About this file
Airport Fencing and Security Upgrades – Roseburg Regional Airport
This is a comprehensive bid specification document for the Airport Fencing and Security Upgrades project at Roseburg Regional Airport, administered by the City of Roseburg Public Works Department in Douglas County, Oregon, with federal funding through the Federal Aviation Administration (FAA) Airport Improvement Program (AIP). The project involves demolition of existing 5-foot chain-link perimeter fencing and installation of new 6-foot chain-link fencing topped with 3 strands of barbed wire across approximately 5,350 linear feet, including fence transitions and gate installations. Work also encompasses clearing of approximately 2 acres, removal of existing fence infrastructure, and riprap slope protection installation. The project is divided into two work areas: Work Area 1 (Base Bid) requiring 50 working days for substantial completion, and Work Area 2 (Bid Additive 1) requiring 20 working days, with both substantially complete by April 1, 2026, and final completion 30 days thereafter. The City held an optional prebid meeting on August 5, 2025, with sealed bids due by 2:00 p.m. on Tuesday, August 19, 2025, to the City Recorder at 900 SE Douglas Avenue, Roseburg, Oregon 97470. Technical questions should be directed to Mark Forslund at Mead & Hunt, Inc., and the project is being issued for bid as of July 2025.
The bid must include a 10 percent bid bond (certified check, cashier's check, or irrevocable letter of credit) and be accompanied by multiple certifications including prevailing wage compliance, employee drug testing program compliance, and buy American preference compliance. The project is subject to both Oregon prevailing wage rates and federal Davis-Bacon Act requirements, with workers paid the higher applicable rate. Bidders must be licensed with the Oregon Construction Contractors Board, must disclose first-tier subcontractors for work exceeding 5 percent of bid value or $15,000 (whichever is greater), and are required to comply with Disadvantaged Business Enterprise (DBE) requirements with a contract goal of 5.43 percent DBE participation. The project is partially federally funded through the AIP, subjecting it to federal requirements including Buy American Preference, Civil Rights compliance, Davis-Bacon wage determinations, debarment certifications, and FAA-specific provisions. Performance and payment bonds equal to the full contract amount are required upon award. The successful bidder must achieve substantial completion within the specified working day limits and demonstrate responsibility through compliance with all federal, state, and local regulations, safety standards, security requirements, and quality assurance provisions detailed in the comprehensive 200-page specification package.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONTRACT DOCUMENTS
FOR THE
CONSTRUCTION OF
AIRPORT FENCING AND SECURITY UPGRADES
ROSEBURG REGIONAL AIRPORT
AIP No.: 3-41-0054-033-2025 City No. : 24GR03
TABLE OF CONTENTS
CITY OF ROSEBURG
PUBLIC WORKS DEPARTMENT
DOUGLAS COUNTY, OREGON
Issued for Bid
PREPARED BY:
Mead & Hunt, Inc.
9600 NE Cascades Pkwy, Suite 100 Portland, Oregon 97220 503-548-1494
Intentionally left blank
July 2025 Mead & Hunt, Inc.
Roseburg Regional Airport Certification Page Roseburg, Oregon Airport Fencing and Security Upgrades AIP No. 3-41-0054-033-2025 Issued for Bid
CERTIFICATION PAGE
THE DOCUMENTS FOR THIS PROJECT WERE PREPARED BY ME OR UNDER MY DIRECT
SUPERVISION:
PAGES OR SHEETS COVERED BY THIS SEAL:
Division 1 – Bid Information
Division 2 – Proposal Forms
Division 3 – Contract Forms
Division 4 – General Contract Provisions
Division 5 – Required Federal Contract Provisions
Division 6 – Technical Specifications
C-105 P-101
P-151 F-162
Division 7 – Construction Safety & Phasing Plan
July 2025 Mead & Hunt, Inc.
Roseburg Regional Airport Certification Page Roseburg, Oregon Airport Fencing and Security Upgrades AIP No. 3-41-0054-033-2025 Issued for Bid
Page i – (Prevailing Wage Projects) Revised 10/2024
Roseburg Regional Airport Advertisement for Bid Roseburg, Oregon Airport Fencing and Security Upgrades City No. 24GR03 Page i Issued for Bid
TABLE OF CONTENTS
ADVERTISEMENT FOR BID
INVITATION TO BID
INFORMATION TO BIDDERS
BIDDER'S CHECK LIST
BID FORM
CERTIFICATION REGARDING DOMESTIC PREFERENCES FOR PROCUREMENTS
STANDARD BID BOND
FIRST TIER SUBCONTRACTOR DISCLOSURE FORM INSTRUCTIONS
FIRST TIER SUBCONTRACTOR DISCLOSURE FORM
EMPLOYEE DRUG TESTING PROGRAM
PAY EQUITY COMPLIANCE TRAINING
BIDDER’S LIST COLLECTION FORM
CERTIFICATION OF OFFER/BIDDER REGARDING TAX DELINQUENCY AND FELONY CONVICTIONS
BUY AMERICAN CERTIFICATION
CERTIFICATE OF BUY AMERICAN COMPLIANCE WITH FAA BUY AMERICAN PREFERENCE
EQUAL EMPLOYMENT OPPORTUNITY REPORT STATEMENT
PUBLIC WORKS BOND - PRE-BID NOTICE AND CERTIFICATION
CONSTRUCTION CONTRACT
STANDARD CONTRACT PROVISIONS
PUBLIC WORKS BOND FILING CERTIFICATION
STANDARD PERFORMANCE BOND
PAYMENT BOND
LOWEST BIDDER RESPONSIBILITY DETERMINATION FORM
PREVAILING WAGE RATES FOR PUBLIC WORKS CONTRACTS
GENERAL CONDITIONS
GENERAL CONTRACT PROVISIONS ............................................................................................................ GP-1
REQUIRED FEDERAL CONTRACT PROVISIONS ......................................................................................... FP-1
TECHNICAL SPECIFICATIONS
ITEM C-105 MOBILIZATION ..................................................................................................................... C-105-1 ITEM P-101 PREPARATION/REMOVAL OF EXISTING PAVEMENTS ................................................... P-101-1 ITEM P-151 CLEARING AND GRUBBING ................................................................................................ P-152-1 ITEM F-162 CHAIN-LINK FENCE .............................................................................................................. F-162-1
CONSTRUCTION SAFETY AND PHASING PLAN (CSPP)
DRAWINGS
Page ii – (Prevailing Wage Projects) Revised 10/2024
City No. 24GR03 Page ii Issued for Bid
Page 1 – (Prevailing Wage Projects) Revised 10/2024
Roseburg, Oregon Airport Fencing and Security Upgrades City No. 24GR03 Page 1 Issued for Bid
CITY OF ROSEBURG
ADVERTISEMENT FOR BID
Project Name: Airport Fencing and Security Upgrades Project Number: 24GR03 Project Description: This Project will update the existing 5-foot chain-link fence to a 6-foot chain-link fence topped with 3 strands of barbed wire.
