245041 Special Provisions.pdf
PDF 354 KB Posted
- Attached to
- Bid No. 245041 Thermal Cured In Place Pipe
- Solicitation number
- S-KS0043-00010492
- Issued by
- Marion County, Oregon
About this file
This document details the Special Provisions for Bid No. 245041 - Thermal Cured In Place Pipe for the City of Salem, Oregon. The work consists of rehabilitating existing gravity sewer pipes by furnishing and installing pipe liners using cured-in-place lining methods. Bid items include sanitary sewer bypass pumping, CIPP setup, manhole work, CIPP lining of various pipe sizes, sampling and testing, and lateral reinstatement. The City will provide the Traffic Control Plan, and the Contractor must submit various technical submittals for review prior to the start of work. The Contractor must comply with requirements for pipe preparation, installation, curing, sampling, testing, and repairs. Payment will be based on the contract unit prices, with deductions for failing to meet design parameters. The document also includes additional requirements for tree protection, temporary traffic control, and erosion prevention.
The contract will be awarded to the lowest responsive and responsible bidder. Contractors must provide pricing for various time and material line items, as well as fixed unit prices for the CIPP lining work. The CIPP lining work must comply with specific design parameters, such as pipe ovality, soil conditions, and safety factors. Sampling and testing procedures are detailed, and the City reserves the right to require removal and replacement of non-compliant CIPP liners.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 245041 Bid Manual.pdf | ||
| Zoom Bid Opening Instructions 6.11.24~1.docx | DOCX document | |
| 245041 Notice Intent to Award.pdf | ||
| 245041 Bid Tabulation.pdf | ||
| Zoom Bid Opening Instructions 6.11.24.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Thermal Cured in Place Pipe
Bid No. 245041
01000 - 1 Special Provisions
Special Provisions
Bid Number 245041
BID
ITEMS
Item Description Measurement and Payment
1 Sanitary Sewer Bypass Pumping
The unit price for this item will be full compensation for the bypass pumping of flows with one 4-inch trash bypass pump and up to 500 linear feet of discharge hose.
All other bypass pumping needs would be subject to a negotiated T&M price.
2 CIPP Setup in ROW (direct vehicular access over one manhole) the setup of each CIPP installation that utilizes factory wetout liners, including installation of hydrophilic end seals, pre-installation CCTV (no PACP, digital format required), and post-installation CCTV (City of Salem coding, digital format required). Preparation and creation of CIPP samples will be paid for under Items 26 and 27.
Laboratory testing will be paid for under Items 28 to 32.
3 CIPP Setup off-road (no vehicular access over either insertion and receiving manhole) the setup of each CIPP installation that utilizes factory wetout liners, including installation of hydrophilic end seals, pre-installation and post-installation CCTV (City defect coding, digital format required). Preparation and creation of CIPP samples will be paid for under Items 26 and 27. Laboratory testing will be paid for under Items
28 to 32.
4 Remove and reset cone/topslab
(less than 40 Sq. Ft.)
Resetting is complete resetting, including all cement, mortar, or grout work required to bond the non-damaged topslab (less than 40 Sq. Ft.) to existing structure.
Damage to the topslab during removal, if performed completely in accordance with the procedures outlined by the ENGINEER, will not be the responsibility of the
CONTRACTOR and the disposal of the damaged topslab and replacement with a new topslab will be paid under Item 6. Payment includes covering of inlets at all times by either the topslab or steel plate.
5 Remove and reset cone/topslab
(greater than 40 Sq. Ft.)
Resetting is complete resetting, including all cement, mortar, or grout work required to bond the non-damaged topslab (greater than 40 Sq. Ft.) to existing structure.
Damage to the topslab during removal, if performed completely in accordance with the procedures outlined by the ENGINEER, will not be the responsibility of the
CONTRACTOR and the disposal of the damaged topslab and replacement with a new topslab will be paid under Item 7. Payment includes covering of inlets at all times by either the topslab or steel plate.
01000 - 2 Special Provisions
Item Description Measurement and Payment
6 Remove and dispose of existing topslab and replace (less than 40
Sq. Ft.)
This item includes preparation for the removal of existing topslab, removal and disposal of existing topslab, replacement with a new topslab. Replacement includes all cement, mortar, or grout work required to bond the new topslab (less than 40 Sq. Ft.) to existing structure.
7 Remove and dispose of existing topslab and replace (greater than
40 Sq. Ft.)
This item includes preparation for the removal of existing topslab, removal and disposal of existing topslab, replacement with a new topslab. Replacement includes all cement, mortar, or grout work required to bond the new topslab (greater than 40 Sq. Ft.) to existing structure.
8 8" CIPP, base cost (assume 8 feet of cover)
Includes all labor, materials, equipment, and incidentals for light cleaning and installing CIPP and post-installation CCTV. Sampling, testing, traffic control, and environmental protection are paid for under other Items.
9 8" CIPP, deduct for each 1.5mm thickness
Includes all labor, materials, equipment, and incidentals for the incremental reduction of CIPP thickness based on less stringent design parameters.
10 8" CIPP, increase for each
1.5mm thickness
Includes all labor, materials, equipment, and incidentals for the incremental increase of CIPP thickness based on more stringent design parameters.
11 10" CIPP, base cost (assume 8 feet of cover)
Includes all labor, materials, equipment, and incidentals for light cleaning and installing CIPP and post-installation CCTV. Sampling, testing, traffic control, and environmental protection are paid for under other Items.
12 10" CIPP, deduct for each 1.5mm thickness
Includes all labor, materials, equipment, and incidentals for the incremental reduction of CIPP thickness based on less stringent design parameters.
