- FY22 MCAF PROJECT PAF160700 SQUADRON OPERATIONS FACILITY, ROYAL AUSTRALIAN AIR FORCE BASE DARWIN, AUSTRALIA
- Solicitation number
- N6274223R1318
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 23r1318-Amd4Dwgs.pdf | ||
| 23R1318-Note5.pdf | ||
| 23R1318-Amd4.pdf | ||
| 23R1318-Note4.pdf | ||
| 23R1318-AMD3.pdf | ||
| 23R1318-Note3.pdf | ||
| 23R1318-AMD2_Dwgs.pdf | ||
| 23R1318-AMD2.pdf | ||
| 23R1318-Note2.pdf | ||
| 23R1318-SiteVisitSignIn.pdf | ||
| 23R1318-AMD1_Dwgs.pdf | ||
| 23R1318-Note1.pdf | ||
| 23R1318-AMD1.pdf | ||
| 23R1318-RFP.pdf | ||
| 23R1318-Dwgs.pdf |
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NAVFAC PACIFIC
WORK ORDER NO:
1641238
SPECIFICATIONS
For
FY22 MCAF PROJECT PAF160700 SQUADRON OPERATIONS FACILITY
At the
RAAF BASE DARWIN, AUSTRALIA
PAF160700
PREPARED BY:
Architectural: Setiadi Architects, LLC.
Mechanical: Thermal Engineering Corporation Civil: GHD, Inc.
Electrical: GHD, Inc.
Structural: GHD, Inc.
Fire Protection: GHD, Inc.
Geotechnical: Douglas Partners Safety: GHD, Inc.
Submitted By: _______Tony Petroccitto_________ Date: _05/20/21_ Name
APPROVED BY:
Specification: _________________________________________________ Mr. Clint Hashiba, P.E.
For Commander, NAVFAC Pacific: ________________________________________________
Mr. Evan A Mizue, P.E.
Date: _______ _______
OO
FY22 MCAF Project PAF160700 Squadron Operations Facility 1641238 RAAF, Darwin
PROJECT TABLE OF CONTENTS
DI VI SI ON 00 - PROCUREMENT AND CONTRACTI NG REQUI REMENTS
00 01 15 02/11, CHG 1: 08/14 LIST OF DRAWINGS
DI VI SI ON 01 - GENERAL REQUI REMENTS
01 11 00 08/15 SUMMARY OF WORK
01 14 00 11/11 WORK RESTRICTIONS
01 20 00.00 20 08/15 PRICE AND PAYMENT PROCEDURES
01 30 00 08/15 ADMINISTRATIVE REQUIREMENTS
01 31 23.13 20 05/17 ELECTRONIC CONSTRUCTION AND FACILITY
SUPPORT CONTRACT MANAGEMENT SYSTEM
01 32 17.00 20 05/18 COST-LOADED NETWORK ANALYSIS SCHEDULES
(NAS)
01 33 00 08/18 SUBMITTAL PROCEDURES
01 33 29 02/17 SUSTAINABILITY REPORTING
01 35 13.01 11/11 SPECIAL PROJECT PROCEDURES FOR ESTATE
PROJECT LIFECYCLE
01 35 26 11/15 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 02/19 SOURCES FOR REFERENCE PUBLICATIONS
01 42 15 02/14 METRIC MEASUREMENTS
01 45 00.00 20 11/11 QUALITY CONTROL
01 45 35 02/15 SPECIAL INSPECTIONS
01 50 00 05/18 TEMPORARY CONSTRUCTION FACILITIES AND
CONTROLS
01 57 19 11/15 TEMPORARY ENVIRONMENTAL CONTROLS
01 58 00 08/19 PROJECT IDENTIFICATION
01 74 19 02/19 CONSTRUCTION AND DEMOLITION WASTE
MANAGEMENT
01 78 00 05/19 CLOSEOUT SUBMITTALS
01 78 23 08/15 OPERATION AND MAINTENANCE DATA
01 78 24.00 20 02/15 FACILITY ELECTRONIC OPERATION AND
MAINTENANCE SUPPORT INFORMATION (eOMSI)
DI VI SI ON 02 - EXI STI NG CONDI TI ONS
02 41 00 05/10, CHG 2: 02/19 DEMOLITION
02 61 13 02/10, CHG 1: 02/21 EXCAVATION AND HANDLING OF
CONTAMINATED MATERIAL
02 81 00 11/18 TRANSPORTATION AND DISPOSAL OF
HAZARDOUS MATERIALS
02 82 16.00 20 05/21 ENGINEERING CONTROL OF ASBESTOS
CONTAINING MATERIALS
02 83 13.00 20 08/11 LEAD IN CONSTRUCTION
DI VI SI ON 03 - CONCRETE
03 30 00 02/19 CAST-IN-PLACE CONCRETE
DI VI SI ON 04 - MASONRY
04 20 00 11/15 UNIT MASONRY
DI VI SI ON 05 - METALS
05 05 23.16 05/14 STRUCTURAL WELDING
05 12 00 05/14 STRUCTURAL STEEL
PROJECT TABLE OF CONTENTS Page 1
05 21 00 05/15 STEEL JOIST FRAMING
05 30 00 05/15 STEEL DECKS
05 40 00 05/15 COLD-FORMED METAL FRAMING
DI VI SI ON 06 - WOOD, PLASTI CS, AND COMPOSI TES
06 10 00 08/16 ROUGH CARPENTRY
06 61 16 08/10 SOLID SURFACING FABRICATIONS
DI VI SI ON 07 - THERMAL AND MOI STURE PROTECTI ON
07 21 16 11/11 MINERAL FIBER BLANKET INSULATION