Optional Prebid Meeting: Tuesday August 5, 2025, at 2:00 pm, Virtual (Airport staff will be available for a site visit) Bids are due by 2:00 p.m. on Tuesday, August 19, 2025 All bids will be opened at 2:00 p.m.
Additional forms disclosing first tier subcontractors are due by 4:00 p.m.
No bids shall be received after this date and time.
Contact – Submit bids to: Address technical questions to:
City of Roseburg City Recorder Mark Forslund 900 SE Douglas Mead & Hunt, Inc.
Roseburg OR 97470 9600 NE Cascades Pkwy, Ste. 100
(541) 492-6866 Portland, OR 97220 bids@roseburgor.gov 503-548-1494 mark.forslund@meadhunt.com
SOLICITATION DOCUMENTS: Solicitation documents, including contract terms, conditions, specifications, all attachments and/or addenda for the Invitation to Bid are available for review at the above contact address. Bid documents will not be mailed to prospective bidders, but may be downloaded from OregonBuys through the following internet address: https://www.oregon.gov/das/Procurement/Pages/oregonbuys.aspx. Bidders without access to OregonBuys may download the documents at a Plan Center or the City of Roseburg’s website at www.cityofroseburg.org under “Bidding Opportunities.”
Bidders are not required to be pre-qualified. Bidders must be licensed with the Oregon Construction Contractors Board and comply with City of Roseburg Municipal Code.
The resulting public works contract is subject to ORS 279C.800 to 279C.870 and the Davis-Bacon Act (40 U.S.C.
3141 to 3148). No bid will be considered unless the bid contains a statement that the bidder will comply with the provisions of ORS 279C.840 (Prevailing Wage Rates).
mailto:bids@roseburgor.gov mailto:mark.forslund@meadhunt.com https://www.oregon.gov/das/Procurement/Pages/oregonbuys.aspx http://www.cityofroseburg.org/
Page 2 – (Prevailing Wage Projects) Revised 10/2024
City No. 24GR03 Page 2 Issued for Bid
Page 3 – (Prevailing Wage Projects) Revised 10/2024
Roseburg Regional Airport Bid Information Roseburg, Oregon Airport Fencing and Security Upgrades City No. 24GR03 Page 3 Issued for Bid
INVITATION TO BID
The City of Roseburg will receive sealed bids or bids submitted via email marked “Bid for Airport Fencing and Security Upgrades, Project No. 24GR03” until the hour of 2:00 p.m. on Tuesday, August 19, 2025, at which time they will be publicly opened and read in-person or virtually. If opened virtually, a link will be posted on the City’s website at https://www.cityofroseburg.org/bidding no later than 24 hours prior to the opening. When required by ORS 279C.370, bidders must submit a list of their first-tier subcontractors providing labor, or labor and materials, no later than 4:00 p.m. that same day. Bids shall be addressed and delivered to Amy Nytes, City Recorder, City Hall, 900 SE Douglas Avenue, Roseburg, Oregon 97470, or emailed to bids@roseburgor.gov. Any and all bids received after the 2:00 p.m. deadline for submission, or for which the list of first-tier subcontractors has not been submitted by 4:00 p.m. that same day, shall be considered nonresponsive and returned to the bidder.
All bidders must list their "Construction Contractors Board" or “State Landscape Contractors Board” license number as required by ORS 701.021 or 671.530 on the bid form.
The proposed work generally consists of furnishing all labor, equipment, materials and supervision for the construction of this project. The project will update the existing 5-foot chain-link fence to a 6-foot chain-link fence with 3 strands of barbed wire. This project includes 2 acres of clearing, removal of approximately 5,350 linear feet of 5-foot chain-link fence and the installation of 5,350 linear feet of 6-foot chain-link fence with 3 strands of barbed wire. The bids will be evaluated as unit price pursuant to OAR 137-049-0380(2)(b). The proposed work will require the bidder to meet the highest standards prevalent in the industry or business related to the work to be performed.
Failure to meet such standards may result in a reduction or withholding of payment; require bidder to provide, at bidder’s own expense, additional work required to meet such standards; or termination of the contract, with damages being sought. Technical questions regarding the work to be performed should be addressed to:
Mark Forslund Mead & Hunt, Inc 9600 NE Cascades Pkwy, Ste. 100 Portland, OR 97220 503-548-1494 mark.forslund@meadhunt.com
Bids must be accompanied by a certified check, cashier's check, irrevocable letter of credit or Bid Bond in an amount equal to not less than ten percent (10%) of the total amount of the bid. Bidders shall state as part of the bid that the provisions of ORS 279C.800 to 279C.870 (Prevailing Wage Rates) shall be complied with on the project. The project is subject to both the state and federal prevailing rates of wage and the bid must contain a statement by the bidder that contractor and every subcontractor shall pay the higher of the applicable state or federal prevailing rate of wage to all workers on the project. Bidders must also certify as part of the bid that the requirements of ORS 279C.505(2) (Employee Drug Testing Program) shall be complied with on the project.
Bidders are not required to be pre-qualified.
https://www.cityofroseburg.org/bidding mailto:bids@roseburgor.gov mailto:mark.forslund@meadhunt.com
Page 4 – (Prevailing Wage Projects) Revised 10/2024
Roseburg, Oregon Airport Fencing and Security Upgrades City No. 24GR03 Page 4 Issued for Bid
Each bid must contain a statement as to whether the bidder is a resident bidder, as defined in ORS 279A.120.
