25-0454 CHILLER REPLACEMENT - PD.pdf

PDF 67 KB Posted

Attached to
Mechanical Repairs to Buildings 1005, 1, PP100, PP200, FC504, FC507, & FC510
Solicitation number
N0448525R9028
Issued by

About this file

This document appears to be a project description for an HVAC chiller installation project at Camp Lejeune, North Carolina. The project scope involves providing and installing new HVAC chiller units at four specific buildings: Bldg.'s 1005, 1, PP100, and PP200. A key operational requirement is that the facility must remain fully operational during the entire construction period, with the contractor mandated to minimize interference with normal base activities.

The document also outlines supervision requirements, allowing flexibility in personnel roles. Specifically, one qualified individual may simultaneously serve as Superintendent, Quality Control Manager, and Safety & Health Officer, provided they meet the qualification criteria defined in the project specification. The project emphasizes maintaining continuous facility operations while executing the HVAC chiller unit upgrades.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROJECT DESCRIPTION

This scope of work is to be accomplished at Bldg.’s 1005, 1, PP100, and PP200 on board Camp Lejeune NC. Contractor will provide and install new HVAC Chiller units at each location.

SPECIAL SCHEDULING

The facility/activity will remain in operation during the entire construction period. The Contractor shall conduct his operations so as to cause the least possible interference with normal operations of the facility/activity.

SUPERVISION

One person may fill the roles of Superintendent, Quality Control Manager, and Safety & Health Officer, if duly qualified for all three positions as defined in the project specification.