25-00706-01-BD_Urbana_Specifications.pdf
PDF 9 MB Posted
- Solicitation number
- FY2026-ITB-165
- Issued by
- Champaign County, Illinois
About this file
This is a specifications document for the City of Urbana, Illinois, detailing requirements for the demolition and disposal of an approximately 10,000 square foot building located at 1407 N. Lincoln Avenue, Urbana, IL (Section 25-00706-01-BD). The project involves complete removal of the structure, including all foundations, retaining walls, and below-grade structures, with the site to be restored as a mixed-use lot consisting of asphalt and grass surfaces. The building, formerly occupied as a fire station since the 1970s, contains known friable and non-friable asbestos-containing building materials (ACBMs) requiring specialized removal and disposal in compliance with U.S. Environmental Protection Agency (EPA), Illinois Environmental Protection Agency (IEPA), and Occupational Safety and Health Administration (OSHA) standards. The contractor is responsible for obtaining all required local permits, including demolition, Class 2 erosion control, and right-of-way permits; however, all City permit fees will be waived. A pre-construction meeting must be scheduled with the contractor's General Superintendent and Jobsite Superintendent to discuss project details, subcontractors, equipment, erosion control plans, construction staging, traffic control, and progress schedules. Traffic control must maintain two-way traffic on Lincoln Avenue with a Traffic Control Plan submitted no later than two weeks before work commencement. The contractor must comply with prevailing wage rates as established by the Illinois Department of Labor and adhere to the City of Urbana noise ordinance, which restricts construction equipment operation between 8:00 p.m. and 7:00 a.m. Monday through Saturday and 8:00 p.m. Saturday through noon Sunday.
The contract includes a one-year guarantee period from the date of completion and acceptance. Asbestos abatement work must be performed by an Illinois Department of Public Health (IDPH) licensed contractor prequalified with the Illinois Capital Development Board, with an on-site supervisor and workers licensed by IDPH. The contractor shall perform air monitoring during asbestos abatement using NIOSH Method 7400 conducted by a qualified air sampling professional, with results and calibration records kept on site for Engineer review. Friable ACBMs and Category II non-friable ACBMs must be removed prior to demolition and disposed of separately from non-ACBM debris. The contractor must submit multiple submittals prior to abatement commencement, including manufacturer certifications for equipment, sealant specifications, proof of disposal arrangements, detailed work plans, prequalification documentation, and upon completion, waste chain-of-custody records, work site entry logs, engineering control maintenance logs, and bulk material analysis and air sampling results. Topsoil sourcing and placement of six inches of uncontaminated loamy topsoil suitable for seeding shall be paid at the contract lump sum price. Building removal, removal and disposal of friable asbestos, and removal and disposal of non-friable asbestos will each be paid at specified contract lump sum unit prices, as will traffic control and protection at a lump sum price.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1407 N. Lincoln Avenue Building Demolition Project
Section 25-00706-01-BD
September 1, 2026
Specifications
TABLE OF CONTENTS
A. City of Urbana Special Provisions
a. General Contractual Conditions
b. Technical Provisions
B. IDOT Special Provisions
a. Index for Supplemental Specifications
b. BLR 11300 – Check Sheet for Recurring Special Provisions
c. BDE Special Provisions
C. City of Urbana Permit Standards
a. Demolition Permit – Building code adoption Ordinance (Excerpt)
b. Class 2 Erosion Control Permit Manual of Practice (Excerpt)
c. Utility and right-of-way Permit Standard Details (Excerpt)
D. Standard Details
a. Highway Standards
E. Supplemental Project Information
a. Asbestos Inspection Report – Prior to Demolition
SECTION A
City of Urbana Special Provisions
City of Urbana 1407 N. Lincoln Avenue Building Demolition
25-00706-01-BD 1407 N. Lincoln Avenue Building Demolition 1
CITY OF URBANA
SPECIAL PROVISIONS
PART 1 – GENERAL CONTRACTUAL CONDITIONS
1.1 COORDINATION OF CONTRACT DOCUMENTS
1.2 PRE-CONSTRUCTION MEETING
1.3 GUARANTEE PERIOD
1.4 CONSTRUCTION AND MAINTENANCE NOISE
1.5 PREVAILING WAGE RATES
1.6 PROSECUTION OF THE WORK AND WORKING DAYS
PART 2 - TECHNICAL PROVISIONS
2.1 LOCATION OF PROJECT
2.2 DESCRIPTION OF WORK
2.3 CITY PERMITS
2.4 TRAFFIC CONTROL AND PROTECTION
2.5 STATUS OF UTILITIES
2.6 TOPSOIL SOURCING AND PLACEMENT
25-00706-01-BD 1407 N. Lincoln Avenue Building Demolition 2
PART 1 – GENERAL CONTRACTUAL CONDITIONS
1.1 Coordination of Contract Documents
The following table supplements the hierarchy of contract documents according to Article 105.05 of the Standard Specifications.
Authorized Change Orders Hold over: Addenda to Contract Documents, Special Provisions, Plans, Recurring Special Provisions, Supplemental Specifications, and Standard Specifications.
Addenda to Contract Documents Hold over: Special Provisions, Plans, Recurring Special Provisions, Supplemental Specifications, and Standard Specifications.
Special Provisions (1) Hold over: Plans, Recurring Special Provisions, Supplemental Specifications, and Standard Specifications.
Plans (2) Hold over: Recurring Special Provisions, Supplemental Specifications, and Standard Specifications.
Notes:
(1) The term “Special Provisions” includes General Information, General Contractual Conditions, and Technical Provisions.
(2) Detail plans hold over Urbana Standard Details, and Urbana Standard Details hold over IDOT District or Highway Standards.
1.2 Pre-Construction Meeting
As soon as possible after receipt of the Notice to Proceed, the ENGINEER will schedule a Pre-construction Meeting for the project. The CONTRACTOR shall have his/her General Superintendent and Jobsite Superintendent present at the appropriate meeting to discuss all details of the project. At these meetings, the CONTRACTOR shall submit for approval information and drawings where appropriate on all major equipment and materials planned for use on the projects to the ENGINEER for approval.
Information shall be included on a minimum of the following items:
A. List of Subcontractors and Material Suppliers B. Shop Drawings C. Erosion Control Plan and Inlet Filter Systems D. Construction Staging and Access to Properties E. Traffic Control Plan F. Progress Schedule
1.3 Guarantee Period
The CONTRACTOR shall warrant all work performed for a period of one (1) year from the date of completion and acceptance by the OWNER.