Bidders are not required to be licensed under ORS 468A.720 (Asbestos Abatement). However, the successful bidder shall at all times during the project provide qualified staff on site that is able to identify asbestos containing material. Bidders are hereby notified there are underground pipelines and structures containing asbestos within the City of Roseburg. If any such material is encountered during the project, the bidder shall thereupon be required to notify the City and comply with all requirements of applicable laws and regulations. Unless exempt under ORS 279C.800 to 279C.870, the successful bidder must file a $30,000 Public Works Bond with the Construction Contractors Board prior to beginning work on the project, and certify that all sub-contractors have also filed such bond. Bidders must agree to use recyclable products to the maximum extent financially feasible. Bidders with 50 or more employees and for contracts over $500,000, are required to possess a certificate issued by the Department of Administrative Services for completion of pay equity training (NEW).
The City of Roseburg may reject any bid not in compliance with all public bidding procedures and requirements, including the requirement to demonstrate the bidder’s responsibility under ORS 279C.375(3)(b), may waive any irregularities, and may reject for good cause any or all bids upon a finding of the City it is the public interest to do
so. The City may also cancel this invitation in accordance with OAR 137-049-0270.
Federal Requirements for Federally Funded Projects. This Project is being partially funded under the Federal Aviation Administration (FAA) Airport Improvement Program (AIP) through Infrastructure Investment and Jobs Act (IIJA). Bidders must comply with specific federally required provisions as listed herein and contained in the bidding documents. The Following federal provisions are incorporated in this solicitation by reference.
1. Buy American Preference (49 USC § 50101)
2. Civil Rights – Title VI Assurance (49 USC § 47123; FAA Order 1400.11)
3. Davis-Bacon Act (2 CFR § 200, Appendix II(D); 29 CFR Part 5)
4. Debarment and Suspension (2 CFR part 180 (Subpart C), 2 CFR part 1200, DOT Order 4200.5)
5. Disadvantaged Business Enterprise (49 CFR part 26)
6. Trade Restriction (49 USC § 50104; 49 CFR part 30)
7. Lobbying and Influencing Federal Employees (31 USC § 1352 – Byrd Anti-Lobbying Amendment; 2 CFR part 200, Appendix II(J); 49 CFR part 20, Appendix A)
8. Procurement of Recovered Materials (2 CFR § 200.322; 40 CFR part 247; Solid Waste Disposal
Disadvantaged Business Enterprise. The requirements of 49 CFR part 26, Regulations of the U.S. Department of Transportation, apply to this contract. It is the policy of the City of Roseburg to practice nondiscrimination based on race, color, sex or national origin in the award or performance of this contract. The Owner encourages participation by all firms qualifying under this solicitation regardless of business size or ownership. The City of Roseburg is an equal opportunity and affirmative action employer. Small, minority, veteran, and women-owned businesses are encouraged to submit bids.
A DBE contract goal of 5.43 percent has been established for this contract.
All bidders will be required to submit the following information:
1. The names and addresses of DBE firms that will participate in the contract;
2. A description of the work that each DBE will perform. To count toward meeting a goal, each DBE firm must be certified in a NACIS code applicable to the kind of work the firm would perform on the contract;
3. The dollar amount of the participation of each DBE firm participating;
4. Written documentation of the bidder/offeror’s commitment to use a DBE subcontractor whose participation it submits to meet a contract goal; and
Page 5 – (Prevailing Wage Projects) Revised 10/2024
Roseburg, Oregon Airport Fencing and Security Upgrades City No. 24GR03 Page 5 Issued for Bid
5. Written confirmation from each listed DBE firm that it is participating in the contract in the kind and amount of work provided in the prime contractor’s commitment. Each DBE listed to perform work as a regular dealer or distributor must confirm its participation according to the requirements of §26.53 (c)(1); and
6. If the contract goal is not met, evidence of good faith efforts (as elaborated in Appendix A of Part 26). The documentation of good faith efforts must include copies of each DBE and non-DBE subcontractor quote submitted to the bidder when a non-DBE subcontractor was selected over a DBE for work on the contract.
Civil Rights - Title VI Solicitation. Notice The City of Roseburg, in accordance with the provisions of Title VI of the Civil Rights Act of 1964 (78 Stat. 252, 42 U.S.C. §§ 2000d to 2000d-4) and the Regulations, hereby notifies all bidders that it will affirmatively ensure that any contract entered into pursuant to this advertisement, disadvantaged business enterprises will be afforded full and fair opportunity to submit bids in response to this invitation and will not be discriminated against on the grounds of race, color, national origin (including limited English proficiency), creed, sex (including sexual orientation and gender identity), age, or disability in consideration for an award.
Federal Fair Labor Standards Act (Federal Minimum Wage). All contracts and subcontracts that result from this solicitation incorporate by reference the provisions of 29 CFR part 201, et seq, the Federal Fair Labor Standards Act (FLSA), with the same force and effect as if given in full text. The FLSA sets minimum wage, overtime pay, recordkeeping, and child labor standards for full and part-time workers.
The Contractor has full responsibility to monitor compliance to the referenced statue or regulation. The Contractor must address any claims or disputes that arise from this requirement directly with the U.S. Department of Labor – Wage and Hour Division.
Dated this day of , 2025.
CITY OF ROSEBURG, DOUGLAS COUNTY, OREGON
/s/ Amy Nytes, City Recorder
Page 6 – (Prevailing Wage Projects) Revised 10/2024
City No. 24GR03 Page 6 Issued for Bid
Page 7 – (Prevailing Wage Projects) Revised 10/2024
Roseburg, Oregon Airport Fencing and Security Upgrades City No. 24GR03 Page 7 Issued for Bid
INFORMATION TO BIDDERS
1. FORM OF BID
All bids must be made upon the blank Bid Form attached hereto and must give a price for each item and an aggregate amount or a lump sum price as required in the Bid Form.
The City reserves the right to reject any or all bids or to accept the bid deemed in the best interest of the City. Without limiting the generality of the foregoing, the City may reject any bid which is incomplete, obscure or irregular; which omits any one or more items in the price sheet; in which unit prices are obviously unbalanced; or which is accompanied by an insufficient or irregular Bid Bond.