07 27 10.00 10 08/19 BUILDING AIR BARRIER SYSTEM
07 41 63 11/16 FABRICATED ROOF PANEL ASSEMBLIES
07 42 63 05/11 FABRICATED WALL PANEL ASSEMBLIES
07 60 00 05/17 FLASHING AND SHEET METAL
07 92 00 08/16 JOINT SEALANTS
DI VI SI ON 08 - OPENI NGS
08 11 13 02/10 STEEL DOORS AND FRAMES
08 14 00 08/16 WOOD DOORS
08 31 00 05/17 ACCESS DOORS AND PANELS
08 51 13 05/19 ALUMINUM WINDOWS
08 71 00 02/16 DOOR HARDWARE
08 81 00 05/19 GLAZING
08 91 00 05/11 METAL WALL LOUVERS
DI VI SI ON 09 - FI NI SHES
09 22 00 02/10 SUPPORTS FOR PLASTER AND GYPSUM BOARD
09 29 00 08/16 GYPSUM BOARD
09 30 10 08/17 CERAMIC TILING
09 51 00 08/17 ACOUSTICAL CEILINGS
09 62 38 08/17 STATIC-CONTROL FLOORING
09 65 00 08/10 RESILIENT FLOORING
09 68 00 11/17 CARPETING
09 90 00 05/11 PAINTS AND COATINGS
DI VI SI ON 10 - SPECI ALTI ES
10 11 00 08/17 VISUAL DISPLAY UNITS
10 14 00.20 08/17 INTERIOR SIGNAGE
10 14 53 02/15 TRAFFIC SIGNAGE
10 21 13 08/17 TOILET COMPARTMENTS
10 22 39 08/17 FOLDING PANEL PARTITIONS
10 28 13 08/17 TOILET ACCESSORIES
10 44 16 11/19 FIRE EXTINGUISHERS
10 51 13 05/11 METAL LOCKERS
DI VI SI ON 12 - FURNI SHI NGS
12 24 13 08/17 ROLLER WINDOW SHADES
12 32 00 11/16 MANUFACTURED WOOD CASEWORK
DI VI SI ON 13 - SPECI AL CONSTRUCTI ON
13 48 00 05/18 SEISMIC BRACING FOR MISCELLANEOUS
EQUIPMENT
PROJECT TABLE OF CONTENTS Page 2
DI VI SI ON 22 - PLUMBI NG
22 00 00 11/15 PLUMBING, GENERAL PURPOSE
DI VI SI ON 23 - HEATI NG, VENTI LATI NG, AND AI R CONDI TI ONI NG ( HVAC)
23 00 00 08/18 AIR SUPPLY, DISTRIBUTION, VENTILATION,
AND EXHAUST SYSTEMS
23 03 00.00 20 08/10 BASIC MECHANICAL MATERIALS AND METHODS
23 05 93 11/15 TESTING, ADJUSTING, AND BALANCING FOR
HVAC
23 07 00 02/13 THERMAL INSULATION FOR MECHANICAL
SYSTEMS
23 09 00 11/15 INSTRUMENTATION AND CONTROL FOR HVAC
23 09 13 11/15 INSTRUMENTATION AND CONTROL DEVICES
FOR HVAC
23 09 23.02 11/15 BACNET DIRECT DIGITAL CONTROL FOR HVAC
AND OTHER BUILDING CONTROL SYSTEMS
23 81 00.00 20 11/09 UNITARY AIR CONDITIONING EQUIPMENT
DI VI SI ON 26 - ELECTRI CAL
26 05 00.00 40 08/19 COMMON WORK RESULTS FOR ELECTRICAL
26 05 19.10 10 05/16 INSULATED WIRE AND CABLE
26 05 26.00 40 08/19 EARTHING AND BONDING FOR ELECTRICAL
SYSTEMS
26 09 23.00 40 08/19 LIGHTING CONTROL DEVICES
26 20 00 08/19 INTERIOR DISTRIBUTION SYSTEM
26 24 13 05/15 SWITCHBOARDS
26 24 16.00 40 08/19 DISTRIBUTION BOARDS
26 41 00 11/13 LIGHTNING PROTECTION SYSTEM
26 50 00 05/16 LIGHTING
DI VI SI ON 27 - COMMUNI CATI ONS
27 05 28.36 40 05/17 CABLE TRAYS FOR COMMUNICATIONS SYSTEMS
27 05 29.00 10 08/11 PROTECTIVE DISTRIBUTION SYSTEM (PDS)
FOR SIPRNET COMMUNICATION SYSTEMS
27 10 00 08/11 BUILDING TELECOMMUNICATIONS CABLING
SYSTEM
27 13 23.00 40 11/14 COMMUNICATIONS OPTICAL BACKBONE CABLING
DI VI SI ON 28 - ELECTRONI C SAFETY AND SECURI TY
28 31 66 08/20 INTERIOR MASS NOTIFICATION SYSTEM,
NON-ADDRESSABLE
28 31 76 08/11 FIRE PROTECTION SYSTEM
DI VI SI ON 31 - EARTHWORK
31 11 00 11/18 CLEARING AND GRUBBING
31 23 00.00 20 02/11 EXCAVATION AND FILL
31 32 11 08/08 SOIL SURFACE EROSION CONTROL
DI VI SI ON 32 - EXTERI OR I MPROVEMENTS
32 11 23 08/17 AGGREGATE SUB-BASE AND BASE COURSES
32 12 16 08/09 HOT-MIX ASPHALT (HMA) FOR ROADS
PROJECT TABLE OF CONTENTS Page 3
32 17 23 08/16 PAVEMENT MARKINGS
DI VI SI ON 33 - UTI LI TI ES
33 11 00 05/16 WATER UTILITY DISTRIBUTION PIPING
33 30 00 04/08 SANITARY SEWERS
33 40 00 02/10 STORM DRAINAGE UTILITIES
33 71 02 02/15 UNDERGROUND ELECTRICAL DISTRIBUTION
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 4
DOCUMENT 00 01 15
LIST OF DRAWINGS
02/ 11, CHG 1: 08/ 14
PART 1 GENERAL
1.1 SUMMARY
DRAWING
NUMBER
NAVFAC DWG
NO.