25-00706-01-BD 1407 N. Lincoln Avenue Building Demolition 3
1.4 Construction and Maintenance Noise
The contractor shall adhere to the City of Urbana noise ordinance Section 16-7 in scheduling work windows. According to the ordinance, it is unlawful to use any construction equipment to perform any construction or maintenance work associated with this project at any time between the hours noted below where such construction equipment is operated within six hundred (600) feet of any residence, hospital, or place of worship.
• 8:00 pm through 7:00 am Monday through Saturday
• 8:00 pm Saturday through 12:00 pm (noon) Sunday
• 8:00 pm Sunday through 7:00 am Monday
This time regulation shall not apply to sawing contraction joints, maintenance or operation of safety and traffic control devices such as barricades, signs and lighting, or to construction of an emergency nature.
Any arrow board used for traffic control that is to remain in place overnight shall be of a non-motorized type in order to eliminate noise and comply with the City’s Ordinance.
Exception: Any machine or device or part thereof which is regulated by or becomes regulated by Federal or State of Illinois noise standards shall conform to those above standards. Such equipment shall be operated as designated above.
1.5 Prevailing Wage Rates
The current prevailing wage rates for Champaign County, Illinois are found on the Illinois Department of Labor (IDOL) website (https://labor.illinois.gov/laws-rules/conmed/current-prevailing-rates.html).
1.6 Prosecution of the Work and Working Days
Replace Article 108.03 of the Standard Specifications with the following:
The Contractor shall begin the work to be performed under the contract according to a satisfactory progress schedule or critical path schedule. If the Contractor has not submitted a satisfactory progress schedule or critical path schedule to the Engineer within five days after the execution of the contract by the Department, then the Contractor shall begin the work to be performed under the contract not later than ten days after the execution of the contract by the Department. The work shall be prosecuted in such a manner and with such a supply of materials, equipment and labor as is considered necessary to ensure its completion according to the time specified in the contract.
The Contractor shall notify the Engineer at least 24 hours in advance of either discontinuing or resuming operations.
Add the following to the end of the first paragraph of Article 108.04 of the Standard Specifications:
The charging of working days may start later than ten days after the execution and approval of the contract according to a satisfactory progress schedule or critical path schedule.
https://labor.illinois.gov/laws-rules/conmed/current-prevailing-rates.html https://labor.illinois.gov/laws-rules/conmed/current-prevailing-rates.html
25-00706-01-BD 1407 N. Lincoln Avenue Building Demolition 4
PART 2 - TECHNICAL PROVISIONS
The following Special Provisions supplement the “Standard Specifications for Road and Bridge Construction, Adopted January 1, 2022”, the “Manual of Test Procedures for Materials” in effect on the date of invitation for bids, the “BDE Special Provisions”, and the “Supplemental Specifications and Recurring Special Provisions”, and indicated on the Check Sheet included herein, which apply to and govern the demolition of the building at 1407 N Lincoln Avenue (Section 25-00706-01-BD) and in case of conflict with any part, or parts, of said Specifications, the said Special Provisions shall take precedence and shall govern.
2.1 Location of Project
1407 N. Lincoln Avenue, Urbana, IL 61801.
2.2 Description of Work
Demolition and disposal services for a building located at 1407 N. Lincoln Avenue, Urbana, IL. The site will be restored to a mixed-use lot, consisting of asphalt and grass. The building is approximately 10,000 square feet and has known asbestos, which requires special care and compliance with all relevant safety protocols for its removal and disposal. See the Asbestos Inspection Report in Section E for the asbestos survey results.
2.3 City Permits
The Contractor shall comply with all applicable provisions of the City of Urbana Code and all regulations governing demolition, construction, and work within the public right-of-way, as specified in Article 107.01 of the Standard Specifications for Road and Bridge Construction. In accordance with Article 107.02 of the Standard Specifications, it is the Contractor’s responsibility to obtain all required utility locates and to secure all necessary local permits including demolition, class 2 erosion control, and right-of-way prior to commencing work.
Additionally, the contractor is required to completely demolish and remove all foundation walls, footings, basement floors/slabs, and any other below grade structures in compliance with the City’s Demolition Permit Standards. For information regarding the required City permits and their related guidelines, the Contractor may visit:
• Demolition Permits and Guidelines https://www.urbanail.gov/community-development-services/page/demolition-permits-and-guidelines
• Erosion Control Permits https://www.urbanail.gov/public-works/page/erosion-control
• Right-of-Way Permits.
https://www.urbanail.gov/public-works/page/utility-and-right-way-permits
All applicable permits, licenses, and final inspections are the responsibility of and shall be obtained or paid for by the Contractor; however, all City permit fees, including demolition, erosion control, and right-of-way fees, will be waived.
https://www.urbanail.gov/community-development-services/page/demolition-permits-and-guidelines https://www.urbanail.gov/public-works/page/erosion-control
25-00706-01-BD 1407 N. Lincoln Avenue Building Demolition 5
2.4 Traffic Control and Protection
The Contractor shall submit a Traffic Control Plan no later than two (2) weeks prior to the start of work.
The traffic control shall be in accordance with the applicable sections of the Standard Specifications for Road and Bridge Construction, the applicable guidelines contained in the Illinois Manual on Uniform Traffic Control Devices for Streets and Highways, these Special Provisions and any special details and highway standards contained herein and in the plans.
Special attention is called to Articles 107.09 and 107.14 of the Standard Specifications, the following Highway Standard related to Traffic Control, and the listed Supplemental Specifications and Recurring Special Provisions.
Highway Standards:
• 701101
• 701106
• 701606
• 701801
• 701901
Special Provisions:
• LRS 3 Work Zone Traffic Control Surveillance
• LRS 4 Flaggers in Work Zone
• BDE Special Provision 80439 Vehicle and Equipment Warning Lights
Traffic: It is the intention of the City that Lincoln Avenue be kept open to two-way traffic at all times during the construction of this section.
During periods when material or equipment is being hauled to or from the project site all haul trucks shall have at least one (1) flashing amber light or one (1) set of dual emergency flashers, operating when within the lane closure. In addition “WORK TRUCK DO NOT FOLLOW” shall be displayed on the rear of all haul trucks. Displays shall be 36 inch x 18 inch (0.91 m x 0.46 m) made of Fluorescent Orange reflective material as specified in Article 1106.01. This work shall be considered as included in the contract unit prices for the construction items involved and no additional compensation will be allowed.
Parking of personal vehicles within the right-of-way will be strictly prohibited. Off-site parking and transportation arrangements shall be the responsibility of the Contractor.
Advanced Notice
The City of Urbana will be responsible for notifying the public, the United States Postal Service and the emergency service agencies for road closures and changes in the traffic maintenance plans.
