245041 Bid Tabulation.pdf
PDF 39 KB Posted
- Attached to
- Bid No. 245041 Thermal Cured In Place Pipe
- Solicitation number
- S-KS0043-00010492
- Issued by
- Marion County, Oregon
About this file
This document is a bid tabulation for Bid No. 245041 Thermal Cured In Place Pipe, a state and local contract opportunity issued by the City of Salem, Oregon. The project entails the rehabilitation of existing sewer and storm gravity pipes through the furnishing and installation of thermal Cured-In-Place-Pipe (CIPP) liners. The scope of work includes sanitary sewer bypass pumping, CIPP setup, manhole work, CIPP lining of various pipe sizes, sampling and testing, and lateral reinstatement. Contractors must provide pricing for various time and material line items, as well as fixed unit prices for the CIPP lining work, which must comply with specific design parameters. The contract will be for a one-year term, with four one-year renewal options, and will be awarded to the lowest responsive and responsible bidder. Bids are due by June 11, 2024 at 2:30 PM local time.
The bid tabulation includes various unit prices and quantities for the CIPP work, as well as allowances for subcontractors, equipment, materials, and bonding. The contract is not set aside for any specific types of organizations, and prevailing wage rates apply. The City may reject any or all bids, and price increases will be considered at the time of contract renewal, subject to justification and documentation. The anticipated award value is not specified.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 245041 Bid Manual.pdf | ||
| Zoom Bid Opening Instructions 6.11.24~1.docx | DOCX document | |
| 245041 Notice Intent to Award.pdf | ||
| 245041 Special Provisions.pdf | ||
| Zoom Bid Opening Instructions 6.11.24.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Bid No. 245041 Thermal Cured In Place Pipe
Close Date: June 11, 2024 @ 2:30 PM (Local Time)
No. Item Quantity Unit of
Measure Unit Price
Total Amount
(Quantity x
Unit Price)
1 Sanitary Sewer Bypass Pumping 15 Day(s) 1,000.00$ 15,000.00$
2 CIPP Setup in ROW (direct vehicular access over one manhole)
10 EA 1,750.00$ 17,500.00$
3 CIPP Setup off-road (no vehicular access over either insertion and receiving manhole)
3 EA 3,500.00$ 10,500.00$
4 Remove and reset cone/topslab (less than 40 Sq. Ft.) 3 EA 8,921.00$ 26,763.00$
5 Remove and reset cone/topslab (greater than 40 Sq. Ft.) 2 EA 8,947.00$ 17,894.00$
6 Remove and dispose of existing topslab and replace (less than 40 Sq. Ft.)
2 EA 3,305.00$ 6,610.00$
7 Remove and dispose of existing topslab and replace
(greater than 40 Sq. Ft.)
2 EA 3,947.00$ 7,894.00$
8 8" CIPP, base cost (assume 8 feet of cover) 1000 LF 70.00$ 70,000.00$
9 8" CIPP, deduct for each 1.5mm thickness 200 LF -$ -$
10 8" CIPP, increase for each 1.5mm thickness 200 LF 2.00$ 400.00$
11 10" CIPP, base cost (assume 8-feet of cover) 1000 LF 73.00$ 73,000.00$
12 10" CIPP, deduct for each 1.5mm thickness 200 LF -$ -$
13 10" CIPP, increase for each 1.5mm thickness 200 LF 2.25$ 450.00$
14 12" CIPP, base cost (assume 8 feet of cover) 700 LF 77.00$ 53,900.00$
15 12" CIPP, deduct for each 1.5mm thickness 150 LF -$ -$
16 12" CIPP, increase for each 1.5mm thickness 150 LF 2.50$ 375.00$
Bid Tabulation
Vendor Name
SAK Construction LLC
No. Item Quantity Unit of
Measure Unit Price
Total Amount
(Quantity x
Unit Price)
17 15" to 21" CIPP, base cost (assume 8 feet of cover) 300 LF 124.00$ 37,200.00$
18 15" to 21" CIPP, deduct for each 1.5mm thickness 300 LF (4.00)$ (1,200.00)$
19 15" to 21" CIPP, increase for each 1.5mm thickness 300 LF 5.00$ 1,500.00$
20 24" to 30" CIPP, base cost (assume 10 feet of cover) 250 LF 200.00$ 50,000.00$
21 24" to 30" CIPP, deduct for each 1.5mm thickness 250 LF (5.50)$ (1,375.00)$
22 24" to 30" CIPP, increase for each 1.5mm thickness 250 LF 8.00$ 2,000.00$
23 36" to 42" CIPP, base cost (assume 10 feet of cover) 200 LF 315.00$ 63,000.00$
24 36" to 42" CIPP, deduct for each 1.5mm thickness 200 LF (9.00)$ (1,800.00)$
25 36" to 42" CIPP, increase for each 1.5mm thickness 200 LF 13.00$ 2,600.00$
26 Restrained Sample 10 EA 50.00$ 500.00$
27 Plate Sample 3 EA 25.00$ 75.00$
28 ASTM D790 Tests 13 EA 263.00$ 3,419.00$
29 ASTM D638 Tests 13 EA 316.00$ 4,108.00$
30 ASTM D2990 Tests 1 EA 6,316.00$ 6,316.00$
31 ASTM D543 Tests 1 EA 4,211.00$ 4,211.00$
32 Thickness per D5813 13 EA 26.00$ 338.00$
33 Reinstatement of tap connection 75 EA 250.00$ 18,750.00$
34 Subcontractors for T&M Work (All Bidders Shall Use
$10,000 - Includes 5% Mark-Up) 1 Assumed
Value 10,000.00$
No. Item Quantity Unit of
Measure Unit Price
Total Amount
(Quantity x
Unit Price)
35 Equipment for T&M Work (All Bidders Shall Use
$15,000 - Includes 15% Mark-Up) 1 Assumed
Value 15,000.00$
36 Materials for T&M Work (All Bidders Shall Use $25,000
- Includes 15% Mark-Up) 1 Assumed
Value 25,000.00$
37 Bonding (All Bidders Shall Use $10,000 - No Mark-up)
Assumed
Value 10,000.00$
549,928.00$
Calculation for Insurance and Taxes
38 Insurance and Taxes 2.00% Percent Bid Subtotal x Percentage
10,998.56$
560,926.56$
Yes
Yes
Bid Requirements:
Bid Bond
First Tier
BID SUBTOTAL
TOTAL BID - ITEMS 1 THRU 38 (All Items Must Be Bid)
File details come from the government source that posted it. Updated .