13 10" CIPP, increase for each
1.5mm thickness
Includes all labor, materials, equipment, and incidentals for the incremental increase of CIPP thickness based on more stringent design parameters.
14 12" CIPP, base cost (assume 8 feet of cover)
Includes all labor, materials, equipment, and incidentals for light cleaning and installing CIPP and post-installation CCTV. Sampling, testing, traffic control, and environmental protection are paid for under other Items.
15 12" CIPP, deduct for each 1.5mm thickness
Includes all labor, materials, equipment, and incidentals for the incremental reduction of CIPP thickness based on less stringent design parameters.
16 12" CIPP, increase for each
1.5mm thickness
Includes all labor, materials, equipment, and incidentals for the incremental increase of CIPP thickness based on more stringent design parameters.
01000 - 3 Special Provisions
Item Description Measurement and Payment
17 15" to 21" CIPP, base cost
(assume 8 feet of cover)
Includes all labor, materials, equipment, and incidentals for light cleaning and installing CIPP and post-installation CCTV. Sampling, testing, traffic control, and environmental protection are paid for under other Items.
18 15" to 21" CIPP, deduct for each
1.5mm thickness
Includes all labor, materials, equipment, and incidentals for the incremental reduction of CIPP thickness based on less stringent design parameters.
19 15" to 21" CIPP, increase for each 1.5mm thickness
Includes all labor, materials, equipment, and incidentals for the incremental increase of CIPP thickness based on more stringent design parameters.
20 24" to 30" CIPP, base cost
(assume 10 feet of cover)
Includes all labor, materials, equipment, and incidentals for light cleaning and installing CIPP and post-installation CCTV. Sampling, testing, traffic control, and environmental protection are paid for under other Items.
21 24" to 30" CIPP, deduct for each
1.5mm thickness
Includes all labor, materials, equipment, and incidentals for the incremental reduction of CIPP thickness based on less stringent design parameters.
22 24" to 30" CIPP, increase for each 1.5mm thickness
Includes all labor, materials, equipment, and incidentals for the incremental increase of CIPP thickness based on more stringent design parameters.
23 36" to 42" CIPP, base cost
(assume 10 feet of cover)
Includes all labor, materials, equipment, and incidentals for light cleaning and installing CIPP and post-installation CCTV. Sampling, testing, traffic control, and environmental protection are paid for under other Items.
24 36" to 42" CIPP, deduct for each
1.5mm thickness
Includes all labor, materials, equipment, and incidentals for the incremental reduction of CIPP thickness based on less stringent design parameters.
25 36" to 42" CIPP, increase for each 1.5mm thickness
Includes all labor, materials, equipment, and incidentals for the incremental increase of CIPP thickness based on more stringent design parameters.
26 Restrained Sample All material and incidentals required to do prepare and create a 30" long restrained sample on CIPP installations
8"-21".
27 Plate Sample All material and incidentals required to do prepare and create plate samples on CIPP installations (generally 24" diameter and greater) , sizes as necessary to create samples for D790, D2990, D543, or D638 tests (typically
10" wide by twenty times the installed CIPP thickness)
28 ASTM D790 Tests Assume 6 or greater samples sent in at a time for testing, includes costs for shipping and handling of samples and reporting results to the City
29 ASTM D638 Tests Assume 6 or greater samples sent in at a time for testing, includes costs for shipping and handling of samples and reporting results to the City
01000 - 4 Special Provisions
Item Description Measurement and Payment
30 ASTM D2990 Tests Assume 1 sample sent in at a time for testing, includes costs for shipping and handling of samples and reporting results to the City
31 ASTM D543 Tests Assume 1 sample sent in at a time for testing, includes costs for shipping and handling of samples and reporting results to the City
32 Thickness per D5813 Assume 6 or greater samples sent in at a time for testing, includes costs for shipping and handling of samples and reporting results to the City
33 Reinstatement of tap connection Assume minimum of three (3) reinstated taps per line
34 Subcontractors for T&M Work
(All Bidders Shall Use $10,000 -
Includes 5% Mark-Up)
Assumed value for bidding purposes only.
35 Equipment for T&M Work (All
Bidders Shall Use $15,000 -
Includes 15% Mark-Up)
Assumed value for bidding purposes only.
36 Materials for T&M Work (All
Bidders Shall Use $25,000 -
Includes 15% Mark-Up)
Assumed value for bidding purposes only.
37 Bonding (All Bidders Shall Use
$10,000 - No Mark-up)
Assumed value for bidding purposes only.
38 Insurance and Taxes The cost of Insurance and Taxes. Including the costs of premiums for all insurance Contractor is required by the
Contract Documents to purchase and maintain, and sales, consumer, use, and other similar taxes related to the
Work, and for which Contractor is liable, imposed by
Laws and Regulations. Costs will be paid per the bid item percentage.
See the corresponding section in the SCS/Special Provisions for further clarification. Work not associated with any of these bid items and approved by the Project Manager will be paid on a negotiated time and material basis (T&M) as per the Contract. The Owner reserves the right to pay for any Work on a negotiated T&M basis even if it is listed as a bid item. The Project Manager will notify Contractor when the City has identified T&M work.
