This document contains the Supplementary Terms and Conditions for a construction project at the Department of Military Affairs' Camp Blanding Joint Training Center in Starke, Florida. The project involves the removal and replacement of two walk-in freezers and one walk-in cooler, including the associated refrigeration systems and other supporting work. The project is to be substantially completed within 90 calendar days of the Notice to Proceed, with liquidated damages of $131 per calendar day for late completion. The contract is being administered by the Department of Military Affairs Construction and Facility Management Office in St. Augustine, Florida.
The document outlines various requirements for the contractor, such as providing an on-site field office for the Architect/Engineer, securing the site, and complying with Davis-Bacon labor requirements, if applicable. It also provides details on the project sign, utilities, and the initial construction conference. The contract opportunity is open to all qualified bidders, with a bid bond required for proposals exceeding $100,000. Insurance and bonding requirements are specified in the General Terms and Conditions.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 221029 PreBid Meeting Agenda with notes.pdf | ||
| 222003 PCS Coolers Addendum #1.pdf | ||
| 221029 Part 2- General Terms & Conditions.pdf | ||
| 221029 CBJTC PCS Coolers Exhibit_1_ITB.pdf | ||
| 221029 Exhibit_3_FNG5085.docx | DOCX document | |
| 221029 Exhibit_4_5_Proposal_SubList.docx | DOCX document | |
| Prebid meeting sign in sheet.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJECT NO. 221029
CBJTC PCS COOLERS REPLACEMENT
CAMP BLANDING JOINT TRAINING CENTER
5629 FL 16 W, STARKE FL 32091
TO BE CONSTRUCTED FOR:
Department of Military Affairs
82 Marine Street
St. Augustine, FL 32084
CONTRACT ADMINISTERED BY
Department of Military Affairs
Construction and Facility Management Office
2305 State Road 207
St. Augustine, Florida, 32033
ARCHITECT / ENGINEER
PROJECT MANAGER
Department Of Military Affairs
Jeff Collins-Project Manager
DPW, Camp Blanding, Florida
904-682-2201
SUPPLEMENTARY TERMS AND CONDITIONS
08/09/2023
Project No. 221029
CBJTC PCS Cooler and Freezer Replacements
OWNER: State of Florida, Department of Military Affairs
ARCHITECT/ENGINEER
This document forms an integral part of the Request for Proposal Documents and the Contract Documents. The receipt of this document must be acknowledged in the space provided on your Proposal. This General Terms and Conditions are hereby modified as follows: (modify below as it applies to the project requirements; remove or strike through unnecessary items)
1. SUBSTANTIAL COMPLETION AND LIQUIDATED DAMAGES: Section C-7 is amended in part as follows: This Project is to be substantially complete within 90 calendar days after the date of the Notice to Proceed. This date may be extended only in accordance with the Contract Documents. If the project is not substantially completed by the required date, liquidated damages shall be assessed at the rate of $131.00 per calendar day.
2. ARCHITECT/ENGINEER'S FIELD OFFICE. The Contractor shall provide and maintain a watertight office at the Project for the exclusive use of the Architect/Engineer and his representatives, not less than 12' x 12' in size, one room with at least one window in each exterior wall and an independent outside entrance door fitted with hardware and lock, artificial light, a bench with one drawer, a blueprint rack, a heater and a window air conditioner. This office and equipment shall become the property of the Contractor upon completion of the contract.
3. TELEPHONE. A telephone shall be installed in the Architect/Engineer's office and it shall remain until the full completion of the project. Charges for long distance calls shall be paid by the person making the calls. All other telephone charges shall be paid by the Contractor.
4. WATER. Water necessary for construction of the building and testing its plumbing and mechanical systems shall be furnished by the Contractor. He shall make all connections, install a meter, take out and pay for all permits necessary, do all piping and clear away all evidence of same after the job is completed.
5. ELECTRICITY. All electricity for light and power necessary for the construction of the building and testing of its electrical and mechanical systems shall be paid for by the Contractor. The Contractor shall make all necessary arrangements for this service and perform the work required.
6. PROJECT SIGN. A sign shall be erected at the site by the Contractor and shall be 3/4"- 4' X 8' exterior grade plywood mounted on 4 x 4 wood posts (p.t.), located in a prominent location approved by the Architect/Engineer and Owner. Sign shall conform to the size, colors and design specifications provided by Architect/Engineer or owner.
7. INITIAL CONSTRUCTION CONFERENCE. Immediately prior to starting construction or as soon as possible after the construction has started, the Owner will arrange a meeting with the project stakeholders. The purpose of this meeting shall be to discuss requirements and responsibilities of the various parties involved with the objective of expeditious handling of the construction contract. The Owner's Contract Manager and Project Manager will chair this meeting.
8. SITE SECURITY. The Contractor shall pay for and be responsible to secure the site and the project against theft, vandalism, fire and for public safety at all times (24 hours per day) from Notice to Proceed until Substantial Completion.
9. DAVIS-BACON REQUIREMENTS. If Davis-Bacon and related laws apply, they will be addressed in Section D of the General Terms and Conditions. If applicable, then all applicable federal labor standards clauses are incorporated into the Contract Documents. The Contractor agrees to familiarize itself with “Making Davis-Bacon Work – A Contractor’s Guide to Prevailing Wage Requirements for Federally-Assisted Construction Projects” and to comply with all applicable regulations.
10. (Insert other provisions, as needed)
EXCEPT AS SPECIFICALLY PROVIDED HEREIN, ALL OTHER TERMS AND CONDITIONS OF THE BIDDING
DOCUMENTS AND CONTRACT DOCUMENTS REMAIN UNCHANGED.
[END]
NOTICE TO BIDDERS
The following General Terms and Conditions and the Supplemental Terms and Conditions are part of the bidding and contract process for construction projects in excess of $200,000. These non-technical documents are designed to (i) ensure compliance with applicable laws, (ii) protect the State’s interests, and (iii) make the contracting process easier for all parties. Please review carefully all sections in the non-technical specifications including the following items:
1. All Bidders must submit a bid bond with their bid proposal if the bid exceeds $100,000.00. For details please refer to Section B-11 of the General Terms and Conditions.
2. All Bidders must submit bids in accordance with the publicized Invitation to Bid (ITB). If prequalification to bid is required, it will be stated within the ITB along with instructions.
3. Criminal History Background Checks, if included in the General Terms and Conditions, must be obtained for all employees and agents of the Contractor and its subcontractors, their agents and employees, and all other persons performing any of the work under a contract to the Contractor working within buildings or facilities either owned or managed by the Department of Military Affairs.
Details of this responsibility are outlined in Article C-38 of the General Terms and Conditions.
4. All Bidders are responsible for the cost of insurance and bonds. Please refer to Sections C-1 through
C-3 of the General Terms and Conditions for required types of insurance and Exhibits 2 and 3 to review the requirements on the bond forms.
5. Proposal Form may be obtained with the ITB or as instructed in the ITB.
6. Samples of some Forms required by the Department of Military Affairs (DMA) are shown in the
General Terms and Conditions. Forms for use during contract performance will be provided by DMA after contract award.