, snap-cover type, with two separate spaces with different covers and spacer for both power and communication wiring. Dimensions needed to enclose power and communications wiring. IK07, IP4X protection ratings. To be installed in ITN room if needed to provide installation flexibility.

e. Weatherproof Metal Raceway: Steel with green epoxy-polyester coating, UNE 50085-1 compliant, cover removable by means of screws, impact resistance 20J, maximum installation temperature 120º, flame resistant, electrically continuous, protection index IP65. Corrosion resistant. To be installed for exposed power distribution from emergency generators to automatic transfer switches.

f. Fittings for Metal Conduit and EMT: Ferrous fittings shall be cadmium- or zinc- coated in accordance with UL 514B. Fittings for Rigid Metal Conduit shall be threaded-type, split couplings unacceptable. Fittings for EMT shall be steel compression type.

g. Fittings for Flexible Metal Conduit: Ferrous fittings shall be cadmium- or zinc- coated in accordance with UL 514B or compatible with UNE-EN 61386-23 conduit.

h. Fittings for Surface Metal Raceway: Standard products from the manufacturer of the raceway.

Include all required fittings and accessories for a complete installation, such as spacers, couplings, angles, cable rails, receptacle/LAN drop boxes, adaptors and covers, end and joint covers, tees, etc.

i. Fittings for Weatherproof Metal Raceway: Standard products from the manufacturer of the raceway. Include all required fittings and accessories for a complete installation, such as couplings, screws, curves, junction boxes, end covers, couplings, gaskets, supports, etc.

1.2.2. Outlet boxes, junction boxes, pull boxes and conduit outlet bodies: UL 514A, zinc-coated ferrous metal. Boxes for shall be of the cast metal hub type when located in normally wet locations and when surface or flush mounted outside of exterior surfaces. Junction, pull and connection boxes of surface mounted devices or lighting fixtures shall be sheet steel. Each box shall have the volume required for the number of conductors enclosed in the box, with 1,640 ml (100 cubic inches) minimum. Boxes installed for concealed wiring shall be provided with suitable extension rings or plastic covers, as required. Boxes to be used in masonry-block or tile walls shall be square-cornered tile-type. Cast metal boxes installed in wet locations and boxes installed flush with the outside of exterior surface shall be gasketed.

1.2.3. The wiring system shall consist of insulated, single-conductor cable installed in conduits, raceways or cable trays. All conductors shall be copper and no smaller than 4 mm². AENOR certified. Conductor color coding shall be as per UNE 21089.

a. Main Distribution Panel to Secondary Panels: Connecting conductors for power circuits from generator sets and/or transformers to the different emergency panelboards, by-pass/isolation switch and Automatic Transfer Switch and for air conditioning units shall be flexible class 5 copper and shall be rated 1000 volts nominal capacity with cross-linked polyethylene (XLPE) insulation in accordance with UNE 21123-4. Insulation shall be moisture and heat resistant and be suitable for maximum operating temperature rise of 90ºC. Technical designation RZ1-K (AS), flame retardant (AS), halogen-free with thermoplastic polyolefin (Z1) jacket.

b. Wiring for Lighting, Receptacles and Other Loads Circuits: Connecting conductors for lighting and power circuits from secondary panels shall be flexible class 5 copper and shall be rated 450/750 volts nominal capacity with halogen-free thermoplastic polyolefin insulation. Insulation shall be moisture and heat resistant and be suitable for maximum operating temperature of 70ºC.

Technical designation H07Z1-K(AS), flame retardant (AS), halogen-free with thermoplastic polyolefin (Z1) jacket. In accordance with UNE 211002.

c. Connecting Conductors to Motors: Cables feeding motors (i.e.: air conditioning units, etc.), shall be flexible class 5 copper and shall be rated 1000 volts nominal capacity with cross-linked polyethylene (XLPE) insulation in accordance with UNE 21123-4, unless otherwise indicated in project drawings. Insulation shall be moisture and heat resistant and be suitable for maximum operating temperature rise of 90ºC. Technical designation RZ1-K (AS), flame retardant (AS), halogen-free with thermoplastic polyolefin (Z1) jacket.

d. Grounding Conductors: Shall be insulated copper, unless otherwise indicated due to size. In that case, the conductors shall be unshielded twisted copper. Grounding conductors shall be same technical designation as the conductors which they run along with.

1.2.4. Device plates: UL compliant, one-piece device plates for outlets to suit the devices installed (one-, two-, three-gang or more as required). Standard size. Plates shall be stainless steel with brushed finish having round or beveled edges in mechanical/utility rooms, Base Power Plant electrical room, over false ceilings and outdoors or thermoplastic nylon in other interior spaces.

Plates shall be same color as receptacle or toggle switch with which they are mounted. Plates for emergency receptacles shall be 302 stainless steel with brushed stainless steel finish and shall have the word ‘EMERGENCY” engraved. Screws shall be machine-type with countersunk heads in color to match finish of plate. Sectional type device plates will not be permitted. Plates installed in wet locations shall be gasketed and UL listed for “wet locations”.

