This document is a Submittal Form, a standard federal contract document used to track and manage required submissions throughout a construction or service project. The form lists numerous preconstruction and closeout submittals across multiple specification sections, including critical administrative and safety documents such as the Accident Prevention Plan (APP), Activity Hazard Analysis (AHA), Construction Schedule, List of Contact Personnel, Quality Control Plan, and various certificates and reports.
Key submission categories include SD-01 Preconstruction Submittals (e.g., Equipment Delivery Schedule), SD-06 Test Reports (e.g., Accident Reports, Regulatory Citations), SD-07 Certificates (e.g., Confined Space Entry Permit), and SD-11 Closeout Submittals (e.g., Submittal Register). The form provides a structured template for contractors to track document submissions, approvals, and key dates, with placeholders for contract title, location, contractor name, and various administrative tracking columns for submission and review processes.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONTRACTOR
SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
(a) (b) (c) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)
01 20 00
1.3
01 30 00
1.4.1
01 31 50
1.2
01 32 16
1.2
1.3
01 33 00
1.4.1
1.6.1
01 35 29
1.9
1.10
1.9.1
1.9.1
1.7.1.4
1.14
1.14.1
1.14.3
1.14.4
1.14.5
1.11
1.14.6
Crane Reports
SD-07 CERTIFICATES
Confined Space Entry Permit
Interim DD1354, Transfer & Acceptance
SD-11 CLOSEOUT SUBMITTALS
Submittal Register
Complete Submittal Package
Approving AuthorityContractor Schedule Dates
TITLE AND LOCATION
(Enter Contract Title and Locaiton Here)
Schedule of Prices
List of Contact Personnel
Construction Schedule of Military Real Property (If Applicable)
A C T I V I T Y
N O
T R A N S M I T T A L
N O
(d)
SD-11 CLOSEOUT SUBMITTALS
Contractor Action
DESCRIPTION
ITEM SUBMITTED
(Enter Contractor Name Here)
Crane Work Plan (If Applicable)
Activity Hazard Analysis (AHA)
SD-06 TEST REPORTS
Certificate of Compliance
SD-01 PRECONSTRUCTION SUBMITTALS
SD-01 PRECONSTRUCTION SUBMITTALS
Accident Prevention Plan (APP)
SD-01 PRECONSTRUCTION SUBMITTALS
Equipment Delivery Schedule
SD-01 PRECONSTRUCTION SUBMITTALS
P A R A G R A P H
N O
S P E C
S E C T
C L A S S I F I C A T I O N
G O V T
O R
A E
R E V W R
Crane Critical Lift Plan (If Applicable)
Crane Operators (If Applicable)
Reports
Accident Reports
Monthly Exposure Reports
Regulatory Citations and Violations
1.14.7
01 45 10
1.6
01 50 00
1.6.2.1
2.1
3.1
1.3
01 57 19
1.6.1
1.6.4
1.7.2
1.7
1.7
PAGE 1 OF _
Third Party Certification of Barge-
Mounted Movile Cranes
Qaulity Control Plan (QC Plan)
Backflow Preventer Tests (If Applicable)
SD-01 PRECONSTRUCTION SUBMITTALS
Traffic Control Plan (If Applicable)
SD-11 CLOSEOUT SUBMITTALS
SUBMITTAL FORM, JAN 96 PREVIOUS EDITION OBSOLETE
MSDS for Class I ODS Waivered Product
SD-01 PRECONSTRUCTION SUBMITTALS
Permit for Storm Water Discharge (If applicab
Environmental Protection Plan
Preconstruction Survey
Notice of Intent (If applicable)
SD-03 PRODUCT DATA
Backflow Preventers (If Applicable)
Backflow Preventers Certificate (If Applicable)
SD-06 TEST REPORTS
SD-07 CERTIFICATES
Backflow Tester Certification (If Applicable)