The bidder shall sign the Bid Form in the blank space provided therefore. All bids must contain the bidder’s tax identification number. Bids made by a corporation, general or limited partnership, or L.L.C., shall contain the name and address of such organization, together with names and addresses of officers, partners or managing members. If the bid is made by a corporation, it must be signed by one of the corporate officers with the authority to sign for the corporation; if made by a partnership, by one of the partners.
All bids must be submitted at the time and place, and in the manner prescribed in the Invitation to Bid.
2. BID PROTEST; REQUEST FOR CHANGE OR CLARIFICATION
A bidder may protest, or request a change in items in the bid documents, including contract terms and conditions or specifications, by filing a written protest with the City not less than ten (10) calendar days prior to the bid submission deadline. Such written protest or request for change must include a detailed statement of the grounds for the protest and a statement of the desired changes to the contract terms and conditions or specifications.
The City shall not consider a bidder’s protest or request for change after the deadline for submitting such protest or request. The City shall provide notice to the bidder if it entirely rejects the bidder’s protest or request for change. If the City agrees with the bidder’s protest or request, in whole or in part, the City shall issue a written Addendum to the bid documents or specifications.
Prior to the deadline for submitting a written protest or request for change, a bidder may request that the City clarify any provision of the bid documents. The City’s clarification to a bidder, whether orally or in writing, shall not change the bid documents and is not binding on the City unless the City amends the bid documents by issuing a written addendum.
If a written addendum is issued by the City, all bidders must provide written acknowledgement, with their bids, of receipt of all issued addenda.
Page 8 – (Prevailing Wage Projects) Revised 10/2024
Roseburg, Oregon Airport Fencing and Security Upgrades City No. 24GR03 Page 8 Issued for Bid
3. CONTRACT DOCUMENTS
The Contract Documents for this Project consist of, but are not necessarily limited to, the Invitation to Bid, Information to Bidders, Bid Form, Construction Contract including Exhibit “A” Standard City Contract Provisions, First-Tier Subcontractor Disclosure Form, Drug Testing Program Certification Form, Bidder’s Responsibility Form, Performance Bond, Payment Bond, Public Works Bond Filing Certification form (when required), Pay Equity Compliance Certification (when applicable), General Conditions, Technical Provisions, Special Conditions, Standard Drawings, Specifications and Plans and Supplemental Specifications, all as required for the full execution and satisfactory completion of the Project. Any person contemplating the submission of a bid and being in doubt as to the meaning or intent of said Contract Documents should request of the City, in writing, an interpretation thereof. Any interpretation of said Contract Documents shall be made only in writing by the City.
4. ESTIMATE OF QUANTITIES
The estimate of quantities of work to be done as stated in the Bid Form, although stated with as much accuracy as possible, is approximate only and is assumed solely for the purpose of comparing bids. The quantities on which payments will be made to the Contractor are to be determined by measurement of the work actually performed and paid at the unit price bid, regardless of the amount of increase or decrease in the estimated quantities as specified in the Contract Documents. The City reserves the right to increase or diminish the amount of any class of work as may be deemed necessary.
5. CONSTRUCTION CONTRACTORS' BOARD - STATE LANDSCAPE CONTRACTORS’ BOARD
All contractors bidding on public contracts must be licensed with the Construction Contractors' Board or the State Landscape Contractors Board as required by ORS 701.021 or 671.530. Bids must be identified with the Contractors' Board license number. No bids will be considered without this information.
6. DISCLOSURE OF FIRST-TIER SUBCONTRACTORS
When a public improvement contract value is greater than $100,000, all bidders are required to disclose information about first-tier subcontractors, providing labor or labor and materials, when the contract amount of such first-tier subcontractor is equal to or greater than:
1) 5% of the project bid, or $15,000, whichever is greater; or
2) $350,000 regardless of the percentage of the total bid.
Bidders must disclose the following information about such subcontracts, on the First-Tier Subcontractor Disclosure Form provided by the City and included herein, within two hours of the bid submission deadline:
1) The subcontractor’s name;
2) The subcontract dollar value; and
3) The category of work to be performed by the subcontractor.
Page 9 – (Prevailing Wage Projects) Revised 10/2024
Roseburg, Oregon Airport Fencing and Security Upgrades City No. 24GR03 Page 9 Issued for Bid
Any bidder not using subcontractors subject to the above disclosure form, must write “NONE” on the Disclosure Form and sign and submit the form. The City will reject a bid if the bidder fails to submit the Disclosure Form before the deadline.
7. DRUG TESTING PROGRAM
ORS 279C.505(2) requires public improvement contracts to include a provision requiring contractors to demonstrate that they have an employee drug and alcohol testing program in place. All bidders are required to certify, on the Drug Testing Program Certification Form provided by the City and included herein, that they have such program in place. This certification will become part of the Contract if awarded and contractor will be required to maintain such program throughout the performance of the Contract.
Failure to maintain a program shall constitute a material breach of the Contract.
8. PROMPT PAY POLICY - TIMELY PROGRESS PAYMENTS
ORS 279C.570 and 279C.580 require prompt payment to contractors and subcontractors and provides for settlement of compensation disputes between the parties. The City is required to automatically calculate and pay interest on invoices from the contractor when payments become overdue. The interest commences thirty (30) calendar days after receipt of the invoice from the contractor, or fifteen (15) calendar days after the payment is approved by the City, whichever is earlier. The rate of interest charged to the City on the amount due shall equal three times the discount rate on 90-day commercial paper, but shall not exceed 30 percent.
The City is also required to ensure that the contractor includes a clause in each subcontract that obligates the contractor to pay first-tier subcontractors for satisfactory performance under its contract. Contractors must pay subcontractors within ten (10) calendar days of receiving payment from the City. Contracts between primary contractors and subcontractors must also contain an interest penalty clause that obligates the contractor, if payment is not made to the subcontractor within thirty (30) calendar days after receipt of payment from the City, to pay the first-tier subcontractor an interest penalty on amounts due in the case of each payment not made in accordance with the subcontract payment clause. The contractor is also required to ensure that first-tier subcontractors include these requirements in each of its subcontracts with lower-tier subcontractors or suppliers.