The contractor shall notify the City 72 hours in advanced of implementing new or adjusting existing traffic control.
Basis of Payment. Traffic Control and Protection will be paid for at the contract lump sum price for
TRAFFIC CONTROL AND PROTECTION, (SPECIAL).
25-00706-01-BD 1407 N. Lincoln Avenue Building Demolition 6
2.5 Status of Utilities
Name & Address of Utility Type Location
Adjustment or
Relocation
Ameren Illinois 1112 West Anthony Drive
Urbana, IL 61802 618-301-5305
Dcjulierequest@Ameren.com
Electric & Gas
ATT/Distribution 1501 East Washington Street
Urbana, IL 61802 217-337-6292
G11629@ATT.com
Communication
Campus Communications (CCG Fiber) 601 North Country Fair Drive
Champaign, IL 61821 217-353-3031xDesk
Gis@Pavlovmedia.com
Communication
Metro Comm/Conxxus 217-728-3621 lsesko@metrocomm.com Communication i3 Broadband - Champaign/Urbana 808 Dennison Drive
Champaign, IL 61820 309-670-0400
Engineering@I3broadband.net
Communication
Illinois American Water-Champaign 1406 Cardinal Court
Urbana, IL 61801 309-644-2402
Timothy.Kerns@Amwater.com
Water
City of Urbana 706 S Glover Ave Urbana, IL 61802
217-384-2396 Daniel.Rothermel@UrbanaIL.gov
Sanitary Storm Sewer
Traffic Signal Wiring Street Light Wiring
Toll Free J.U.L.I.E. Telephone Number (800) 892-0123 *= J.U.L.I.E. Member mailto:Dcjulierequest@Ameren.com mailto:G11629@ATT.com mailto:Gis@Pavlovmedia.com mailto:lsesko@metrocomm.com mailto:Engineering@I3broadband.net mailto:Timothy.Kerns@Amwater.com
25-00706-01-BD 1407 N. Lincoln Avenue Building Demolition 7
2.6 Topsoil Sourcing and Placement
Contractor is responsible for sourcing and placing 6 inches of uncontaminated loamy topsoil suitable for seeding to backfill the excavated area in accordance with Articles 211 and 1081.05 of the Standard Specifications.
Basis of Payment. Topsoil Sourcing and Placement will be paid for at the contract lump sum price for TOPSOIL FURNISH AND PLACE, of the thickness specified.
SECTION B
IDOT Special Provisions ii
INDEX
FOR
SUPPLEMENTAL SPECIFICATIONS
AND RECURRING SPECIAL PROVISIONS
Adopted January 1, 2026
This index contains a listing of SUPPLEMENTAL SPECIFICATIONS, frequently used RECURRING SPECIAL PROVISIONS, and LOCAL ROADS AND STREETS
RECURRING SPECIAL PROVISIONS.
ERRATA Standard Specifications for Road and Bridge Construction (Adopted 1-1-22) (Revised 1-1-26)
SUPPLEMENTAL SPECIFICATIONS
Std. Spec. Sec. Page No.
109 Measurement and Payment 202 Earth and Rock Excavation 204 Borrow and Furnished Excavation 207 Porous Granular Embankment 211 Topsoil and Compost 214 Grading and Shaping Ditches 406 Hot-Mix Asphalt Binder and Surface Course 407 Hot-Mix Asphalt Pavement (Full-Depth) 420 Portland Cement Concrete Pavement 502 Excavation for Structures 504 Precast Concrete Structures 509 Metal Railings 522 Retaining Walls 540 Box Culverts 542 Pipe Culverts 550 Storm Sewers 586 Granular Backfill for Structures 601 Pipe Drains, Pipe Underdrains, and French Drains 630 Steel Plate Beam Guardrail 632 Guardrail and Cable Road Guard Removal 644 High Tension Cable Median Barrier 665 Woven Wire Fence 701 Work Zone Traffic Control and Protection 781 Raised Reflective Pavement Markers 782 Reflectors 801 Electrical Requirements 821 Roadway Luminaires
1003 Fine Aggregates 1004 Coarse Aggregates 1010 Finely Divided Minerals 1020 Portland Cement Concrete ……… 1030 Hot-Mix Asphalt 1040 Drain Pipe, Tile, and Wall Drain 1042 Precast Concrete Products 1061 Waterproofing Membrane System iii
1067 Luminaire ……… 1097 Reflectors 1102 Hot-Mix Asphalt Equipment
Check Sheet for Recurring Special Provisions
Page 1 of 2 BLR 11300 (Rev. 10/27/25)Printed 12/03/25
Local Public Agency
City of Urbana
County
Champaign
Section Number
25-00706-01-BD
Check this box for lettings prior to 01/01/2026
The Following Recurring Special Provisions Indicated By An "X" Are Applicable To This Contract And Are Included By Reference:
Recurring Special Provisions
Check Sheet # Page No.
1 Additional State Requirements for Federal-Aid Construction Contracts 87
2 Subletting of Contracts (Federal-Aid Contracts) 90
3 EEO 91
4 Specific EEO Responsibilities Non Federal-Aid Contracts 101
5 Required Provisions - State Contracts 106
6 Asbestos Bearing Pad Removal 112
7 Asbestos Waterproofing Membrane and Asbestos HMA Surface Removal 113
8 Temporary Stream Crossings and In-Stream Work Pads 114
9 Construction Layout Stakes 115
10 Use of Geotextile Fabric for Railroad Crossing 118
11 Subsealing of Concrete Pavements 120
12 Hot-Mix Asphalt Surface Correction 124
13 Pavement and Shoulder Resurfacing 126
14 Patching with Hot-Mix Asphalt Overlay Removal 127
15 Polymer Concrete 129
16 Reserved 131
17 Bicycle Racks 132
18 Temporary Portable Bridge Traffic Signals 134
19 Nighttime Inspection of Roadway Lighting 136
20 English Substitution of Metric Bolts 137
21 Calcium Chloride Accelerator for Portland Cement Concrete 138
22 Quality Control of Concrete Mixtures at the Plant 139
23 Quality Control/Quality Assurance of Concrete Mixtures 147
24 Reserved 163
25 Reserved 164
26 Temporary Raised Pavement Markers 165
27 Restoring Bridge Approach Pavements Using High-Density Foam 166
28 Portland Cement Concrete Inlay or Overlay 169
29 Portland Cement Concrete Partial Depth Hot-Mix Asphalt Patching 173
30 Longitudinal Joint and Crack Patching 176
31 Concrete Mix Design - Department Provided 178
32 Station Numbers in Pavements or Overlays 179
Page 2 of 2 BLR 11300 (Rev. 10/27/25)
Local Public Agency
City of Urbana
County
Champaign
Section Number
25-00706-01-BD
Printed 12/03/25
The Following Local Roads And Streets Recurring Special Provisions Indicated By An "X" Are Applicable To This Contract And Are Included By Reference:
Local Roads And Streets Recurring Special Provisions
Check Sheet # Page No.