1.2.5. Toggle switches: Standard size. Shall meet Federal Spec W-S-896. Wall switches shall be of the totally enclosed type with bodies of thermoplastic or thermoset plastic and mounting strap with grounding screw. Handles shall be ivory for interior areas or gray thermoplastic for exterior/mechanical/utility room areas. Wiring terminals shall be side wired screw type. Not more than one switch shall be installed in a single gang position. Switches shall be rated 20 amperes, 120/277 volts for use on an alternating current only, shall be suitable for the control of lamp loads up to their full rated capacity and be single-pole, two-pole or three-ways as required. Toggle switches shall industrial heavy duty grade.

1.2.6. Receptacles: Standard size. UL 498, heavy-duty, self-grounding type and NEMA WD 1, heavy-duty grade, 120 Volt, 20 Amp, 3 wires NEMA 5-20R, 240 Volt, 20 Amp, 3 wires NEMA 6-20R, or as needed for special applications, wiring terminals shall be screw type, side wired.

Dimensional requirements shall be per NEMA WD 6. Connect grounding pole to mounting strap.

Bases will be duplex or four-plex as indicated in drawings. Gray color in mechanical room, red color for emergency receptacles connected to emergency panelboards with backup generators and ivory color for all the other interior spaces.

a. Ground-Fault Circuit Interrupter (GFCI) Receptacles: Conform to UL standard 943, Class A, GFCI and 498 (receptacles), UL Listed, duplex type for mounting in standard outlet box. Device shall be capable of detecting current leak of 6 milliamperes or greater and tripping per requirements of UL 943 for Class A GFCI devices. It will be NEMA 5-20 R for 20 Amps and 125 V AC at receptacles and feed-through, and tamper-resistant. Color as indicated for receptacles above.

b. Panelboards: The panelboards and their components shall be designed and wired in compliance with the following norms and recommendations UNE-EN 61439-1, or UL 67 and UL 50. All components made of plastic shall comply with self-extinguishing requirements of 960° C and in conformance to norm CEI 695.2.1. Cabling to be installed on the panelboards shall be 750 V in accordance with UNE 21027-9, designation HO7Z-K, halogen free and low emission of opaque fumes. Short circuit nominal current for panelboard shall be as calculated on pertinent diagram duration being 1 second. Nominal frequency shall be 60 Hz. Directories shall indicate load served by each circuit of panelboard. Type directories and mount in holder behind transparent protective covering.

• Control and Protection Devices: Plug connection shall be independent and shall be located on the front part of compartment. The distance between the devices and the metal separators shall prevent that power breaks of elevated short circuit currents or notable faults affect the electric equipment installed in adjacent compartments. All components shall be clearly and permanently labeled to correspond with branch indicated on the diagram. Directories shall indicate load served by each circuit in panelboard. Directories shall also indicate source of service to panelboard (e.g., Panel LDP served from Panel MDP). Provide new directories for existing panels modified by this project as indicated. Type directories and mount in holder behind transparent protective covering.

Panelboard shall have nameplates .

• Construction: The structure of the panelboard shall be constructed with steel sections and locking panels of sheet metal with a minimum thickness of 1.5 mm. Panelboards shall be expandable and frame panels shall be removable by means of screws. Screws shall be class 8/8 with a zinc based anti-corrosive treatment. Back panel shall be fixed or pivoting with hinges. Front panel shall be provided with safety glass and key lock. All electrical components shall be readily available from front panel by means of covers which are screwed on or have hinges. All switchgear shall be fixed on guides or fixed panels on cross members for fastening. Protection grade adaptable on same framework structure shall be IP55, or IP65, as required.

• Varnish: In order to guaranty effective resistance to corrosion, the structure and the panels shall be adequately treated and varnished. Base treatment shall consist of washing, phosphatization and passivation by chrome or electro zinc-plating of panels. The panels shall be varnished with thermoset paint with a resin-epoxy base mixed with polyester resin, final color white for distribution panels and red for emergency panels and matte with a minimum thickness of 40 microns.

• Auxiliary Connections: Each conductor shall be completed by a numbered ring corresponding with the number on the strip and the operating diagram.

• Power Supply Wiring: The busbars and conductors shall be sized to support the thermal and dynamic requirements corresponding to the nominal current values and the short circuit current.

The busbars shall be completely perforated with holes of 10 mm diameter, copper section with sliding screws frontal access, connections with access from the front of panelboard, supports shall be sized and calculated so that electrodynamic stresses due to short circuit currents are withstood.

The busbars shall be identified with self-adhering marks in accordance with phase, as cables which will be equipped with terminal color rings.

• Certificate of Compliance: Prior to the installation of any of the panelboards in their final location, Contractor shall submit a Certificate of Compliance for each panelboard verifying that each has passed the tests and verifications established in norm UNE-EN 61.439.1 detailed as follows:

a. Verification of heat limitations.

b. Verification of dielectric properties.

c. Verification of short circuit resistance.

d. Verification of circuit protection (resistance to short circuit and continuity of circuit protection.)

e. Verification of mechanical operation.

f. Verification of protection grade IP, IK.

g. Verification of wiring and electrical operation.

h. Verification of insulation.

i. Verification of safety measures.

j. Verification of insulation resistance.

1.2.7. Circuit Breakers: In accordance with IEC 947-2, VDE 0660 or UL 489, thermal magnetic-type having a minimum short-circuit current rating equal to the short circuit current rating of the panelboard in which the circuit breaker shall be mounted. Breaker terminals shall be UL listed as suitable for type of conductor provided. Plug-in circuit breakers and series rated circuit breakers are unacceptable. Circuit breakers shall be in accordance with REBT 2002.