If requested in writing by a first-tier subcontractor, within ten (10) calendar days after receiving the request, the contractor must provide the first-tier subcontractor, a copy of that portion of any invoice or request for payment submitted to the City, or pay document provided by the City to the contractor, specifically related to any labor or materials supplied by the first-tier subcontractor.
9. PRE-QUALIFICATION OF BIDDERS
Pre-qualification is not required.
Page 10 – (Prevailing Wage Projects) Revised 10/2024
Roseburg, Oregon Airport Fencing and Security Upgrades City No. 24GR03 Page 10 Issued for Bid
10. BID BOND, PUBLIC WORKS BOND, PAYMENT BOND AND PERFORMANCE BOND
A Bid Bond, Public Works Bond Filing Certification, Payment Bond and Performance Bond shall be provided as specified in Subsection 5.4 of the General Conditions. No waivers, special requirements or emergency provisions have been established for this Contract.
11. PAY EQUITY COMPLIANCE CERTIFICATION (NEW)
ORS 279A.167 requires businesses with fifty (50) or more employees, and a contract valued at more than $500,000, to provide proof they are properly trained on Oregon’s pay equity laws. A certificate proving the contractor has completed the training shall be provided as specified in Subsection 26 of the “Bid Form”.
12. HIGHEST STANDARDS OF WORK AND CONSEQUENCES FOR FAILURE
The work to be performed must meet the highest standards prevalent in the industry or business most closely related to the work to be performed. Failure to meet such standards may result in consequences including, but not limited to a reduction or withholding of payment; a requirement that bidder perform, at bidder’s own expense, additional work required to meet such standards; or termination of the contract, with damages being sought.
13. CONDITIONS OF WORK
Bidders must make their own determination of the nature of the work proposed under this Contract, the local conditions which can be encountered in this area, and all other matters which can in any way affect the work proposed under this Contract. It shall also be the bidder's responsibility to be thoroughly familiar with the Contract Documents. Failure to make the examination necessary for this determination or to examine any form, instrument or document of the Contract shall not release the bidder from the obligations of this Contract.
14. REVIEW OF BIDS; BASIS FOR AWARD; NOTICE OF INTENT TO AWARD; AND RIGHT TO PROTEST
AWARD
In reviewing all bids received and determining the lowest responsible bidder, the City reserves the right to take into account and give reasonable weight to the extent of the bidder's experience on work of the nature involved, on the bidder's record as to dependability in carrying out of contracts, and evidence of present ability to perform the Contract in a satisfactory manner.
The City may make such investigations as deemed necessary to determine the ability of the bidder to perform the work, and the bidder shall furnish to the City all such information and data for this purpose as the City may request. The City reserves the right to reject any bid if the evidence submitted by, or investigation of, such bidder fails to satisfy the City that such bidder is properly qualified to carry out the obligations of the Contract, to complete the work contemplated therein, and to do so in a timely manner.
The City specifically reserves the right to reject a bid from a bidder who, at the time bids are opened, has failed to complete work in a timely manner under a contract previously awarded to the bidder by the City.
Conditional bids will not be accepted.
Page 11 – (Prevailing Wage Projects) Revised 10/2024
Roseburg, Oregon Airport Fencing and Security Upgrades City No. 24GR03 Page 11 Issued for Bid
In accordance with ORS 279A.120(2)(b), in determining the lowest responsible bidder, the City shall, for the purpose of awarding the Contract, add a percentage increase on the bid of a non-resident bidder equal to the percent, if any, of the preference given to that bidder in the state in which the bidder resides.
Within forty-five (45) calendar days after the bid opening, the City will accept one of the bids or reject all of the bids received. If the City intends to accept one of the bids, it shall issue a Notice of Intent to Award the Contract to all bidders. The City’s award will not be final until seven (7) calendar days after the date of the notice if no protest is filed; or if a protest is filed, until the City provides a written response to all timely-filed protests that denies the protest and affirms the award.
A bidder may submit a formal written protest to the City’s Notice of Intent to Award the Contract within seven (7) calendar days of the date of the City’s Notice of Intent. The written protest must specify the grounds upon which the protest is based and must show that the protesting party is an adversely affected or aggrieved bidder. A bidder is adversely affected or aggrieved only if the bidder is eligible for award of the Contract as the responsible bidder submitting the lowest responsible bid, is next in line for award and claims that all lower bidders are ineligible for award in accordance with law.
Such protest must be submitted to the City Recorder, 900 SE Douglas, Roseburg, OR 97470 or by email at info@roseburgor.gov. Any protest received after the 7-day deadline will not be considered. The City Recorder shall forward such protest to the City Manager who shall have the authority to settle or resolve the protest by written decision.
15. EXECUTION OF CONTRACT, BONDS AND DAMAGES FOR FAILURE TO EXECUTE
The bidder whose bid is accepted will be required to appear within ten (10) calendar days after notice that the Contract has been awarded to bidder and to execute the Contract with the City for the full and complete performance of all work specified, and as required by Subsection 5.4 of the General Conditions, deliver the Public Works Bond Filing Certification form, the Payment Bond to assure payment of the obligations incurred in the performance of the Contract and the Performance Bond and to ensure performance of the Contract.
Should the successful bidder fail or refuse to execute the Contract and furnish the Public Works Bond Filing Certification form, Payment Bond and/or Performance Bond when required, then the Bid Bond deposited by said bidder shall be retained by the City as liquidated damages.
16. COMMENCEMENT DATE AND EXPIRATION DATE OF CONTRACT
This Contract shall be in effect from the time the Contract is signed until the Project is completed. The Contractor must be capable of completing substantial completion by April 1, 2026. Final completion shall be 30 days after substantial completion and include any items identified on the punch list.
17. DURATION OF BIDS; RETURN OF BID BONDS
All bids will be binding until the later of:
1) the day the contract is executed; or
2) forty-five (45) calendar days after the date of bid opening.
mailto:info@roseburgor.gov
Page 12 – (Prevailing Wage Projects) Revised 10/2024
City No. 24GR03 Page 12 Issued for Bid
Bid bonds will be returned to unsuccessful bidders not later than the date on which the bids are no longer binding.
