25-0428 RR24-RR44 SIDEWALK - TOWER PAD - PD.pdf
PDF 50 KB Posted
- Solicitation number
- N4008526R9076
About this file
This is a Project Description for a Department of Defense construction contract located at Camp Lejeune and New River, North Carolina. The primary scope of work involves the removal and replacement of damaged sidewalk portions off Powder Lane on Stone Bay, Camp Lejeune NC, with repairs to any damaged grass and/or roads resulting from construction activities.
The secondary scope includes pouring four new 4-inch concrete slabs measuring 20 feet by 22 feet 6 inches each at MTI Reflector Towers 01, 05, 19, and 23 on the flightline at New River, North Carolina. Three sites require minimal site work to ensure level placement, while one site requires construction of a retaining wall and dirt infill. Each concrete slab will incorporate two 2-inch Schedule 40 PVC conduits built into the slab and extending 5 feet below grade beyond the slab edge for future use. The facility will remain operational during the entire construction period, requiring the contractor to minimize interference with normal operations. Supervision may be consolidated under a single qualified individual serving as Superintendent, Quality Control Manager, and Safety & Health Officer, provided that person meets all qualifications defined in the project specification.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DISTRIBUTION: DoD COMMUNITY ONLY
PROJECT DESCRIPTION
The work includes removal and replacement of damaged sidewalk portions located off Powder Lane on Stone Bay, Camp Lejeune NC as well as repair to any damaged grass and/or road that occurred during construction of this project.
This scope of work is to be accomplished at MTI Reflector Towers 01, 05, 19 & 23 on the flightline aboard, New River, North Carolina. The work includes pouring (4) new 4" concrete slabs measuring 20'x22'-6" each over crushed rock at existing MTI reflector locations. (3) of the sites will include minimal site work to ensure level slab, (1) site includes building of retaining wall and dirt infill to create level slab.
Each concrete slab will have (2) 2” Sch 40 PVC conduits built into slab and ran below grade 5’ beyond slab edge for future use.
SPECIAL SCHEDULING
The facility/activity will remain in operation during the entire construction period. The Contractor shall conduct his operations so as to cause the least possible interference with normal operations of the facility/activity.
SUPERVISION
One person may fill the roles of Superintendent, Quality Control Manager, and Safety & Health Officer, if duly qualified for all three positions as defined in the project specification.