LRS 1 Reserved 181
LRS 2 Furnished Excavation 182
LRS 3 Work Zone Traffic Control Surveillance 183
LRS 4 Flaggers in Work Zones 184
LRS 5 Contract Claims 185
LRS 6 Bidding Requirements and Conditions for Contract Proposals 186
LRS 7 Bidding Requirements and Conditions for Material Proposals 192
LRS 8 Reserved 198
LRS 9 Bituminous Surface Treatments 199
LRS 10 Reserved 203
LRS 11 Employment Practices 204
LRS 12 Wages of Employees on Public Works 206
LRS 13 Selection of Labor 208
LRS 14 Paving Brick and Concrete Paver Pavements and Sidewalks 209
LRS 15 Partial Payments 212
LRS 16 Protests on Local Lettings 213
LRS 17 Substance Abuse Prevention Program 214
LRS 18 Multigrade Cold Mix Asphalt 215
LRS 19 Reflective Crack Control Treatment 216
BDE SPECIAL PROVISIONS
For the January 16 and February 27, 2026 Lettings
The following special provisions indicated by a “check mark” are applicable to this contract and will be included by the Project Coordination and Implementation Section of the Bureau of Design & Environment (BDE).
File Name # Special Provision Title Effective Revised 80099 1 Accessible Pedestrian Signals (APS) April 1, 2003 Jan. 1, 2022 80274 2 Aggregate Subgrade Improvement April 1, 2012 April 1, 2022 80192 3 Automated Flagger Assistance Devices Jan. 1, 2008 April 1, 2023 80173 4 Bituminous Materials Cost Adjustments Nov. 2, 2006 Aug. 1, 2017 80426 5 Bituminous Surface Treatment with Fog Seal Jan. 1, 2020 Jan. 1, 2022 80475 6 Bridge Deck Concrete Overlays Jan. 1, 2026
* 80241 7 Bridge Demolition Debris July 1, 2009
* 5053I 8 Building Removal Sept. 1, 1990 Aug. 1, 2022
* 5026I 9 Building Removal with Asbestos Abatement Sept. 1, 1990 Aug. 1, 2022
80460 10 Cement, Finely Divided Minerals, Admixtures, Concrete, and Mortar Jan. 1, 2025 Jan. 1, 2026 80384 11 Compensable Delay Costs June 2, 2017 April 1, 2019
* 80198 12 Completion Date (via calendar days) April 1, 2008
* 80199 13 Completion Date (via calendar days) Plus Working Days April 1, 2008
80461 14 Concrete Barrier Jan. 1, 2025 80453 15 Concrete Sealer Nov. 1, 2023 80261 16 Construction Air Quality – Diesel Retrofit June 1, 2010 Jan. 1, 2025 80476 17 Deck Slab Repair Jan. 1, 2026
* 80029 18 Disadvantaged Business Enterprise Participation Sept. 1, 2000 Jan. 2, 2025 80467 19 Erosion Control Blanket Aug. 1, 2025 80229 20 Fuel Cost Adjustment April 1, 2009 Aug. 1, 2017 80452 21 Full Lane Sealant Waterproofing System Nov. 1, 2023 80433 22 Green Preformed Thermoplastic Pavement Markings Jan. 1, 2021 Jan. 1, 2022 80471 23 Guardrail Nov. 1, 2025 80472 24 High Friction Surface Treatment Nov. 1, 2025 80456 25 Hot-Mix Asphalt Jan. 1, 2024 Jan. 1, 2026 80446 26 Hot-Mix Asphalt - Longitudinal Joint Sealant Nov. 1, 2022 Aug. 1, 2023 80438 27 Illinois Works Apprenticeship Initiative – State Funded Contracts June 2, 2021 April 2, 2024 80477 28 Longitudinal Tining Jan. 1, 2026 80450 29 Mechanically Stabilized Earth Retaining Walls Aug. 1, 2023 Aug. 1, 2025 80478 30 Modified Longitudinal Construction Joint Jan. 1, 2026 80464 31 Pavement Marking April. 1, 2025 Nov. 1, 2025 80468 32 Pavement Patching Aug. 1, 2025 80441 33 Performance Graded Asphalt Binder Jan. 1, 2023 80459 34 Preformed Plastic Pavement Marking June 2, 2024
* 3426I 35 Railroad Protective Liability Insurance Dec. 1, 1986 Jan. 1, 2022 80473 36 Raised Reflective Pavement Markers Nov. 1, 2025 80455 37 Removal and Disposal of Regulated Substances Jan. 1, 2024 April 1, 2024 80474 38 Residential Driveway Temporary Signal Nov. 1, 2025 80445 39 Seeding Nov. 1, 2022 80457 40 Short Term and Temporary Pavement Markings April 1, 2024 April 2, 2024 80462 41 Sign Panels and Appurtenances Jan. 1, 2025 Jan. 1, 2026 80479 42 Sinusoidal Rumble Strips Jan. 1, 2026 80469 43 Slope Wall Aug. 1, 2025 80448 44 Source of Supply and Quality Requirements Jan. 2, 2023 Jan. 1, 2026 80340 45 Speed Display Trailer April 2, 2014 Jan. 1, 2022 80127 46 Steel Cost Adjustment April 2, 2004 Nov. 1, 2025 80480 47 Structural Repair of Concrete Jan. 1, 2026 80397 48 Subcontractor and DBE Payment Reporting April 2, 2018 80391 49 Subcontractor Mobilization Payments Nov. 2, 2017 April 1, 2019 80463 50 Submission of Bidders List Information Jan. 2, 2025 Mar. 2, 2025 80437 51 Submission of Payroll Records April 1, 2021 Nov. 2, 2023
80435 52 Surface Testing of Pavements – IRI Jan. 1, 2021 Jan. 1, 2023 80465 53 Surveying Services April 1, 2025
80481 54 Temporary Concrete Barrier Jan. 1, 2026 80466 55 Temporary Rumble Strips April 1, 2025 80470 56 Traffic Signal Backplate Aug. 1, 2025
* 20338 57 Training Special Provisions Oct. 15, 1975 Sept. 2, 2021 80429 58 Ultra-Thin Bonded Wearing Course April 1, 2020 Jan. 1, 2022 80439 59 Vehicle and Equipment Warning Lights Nov. 1, 2021 Nov. 1, 2022 80458 60 Waterproofing Membrane System Aug. 1, 2024 80302 61 Weekly DBE Trucking Reports June 2, 2012 Jan. 2, 2025 80454 62 Wood Sign Support Nov. 1, 2023
80427 63 Work Zone Traffic Control Devices Mar. 2, 2020 Jan. 1, 2026
* 80071 64 Working Days Jan. 1, 2002
Highlighted items indicate a new or revised special provision for the letting.
An * indicates the special provision requires additional information from the designer, which needs to be submitted separately.
The Project Coordination and Implementation Section will then include the information in the applicable special provision.
The following special provisions are in the 2026 Supplemental Specifications and Recurring Special Provisions.
File Name Special Provision Title New Location(s) Effective Revised
80447 Grading and Shaping Ditches Articles 214.03 & 214.04 Jan. 1, 2023
BUILDING REMOVAL WITH ASBESTOS ABATEMENT (BDE)
Effective: September 1, 1990 Revised: August 1, 2022
Description. This work shall consist of the removal and disposal of building(s), including all foundations, retaining walls, and piers, down to a plane 1 ft (300 mm) below the ultimate bottom of building elevation or proposed bottom of construction elevation. The building(s) are identified as follows:
Parcel Bldg. No. No. Location Description
CONSTRUCTION REQUIREMENTS
General. The IEPA’s "State of Illinois Demolition/Renovation/Asbestos Project Notification Form” shall be submitted and a copy sent to the Engineer. It shall be updated if there is a change in the start and/or finish date or if the quantity of asbestos changes by more than 20 percent.
Asbestos abatement work shall be performed by an IDPH licensed Contractor prequalified with the Illinois Capital Development Board who has an on-site supervisor licensed by IDPH and employs workers licensed by IDPH. This work shall be completed according to the requirements of the U.S. Environmental Protection Agency (USEPA), IEPA, OSHA, and local regulatory agencies.
Discontinuance of Utilities. The Contractor shall arrange for the discontinuance of all utility services and the removal of the metering devices that serve the building(s) according to the respective requirements and regulations of the city, county, or utility companies involved. The Contractor shall disconnect and seal the service outlets.
Posting. Upon execution of the contract and prior to the removal of any buildings, the Contractor shall paint or stencil, in contrasting colors of an oil base paint, on all sides of each building or structure, the following posting:
NO TRESPASSING
VIOLATORS WILL BE PROSECUTED
The postings shall be positioned prominently on the structure(s) so they can be easily read and at a sufficient height to prevent defacing.
1 PIN: 91-21-07-226-009 1407 N Lincoln Ave, Urbana, IL 61801
A single-story building of 10,000 square feet that has been occupied and used as a fire station by the fire department of the City of Urbana since the 1970's.
Sallam, Omar StrikeOut
Asbestos Abatement. Friable asbestos containing building materials (ACBMs) and Category II non-friable ACBMs shall be removed from the building(s) prior to demolition. Category II non-friable ACBMs include asbestos containing transite boards, siding, and other cementitious materials (cement pipe or highly weathered roofing shingles/materials) which have a likelihood of becoming friable during typical demolition activities (by crumbling, pulverizing, or otherwise reducing to powder) making them regulated asbestos containing materials (RACM). Removed ACBM shall be kept separate from non-ACBM demolition debris for purposes of transport and disposal.
Category I non-friable ACBM may be kept in place for demolition or removal of the building unless it has become friable as determined by the ACBM inspector. If the Contractor demolishes the building(s) with the non-friable asbestos in place, the following shall apply.
(a) The Contractor shall continuously wet the non-friable ACBM and other building debris with water during demolition and loading for disposal.
(b) The Contractor shall dispose of all demolition debris as ACBM.
The Contractor shall perform air monitoring during asbestos abatement activities. Air sampling shall be conducted by a qualified air sampling professional. Air sampling shall be conducted according to NIOSH Method 7400. Air monitoring equipment shall be calibrated and maintained in proper operating condition. The Contractor shall submit a copy of the air sampling professional’s certificate to the Engineer. The results of the tests, and daily calibration and maintenance records shall be kept on site and be available to the Engineer upon request.
Personal monitoring shall be conducted per applicable OSHA regulations. Excursion limits shall be monitored daily, and corrective actions taken immediately to bring excursions within OSHA permissible exposure limits.
When asbestos is removed prior to demolition, clearance testing per IDPH shall be conducted upon the removal of ACBM.
Submittals. The following submittals shall be made to the Engineer prior to the start of the asbestos abatement:
(a) Manufacturer's certification stating that vacuums, ventilation equipment, and other equipment required to contain airborne fibers conform to ANSI 29.2.
(b) A listing of the brand name, manufacturer, and specification of all sealants or surfactants to be used.
(c) Proof that arrangements for transport and disposal of ACBMs have been obtained (i.e., a letter of authorization to utilize designated landfill).
(d) A detailed work plan of the Contractor’s anticipated procedures including the location and layout of decontamination units, the sequencing of work, the respiratory protection plan, a site safety plan, a disposal plan, and a detailed description of the methods to be used to control pollution.
(e) Proof of the Contractor’s prequalification with Capital Development Board and employee certifications with IDPH.
Submittals that shall be made upon completion of abatement work:
(f) Copies of waste chain-of-custodies, trip tickets, shipping manifests, or disposal receipts for asbestos waste materials removed from the work area.
(g) Copies of each day’s work site entry logbook with information on worker and visitor access.
(h) Logs documenting filter changes on respirators, HEPA vacuums, negative pressure ventilation units, and other engineering controls.
(i) Test results of any bulk material analysis and air sampling data collected during the abatement including results of any on-site testing by any federal, state, or local agency.
Any holes, such as basements, shall be backfilled according to Article 502.10.
Basis of Payment. This work will be paid for at the contract lump sum unit price for BUILDING
REMOVAL NO. ___.
Removal and disposal of friable ACBM will be paid for at the contract lump sum unit price for
REMOVAL AND DISPOSAL OF FRIABLE ASBESTOS, BUILDING NO. ____.
Removal and disposal of non-friable ACBM will be paid for at the contract lump sum unit price for
REMOVAL AND DISPOSAL OF NON-FRIABLE ASBESTOS, BUILDING NO. ____.