18. PUBLIC RECORDS
These Contract Documents and each bid received in response to it, together with copies of documents pertaining to the award of a contract shall be kept on file as a public record by the City Recorder; provided however, such records shall not be disclosed until after the notice of intent to award the contract has been issued.
19. RECORDS REVIEW; CONFIDENTIALITY
After notice of intent to award the resulting contract has been issued, all bids shall be available for public inspection except for those portions of a bid that the bidder designates in its bid as trade secrets or as confidential proprietary data in accordance with applicable state law. If the City determines such designation is not in accordance with applicable law, the City shall make those portions available for public inspection. The bidder shall separate information designated as confidential from other non-confidential information at the time of submitting its proposal. Prices, makes, models or catalog numbers of items offered, scheduled delivery dates and terms of payment are not confidential, and shall be publicly available regardless of a bidder’s designation to the contrary.
20. MATERIALS CONTAINING ASBESTOS
Materials containing asbestos may be present in underground pipe systems. All appropriate Federal, State, County and Municipal rules, regulations and guidelines must be followed when working with asbestos containing material. Non friable material must be handled, transported and disposed of in a way that prevents it from becoming friable and releasing asbestos fibers. If AC pipe is shattered, damaged or badly weathered, it is considered to be friable and will likely release asbestos fibers. A DEQ licensed asbestos abatement contractor using DEQ certified workers must remove all friable asbestos material.
Any and all permits and fees that are required by the DEQ, Douglas County and any other regulatory agency must be obtained and paid for by the Contractor prior to disposing of the asbestos containing material. For information about asbestos rules, contact the DEQ Western Region office in Medford, Oregon.
21. REQUIRED FEDERAL CONTRACT PROVISIONS
Contractor shall comply with the Required Federal Contract Provisions and include in all subcontracts.
Page 13 – (Prevailing Wage Projects) Revised 10/2024
Roseburg, Oregon Airport Fencing and Security Upgrades City No. 24GR03 Page 13 Issued for Bid
22. DISADVANTAGED BUSINESS ENTERPRISE
The requirements of 49 CFR part 26, Regulations of the U.S. Department of Transportation, apply to this contract. It is the policy of the City of Roseburg to practice nondiscrimination based on race, color, sex or national origin in the award or performance of this contract. The Owner encourages participation by all firms qualifying under this solicitation regardless of business size or ownership. The City of Roseburg is an equal opportunity and affirmative action employer. Small, minority, veteran, and women-owned businesses are encouraged to submit bids.
A DBE contract goal of 5.43 percent has been established for this contract.
All bidders will be required to submit the following information:
1) The names and addresses of DBE firms that will participate in the contract;
2) A description of the work that each DBE will perform. To count toward meeting a goal, each DBE firm must be certified in a NAICS code applicable to the kind of work the firm would perform on the contract;
3) The dollar amount of the participation of each DBE firm participating;
4) Written documentation of the bidder/offeror’s commitment to use a DBE subcontractor whose participation it submits to meet a contract goal; and
5) Written confirmation from each listed DBE firm that is participating in the contract in the kind and amount of work provided in the prime contractor’s commitment. Each DBE listed to perform work as a regular dealer or distributor must confirm its participation according to requirements § 26.53 (c)(1); and
6) If the contract goal is not met, evidence of good faith efforts (as elaborated in Appendix A of Part 26). The documentation of good faith efforts must include copies of each DBE and non-DBE subcontractor quote submitted to the bidder when a non-DBE subcontractor was selected over a DBE for work on the contract.
Page 14 – (Prevailing Wage Projects) Revised 10/2024
City No. 24GR03 Page 14 Issued for Bid
Page 15 – (Prevailing Wage Projects) Revised 10/2024
Roseburg, Oregon Airport Fencing and Security Upgrades City No. 24GR03 Page 15 Issued for Bid
BIDDER'S CHECK LIST
Bidder's attention is called to the following forms, which must be executed in full as required with the bid:
A. BID FORM(S): Each bidder shall complete the bid form(s). Prices must be shown in the spaces provided and must be expressed in figures.
B. BID BOND: This form is to be executed by bidder and bidder's Surety. The amount of cash, certified check, cashier's check, irrevocable letter of credit or Bid Bond shall not be less than 10% of the total Bid amount.
C. FIRST-TIER SUBCONTRACTOR DISCLOSURE FORM: When required by law, this form must be submitted by the bid submission deadline, at which time bids will be opened and read, or within two (2) working hours of such submission deadline. If no subcontractors for labor or for labor and materials will be used, the bidder must write “NONE” on the disclosure form, sign and submit the form as required.
Failure to submit this form within two hours of the bid submission deadline will result in the bid becoming non-responsive and such bid will be returned to the bidder.
D. DRUG TESTING PROGRAM CERTIFICATION FORM: This form must be submitted with the bid to demonstrate that bidder has an employee drug and alcohol testing program in place and will continue to keep the program in place throughout the duration of performing the Contract awarded.
E. PUBLIC WORKS BOND PRE-BID NOTICE & CERTIFICATION FORM: This form must be submitted with the bid to demonstrate contractor’s awareness of and intended compliance with the requirement to file a Public Works Bond with the Construction Contractors Board prior to beginning work on the project if awarded the bid.
F. PAY EQUITY COMPLIANCE CERTIFICATION FORM (NEW): If applicable pursuant to Section 11 of “Information for Bidders”, this form must be submitted with the bid to demonstrate contractor has completed required training regarding pay equity and the prohibition against discrimination in compensation or wage benefits.
G. BIDDER’S LIST: Each bidder shall complete the form in its entirety.
H. DBE UTILIZATION STATEMENT: Each bidder shall complete the form in its entirety.
I. DBE LETTER OF INTENT: This form shall be submitted for each DBE firm intended to perform work on the project.
J. DBE GOOD FAITH EFFORTS: Each bidder shall provide evidence of good faith efforts when unable to meet the contract goal.
K. CERTIFICATION OF OFFERER/BIDDER REGARDING TAX DELIQUENCY AND FELONY
CONVICTIONS: Each bidder shall check the appropriate boxes, date, and sign.