APPLICABLE STANDARD SPECIFICATIONS
The Standard Construction Specifications of the City of Salem, including revisions up to and effective as of February 2017, and the revised City of Salem Standard Plans effective prior to advertisement, shall be considered a part of these Specifications, the same as though contained fully herein. They will hereinafter be referred to as Standard Construction Specifications, or abbreviated SCS. The Contractor must review the SCS and take them into consideration in the preparation of their bid. Copies of these documents are available to view or download at the City of Salem’s website: https://www.cityofsalem.net/Pages/standard-plans-and-specifications.aspx https://www.cityofsalem.net/Pages/standard-plans-and-specifications.aspx https://www.cityofsalem.net/Pages/standard-plans-and-specifications.aspx
01000 - 5 Special Provisions
These Special Provisions supplement the SCS and do not replace the SCS unless otherwise indicated. Where section numbering is used in these Special Provisions it refers to the SCS. The Special Provisions apply specifically to the details of the Work that will be shown on the project specific Drawings for each Public
Works Construction Project. Specific drawings showing the location, character of work, and details of construction will be provided to the Contractor at a later time and will be included with these Contract
Documents and incorporated herein by reference.
When called out as a reference, Sections and subsections of the Oregon Standard Specifications for
Construction (OSSC), Latest Edition, and Oregon Standard Drawings (OSD), Latest Edition, may also apply to this work.
DIVISION 1—GENERAL REQUIREMENTS
Section 130—Submittals
130.40 – General
(b) Sequence—Add the following text to this item of the SCS:
Allow five working days for Owner review and return of each iteration of submittals.
—Add the following new item to this subsection of the SCS:
(h) Measurements—Contractor shall verify field measurements prior to transmittal.
Section 170—Execution Requirements
Requirements
170.47 – Notification and Coordination—Delete the text of this subsection of the SCS and replace with the following:
Notify all affected Utilities and Government Agencies prior to start of construction. Coordinate necessary relocation work and detours. The following is a partial contact list:
Northwest Natural (Cameron Marcom) ....................................................................... 971-979-6810
Comcast (Jason McDonald 97301, 97303, 97304, 97305) .......................................... 503-924-9120
Comcast (Chris Cranford 97302) ................................................................................ 503-924-9120
Comcast (Jonathon Humphreys 97306, 97317) .......................................................... 503-302-0853
City of Salem Public Work Operations ....................................................................... 503-588-6333
Salem Electric-Distribution and Street Lighting (Adam Deshon) ............................... 503-316-2423
Portland General Electric (Ken Spencer) .................................................................... 503-970-7200
Portland General Electric-Street Lighting (Jeff Steigleder) ........................................ 503-672-5462
01000 - 6 Special Provisions
Lumen (Josh Fallin) ..................................................................................................... 503-399-4931
Salem/Keizer School District, Transportation (Michael Shields or Kevin Baker) ...... 503-399-3108
Cherriots (Dispatch). ................................................................................................... 503-588-2424
170.50 – Project Specific Requirements―Add the following new subsection to the SCS:
Schedule to Provide Service – The successful bidder shall be required to submit scope of service within
14 calendar days of City request. The successful bidder shall be required to complete the tasks indicated in the Scope of Services within 60 calendar days after issuance of the Notice to Proceed or as designated by the Contract Administrator or Project Manager.
Section 171—Work Site Access Encumbrances and Restrictions
171.41 – Project Specific Requirements—Add the following text to this subsection of the SCS:
(a) Unless otherwise specified, normal work days shall be Monday through Friday, 7 a.m to 5 p.m.
Performing work on holidays, Saturdays, and Sundays will only be allowed as approved by the Project
Manager. Additional traffic control work hour restrictions may apply.
—Delete this section of the SCS and replace with the following:
Section 180 – Progress Schedule
180.01 – Project Specific Schedule Requirements
Provide a schedule for each work assignment that lists work tasks on a time scale bar chart. The length of each task bar shall represent the task duration. The beginning and end of each bar will align on the time scale with the start and finish dates for each task. The schedule shall have a sufficient number of tasks to illustrate the orderly, timely and efficient prosecution of the work. The schedule will enable both the
Contractor and the Project Manager to plan, coordinate, appraise, document and control their respective contract responsibilities. It shall be the contractor’s responsibility to ensure that all of the work is described in the project schedule and that it represents the sequence and time planned for the work. Upon Project
Manager’s request, provide updates to the progress schedule that represents progress to date and changes from previous versions of the schedule.
⸺Add the following new section to the SCS:
Section 191 – Cost of the Work; Contractor’s Fee
191.01 – Cost of the Work
(a) Costs Included: The term Cost of the Work means the sum of all costs, except those excluded in
Paragraph 191.01.b, necessarily incurred and paid by Contractor in the proper performance of the
Work. When the value of any Work covered by a Change Order or when a Claim for an adjustment in Contract Price is determined on the basis of Cost of the Work, the costs to be reimbursed to
Contractor will be only those additional or incremental costs required because of the change in the
01000 - 7 Special Provisions
Work or because of the event giving rise to the Claim. Except as otherwise may be agreed to in writing by Owner, such costs shall be in amounts no higher than those prevailing in the locality of the Project, shall include only the following items, and shall not include any of the costs itemized in Paragraph 191.01.b.
(1) Unit costs as bid by the Contractor in the Invitation to Bid, and shall only include the actual quantities associated with performing the work.
(2) Materials and Equipment costs including the following:
A. Cost of all materials and equipment furnished and incorporated in the Work, including costs of transportation and storage thereof, and Suppliers’ field services required in connection therewith.
B. Cost of construction equipment employed and parts therefor, whether such equipment is owned or leased by Contractor or rented from bonafide equipment rental companies in accordance with rental agreements approved by Owner, including the costs of transportation, loading, unloading, assembly, dismantling, and removal thereof. The rental of any such equipment, machinery, or parts shall cease when the use thereof is no longer necessary for the Work.