5026I
Sallam, Omar StrikeOut
CEMENT, FINELY DIVIDED MINERALS, ADMIXTURES, CONCRETE, AND MORTAR (BDE)
Effective: January 1, 2025 Revised: January 1, 2026
Revise the first paragraph of Article 285.05 of the Standard Specifications to read:
“ 285.05 Fabric Formed Concrete Revetment Mat. The grout shall consist of a mixture of cement, fine aggregate, and water so proportioned and mixed as to provide a pumpable slurry.
Fly ash or ground granulated blast furnace (GGBF) slag, and concrete admixtures may be used at the option of the Contractor. The grout shall have an air content of not less than 6.0 percent nor more than 9.0 percent of the volume of the grout. The mix shall obtain a compressive strength of 2500 psi (17,000 kPa) at 28 days according to Article 1020.09.”
Revise Article 302.02 of the Standard Specifications to read:
“ 302.02 Materials. Materials shall be according to the following.
Item Article/Section
(a) Cement
(b) Water
(c) Hydrated Lime .................................................................................................... 1012.01
(d) By-Product, Hydrated Lime ................................................................................ 1012.02
(e) By-Product, Non-Hydrated Lime ........................................................................ 1012.03
(f) Lime Slurry ......................................................................................................... 1012.04
(g) Fly Ash
(h) Soil for Soil Modification (Note 1) ....................................................................... 1009.01
(i) Bituminous Materials (Note 2)
Note 1. This soil requirement only applies when modifying with lime (slurry or dry).
Note 2. The bituminous materials used for curing shall be emulsified asphalt RS-2, CRS- 2, HFE 90, or HFE 150; rapid curing liquid asphalt RC-70; or medium curing liquid asphalt MC-70 or MC-250.”
Revise Article 312.07(c) of the Standard Specifications to read:
“ (c) Cement .................................................................................................................... 1001”
Add Article 312.07(i) of the Standard Specifications to read:
“ (i) Ground Granulated Blast Furnace (GGBF) Slag ...................................................... 1010”
Revise the first paragraph of Article 312.09 of the Standard Specifications to read:
“ 312.09 Proportioning and Mix Design. At least 60 days prior to start of placing CAM II, the Contractor shall submit samples of materials to be used in the work for proportioning and testing.
The mixture shall contain a minimum of 200 lb (120 kg) of cement per cubic yard (cubic meter).
Cement may be replaced with fly ash or ground granulated blast furnace (GGBF) slag according to Article 1020.05(c)(1) or 1020.05(c)(2), respectively, however the minimum cement content in the mixture shall be 170 lbs/cu yd (101 kg/cu m). Blends of coarse and fine aggregates will be permitted, provided the volume of fine aggregate does not exceed the volume of coarse aggregate. The Engineer will determine the proportions of materials for the mixture according to the “Portland Cement Concrete Level III Technician Course” manual. However, the Contractor may substitute their own mix design. Article 1020.05(a) shall apply, and a Level III PCC Technician shall develop the mix design.”
Revise Article 352.02 of the Standard Specifications to read:
“ 352.02 Materials. Materials shall be according to the following.
(a) Cement (Note 1)
(b) Soil for Soil-Cement Base Course ....................................................................... 1009.03
(c) Water
(d) Bituminous Materials (Note 2)
Note 1. Bulk cement may be used for the traveling mixing plant method if the equipment for handling, weighing, and spreading the cement is approved by the Engineer.
Note 2. The bituminous materials used for curing shall be emulsified asphalt RS-2, CRS-2, HFE 90, or HFE 150; rapid curing liquid asphalt RC-70; or medium curing liquid asphalt MC-70 or MC-250.”
Revise Article 404.02 of the Standard Specifications to read:
“ 404.02 Materials. Materials shall be according to the following.
(a) Cement
(b) Water
(c) Fine Aggregate .................................................................................................... 1003.08
(d) Bituminous Material (Tack Coat) .......................................................................... 1032.06
(e) Emulsified Asphalts (Note 1) (Note 2) .................................................................. 1032.06
(f) Fiber Modified Joint Sealer .................................................................................. 1050.05
(g) Additives (Note 3)
Note 1. When used for slurry seal, the emulsified asphalt shall be CQS-1h according to Article 1032.06(b).
Note 2. When used for micro-surfacing, the emulsified asphalt shall be CQS-1hP according to Article 1032.06(e).
Note 3. Additives may be added to the emulsion mix or any of the component materials to provide the control of the quick-traffic properties. They shall be included as part of the mix design and be compatible with the other components of the mix.
Revise the last sentence of the fourth paragraph of Article 404.08 of the Standard Specifications to read:
“When approved by the Engineer, the sealant may be dusted with fine sand, cement, or mineral filler to prevent tracking.”
Revise Note 2 of Article 516.02 of the Standard Specifications to read:
“ Note 2. The sand-cement grout mix shall be according to Section 1020 and shall be a 1:1 blend of sand and cement comprised of a Type I, IL, or II cement at 185 lb/cu yd (110 kg/cu m). The maximum water cement ratio shall be sufficient to provide a flowable mixture with a typical slump of 10 in. (250 mm).”
Revise Note 2 of Article 543.02 of the Standard Specifications to read:
“ Note 2. The grout mixture shall be 6.50 hundredweight/cu yd (385 kg/cu m) of cement plus fine aggregate and water. Fly ash or ground granulated blast furnace (GGBF) slag may replace a maximum of 5.25 hundredweight/cu yd (310 kg/cu m) of the cement. The water/cement ratio, according to Article 1020.06, shall not exceed 0.60. An air-entraining admixture shall be used to produce an air content, according to Article 1020.08, of not less than 6.0 percent nor more than 9.0 percent of the volume of the grout. The Contractor shall have the option to use a water-reducing or high range water-reducing admixture.”
Revise Article 583.01 of the Standard Specifications to read:
“ 583.01 Description. This work shall consist of placing cement mortar along precast, prestressed concrete bridge deck beams as required for fairing out any unevenness between adjacent deck beams prior to placing of waterproofing membrane and surfacing.”
Revise Article 583.02(a) of the Standard Specifications to read:
“ (a) Cement .................................................................................................................... 1001”
Revise the first paragraph of Article 583.03 of the Standard Specifications to read:
“ 583.03 General. This work shall only be performed when the air temperature is 45 °F (7 °C) and rising. The mixture for cement mortar shall consist of three parts sand to one part cement by volume. The amount of water shall be no more than that necessary to produce a workable, plastic mortar.”
Revise Article 606.02(h) of the Standard Specifications to read:
“ (h) Fibers (Note 1) ........................................................................................................ 1014”
Revise Note 1 in Article 606.02(h) of the Standard Specifications to read:
“ Note 1. Fibers, when required, shall only be used in the concrete mixture for slipform applications.”