TITLE
G-001 17250696 TITLE SHEET
G-002 17250697 INDEX OF DRAWINGS
G-101 17250698 TEST PIT LOGS
G-102 17250699 HAUL ROUTE, LAYDOWN AND STOCKPILE AREAS
C-001 17250700 CIVIL GENERAL NOTES
C-101 17250701 SITE LAYOUT PLAN AND SET OUT TABLES
C-102 17250702 ROAD PLAN AND LONGITUDINAL SECTION AND CROSS SECTIONS
C-103 17250703 LINEMARKING AND SIGNAGE PLAN
C-104 17250704 STORMWATER AND UTILITIES LAYOUT PLAN
C-301 17250705 CIVIL SECTIONS
C-302 17250706 WATER & SANITARY PROFILES
C-303 17250707 DRAINAGE LONGITUDINAL SECTION AND PIT LABEL SCHEDULE TABLE
C-501 17250708 CIVIL DETAILS - SHEET 1
C-502 17250709 CIVIL DETAILS - SHEET 2
C-503 17250710 CIVIL DETAILS - SHEET 3
A-001 17250711 GENERAL NOTES
A-101 17250712 FLOOR PLAN
A-102 17250713 REFLECTED CEILING PLAN
A-103 17250714 ROOF PLAN
A-201 17250715 BUILDING ELEVATIONS
DOCUMENT 00 01 15 Page 1
A-301 17250716 BUILDING SECTIONS
A-401 17250717 ENLARGED PLAN & INTERIOR ELEVATIONS
A-501 17250718 WALL TYPES
A-502 17250719 WALL SECTIONS
A-601 17250720 ROOM FINISH & INTERIOR SIGNAGE SCHEDULE
A-602 17250721 MOUNTING HEIGHT SCHEDULE
A-603 17250722 DOOR & WINDOW SCHEDULE, TYPES
A-701 17250723 MILLWORK DETAILS
A-801 17250724 DOOR AND WINDOW DETAILS
A-802 17250725 MISCELLANEOUS DETAILS
I-101 17250726 FURNITURE & EQUIPMENT PLAN AND SCHEDULE
S-001 17250727 GENERAL AND STRUCTURAL NOTES - SHEET 1
S-002 17250728 GENERAL AND STRUCTURAL NOTES - SHEET 2
S-003 17250729 GENERAL AND STRUCTURAL NOTES - SHEET 3
S-101 17250730 FOOTING AND SLAB PLAN
S-102 17250731 STRUCTURAL WALL PLAN
S-103 17250732 LOWER ROOF FRAMING PLAN
S-104 17250733 UPPER ROOF FRAMING PLAN
S-105 17250734 UPPER ROOF PURLIN PLAN
S-201 17250735 FRAMING SECTIONS - SHEET 1
S-203 17250736 BUILDING ELEVATIONS - SHEET 1
S-301 17250737 CONCRETE DETAILS - SHEET 1
S-401 17250738 WALL AND MASONRY DETAILS
S-501 17250739 STEEL FRAMING DETAILS - SHEET 1
S-502 17250740 STEEL FRAMING DETAILS - SHEET 2
M-001 17250741 LEGEND AND ABBREVIATIONS AND SYMBOL LEGEND
M-002 17250742 MECHANICAL NOTES
DOCUMENT 00 01 15 Page 2
M-101 17250743 MECHANICAL PLAN
M-102 17250744 MECHANICAL ENCLOSURE PLAN
M-301 17250745 SECTIONS
M-302 17250746 SECTIONS
M-501 17250747 DETAILS
M-502 17250748 DETAILS
M-601 17250749 AIR CONDITIONING AND VENTILATION SCHEMATIC DIAGRAM
M-602 17250750 SEQUENCE OF OPERATION AND CONTROL DIAGRAM
M-603 17250751 DDC SYSTEM RISER DIAGRAM AND CONTROL DIAGRAM
M-604 17250752 DDC SYSTEM POINTS LIST
M-605 17250753 EQUIPMENT SCHEDULE
M-606 17250754 EQUIPMENT SCHEDULE
M-901 17250755 REFRIGERANT PIPING DIAGRAM
P-001 17250756 LEGEND AND ABBREVIATION AND SYSMBOL LEGEND
P-002 17250757 PLUMBING NOTES
P-101 17250758 PARTIAL PLUMBING PLAN
P-102 17250759 PARTIAL PLUMBING PLAN
P-103 17250760 ROOF PLAN
P-501 17250761 DETAILS
P-502 17250762 DETAILS
P-601 17250763 PLUMBING SCHEMATIC DIAGRAM
P-602 17250764 EQUIPMENT SCHEDULE
P-901 17250765 COLD AND HOT WATER PIPING DIAGRAM
P-902 17250766 SANITARY PIPING DIAGRAM
E-001 17250767 LEGEND & NOTES
E-100 17250768 ELECTRICAL AND COMMUNICATIONS SITE PLAN (1/2)
E-101 17250769 ELECTRICAL AND COMMUNICATIONS SITE PLAN (2/2)
DOCUMENT 00 01 15 Page 3
E-102 17250770 POWER AND SECURITY LAYOUT
E-103 17250771 COMMUNICATION LAYOUT
E-104 17250772 LIGHTING AND FIRE LAYOUT
E-105 17250773 PHOTOMETRIC CALCULATIONS
E-106 17250774 LIGHTNING PROTECTION PLAN
E-107 17250775 CEILING HVAC POWER LAYOUT
E-108 17250776 PHOTOMETRIC CALCULATIONS - EXTERNAL
E-501 17250777 BUILDING CONNECTION DETAILS
E-601 17250778 MAIN SWITCHBOARD - SINGLE LINE DIAGRAM
E-602 17250779 DISTRIBUTION BOARD - SINGLE LINE DIAGRAMS
E-603 17250780 DIAGRAM & SCHEMATICS
F-001 17250781 COVER SHEET, LEGEND AND SPECIFICATIONS
F-101 17250782 FIRE PROTECTION PLAN
F-601 17250783 FIRE DETECTION SCHEMATIC
-- End of Document --
DOCUMENT 00 01 15 Page 4
FY22 MCAF Project PAF160700 APSI Squadron Operations Facility 1641238
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.1 GENERAL REQUIREMENTS
The Contractor acknowledges and agrees that:
a. the Contractor is a party to the contract with the Naval Facilities Engineering Command, Pacific (NAVFAC Pacific) to carry out the Contractor's Activities and Works on the Royal Australian Air Force (RAAF) base;
b. the Contracting Officer is an employee of the Naval Facilities Engineering Command who NAVFAC Pacific has assigned administration and enforcement authority and responsibility for this contract;
c. Australian Requirements are laws, codes, decrees, labor standards, and regulations of the host country, Commonwealth, State and Territory, currently in effect, that the Contractor is required to comply with, including but not limited to the Australian Requirements Schedule attached at the end of this section;
d. the Contractor is responsible for ensuring it complies with all requirements of the contract, including the Division 01 (General Requirements), Australian Requirements, and any other laws, codes, decrees, labor standards, and regulations of the host country, Commonwealth, State and Territory; Federal Acquisition Regulation (FAR) 52.236-7, Permits and Responsibilities; Defense Federal Acquisition Regulation Supplement (DFARS) 252.222-7002, Compliance with Local Labor Laws (Overseas) of the Request For Proposal, Document 00700;
e. if the Contractor identifies any ambiguity, discrepancy or inconsistency between the requirements of the contract, including the requirements of Division 01, Australian Requirements, and any other laws, codes, decrees, labor standards, and regulations of the host country, Commonwealth, State and Territory, the Contractor must immediately submit a Request for Information (RFI) to the Contracting Officer clearly describing the ambiguity, discrepancy and inconsistency and offer a proposed solution;
f. Immediately notify the Contracting Officer if the Commonwealth or any person authorised by the Commonwealth impedes, disrupts, or frustrates the Contractor's performance of the Contract, or otherwise causes potential Contractor delay; and
g. when an Australian standard or requirement is offered as an equivalent to a U.S. standard or requirement, the Contractor must furnish documentation proving equivalency.