L. BUY AMERICAN CERTIFICATION: Each bidder shall check the appropriate boxes and sign.
M. EQUAL OPPORTUNITY REPORT STATEMENT: Each Bidder shall check the appropriate boxes, and sign, and date.
Page 16 – (Prevailing Wage Projects) Revised 10/2024
Roseburg, Oregon Airport Fencing and Security Upgrades City No. 24GR03 Page 16 Issued for Bid
The following forms are to be executed after the Contract is awarded, prior to beginning work on the project:
A. CONSTRUCTION CONTRACT: This agreement is to be executed by the successful bidder.
B. PERFORMANCE BOND AND PAYMENT BOND: Both a Performance Bond and a Payment Bond are to be executed by the successful bidder and bidder's Surety Company and submitted at the time the Contract is executed.
C. PUBLIC WORKS WAGE CERTIFICATION FORM: This form is to be completed in accordance with state law and submitted monthly during the duration of the contract, by the fifth business day of the following month, with request for payment.
D. CERTIFICATE OF INSURANCE: This certificate is to be executed by the successful bidder and bidder's insurance company and submitted at the time the Contract is executed.
E. PUBLIC WORKS BOND FILING CERTIFICATION: This form is to be executed by the successful bidder and submitted at the time the Contract is executed to certify if Contractor has filed the required Public Works Bond or elected not to file the Bond due to qualifying under ORS 200.055.
Page 17 – (Prevailing Wage Projects) Revised 10/2024
Roseburg, Oregon Airport Fencing and Security Upgrades City No. 24GR03 Page 17 Issued for Bid
BID FORM
City of Roseburg 900 SE Douglas Avenue Roseburg, Oregon 97470
The undersigned bidder has carefully examined the Contract Documents for the construction of the
Airport Fencing and Security Upgrades Project No. 24GR03 referred to in the Invitation to Bid dated Tuesday, July 29, 2025, inviting bids on such Project and also the site of the Project. Bidder will provide all necessary labor, equipment, tools, apparatus and other means of construction, do all the work and furnish all the materials called for by said Contract Documents in the manner prescribed therein to provide a complete Project.
The undersigned bidder understands that the quantities of work as shown herein are approximate only, unless noted otherwise, and are subject to increase or decrease. The bidder offers to perform the work, at the unit price stated in the following schedule, whether the quantities are increased or decreased.
Page 18 – (Prevailing Wage Projects) Revised 10/2024
City No. 24GR03 Page 18 Issued for Bid
Page 19 – (Prevailing Wage Projects) Revised 10/2024
Roseburg, Oregon Airport Fencing and Security Upgrades City No. 24GR03 Page 19 Issued for Bid
ROSEBURG REGIONAL AIRPORT
AIRPORT FENCING AND SECURITY UPGRADES
CITY NO. 24GR03
BASE BID
ITEM
NO.
SECTION/
ITEM ITEM DESCRIPTION QTY UNITS UNIT PRICE
(IN FIGURES)
TOTAL PRICE
(IN FIGURES)
1 C-105 Mobilization (10% Maximum) 1 LS
2 GP 50-07 Construction Survey 1 LS
3 P-101 Chain-Link Fence Removal 4,771 LF
4 P-101 Riprap Slope Protection, 30” Depth 82 SY
5 P-151 Clearing 1.8 AC
6 F-162 6-foot Chain-Link Fence, with 3-strand barbed wire 5,050 LF
7 F-162 5-foot to 6-foot Chain Link Fence Transition, with 3-strand barbed wire 16 LF
8 F-162 2-foot to 5-foot Chain Link Fence Transition, with 3-strand barbed wire 22 LF
9 F-162 2-foot Chain-Link Fence, with 3-strand barbed wire 14 LF
TOTAL Base Bid in Figures
Total Base Bid in Writing:
Page 20 – (Prevailing Wage Projects) Revised 10/2024
Roseburg, Oregon Airport Fencing and Security Upgrades City No. 24GR03 Page 20 Issued for Bid
ROSEBURG REGIONAL AIRPORT
AIRPORT FENCING AND SECURITY UPGRADES
CITY NO. 24GR03
BID ADDITIVE 1
ITEM
NO.
SECTION/
ITEM ITEM DESCRIPTION QTY UNITS UNIT PRICE
(IN FIGURES)
TOTAL PRICE
(IN FIGURES)
1 C-105 Mobilization (10% Maximum) 1 LS
2 GP 50-07 Construction Survey 1 LS
3 P-101 Chain-Link Fence Removal 560 LF
4 F-162 6-foot Chain-Link Fence, with 3-strand barbed wire 560 LF
5 F-162 Single Panel Swing Gate, 6’-5” 1 EA
6 F-162 3-strand barbed wire installed on 19-foot automatic vertical pivot gate 1 LS
TOTAL Bid Additive 1 in Figures Total Bid Additive 1 in Writing:
ROSEBURG REGIONAL AIRPORT
AIRPORT FENCING AND SECURITY UPGRADES
CITY NO. 24GR03
BID ALTERNATE 1
ITEM
NO.
SECTION/
ITEM ITEM DESCRIPTION QTY UNITS UNIT PRICE
(IN FIGURES)
TOTAL PRICE
(IN FIGURES)
1 F-162 Tension Wire to Replace Top Rail on Chain-Link Fence in Work Area 1 5,102 LF
TOTAL Bid Alternate 1 in Figures
Total Bid Alternate 1 in Writing:
Page 21 – (Prevailing Wage Projects) Revised 10/2024
Roseburg, Oregon Airport Fencing and Security Upgrades City No. 24GR03 Page 21 Issued for Bid
*Abbreviations:
LS – Lump Sum CY – Cubic Yard EA – Each
LBS – Pounds LF – Lineal Feet IN – Inches
SY – Square Yard TONS – Tons AC - Acres
THE APPARENT LOW BIDDER WILL BE DETERMINED BASED ON THE LOW SUM TOTAL OF THE BASE
BID.