Revise the third paragraph in Article 606.10 of the Standard Specifications to read:
“ Welded wire fabric shall be 6 x 6 in. (150 x 150 mm) mesh, #4 gauge (5.74 mm), 58 lb (26 kg) per 100 sq ft (9 sq m).”
Revise Article 1001.01(d) of the Standard Specifications to read:
“ (d) Rapid Hardening Cement. Rapid hardening cement shall be according to the Bureau of Materials Policy Memorandum “Portland or Blended Cement Acceptance Procedure for Qualified and Non-Qualified Plants”, and ASTM C 1600, Type URH, Type VRH, or Type RH-CAC. It shall be used according to Article 1020.04 or when approved by the Engineer.
The Contractor shall submit a report from the manufacturer or an independent lab that contains results for testing according to ASTM C 1600 which shows the cement meets the requirements of either Type URH, Type VRH, or Type RH-CAC. Test data shall be less than 1 year old from the date of submittal.
Revise Article 1001.01(e) of the Standard Specifications to read:
“ (e) Other Cements. Other cements shall be according to the Bureau of Materials Policy Memorandum “Portland or Blended Cement Acceptance Procedure for Qualified and Non- Qualified Plants”, and ASTM C 1157 or ASTM C 1600, as applicable. Other cements shall be used according to Article 1020.04 or when approved by the Engineer. For cements according to ASTM C 1157, the Contractor shall submit a report from the manufacturer or an independent lab that contains results of tests which shows the cement meets the requirements Type GU, HE, MS, MH, or LH. For cements according to ASTM C 1600, the Contractor shall submit a report from the manufacturer or an independent lab that contains results of tests which shows the cement meets the requirements Type MRH or GRH. Test data shall be less than 1 year old from the date of submittal.”
Revise Article 1002.02 of the Standard Specifications to read:
“ 1002.02 Quality. Water used with cement in concrete or mortar and water used for curing concrete shall be clean, clear, and free from sugar. In addition, water shall be tested and evaluated for acceptance according to one of the following options.
OPTION 1.
(a) Acceptable limits for acidity and alkalinity when tested according to ITP T 26.
(1) Acidity -- 0.1 Normal NaOH ........................................................................ 2 ml max.*
(2) Alkalinity -- 0.1 Normal HCI ....................................................................... 10 ml max.*
*To neutralize 200 ml sample.
(b) Acceptable limits for solids when tested according to the following.
(1) Organic (ITP T 26) .................................................................................... 0.02% max.
(2) Inorganic (ITP T 26) .................................................................................. 0.30% max.
(3) Sulfate (SO4) (ASTM D 516-82) ............................................................... 0.05% max.
(4) Chloride (ASTM D 512) ............................................................................ 0.06% max.
(c) The following tests shall be performed on the water sample and on deionized water. The same cement and sand shall be used for both tests.
(1) Unsoundness (ASTM C 151).
(2) Initial and Final Set Time (ASTM C 266).
(3) Strength (ASTM C 109).
The test results for the water sample shall not deviate from the test results for the deionized water, except as allowed by the precision in the test method.
OPTION 2. Water shall meet the requirements ASTM C 1602 Tables 1 and 2 as outlined in Sections 5.1, 5.2, and 5.4.”
Revise Note 2/ in Article 1003.01(b) of the Standard Specifications to read:
“ 2/ Applies only to sand. Sand exceeding the colorimetric test standard of 11 (Illinois
Modified AASHTO T 21) will be checked for mortar making properties according to Illinois Modified ASTM C 87 and shall develop a compressive strength at the age of 14 days when using Type I, IL, or II cement of not less than 95 percent of the comparable standard.
Revise the second sentence of Article 1003.02(e)(1) of the Standard Specifications to read:
“ The test will be performed with Type I, IL, or II portland cement having a total equivalent alkali content (Na2O + 0.658K2O) of 0.90 percent or greater.”
Revise the first sentence of the second paragraph of Article 1003.02(e)(3) of the Standard Specifications to read:
“ The ASTM C 1293 test shall be performed with Type I, IL, or II portland cement having a total equivalent alkali content (Na2O + 0.658K2O) of 0.80 percent or greater.”
Revise the second sentence of Article 1004.02(g)(1) of the Standard Specifications to read:
“ The test will be performed with Type I, IL, or II portland cement having a total equivalent alkali content (Na2O + 0.658K2O) of 0.90 percent or greater.”
Add the following Section to the Standard Specifications.
“SECTION 1014. FIBERS FOR CONCRETE
1014.01 General. Fibers used in concrete shall be Type II or Type III (polyolefin or carbon) according to ASTM C 1116. The testing required for Type II fibers or Type III polyolefin fibers shall be performed by an independent lab a minimum of once every five years, and the test results provided to the Department. Manufacturers of Type III carbon fibers shall provide materials certification documentation not more than 6 years old a minimum of once every 5 years to the Department. The Department will maintain a qualified product list. The method of inclusion of fibers into concrete mixtures shall be according to the manufacturer’s specifications.
At the discretion of the Engineer, the concrete mixture shall be evaluated in a field demonstration for fiber clumping, ease of placement, and ease of finishing. The field demonstration shall consist of a minimum 2 cu yd (1.5 cu m) trial batch placed in a 12 ft x 12 ft (3.6 m x 3.6 m) slab.
1014.02 Concrete Gutter, Curb, Median and Paved Ditch. Fibers shall be Type III. Fibers shall have a minimum length of 1/2 in. (13 mm) and a maximum length of 0.75 in. (19 mm). The maximum dosage rate in the concrete mixture shall not exceed 1.5 lb/cu yd (0.9 kg/cu m). The minimum dosage rate shall be per the manufacturer’s recommendation.
1014.03 Concrete Inlay or Overlay. Fibers shall be Type III. Fibers shall have a minimum length of 1.0 in. (25 mm), a maximum length of 2 1/2 in. (63 mm), and a maximum aspect ratio (length divided by the equivalent diameter of the fiber) of 150. The maximum dosage rate shall not exceed 5.0 lb/cu yd (3.0 kg/cu m). The minimum dosage rate shall be per the manufacturer’s recommendation.
1014.04 Bridge Deck Fly Ash, Ground Granulated Blast Furnace (GGBF) Slag, High
Reactivity Metakaolin, or Microsilica (Silica Fume) Concrete Overlay. Fibers shall be Type III. The dosage rate shall be a minimum of 3.0 lb/cu yd (1.8 kg/cu m), unless a field demonstration according to Article 1014.01 indicates that a lower dosage rate is necessary.
Based on the results of the field demonstration, the Department has the option to reduce the dosage rate of fibers, but the dosage will not be reduced to less than 2.0 lb / cu yd (1.2 kg/cu m).
1014.05 Bridge Deck Latex Concrete Overlay. Fibers shall be Type II or III. Fibers shall have a minimum length of 0.75 in. (19 mm), a maximum length of 1.75 in. (45 mm), and an aspect ratio (length divided by the equivalent diameter of the fiber) of between 70 and 100. The dosage rate shall be a minimum of 3.0 lb/cu yd (1.8 kg/cu m), unless a field demonstration according to Article 1014.01 indicates that a lower dosage rate is necessary. Based on the results of the field demonstration, the Department has the option to reduce the dosage rate of fibers, but the dosage will not be reduced to less than 2.0 lb/cu yd (1.2 kg/cu m).”
Add the following Section to the Standard Specifications:
“SECTION 1015. HIGH PERFORMANCE SHOTCRETE
1015.01 Packaged Shotcrete With Aggregate. The packaged shotcrete with aggregate shall be a pre-blended dry combination of materials for the wet-mix shotcrete method according to ASTM C 1480, Type FA or CA, Grade FR, Class I. The fibers shall be Type III according to Article 1014.01. The cement and finely divided minerals in the mixture shall be a minimum
6.65 cwt/cu yd (395 kg/cu m), and the portland cement shall not be below 4.70 cwt/cu yd (279 kg/cu m). Microsilica is required in the mixture and shall be a minimum of 5 percent by weight (mass) of cementitious material, and a maximum of 10 percent. Strength requirements shall be according to ASTM C 1480 except that the strength at 28 days shall be at least 4000 psi (27,500 kPa). Strength testing shall be according to ASTM C 1140. The air content as shot shall be 4.0 – 8.0 percent when tested according to AASHTO T 152, and the coarse aggregate shall be a maximum size of 1/2 in. (12.5 mm).
The packaged shotcrete shall have a water soluble chloride ion content of less than 0.15% by weight of cementitious material when tested according to ASTM C 1218 or AASHTO T 260.
The testing according to ASTM C 1480, ASTM C 1140, AASHTO 152, and ASTM C 1218 or
AASHTO T 260 shall be performed by an independent lab a minimum of once every 5 years, and the test results shall be provided to the Department. The Department will maintain a qualified product list. Batching and mixing shall be per the manufacturer’s recommendations.
1015.02 Packaged Shotcrete Without Aggregate. The packaged shotcrete that does not include pre-blended aggregate shall be according to Article 1015.01, except the added aggregate shall be according to Articles 1003.02 and 1004.02. The aggregate gradation shall be according to the manufacturer. The Department will maintain a qualified product list. Batching and mixing shall be per the manufacturer’s recommendations.”
Revise Section 1017 of the Standard Specifications to read:
“SECTION 1017. PACKAGED, DRY, COMBINED MATERIALS FOR MORTAR AND
CONCRETE
1017.01 Mortar. The mortar shall be high-strength according to ASTM C 387 and shall have a minimum 80.0 percent relative dynamic modulus of elasticity when tested according to AASHTO T 161. For prestressed concrete applications, the mortar shall have a water-soluble chloride ion content of less than 0.06 percent by weight of cementitious material when tested according to ASTM C 1218 or AASHTO T 260; and for non-prestressed concrete applications, the water soluble chloride content shall be less than 0.15 percent by weight of cementitious material. The testing according to ASTM C 387, AASHTO T 161, and either ASTM C 1218 or AASHTO T 260 shall be performed by an independent lab a minimum of once every five years, and the test results shall be provided to the Department. The Department will maintain a qualified product list. Mixing of the high-strength mortar shall be according to the manufacturer’s specifications.
1017.02 Concrete. The materials, testing, and preparation of aggregate for the “high slump” packaged concrete mixture shall be according to ASTM C 387. The mixture shall be air entrained, the slump shall be 5-10 in. (125-250 mm), and the coarse aggregate shall be a maximum size of 1/2 in. (12.5 mm). Strength requirements shall be according to ASTM C 387 except that the strength at 28 days shall be at least 4000 psi (27,500 kPa). The “high slump” packaged concrete mixture shall have a water soluble chloride ion content of less than 0.15% by weight of cementitious material when tested according to ASTM C 1218 or AASHTO T 260. The testing according to ASTM C 387, and either ASTM C 1218 or AASHTO T 260 shall be performed by an independent lab a minimum of once every 5 years, and the test results shall be provided to the Department. The Department will maintain a qualified product list. Mixing shall be per the manufacturer’s recommendations.
1017.02 Self-Consolidating Concrete. The materials, testing, and preparation of aggregate for the “self-consolidating concrete” packaged concrete mixture shall be according to ASTM C 387. The mixture shall be air entrained, it should be uniformly graded, and the coarse aggregate shall be a maximum size of 1/2 in. (12.5 mm). Strength requirements shall be according to ASTM C 387 except that the strength at 28 days shall be at least 4000 psi (27,500 Pa). Slump flow range shall be 22 in. (550 mm) minimum to 28 in. (700 mm) maximum when tested according to AASHTO T 347. The visual stability index shall be a maximum of 1 when tested according to AASHTO T 351. At the option of the manufacturer, either the J-Ring value shall be a maximum of 2 in. (50 mm) when tested according to AASHTO T 347 or the L- Box blocking ratio shall be a minimum of 80 percent when tested according AASHTO T 419. The hardened visual stability index shall be a maximum of 1 when tested according to AASHTO R 81.
The “self -consolidating concrete” packaged concrete mixture shall have a water soluble chloride ion content of less than 0.15 percent by weight of cementitious material when tested according to ASTM C 1218 or AASHTO T 260.
The testing according to ASTM C 387, AASHTO T 347, AASHTO T 351, AASHTO T 419, AASHTO R 81, ASTM C 1218 and AASHTO T 260 shall be performed by an independent lab a minimum of once every 5 years, and the test results shall be provided to the Department. The Department will maintain a qualified product list. Mixing shall be per the manufacturer’s recommendations.”
Revise Article 1018.01 of the Standard Specifications to read:
“ 1018.01 Requirements. The rapid hardening mortar or concrete shall be according to ASTM C 928 and shall have successfully completed and remain current with the AASHTO Product Eval and Audit Rapid Hardening Concrete Patching Materials (RHCP) testing program. R1, R2, or R3 concrete shall be air entrained, the slump shall be 5-10 in. (125-250 mm), and the coarse aggregate shall be a maximum size of 1/2 in. (12.5 mm).