1.2 WORK COVERED BY CONTRACT DOCUMENTS
1.2.1 Project Description
The work includes construction of a United States Air Force (USAF) squadron
SECTION 01 11 00 Page 1 operations facility at the Royal Australian Air Force (RAAF) Base in Darwin, Australia. Space is required for aircrew flight equipment maintenance and care, mission planning, intelligence, crew briefings, and crew readiness to support eight KC-10 aircraft, and incidental related work.
Systems to be commissioned in this project include, but is not limited to, Ventilating and Air Conditioning Systems (no heating or refrigeration), Building Automation System (HVAC Control System), Service Water Heating System, Plumbing System, and Utility Energy Metering Systems and Sub-Meters.
In addition to the requirements specified in the Contract Documents, all work must also be conducted in accordance with the applicable Australian legislation, Australian codes of practice, applicable AS/NZS standards, Australian Defence policies, and relevant Australian Defence authorization.
1.2.2 Location
The work is located at the Royal Australian Air Force (RAAF) Base Darwin, Northern Territory, Australia, approximately as indicated. The exact location will be shown by the Contracting Officer.
1.3 OCCUPANCY OF PREMISES
Before work is started, arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.
1.4 EXISTING WORK
In addition to FAR 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements:
a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.
1.5 LOCATION OF UNDERGROUND UTILITIES
Obtain permit to work for excavation prior to start of excavation, and comply with Installation requirements for locating and marking underground utilities. Contact the Contracting Officer to coordinate with the RAAF Base Darwin Estate and Infrastructure Group (E&IG) Base Support Services for utility information prior to excavating, and within sufficient time required if work occurs on a Monday or after a Northern Territory public or regional holiday. Verify existing utility locations indicated on contract drawings, within area of work.
Identify and mark all other utilities. Scan the construction site with Ground Penetrating Radar (GPR), electromagnetic, or sonic equipment, and mark the surface of the ground or paved surface where existing underground utilities are discovered. Verify the elevations of existing piping, utilities, and any type of underground or encased obstruction not indicated, or specified to be removed, that is indicated or discovered during scanning, in locations to be traversed by piping, ducts, and other
SECTION 01 11 00 Page 2 work to be conducted or installed. Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.
1.5.1 Notification Prior to Excavation
Notify the Contracting Officer at least 15 calendar days prior to starting excavation work.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
-- End of Section --
SECTION 01 11 00 Page 3
Version 1.4 dated September 09, 2020
Australian Requirements Schedule
1. Definitions
For the purposes of this Australian Requirements Schedule:
(a) ACM means asbestos containing material.
(b) Approvals means any licence, permit, consent, approval, determination, certificate, notice or other requirement any authority, body or organisation having any jurisdiction in connection with the Site, the Contractor's Activities or the Works or under any applicable Statutory Requirement, which must be obtained or satisfied to:
(i) carry out the Contractor's Activities or the Works; or
(ii) occupy, use, maintain or operate the completed Works.
(c) Classified Information includes:
(i) any Commonwealth document marked with a national security classification; and
(ii) any information that the Contractor knows or ought to know is subject to, or ought to be treated in accordance with, the provisions of the Defence Security Manual.
(d) Code of Federal Regulations (CFR) means the codification of the general and permanent rules and regulations (administrative law) published in the Federal Register by the executive departments and agencies of the U.S. Government.
(e) Code of Practice means a code of practice approved in accordance with the WHS Legislation.
(f) Commonwealth means the Commonwealth of Australia.
(g) Contamination means the presence in, on or under land, air or water of a substance (whether a solid, liquid, gas, odour, heat, sound, vibration or radiation) at a concentration above the concentration at which the substance is normally present in, on or under land, air or water in the same locality, that presents a risk of Environmental Harm, including harm to human health or any other aspect of the Environment, or could otherwise give rise to a risk of non-compliance with any Statutory Requirement for the protection of the Environment.
(h) Contract means the contract awarded under RFP [#INSERT] between the U.S. Government and the
Contractor to perform the construction of the Works.
(i) Contracting Officer has the meaning given in the Contract.
(j) Contractor has the meaning given in the Contract.
(k) Contractor's Activities means all things or tasks which the Contractor is, or may be, required to do to comply with its obligations under the Contract.
(l) Contractor HOTO Obligation means any task, function, requirement or obligation relating to the
HOTO Process (including commissioning of the Works) required to be performed by the Contractor under this Contract or which a HOTO Requirement allocates, or would reasonably be inferred as allocating, to the Contractor, including those that the HOTO Plan and Checklist expressly allocates to the "Contractor Representative" (as that term is used in the HOTO Plan and Checklist).
(m) Dangerous Goods has the meaning given in the Australian Code for the Transport of Dangerous Goods by Road and Rail, Edition 7.7.
(n) Defence means the Commonwealth Department of Defence.
(o) Defence Environmental Requirements means the Defence Environmental Management System and
Defence Environmental Plan applicable to the Site, the Contractor's Activities or the Works, including any procedures, instructions, requirements and standing orders which have been developed or issued under the Defence Environmental Management System or Defence Environmental Plan.
(p) Defence Environmental Management System means the environmental management system applicable to the Site (if any).
(q) Defence Environmental Plan means the environmental plan applicable to the Site (if any).
(r) Defence Requirements means all policies, plans, manuals, guidelines, instructions (including departmental procurement policy instructions) and other Commonwealth or Defence requirements which are, or may become, applicable to the Site, the Contractor's Activities or the Works. To the extent that any of the requirements would require or suggest the insertion of provisions into the Contract, then those provisions will be incorporated by reference into the Contract.
(s) Defence Security Principles Framework is a reference to that document available at https://www.defence.gov.au/dsvs/dspf.asp, as amended from time to time.
(t) Defense Federal Acquisition Regulation Supplement means the Department of Defense supplement to the Federal Acquisition Regulation (FAR) that contains requirements of U.S. law, DoD-wide policies, delegations of FAR authorities, deviations from FAR requirements, and DoD policies/procedures.
(u) DEQMS means the Defence Estate Quality Management System website available at www.defence.gov.au/estatemanagement.
(v) eDEOP 101 means the document titled “Defence Explosive Ordnance Publication (DEOP) 101 - Department of Defence Explosives Regulations” as amended from time to time.
(w) Effective Date means the date shown in Block 31C. AWARD DATE of the Standard Form (SF)
1442, SOLICITATION, OFFER, AND AWARD.
(x) EM 385-1-1 means the latest version of the U.S. Army Corps of Engineers manual in effect on the date the solicitation was issued (refer to Block 3. DATE ISSUED on the SF1442) and prescribing the safety and health requirements for construction contract work.
(y) Environment includes:
(i) ecosystems and their constituent parts, including people and communities;
(ii) natural and physical resources;
(iii) the qualities and characteristics of locations, places and areas; and
(iv) the social, economic, aesthetic and cultural aspects of a thing mentioned in paragraphs (i), (ii) or (iii).
(z) Environmental Clearance Certificate means the Environmental Clearance Certificate issued by the Commonwealth relating to the Contractor's Activities or the Works and any conditions incorporated in that certificate.
(aa) Environmental Harm means any actual or threatened adverse impact on, or damage to, the
Environment.
(bb) Environmental Incident means any Environmental Harm or Contamination arising out of or in connection with the Contractor's Activities or the Works.
(cc) Environmental Requirements includes the:
(i) Environmental Clearance Certificate; and
(ii) Defence Environmental Requirements.
(dd) EO CCC Plan has the meaning given in clause 5.3.
(ee) Federal Acquisition Regulation means the primary document of the United States Government Federal Acquisition Regulations System for the codification and publication of uniform policies and procedures for acquisition.
(ff) GHS means the Globally Harmonised System of Classification and Labelling of Chemicals published by the United Nations, (Rev.8) (2019), as modified by the relevant WHS Legislation.
https://www.unece.org/trans/danger/publi/ghs/ghs_rev08/08files_e.html
(gg) GHS Material means material suspected of containing or likely to contain a substance defined or listed in the GHS.
(hh) GST the tax payable on taxable supplies under the GST Legislation.
(ii) GST Legislation means A New Tax System (Goods and Services Tax) Act 1999 (Cth) and any related Act imposing such tax or legislation that is enacted to validate, recapture or recoup such tax.
(jj) Hazardous Chemical has the meaning given in subregulation 5(1) of the Work Health and Safety
Regulations 2011 (Cth) and includes:
(i) prohibited carcinogen, as defined in subregulation 5(1) of the Work Health and Safety Regulations 2011 (Cth);
(ii) restricted carcinogen, as defined in subregulation 5(1) of the Work Health and Safety
Regulations 2011 (Cth);
(iii) hazardous chemicals the use of which is restricted under regulation 382 of the Work Health and Safety Regulations 2011 (Cth), including polychlorinated biphenyls;
(iv) Schedule 11 Hazardous Chemicals;
(v) hazardous chemicals listed in Table 14.1 of Schedule 14 of the Work Health and Safety
Regulations 2011(Cth);
(vi) Schedule 15 Chemicals; and
(vii) lead as defined in subregulation 5(1) of the Work Health and Safety Regulations 2011 (Cth).
(kk) Hazardous Substances means Ozone Depleting Substances, Synthetic Greenhouse Gases, Hazardous
Chemicals or Dangerous Goods.
(ll) HOTO Plan and Checklist means the worksheets contained within the excel workbook titled "HOTO Plan & Checklist" available at https://defence.gov.au/estatemanagement/lifecycle/PlanHandoverTakeover/Default.asp, as updated, superseded or replaced from time to time.
HOTO Process means the process for handover and takeover of the Works to the Contracting Officer and the Commonwealth to enable the occupation, use, operation and maintenance of the Works by the Commonwealth and other users including the:
(i) commissioning of the Works (including the inspection and testing process);
(ii) handover of the Works; and
(iii) occupation, use, operation and maintenance of the Works by the Commonwealth and other users, in accordance with the HOTO Requirements.
HOTO Requirements means the requirements published on DEQMS in respect of the commissioning, handover and takeover of projects on the Defence Estate, including:
(i) the documents set out at https://defence.gov.au/estatemanagement/lifecycle/PlanHandoverTakeover/Default.asp, and all applicable requirements referred to therein; and
(ii) any other requirement published on DEQMS expressed as applying to the commissioning, handover and takeover of projects on the Defence Estate, each as updated, superseded or replaced from time to time.
(mm) NATA means National Association of Testing Authorities Australia.
(nn) MFPE means the Defence Manual of Fire Protection Engineering, as that document is amended from time to time.
(oo) National Construction Code means the National Construction Code that applies in the Northern
Territory, as amended from time to time, produced and maintained by the Australian Building Codes Board on behalf of the Commonwealth government and each Australian State and Territory government.
(pp) Ozone Depleting Substance means any substance identified as having ozone depleting potential in the
Ozone Protection and Synthetic Greenhouse Gas Management Act 1989 (Cth) or any regulations made under that Act.
(qq) Other Contractor means any other contractor, consultant, artist, tradesperson or other person engaged to do work at or in the vicinity of the Site other than the Contractor and its subcontractors.
(rr) PFAS means per- and poly-fluoroalkyl substances.
(ss) Plant, Equipment and Work means those things used, or work undertaken, by the Contractor to construct the Works but which will not form part of the Works.
(tt) Project Documents includes:
(i) Design documentation (shop drawings), Project Plans;
(ii) Approvals;
(iii) any other data, documents, drawings, records, information, and material produced or provided
(or required to be provided) to the Contracting Officer, under or in connection with the Contract, the Contractor's Activities or the Works by, for or on behalf of the Contractor (including by subcontractors); and
(iv) all material at any time derived (under or in connection with the Contract, the Contractor's
Activities or the Works) from, or based on, the material described in subparagraphs (i) and (iii).
(uu) Project Lifecycle and HOTO Plan means the plan prepared by the Contractor in accordance with, and for the purposes of, the HOTO Requirements and finalised under clause 4.2, which must:
(i) be prepared in accordance with the HOTO Plan and Checklist;
(ii) meet all applicable HOTO Requirements and Statutory Requirements; and
(iii) include any other matters required by:
A. the Contract; or B. the Contracting Officer or the Commonwealth.
(vv) Project Plans (also referred to in the Contract as Outline Project Plans) means the Environmental Management Plan, Project Lifecycle and HOTO Plan, Site Management Plan, Work Health and Safety Management Plan and (where required under clause 5.3) the EO CCC Plan.
(ww) Request for Information is a written request for information submitted by the Contractor to the
Contracting Officer. NAVFAC form is available from the Contracting Officer.
(xx) Schedule 11 Hazardous Chemical has the meaning given in subregulation 5(1) of the Work Health and Safety Regulations 2011 (Cth).
(yy) Schedule 15 Chemical has the meaning given in subregulation 5(1) of the Work Health and Safety
Regulations 2011 (Cth).
(zz) Site means the site or sites for the Works as set out in the Contract.
(aaa) Smart Infrastructure Handbook means the Defence Smart Infrastructure Handbook: Planning, Design and Construction available on DEQMS, as amended from time to time.
(bbb) Statutory Requirements means:
(i) any law applicable to the Contractor's Activities or the Works (including Acts, ordinances, regulations, by-laws and other subordinate legislation) including those of the Commonwealth and the Northern Territory;
(ii) Approvals (including any condition or requirement under an Approval);
(iii) Defence Requirements; and
(iv) Environment Requirements.
(ccc) Synthetic Greenhouse Gas means any gas identified as a Synthetic Greenhouse Gas in the Ozone
Protection and Synthetic Greenhouse Gas Management Act 1989 (Cth) or in any regulations made under that Act.
(ddd) U.S. Government means the federal government of the United States.
(eee) WHS Legislation means:
(i) Work Health and Safety (National Uniform Legislation) Act 2011 (NT) and Work Health and Safety (National Uniform Legislation) Regulations 2011 (NT);
(ii) Work Health and Safety Act 2011 (Cth) and Work Health and Safety Regulations 2011
(Cth); and
(iii) any other legislation and Codes of Practice in the Northern Territory addressing work health and safety.
(fff) Work Health and Safety Plan is
(i) included as part of the Accident Prevention Plan submitted in accordance with Section 01 35 26 Government Safety Requirements and refers to Australian safety requirements in addition to those in the Contract; and
(ii) prepared by the Contractor and finalised under paragraph 5.2 of this Australian Requirements
Schedule which must set out in adequate detail the procedures the Contractor will implement to manage the Contractor's Activities and the Works from a work health and safety perspective to ensure compliance with all Statutory Requirements (including the WHS Legislation).
(ggg) Works means the physical work, which the Contractor must (to the extent required by the Contract), design, construct, commission, complete and hand over in accordance with the Contract.
2. Statutory Requirements
Pursuant to Document 00700, Contract Clauses, Division 01 Specification Section 01 11 00 Paragraph 1.1, FAR 52.236-7, and DFARS 252.225-7042, the Contractor must:
(a) comply with all applicable Statutory Requirements; without limiting paragraph (a):
(b) apply for and obtain all Approvals;
(c) give all notices and pay all fees and other amounts which it is required to pay in respect of the carrying out of its Contract obligations; and
(d) promptly give the Contracting Officer copies of all documents (including Approvals and other notices) that any authority, body, or organisation having jurisdiction over the Site, the Contractor's Activities or the Works issues to the Contractor.
3. Environmental Requirements
The Contractor must:
(a) ensure that in carrying out the Contractor's Activities:
(i) it complies with Statutory Requirements for the protection of the Environment;
(ii) it does not cause or contribute to any Environmental Incident;
(iii) without limiting subparagraph (ii), it does not cause or contribute to Contamination of the Site or any other land, air or water or cause or contribute to any Contamination emanating from the Site;
(iv) it immediately notifies the Contracting Officer of:
A. any non-compliance with the requirements of this paragraph 3;
B. any breach of a Statutory Requirement for the protection of the Environment;
C. any Environmental Incident; or
D. the receipt of any notice, order or communication received from an authority for the protection of the Environment; and
(v) its subcontractors comply with the requirements in this paragraph 3; and
(b) clean up and restore the Environment, including any Contamination or Environmental Harm, arising out of or in connection with, the Contractor's Activities or the Works, whether or not it has complied with all Statutory Requirements and other requirements of the Contract for the protection of the Environment.
4. Project Plans
4.1 Contents of Project Plans
Each Project Plan must set out in adequate detail the following:
(a) the procedure for preparing (including tailoring) and finalising the Project Plans under Paragraph 4.2;
(b) the procedure for regularly reviewing, updating and amending the Project Plan under Paragraph 4.2;
(c) the procedure for ensuring subcontractor compliance with the Project Plans;
(d) the procedure for regularly auditing or other monitoring of Contractor and subcontractor compliance with the Project Plan; and
4.2 Preparation of Project Plans
4.2.1 The Contractor:
(a) must carry out the Contractor's Activities in accordance with, and otherwise implement, the Project Plans; and
(b) for the purposes of paragraph (a), must:
(i) prepare Project Plans in accordance with the requirements of the Contract and this Australian
Requirements Schedule and submit them to the Contracting Officer for review in accordance with the Contract;
(ii) submit Project Plan information included in or supplement to the relevant required submittals identified in the Contract Division 01 specifications;
(iii) not commence any of the Contractor's Activities to which any Project Plan applies until Contracting Officer Approval is obtained and all other preconstruction requirements per Contract are satisfied;
(iv) if any Project Plan is rejected, submit an amended Project Plan to the Contracting Officer whereupon subparagraphs (i) to (iv) will reapply;
(v) after each Project Plan has been approved:
A. regularly review, update and amend each Project Plan and otherwise at least on each anniversary of the Effective Date;
B. update or amend a Project Plan on request of the Contracting Officer; and
C. continue to correct any defects in or omissions from a Project Plan (whether identified by the Contracting Officer or the Contractor), and submit an updated or amended Project Plan to the Contracting Officer, after which:
D. the Contractor must continue to comply with the requirements of the then current Project Plan until the process in this paragraph (b) has been completed in respect of the updated or amended Project Plan; and
E. subparagraphs (i) to (iv) will apply (to the extent applicable); and
(c) The Contractor will not be relieved from compliance with any of its obligations under this contract
(including this Australian Requirements Schedule) or otherwise at law or in equity, as a result of:
(i) the implementation of, and compliance with, the requirements of any Project Plan;
(ii) any direction by the Contracting Officer to update, amend, modify or otherwise implement and comply with a Project Plan or the Contractor's compliance or non-compliance with a Project Plan; and
(iii) any failure by the Contracting Officer , to detect any defect in or omission from a Project Plan.
5. Safety Requirements
5.1 Work Health and Safety
(a) Without limiting the Contractor’s obligation under the Contract to comply with EM 385-1-1, Division 01 Specification Section 01 35 26 Governmental Safety Requirements, 29 CFR 1910 Occupational Safety and Health Standards, the Contractor shall:
(i) ensure that in carrying out the Contractor's Activities:
A. it complies with all Statutory Requirements and other requirements of the
Contract in respect of work health and safety; and
B. it complies with its duty under the WHS Legislation to consult, cooperate and coordinate activities with all other persons who have a work health and safety duty in relation to the same matter;
(ii) Where more stringent safety and occupational health standards are set forth in these Australian requirements and regulations and it satisfies the U.S. safety requirements, the Australian standards shall apply.
(b) without limiting the Contractor's obligations under the Contract or otherwise at law or in equity, notify the
Contracting Officer:
(i) in respect of notifiable incidents within the meaning of the WHS Legislation, immediately (and in any event within 12 hours of such notifiable incident occurring);
(ii) in respect of work health and safety incidents or accidents (which are not notifiable incidents) where the nature of the incident or accident indicates a potential systemic failure to identify hazards and manage risks to health and safety, so far as is reasonably practicable, within 24 hours of the incident or accident occurring; and
(iii) in respect of all other work health and safety matters arising out of or in connection with the
Contractor's Activities and the Works, including the occurrence of any other incident or accident (not required to be reported in accordance with subparagraphs (i) or (ii)), by a monthly report;
(c) for the purposes of paragraph (b), in respect of any notifiable incident:
(i) immediately provide the Contracting Officer and Commonwealth with a copy of the notice required to be provided to the relevant Commonwealth or Northern Territory regulator;
(ii) promptly provide the Contracting Officer and Commonwealth with a copy of all witness statements and the investigation report relating to the notifiable incident;
(iii) promptly provide the Contracting Officer and Commonwealth with copies of any notice(s) or other documentation issued by the relevant Commonwealth or Northern Territory regulator; and
(iv) within 10 days of the date of notification to the relevant Commonwealth or Northern Territory regulator, provide the Contracting Officer with a summary of the related investigations, actions to be taken and any impact on the Contract that may result from the notifiable incident;
(d) institute systems to:
(i) obtain regular written assurances from each Other Contractor and subcontractor about their ongoing compliance with the WHS Legislation; and
(ii) provide, in a format approved by the Contracting Officer, the written assurances regarding the Contractor's ongoing compliance with the WHS Legislation:
A. on a monthly basis; and
B. as otherwise directed by the Contracting Officer;
(e) provide the written assurances obtained under paragraph (d) to the Contracting Officer in accordance with paragraph (d);
(f) without limiting the Contractor's obligations under the Contract or otherwise at law or in equity, within 10 days of receipt provide to the Contracting Officer copies of:
(i) all formal notices and written communications issued by a regulator or agent of the regulator under or in compliance with the applicable WHS Legislation to the Contractor or subcontractor relating to work health and safety matters;
(ii) all formal notices issued by a health and safety representative of the Contractor or subcontractor under or in compliance with the applicable WHS Legislation; and
(iii) all formal notices, written communications and written undertakings given by the Contractor or subcontractor to the regulator or agent of the regulator under or in compliance with the applicable WHS Legislation, arising out of or in connection with the Contractor's Activities or the Works;
(g) exercise a duty of the utmost good faith in carrying out the Contractor's Activities and discharging its duties under the WHS Legislation;
(h) ensure all subcontracts include provisions equivalent to the obligations of the Contractor in this paragraph 5.1;
(i) ensure that, if the Statutory Requirement requires that:
(i) a person:
A. be authorised or licensed (in accordance with the WHS Legislation) to carry out any work at that workplace, that person is so authorised or licensed, and complies with any conditions of such authorisation or licence; and
B. has prescribed qualifications or experience, or if not, is to be supervised by a person who has prescribed qualifications or experience (as defined in the WHS Legislation), that person has the required qualifications or experience or is so supervised; or
(ii) a workplace, plant or substance (or design), or work (or class of work) be authorised or licensed, that workplace, plant or substance, or work is so authorised or licensed;
(iii) However, refer to “The Force Posture Agreement Between the Government of the United States of America and the Government of Australia”, Article XI, paragraph 3.
(j) not direct or allow a person to carry out work, or use plant or a substance at a workplace unless, the authorisation, licensing, prescribed qualifications or experience required by any Statutory Requirement and paragraph (i) are met;
(k) without limiting the Contractor's obligations under the Contract (including paragraph
(c) in respect of notifiable incidents) or otherwise at law or in equity, within 10 days of a request by the Contracting Officer, provide all information or copies of documentation held by the Contractor or a subcontractor to enable NAVFAC to comply with its obligations under the WHS Legislation;
(l) if requested by the Contracting Officer or required by the WHS Legislation, produce evidence of any Approvals including any authorisations, licences, registrations, prescribed qualifications or experience, or any other information relevant to work health and safety to the satisfaction of the Contracting Officer before the Contractor or any subcontractor commences such work;
(m) where the Contractor is a supplier, manufacturer, designer or importer for the purposes of the WHS Legislation, provide to the Contracting Officer as a condition precedent to completion of the Works and before the expiry of any defects liability period (however described) specified in the Contract information concerning:
(i) the purpose for which any plant, structure or substance (as defined in the WHS Legislation) has been designed or manufactured;
(ii) the results of any calculations, analysis, testing or examination carried out concerning the safety of the plant, substances or structures referred to in subparagraph (i) (and the risks to the health and safety of persons); and
(iii) any conditions necessary to ensure the plant, substances or structures are without risks to health and safety when used for the purpose for which they were designed or manufactured;
(n) if the Contractor is responsible for any design, ensure its design documentation eliminates or minimises the need for any hazardous manual tasks to be carried out in connection with a plant or structure;
(o) not use asbestos or ACM in carrying out the Contractor's Activities;
(p) not use, install or incorporate asbestos or ACM into the Works;
(q) provide a certificate to the Contracting Officer in a form satisfactory to the Contracting Officer as a condition precedent to completion of the Works which states that:
(i) all materials, goods, products, equipment and plant (including any imported materials, goods, products, equipment and plant) used, installed or incorporated into the Works are entirely (meaning 100%) free of asbestos and ACM; and
(ii) the Contractor has otherwise complied with all Statutory Requirements in relation to asbestos and ACM in carrying out the Contractor's Activities and the Works;
(r) without limiting paragraph (q), if any imported materials, goods, products, equipment and plant have or has been used, installed or incorporated into the Works, the Contractor must provide to the Contracting Officer as a condition precedent to completion of the Works:
(i) sample test reports; and
(ii) test report information, in the form of an analysis certificate from a NATA accredited laboratory or an equivalent international laboratory (listed at the NATA website) accredited for the relevant test method,
(s) in relation to the imported materials, goods, products, equipment or plant which have or has been used, installed or incorporated into the Works; and
(t) if the Contractor is a designer of a structure or part of a structure for the purposes of the WHS Legislation, the Contractor must provide to the Contracting Officer, with each submission of design documentation under the Contract, a written report that specifies the hazard relating to the design of the structure (or part) which, as far as the Contractor is reasonably aware:
(i) create a risk to health or safety to those carrying out construction work on the structure (or part); and
(ii) are associated only with the particular design.
5.2 Work Health and Safety Plan
(a) Without limiting its obligations under the Contract, the Contractor must:
(i) prepare a Work Health and Safety Plan in accordance with the requirements in the Contract and submit it to the Contracting Officer so as to ensure there is no delay or disruption to the Contractor's Activities;
(ii) if the Work Health and Safety Plan is rejected by the Contracting Officer, submit an amended
Work Health and Safety Plan to the Contracting Officer;
(iii) in any event, finalise the Work Health and Safety Plan in accordance with the requirements of the Contract to the satisfaction of the Contracting Officer;
(iv) carry out the Contractor's Activities in accordance with, and otherwise implement, the Work
Health and Safety Plan; and
(v) after the Work Health and Safety Plan has been finalised:
A. regularly review, update and amend the Work Health and Safety Plan in accordance with the process set out in the Work Health and Safety Plan;
B. update or amend the Work Health and Safety Plan on request of the Contracting
Officer; and
C. submit any updated or amended Work Health and Safety Plan prepared under subparagraphs B or C to the Contracting Officer and finalise the updated or amended Work Health and Safety Plan to the satisfaction of the Contracting Officer.
(b) The Work Health and Safety Plan must address, at a minimum:
(i) the names, positions and responsibilities of all persons at the workplace whose positions or roles involve specific health and safety responsibilities in connection with the Contractor's Activities and the Works;
(ii) the arrangements in place, or to be implemented, between any persons conducting a business or undertaking at the workplace where the Contractor's Activities and the Works are being undertaken;
(iii) the arrangements in place, or to be implemented, for managing any work health and safety incidents that occur at a workplace where the Contractor's Activities and the Works are carried out, including:
A. incident (including notifiable incident) reporting procedures;
B. preventative and corrective action procedures; and
C. record-keeping and reporting requirements, including reporting to the Contracting Officer with respect to incidents and accidents under paragraph 5.1 of this Australian Requirements Schedule;
(iv) any Site-specific health and safety rules, and the arrangements for ensuring that all persons at the workplace are informed of these rules;
(v) the arrangements for the collection and recording, and any assessment, monitoring and review of safe work method statements at the workplace;
(vi) procedures and arrangements for the management of work health and safety generally, including:
A. details of the Contractor's work health and safety policy;
B. details of any work health and safety management system (whether certified or uncertified), including procedures for managing work health and safety disputes;
C. inductions, training and other awareness programmes regarding work health and safety and any workplace specific work health and safety induction, training and other awareness programmes; and
D. emergency procedures, emergency management planning, the use of emergency equipment and the establishment of workplace specific first aid facilities;
(vii) procedures for ensuring the provision of written assurances to the Contracting Officer under paragraph 5.1(d) of this Australian Requirements Schedule regarding compliance with the WHS Legislation by the Contractor, subcontractors and Other Contractors;
(viii) procedures for the preparation, finalisation and regular reviewing of the Work Health and
Safety Plan under paragraph 5.2 of this Australian Requirements Schedule (including as a consequence of any review of hazards, risks and control measures regarding the Contractor's Activities, the Works and any notifiable incident or systemic risk management failure);
(ix) procedures for the management of subcontractors, including:
A. inductions, training and other awareness programmes;
B. the subcontractor's development and provision of safe work method statements, job safety assessments or equivalent documentation;
C. ensuring subcontractors comply with their obligation to consult, cooperate and coordinate activities (including the information-sharing and communication of information); and
D. ensuring subcontractor compliance with the Work Health and Safety Plan;
(x) the approach to the management of project (and Contract) hazards and risks including how the Contractor will identify hazards and eliminate or minimise risks arising from those hazards so far as is reasonably practicable:
A. prior to commencing the Contractor's Activities and the Works; and
B. during the Contractor's Activities and the Works;
(xi) the actions the Contractor will take to proactively identify and manage risks to ensure it avoids systematic work health and safety risk management failures occurring during the Contractor's Activities and the Works;
(xii) the procedures the Contractor will adopt to audit or otherwise monitor and verify its (and its subcontractors') compliance with the Work Health and Safety Plan and the WHS Legislation (including details of the regularity, form and content of such audit, monitoring and verification activities);
(xiii) the procedures the Contractor will adopt to ensure it provides to NAVFAC, when conducting handover and takeover activities, all information regarding hazards and risks present in or arising out of or in connection with the use of the Works including for the purpose for which they were designed or manufactured (including the supply of information in accordance with paragraph 5.1(m)) of this Australian Requirements Schedule;
(xiv) the approach the Contractor will adopt in identifying, controlling and managing work health and safety hazards and risks concerning (as applicable):
A. Hazardous Substances, including, where Hazardous Substances are used or handled in the Contractor's Activities, incorporated into the Works, stored by the Contractor at the workplace or transported by the Contractor to or from the workplace…