1. Cost computation for Contractor owned or leased equipment shall be made in accordance with the rates established in the Blue Book. Rate adjustment factors shall be applied to equipment for equipment age, geographic region of work, and standby status.
Hourly rates shall be calculated by dividing the adjusted monthly rate by 176 and then adding the hourly operating rate. If applicable, standby rates shall be determined pursuant to the recommendations in the Blue Book.
2. Cost computation for equipment rented from bonafide equipment rental companies shall be for only the proportional share of the executed rental agreement, and shall not exceed 30 percent of the total equipment cost for each project performed by the
Contractor without written approval from the Engineer.
3. Equipment items considered incidental to the work include, but are not limited to:
jumping jacks, plate compactors, pipe laser, line level, EL-1 level, generators 3000 watts or less, water pipeline pressure test equipment, dewatering pumps 2-inch diameter discharge and smaller, pressure washing equipment, hot saws with blades up to 14-inch diameter, and grinders with blades up to 4-inch diameter.
(3) Payments made by Contractor to Subcontractors for Work performed by Subcontractors. If required by Owner, Contractor shall obtain competitive bids from subcontractors acceptable to Owner and Contractor, and shall deliver such bids to Project Manager, who will then determine which bids, if any, will be acceptable. If any subcontract provides that the
Subcontractor is to be paid on the basis of Cost of the Work plus a fee, the Subcontractor’s
Cost of the Work and fee shall be determined in the same manner as Contractor’s Cost of the
Work and fee as provided in Paragraph 191.01.
01000 - 8 Special Provisions
(4) Costs of special consultants (including but not limited to engineers, architects, testing laboratories, surveyors, attorneys, and accountants) employed for services specifically related to the Work, but only to the extent authorized and approved, in writing, by Owner.
(5) Supplemental costs, subject to approval of the City’s Project Manager, including the following:
A. Cost, including transportation and maintenance, of all materials, supplies, equipment, machinery, appliances, office, and temporary facilities at the Site, and hand tools not owned by the workers, which are consumed in the performance of the Work, and cost, less market value, of such items used, but not consumed, which remain the property of Contractor.
B. The cost of Insurance and Taxes. Including the costs of premiums for all insurance
Contractor is required by the Contract Documents to purchase and maintain, and sales, consumer, use, and other similar taxes related to the Work, and for which Contractor is liable, imposed by Laws and Regulations. Costs will be paid per the bid item percentage.
C. Deposits lost for causes other than negligence of Contractor, any Subcontractor, or anyone directly or indirectly employed by any of them, or for whose acts any of them may be liable, and royalty payments and fees for permits and licenses.
D. Losses and damages (and related expenses) caused by damage to the Work, not compensated by insurance or otherwise, sustained by Contractor in connection with the performance of the Work, provided such losses and damages have resulted from causes other than the negligence of Contractor, any Subcontractor, or anyone directly or indirectly employed by any of them, or for whose acts any of them may be liable. Such losses shall include settlements made with the written consent and approval of Owner. No such losses, damages, and expenses shall be included in the Cost of the Work for the purpose of determining Contractor’s fee.
E. The cost of utilities, fuel, and sanitary facilities at the Site.
F. Minor expenses such as petty cash items in connection with the Work.
G. The costs of premiums for all bonds Contractor is required by the Contract Documents to purchase and maintain. No additional markup is allowed for bonding.
(b) Costs Excluded―The term Cost of the Work shall not include any of the following items:
(1) Not used.
(2) Expenses of Contractor’s principal and branch offices.
(3) Any part of Contractor’s capital expenses, including interest on Contractor’s capital employed for the Work and charges against Contractor for delinquent payments.
01000 - 9 Special Provisions
(4) Costs due to the negligence of Contractor, any Subcontractor, or anyone directly or indirectly employed by any of them, or for whose acts any of them may be liable, including but not limited to the correction of defective Work, disposal of materials or equipment wrongly supplied, and making good any damage to property.
(5) Other overhead or general expense costs of any kind and the costs of any item not specifically and expressly included in Paragraphs 191.01.a.
(c) Contractor’s Fee: When the value of any Work covered by a Change Order or when a Change Order
Request for an adjustment in Contract Price is determined on the basis of Cost of the Work, Contractor’s fee shall be determined as set forth in Paragraph 191.02.a.
(d) Documentation: Whenever the Cost of the Work for any purpose is to be determined pursuant to
Paragraphs 191.01.a and 191.01.b, Contractor will establish and maintain records thereof in accordance with generally accepted accounting practices and submit, in a form acceptable to
Project Manager, an itemized cost breakdown together with supporting data.
191.02 – Contractor’s Fee
(a) The Contractor’s fee for overhead and profit shall be determined as follows:
(1) A fee based on the following percentages of the various portions of the Cost of the Work:
A. for costs incurred under Paragraph 191.01.a.1, there shall be no additional Contractor’s fee above the unit price bid; and under Paragraph 191.01.a.2, the Contractor’s fee shall be 15 percent;
B. for costs incurred under Paragraph 191.01.a.3 and 191.01.a.4, the Contractor’s fee shall be 5 percent;
C. where one or more tiers of subcontracts are on the basis of Cost of the Work plus a fee, the intent of Paragraph 191.02.a.1.A is that the Subcontractor who actually performs the
Work, at whatever tier, will be paid a percentage fee in accordance with Paragraph
191.02.a.1.A, and that any higher tier Subcontractor and Contractor will each be paid a fee of 5 percent of the amount paid to the next lower tier Subcontractor;
D. no additional fee shall be payable on the basis of costs itemized under Paragraphs
191.01.a.5 and 191.01.b;
E. the amount of credit to be allowed by Contractor to Owner for any change that results in a net decrease in cost will be the amount of the actual net decrease in cost plus a deduction in Contractor’s fee by an amount equal to 5 percent of such net decrease; and
01000 - 10 Special Provisions
F. when both additions and credits are involved in any one change, the adjustment in
Contractor’s fee shall be computed on the basis of the net change in accordance with
Paragraphs 191.02.a.1.A through 191.02.a.1.E, inclusive.
⸺END OF SECTION⸺
01000 - 11 Special Provisions
DIVISION 2—GENERAL TECHNICAL REQUIREMENTS
202 TEMPORARY TRAFFIC CONTROL
⸺Add the following new subsection to this section of the SCS:
202.3.06 ACCOMMODATIONS FOR PEDESTRIANS
Description
Scope—This work consists of providing and maintaining alternate pedestrian access routes, and temporary pedestrian barricades and channeling devices according to the Drawings, Standard Drawings, the sidewalk closure permit, these specifications, or as directed.
Abbreviations, Definitions, and Standards
(a) Abbreviations
TCD—Traffic Control Devices
(b) Definitions
Detectable—A surface having a continuous edge within 6 inches of the surface so that pedestrians who have visual disabilities can sense its presence and receive usable guidance information.
Pedestrian—A person on foot, in a wheelchair, on skates, or on a skateboard.
Traffic Control Device—A sign, signal, marking, or other device used to regulate, warn, or guide traffic, placed on, over, or adjacent to a street, pedestrian facility, or shared-use path
(c) Standards—When designing, applying, installing, maintaining, inspecting, and removing TCD, use and follow the most current versions in effect of the MUTCD.
General Requirements
(a) Alternate Pedestrian Access Route—When a sidewalk or pathway is temporarily closed by construction, alterations, maintenance operations, or other conditions, provide an alternate pedestrian access route complying with the most current version in effect of MUTCD.
Materials
(a) Pedestrian Barricades and Channelizing Devices—Furnish temporary barricades, barrier, pedestrian fencing, channelizing devices and accessories meeting the requirements set forth in
ODOT 00225.12.
01000 - 12 Special Provisions
⸺Delete the text in this subsection of the SCS and replace with the following:
202.4.02 INCIDENTAL BASIS
When not listed in the Proposal for separate payment, all temporary traffic control will be considered incidental work for which no separate payment will be made, except that the contractor can be compensated for the time spent preparing the traffic control plan at the hourly rates established in the bid price for “Traffic
Control Specialist”.
⸺Add the following new subsection to this section of the SCS:
202.4.03 TRAFFIC CONTROL PLAN PREPARED BY THE CITY
When traffic control plans are required, the City will determine during the scoping of the Work who will prepare the Traffic Control Plan. When prepared by the City, there will be no payment for the Traffic
Control Specialist to the Contractor. Payment for the Traffic Control Specialist will only occur when the
Traffic Control Plan is prepared by the Contractor.
204 EXCAVATION, EMBANKMENT, BEDDING, AND BACKFILL
204.4.00 MEASUREMENT AND PAYMENT―Delete this subsection from the SCS.
207 EROSION PREVENTION AND SEDIMENT CONTROL
207.9.02 EROSION CONTROL—Add the following text after the first sentence of this subsection of the
SCS:
• Concrete Management Facilities
208 RESTORATION AND CLEANUP
208.3.00 CONSTRUCTION—Add the following new subsection to this section of the SCS:
208.3.09 GENERAL RESTORATION
All areas which are disturbed, damaged, and/or destroyed during construction shall be restored in conformance with the various subsections of the SCS and these Special Provisions. All restoration work associated with areas outside pavement, gravel, sidewalk, curbs, and similar areas shall meet the requirements of Section 701.
All landscaping shall be restored within three weeks of initially being disturbed unless approved in writing by the Project Manager.
All disturbed or removed fencing, pavers, retaining walls, and bark mulch shall be restored to prior existing condition or better.
01000 - 13 Special Provisions
408 THERMAL CURED-IN-PLACE PIPE LINING
—Delete this section of the SCS and replace with the following:
408.1.00 DESCRIPTION
This work consists of rehabilitating existing gravity sewer pipes by furnishing and installing pipe liners by cured-in-place lining methods as shown.
408.1.01 DEFINITIONS
Cured-In-Place Pipe (CIPP)⸺Inserting a resin impregnated tube into an existing pipe, expanding it, and curing it to form a new lined pipe and in accordance with ASTM F1216 or ASTM F1743.
End Seal⸺Hydrophilic continuous O-rings or fully continuous material (no gaps) to seal the ends of the
CIPP with the existing mainline host pipe and prevent future infiltration or fine migration.
Gravity Pipe⸺Pipe designed to convey fluids under conditions where the hydraulic gradient and water surface are coincident within the pipe.
Impregnation⸺Complete saturation of the CIPP tube with resin.
408.1.02 SUBMITTALS
Submit in accordance with Section 130 the following for review in a single package prior to the start of work:
(a) Certification⸺Submit certification from the CIPP component manufacturer(s) showing installers are certified and licensed installers.
(b) Personnel⸺Provide the names of the superintendent(s) on the project. Submit a list of the additional key personnel who will work on this project, including certification of worker training for key personnel involved with installing thermal CIPP (foreman, lateral reinstatement operator, etc.). Include a summary of their experience and qualifications related to thermal CIPP installations.
(c) Test Reports⸺Certified documentation that short-term physical properties of the resin/liner combination meet the requirements for initial structural properties (performed in accordance with ASTM
F1216, ASTM D638, and ASTM D790) and chemical resistance (performed in accordance with ASTM
F1216-Appendix X2).If extrapolated long-term test results are submitted to support a flexural modulus retainage greater than 50 percent, then initial data between time “0” and “1,000” hours must be excluded.
(d) Technical Data⸺Liner system manufacturer’s technical data documenting information on material composition, chemical and physical properties, and dimensions of components of the tube and resin system.
Include manufacturer’s recommendation for allowable mixing, impregnation, and handling times, transportation and storage, insertion pressures, curing, trimming, finishing, and data on the maximum allowable stresses and elongation of the tube. Specify resin color to be used.
(e) Calculations⸺Engineering calculations (stamped by a professional engineer registered in Oregon) for the design of the CIPP liner. Identify the design methodology, assumptions, design criteria, safety factor and material properties.
(f) End Seals⸺End seal material to be used, and method of installation.
01000 - 14 Special Provisions
(g) Wet Out Process⸺Description, schedule and location of the wet-out process. Include manufacturer’s wet-out recommendations: the roller gap, material feed speed and vacuum requirements for each liner size and thickness.
(h) Installation Plan⸺Description of the pipe lining and curing process including staging and insertion locations (typically includes an incomplete cure log for each shot). The plan must also include specific curing times and pressure specific to each liner segment and address project design parameters and site conditions. If possible, include a contingency curing cycle in the event temperatures fall over or under the liner system manufacturer’s recommendations. Identify in the description the type of temperature sensors that will be used, their proposed locations, and recording method and/or equipment. Include in the overall installation plan the sequence of lateral rehabilitation or reinstatement.
Include a control protocol for each installation. The control protocol must include certification of approval by the liner manufacturer, including the following minimum information:
(1) Date and time
(2) Length of liner
(3) Location of installation
(4) Curing Speed
(5) Inner air or water pressure
(6) Exothermic (curing) temperature
(i) Shot Schedule⸺Include a schedule detailing when the work is to begin and the order of locations to be completed.
(j) Styrene Control Plan⸺For stormwater pipe installations, include a detailed description of the styrene mitigation plan for reducing the styrene concentrations in all discharged process water to 2.5 mg/L or less.
Plan shall also provide details for the water sampling methods and analytical analysis procedures to demonstrate compliance with this requirement. In addition, provide plan for controlling the airborne concentration of styrene to below OSHA limits.
(k) Pipe Access⸺Identify all required manhole, structure or pit access for CIPP installation. Identify required modifications to existing facilities and describe proposed preparation, modification, preservation, and restoration activities. Include sketches, shop drawings and/or engineered repair drawings as required.
Include locations of intermediate pipe access and proposed repair plan that meets the requirements of the
Contract.
(l) Lateral Reinstatement Plan⸺Include method, materials and personnel assigned to do the work.
(m) Sampling Plan⸺Include proposed methods, locations, and proposed chain-of-custody process for sample delivery to the City’s Construction Manager.
(n) Liner Repair Plan⸺Include a detailed description of methods and materials required to repair typical and isolated areas of minor liner damage, such as: installation tears less than 4 inches in length and no more frequent than one in one-hundred linear feet, discrete blisters, areas of pinholes, areas of dry tube, and soft spots. Include proposed method for repairing trimmed wrinkles and fins. Provide the CIPP liner system manufacturer’s recommendations for liner repairs. Liner Repair Plan approval is required prior to making each repair.
Submit the following for review, during construction:
(o) Wet Out Logs⸺Document resin volumes used, and provide logs upon delivery of liner system to project site. Provide certification by the person responsible that the entire wet out process, including handling and delivery to the site, followed the defined procedures.
01000 - 15 Special Provisions
(p) Cure Logs⸺Record installation data, and submit cure log upon completion of the installation.
408.1.03 DESIGN PARAMETERS
Follow the requirements of ASTM F1216 and meet the following conditions and parameters:
Condition Parameter
Service Life ............................................. Greater than 50 years
Pipe Conditions ....................................... Fully Deteriorated
Load Conditions ...................................... Continuous
Soil ............................................. 100-pound/cubic-foot
Traffic ........................................ HS-20
Groundwater Elevation ........................... Below the Pipe
Pipe Ovality ............................................ 3%
Modulus of Soil Reaction ....................... 700 psi
Enhancement Factor................................ 7.0
Flexural Strength, long-term ................... 50%* of Initial (ASTM D790)
Modulus of Elasticity, long-term ............ 50%* of Initial (ASTM D790)
Maximum Deflection .............................. 5%
Poisson’s Ratio ....................................... 0.3
Dimension Ratio ..................................... 55 minimum
Design Safety Factor ............................... 2.0
*unless long-term test results are provided that substantiate a greater retainage.
408.2.00 MATERIALS
408.2.01 Tube
Furnish tubing that consists of one or more layers of flexible, absorbent non-woven felt fabric meeting the requirements of ASTM F1216, Section 5.1.
Fabricate the tube to a size that when installed, conforms to the internal circumference and length of the host pipe. Verify pipe diameters prior to ordering tubing. Make allowance for circumferential or longitudinal stretching during inversion. Provide flexible tubing exhibiting the following characteristics:
• Homogeneous wall thickness.
• Contains no intermediate or encapsulated elastomeric layers.
• Contains no material that may cause delamination in the cured CIPP.
• Before inversion, tubing is coated with an impermeable, flexible material on the outside layer of the tube.
• Sewn or bonded seams, as recommended by the tube manufacturer, stronger than the non-seamed material.
408.2.02 Resin
Furnish resins meeting the requirements of ASTM F1216, Section 5.2, or ASTM F1743, Section 5.2.3
Resin. Comply with the structural requirements specified for the installed liner system.
Provide thermosetting polyester or vinyl ester resin and a catalyst system compatible with the installation process, with the ability to cure in the presence or absence of water, and with a curing initiation temperature as recommended by the resin manufacturer. No onsite or mobile impregnation will be allowed.
01000 - 16 Special Provisions
Color the resin with a pigment compatible with the resin system, as specified by the resin manufacturer, and as approved.
408.2.03 Liner Properties
Provide liners that have the minimum physical properties stated in ASTM F1216, F1743 and ASTM D2990, and also be resistant to chemical properties and flow characteristics typically found in municipal sanitary sewer flows. Fabricate the liner to a size that when cured, will tightly fit the pipe being rehabilitated.
Characteristic Test Method Polyester Resin
Initial Flexural Strength ASTM D790 4,500 psi
Initial Flexural Modulus of Elasticity ASTM D790 400,000 psi (min)
408.2.04 Pipe Liner End Seal
The hydrophilic waterstop end seals completely seal the CIPP liner from any annular space leakage between the CIPP liner and the host pipe. Hydrophilic end seals must be one of the following:
1. Bands that are 20 mm wide and 5 mm high, with a double bump on one side and flat on the other side. Product shall be Hydrotite Style DS-0520-3.51 or approved equal.
2. Tubular hydrophilic sleeve, 2 mm in thickness and 3.5 inches in length, with a mechanical fastener with worm gear expander. Product shall be Insignia End Seal by LMK Technologies, or approved equal.
408.2.05 Temperature Monitoring Equipment
For all installations 21-inch in diameter or greater, provide full length monitoring equipment that takes continuous temperature readings with sensors placed a minimum of 10 feet between sensors for the entire length of the pipe being lined. Use equipment that includes both the software and the hardware necessary to operate and monitor the system. Provide one licensed copy of the software to the City’s Construction
Manager to remain the property of the City upon completion of the Work. Temperature monitoring system and related software shall be Zia Systems, Inc., VeriCure by Pipeline Renewal Technologies, or approved equal.
408.3.00 CONSTRUCTION
408.1.01 Personnel
Crews and key personnel may not work more than 12 hours per 24-hour day unless otherwise approved.
408.3.02 General
Handle and store all liner material to ensure that the material is not torn, cut, exposed to direct sunlight or otherwise damaged. Before installing the liner, verify its condition with the Owner’s Representative. If any part of the liner material becomes torn, cut or otherwise damaged before or during insertion, repair or replace it at no additional cost before proceeding further. Manned entry in unlined pipe is not allowed. If manned intermediate access is required, an access pit must be dug at the required location
01000 - 17 Special Provisions
408.3.03 Water and Electric Service
Furnish and supply generators or obtain temporary power to provide all electric power required for installation. Obtain a permit and pay all fees required for any water obtained from the City.
408.3.04 Diversion of Flow
Furnish, install, maintain and operate a flow diversion system as needed in accordance with Section
404.3.11.
408.3.05 Pre-Installation Video Inspection
Prior to installation, flush and clean all parts of the existing pipe system to remove all debris and obstructions, and after cleaning, inspect the existing pipe according to Section 406.4.00. Provide the video and inspection report for approval at least two calendar days prior to beginning CIPP installation operations.
Make corrections as directed before continuing with liner installation.
408.3.06 Pipe Preparation
Remove all protruding taps and any other obstructions in the host pipe that may prevent the succesful installation of the CIPP liner. Pipe may need additional cleaning and video inspection to assure that shavings are removed prior to liner installation.
408.3.07 Line Obstructions
If inspection reveals unanticipated obstructions, undersized pre-existing point repairs, sags, running leakage, or structural defects in the pipe, submit to the City location and proposed method of repair. City will provide a response within 5 business days.
408.3.08 Receiving and Insertion Locations
Locate all manholes or pits to suit the pipe lining operation. Use existing manholes where practical. Remove manhole flattops, inverts, benches, and channels to permit access for installation equipment, if required.
Enlarge the incoming and outgoing pipe openings, if required, to accommodate the maximum outside diameter size of the insertion equipment. Do not put undue stress on existing structures. In areas where existing manholes are not available, intermediate access pits may be excavated and utilized at no additional cost to the City. Intermediate pipe repair and restoration must be done in accordance with the Drawings at no additional cost to the City.
408.3.09 Installation
Install liner system according to ASTM F1216 Section 7 or ASTM F1743 Section 6, and the manufacturer’s recommendations.
(a) General⸺Where practicable, install liners in continuous runs through manholes where there are two or more continuous host pipe segments requiring lining. If manholes are lined through, remove crown of liner inside manhole flow channel. Provide temporary downstream dams in the pipeline to catch excess resin and construction debris. Contractor to dispose of excess resin per the resin manufacturer’s recommendations.
Do not allow the temperature of water discharged from processing liners to exceed 77 degrees Fahrenheit unless DEQ, upon the request of the City, approves alternate temperature limits not to exceed 125 degrees
Fahrenheit.
Furnish and keep one additional operational robotic cutter assembly train and key spare components on-site on a continuous basis as a “stand-by” unit in the event of primary equipment breakdowns.
01000 - 18 Special Provisions
(b) Pipe Liner End Seal⸺Install a continuous or properly trimmed end seal between the ends of the new pipe liner and the host pipe connection. Insert end seals at each structure opening approximately 3 inches max, 2 inches min from inside of structure wall to the inside edge of the end seal. For bands, butt-up trimmed end seal edges against each other at the crown of the pipe using a miter cut. Seals that have any gap between the ends will be rejected and repaired with an internal joint seal at no additional cost to the
Owner.
(c) Wet Out⸺Impregnate ("wet out") the tube with resin using distribution rollers and vacuum, or other approved method, to thoroughly saturate the tube prior to its dispatch. Transport and store the impregnated liner in a refrigerated truck or container until installation in such a manner that it will not be damaged, exposed to direct sunlight, or result in any public safety hazard.
Use a sufficient quantity of resin to fill air voids, and include additional allowance for polymerization and for any migration of resin into cracks and joints in the host pipe.
The City reserves the right to check, verify, or inspect all phases of production including manufacturing, shipping, wet-out, installation, cure, and/or finished product. Any departure from the submitted procedures may be cause for rejection.
(d) Insertion⸺Prior to insertion mark the exterior of the manufactured tube along its length at regular intervals not to exceed five (5) feet. Use the marks to measure elongation during insertion. The tube will be rejected and replacement required if the overall elongation of a tube reach exceeds five percent (5%), or as otherwise approved.
Maintain the pressure required to hold the flexible tube tight against the host pipe, per the manufacturer’s recommendations, until curing is complete. No other depressurization outside of the range required by the manufacturer for curing is permitted until the tube is fully cured and cooled. Capture and clean up all escaped resin.
(f) Curing⸺Use a suitable source of hot water or steam and a recirculation system capable of delivering the required amount of heat uniformly throughout the segment for a complete cure of the resin.
Fit the heat source with monitors to gauge the temperature of the incoming and outgoing heat supply. Install full-length temperature monitors prior to installing the liner. Additionally, place remote sensing devices
(such as thermocouples) between the impregnated tube and the invert and crown of the host pipe at each manhole to determine the temperatures during the resin cure process.
Modify the curing process if curing temperatures are above or below the resin manufacturer’s recommendations, as approved.
(g) Cool Down⸺Use a controlled cool-down process to cool the hardened pipe to a temperature in accordance with resin manufacturer's recommendation. Obtain the recommended cool temperature before relieving the static head or pressure in the lined pipe and returning normal flow back to the system. Take measures to release the pressure so that a vacuum will not develop and damage the newly installed CIPP system.
(h) Pollutant Control⸺For stormwater installations, process water, condensate, or any other material must not have a styrene concentration greater than 2.5 mg/L for discharge into downstream pipes that are carrying live sanitary flows. No water can be discharged until water chemistry compliance is met.
Contractor can utilize available downstream sewer, prior to live waste streams, for short term (48 hour) storage of water utilized in CIPP installation. Water, condensate, or any other material that exceeds this concentration must be captured or treated prior to discharge into the City’s sanitary sewer system. The use
01000 - 19 Special Provisions of styrene reducing agents will be allowed upon approval by the engineer. Styrene mitigation controls must be approved and fully operational prior to any lining work being completed.
Set up a containment barrier to capture the release of any inversion, cure, steam condensate, cool-down, or flushing water. All inversion, cure, cool down, flush water, and steam condensate that does not meet the requirements listed in the previous paragraph must be treated prior to discharge or contained and shipped off-site for disposal at an approved disposal facility.
Sample process water and submit to a third-party laboratory for analysis of VOCs. Submit all chain-of-custody forms to the Engineer. Analytical results demonstrating compliance with the maximum styrene concentrations must be provided within 24 hours following the initial installation and prior to the discharge of any additional process water.
408.3.10 Reconnection of Existing Service Laterals
Re-instate all service lateral connections after the liner system has been accepted except as directed. Locate and re-establish service laterals according to the manufacturer’s recommendations. Use equipment including, but not limited to, cutter heads, crawlers, CCTV cameras, hydraulic drums, counters, etc. that is suitable for the Work and in good working order. Use an approved internal cutting device and video camera to restore service connections to the full diameter of the service. Use qualified individuals with experience in successful internal lateral reinstatement to perform the work. Provide a permanent connection between lateral and main pipeline that is a water-tight, flush, smooth transition free of loose or abraded material.
Repair overcuts or undercuts, punctures, and ragged edges due to poor cutting of liner material at no additional cost.
Re-instate or correct, without any delay, all missed or faulty reconnections, as well as any sewage spill damage to property owners caused by missed reconnections.
408.3.11 Manhole Restoration and Structure Connections
After the cool-down period is complete, perform final trimming and sealing of the liner at access structures.
Provide watertight pipe and structure seals. Trim the finished ends of the liner to within one inch of access structure wall. Provide a smooth transition between the existing structure channel invert and the liner using a cementitious coating, or other approved material, to prevent settling of sediment or debris, and ponding of standing water. Seal all holes and voids in manhole and structure walls immediately surrounding the new liner with a chemical grout that is compatible with the resin mixture of the liner.
Reinstall manhole cones, slabs, grade rings, frames, covers, inverts, and reconstruct benches and channels after each pipe liner installation. Internal rehabilitation of manholes is not permitted until after the liner is installed and accepted.
408.4.00 TESTING AND ACCEPTANCE
408.4.01 Sampling and Testing Requirements
(a) Sample Preparation and Collection – For each installation, prepare at least two samples. Immediately deliver to the City one sample of each completed liner segment. Any sample removed from the project site without approval will be rejected. Obtain samples in accordance with ASTM 1216 and F1743. Send the second sample for testing per 408.4.01(b).
Samples must be large enough to provide five specimens for short-term flexural property tests. For flexural properties, the full wall thickness of the CIPP samples will be tested. Exterior film thickness will be subtracted from the measured thickness. The film will be physically removed from the specimen prior to testing.