SHOULD THE APPARENT LOW BIDDER BE LOW ON THE SUM OF THE BASE BID, BID ADDITIVE 1 AND/OR BID ALTERNATE 1, THEN BID ADDITIVE 1 AND/OR BID ALTERNATE 1 MAY ALSO BE AWARDED TO THE
APPARENT LOW BIDDER.
SPLIT AWARDS WILL NOT BE MADE.
ACCEPTED ADDITIVES WILL BE IDENTIFIED IN THE CONSTRUCTION CONTRACT. THE ORDER OF THE ADDITIVES LISTED ABOVE DOES NOT REPRESENT THE ORDER IN WHICH ANY OF THESE ADDITIVES
MAY BE CHOSEN.
The undersigned also declares and agrees as follows:
1. That the only persons or parties interested in this bid are those named herein, that the bid is in all respects fair and without fraud, and that it is made without any connection or collusion with any person making another bid on this Contract.
2. That the bidder, and any subcontractor upon which the bidder is relying, have carefully examined and had an opportunity to comment on, the Contract Documents for the construction of the proposed improvements including a full set of the plans and specifications, including all addenda thereto; that bidder has personally inspected the contemplated construction area or areas; that bidder is satisfied as to the adequacy and completeness of the plans and specifications, the feasibility of the work described therein, quantities of materials, items of equipment and conditions of work involved, including the fact that the description of work and materials as included herein are approximate only; and that this bid is made according to the provisions and under the terms of the Specifications which are hereto attached and hereby made a part of this bid.
3. All of the Specifications and Plans which are listed herein have been examined by the undersigned bidder and the terms and conditions thereof are hereby accepted.
4. It is understood that the Plans may be supplemented by additional Drawings and Specifications in explanation and elaboration of the Plans and it is agreed that such Supplemental Drawings, when not in conflict with those referred to in Paragraph 3 above, will have the same force and effect as if completed and attached hereto, and that when received, will be considered a part of the Contract Documents.
Page 22 – (Prevailing Wage Projects) Revised 10/2024
Roseburg, Oregon Airport Fencing and Security Upgrades City No. 24GR03 Page 22 Issued for Bid
5. It is understood that all work will be performed under the price schedule outlined herein and that all services, materials, labor and equipment and all work necessary to complete the Project in accordance with the Plans and Specifications shall be furnished for the prices named in the bid. If there is a change in the scope of work or work which cannot be properly classified under the price schedule then bidder agrees to do this work as "extra work". The undersigned bidder agrees to do any extra work and furnish materials, and to accept as full compensation therefore at such prices as may be agreed upon in writing by the City and the Contractor before extra work begins. Each party binds itself to agree to reasonable prices.
6. It is understood the work to be performed must meet the highest standards prevalent in the industry or business most closely related to the work to be performed. It is further understood that failure to meet such standards may result in consequences including, but not limited to, a reduction or withholding of payment; a requirement that bidder perform, at bidder’s own expense, additional work required to meet such standards; or termination of the contract, with damages being sought.
7. The bidder agrees that if this bid is accepted, the bidder will, within ten (10) calendar days after the notification of acceptance, execute the Construction Contract with the City in the form of Contract specified, and will, at the time of execution of the Contract, deliver to the City the Performance Bond, Payment Bond and Public Works Bond Filing Certification form as required herein, and will furnish all the materials necessary to complete the Project in the manner, in the time and according to methods as specified in the Specifications and required by the City.
8. The cash, certified check, cashier's check, irrevocable letter of credit or Bid Bond shall be payable to the
City to the extent of 10% of the amount of the bid in case this bid is accepted by the City and the undersigned shall fail or refuse to execute the Contract and furnish a Payment Bond, a Performance Bond or the Public Works Bond Filing Certification form as required by the Specifications within the time limit named therein after notification that said bid is accepted, all in accordance with the provisions of this bid and the Plans and Specifications which are a part hereof.
9. All items for the Contract for which forms are provided herein have been completed in full by the showing of prices for each and every item thereof, and for the showing of other information indicated by the Bid Form.
10. Bidder agrees to be substantially complete by April 1, 2026. Final completion shall be 30 days after substantial completion and include any items identified on the punch list. Once work commences, the contractor has 50 working days to complete Work Area 1 and 20 working days to complete Work Area 2.
11. In the event the bidder is awarded the Contract and fails to complete the Project within the time limit or extended time agreed upon, as more specifically set forth in the General Conditions, liquidated damages shall be paid to or withheld by the City pursuant to Paragraph 4 of the Construction Contract (Time of Performance - Liquidated Damages) at the rate of identified in GP80-08, until the Project has been completed as provided in the General Conditions.
Page 23 – (Prevailing Wage Projects) Revised 10/2024
Roseburg, Oregon Airport Fencing and Security Upgrades City No. 24GR03 Page 23 Issued for Bid
12. The undersigned bidder hereby states, as part of this bid, that the applicable provisions of Oregon’s Prevailing Wage Law (ORS 279C.800 to 279C.870) and the Federal Prevailing Wage Law (Davis-Bacon Act, 40 U.S.C. 3141-3148), shall be complied with. The Project is subject to both the State and Federal Prevailing Wage Laws and rates and workers in each trade will be paid the higher of the two rates.
13. The undersigned bidder and bidder's subcontractors shall comply with ORS 656.017, which requires them to provide Workers' Compensation coverage for all their subject workers.
14. The undersigned bidder hereby states, as part of this bid, that bidder shall comply with ORS 279C.505(2) which requires bidder to have an employee drug testing program in place.
15. The undersigned bidder and bidders’ subcontractors shall comply with ORS 279C.570 and 279C.580, which require timely progress payments for public improvement projects and provide interest penalties for late payment.
16. The undersigned bidder hereby states, as part of this bid, bidder and bidder's subcontractors shall comply with the provisions of Exhibit "A" - "Standard City Contract Provisions".
17. If applicable pursuant to Section 11 of “Information for Bidders”, the undersigned bidder hereby states, as part of this bid, that bidder has completed pay equity compliance training and received a certificate of completion from the Oregon Department of Administrative Services.
18. If the bidder is awarded the Contract for this work, the name and address of the Surety who will provide the Payment Bond, Performance Bond and Public Works Bond (if required) will be:_______________________________________________________.
19. The name and…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .