25-0061 SOW.pdf
PDF 56 KB Posted
- Attached to
- ECP OPT Traffic Calming Federal contract opportunity
- Solicitation number
- N4008525R9003
About this file
This document is a Statement of Work (SOW) for a traffic calming project at Marine Corps Base Camp Lejeune and Marine Corps Air Station New River. The project involves installing rumble strips and rubber speed bumps at multiple Entry Control Points (ECPs), including Wilson Blvd, Curtis Road, Stone Bay, Holcomb, Piney Green, Midway Park, Douglass, Camp Johnson, and Sneads Ferry. The Provost Marshall Office (PMO) is the customer, and the project has been approved by the Commanding Officers of H&S Battalion and MCAS New River.
The SOW includes specific scheduling requirements: for Wilson Blvd, Curtis Road, Stone Bay, and Holcomb ECPs, contractors must keep half of inbound and outbound lanes open, while for the remaining ECPs, contractors can use all lanes for three consecutive days and are permitted to work multiple shifts, overtime, nights, and weekends to complete the work. The document also allows flexibility in project management, stating that one person may serve as Superintendent, Quality Control Manager, and Safety & Health Officer if qualified for all three positions as defined in the project specification.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amend 0004.pdf | ||
| Amend 0003.pdf | ||
| Amend 0002.pdf | ||
| Amend 0001.pdf | ||
| N4008525B0061 Specs.pdf | ||
| RFP 250061.pdf | ||
| N4008525B0061 Dwgs.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJECT DESCRIPTION
This project will install rumble strips and rubber speed bumps at each of the ECFs.
The work is located aboard MCB Camp LeJeune and MCAS New River.
IMPACT STATEMENT
- The customer for this project is the Provost Marshall Office (PMO) who was the lead for the Operational Planning Team (OPT) for the traffic calming efforts. All plans were approved by the CO H&S Bn or CO MCAS NR.
- This project has the attention of CG MCI-E, CO H&S Bn and
CO MCAS NR.
SPECIAL SCHEDULING
For work at Wilson Blvd Entry Control Point (ECP), Curtis Road ECP, Stone Bay ECP, and Holcomb ECP, Contractor will keep half of both the inbound and outbound lanes always open.
For work at the remaining ECPs (Piney Green, Midway Park, Douglass, Camp Johnson and Sneads Ferry), contractor can have all lanes for a period of three consecutive days. All work at that ECP must be completed within those 3 days. Contractor is permitted to work multiple shifts, overtime, night and weekends to accomplish the work within the 3-day period.
SUPERVISION
One person may fill the roles of Superintendent, Quality Control Manager and Safety & Health Officer, if duly qualified for all three positions as defined in the project specification.