21343 - OKC 100% Plans_OCAT-OKC-2519_Executed.pdf
PDF 30 MB Posted
- Attached to
- REHABILITATE AAR RAMP – PHASE I
- Solicitation number
- OCAT OKC 2519
- Issued by
- Oklahoma County, Oklahoma City, Oklahoma
About this file
This document is a comprehensive set of construction project plans and specifications for the Oklahoma City Airport Trust (OCAT) for the rehabilitation of the AAR Ramp at Will Rogers World Airport, located in Oklahoma City, Oklahoma. The project encompasses base bid and an add alternate for pavement rehabilitation, involving the removal and replacement of approximately 8,000 square yards of concrete pavement in the base bid and an additional 2,470 square yards in the alternate. The total project duration is 216 calendar days for the base bid and 246 calendar days including the alternate, with work phased into three distinct construction stages. The project includes extensive storm drainage improvements, underdrain installation, electrical system modifications, pavement marking, and associated infrastructure upgrades.
Pre-qualification is required for contractors, specifically those classified as a Paving Contractor "A" or Stormwater Contractor "A" under Oklahoma City's Pre-qualification Review Board provisions. The project involves significant technical complexity, including precise concrete pavement reconstruction, storm sewer system modifications, and careful coordination with airport operations to minimize disruption. The estimated quantities include multiple components such as unclassified excavation, concrete pavement removal, base course preparation, storm pipe replacements, and electrical system updates. Funding appears to be from airport capital improvement sources, with the work designed to enhance the airport's operational infrastructure and maintain critical airfield facilities. The project requires meticulous attention to airport safety protocols, environmental considerations, and minimal disruption to ongoing airport operations.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Business Relationship Affidavit.pdf | ||
| OKC IFB Specs_OCAT-OKC-2519_Executed.pdf | ||
| Anti Noncollusion Affidavit.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJECT NO. OCAT-OKC-2519
D ra w in g N am e:
C :\p w _w or ki ng \lo ch ne r-pw
-0 1\ d0
\2
TI
TL
E S
H E
E T.
dw g
Fe b
,2
- 9 :4
2a m
G100
TITLE SHEET
VICINITY MAP
NO SCALE
BASE BID:
CONSTRUCTION PLANS
FOR
OKLAHOMA CITY AIRPORT TRUST
OKC WILL ROGERS INTERNATIONAL AIRPORT
H.W. LOCHNER, INC
Certificate of Authorization License No. 6131 Expires: 6-30-2025
NO SCALE
LOCATION MAP
TULSA
OKLAHOMA CITY
GUYMON
WOODWARD
PONCA CITY
ENID
BARTLESVILLE
MUSKOGEE
MCALESTER
ADA
ARDMORE HUGO
IDABEL
PAULS VALLEY
PURCELL
LAWTONALTUS
WEATHERFORD
STILLWATER
40 40
WATONGA
GUTHRIE
OKEENE
GROVE
ANTLERS
DURANT
DUNCAN
ANADARKO
183 281
CHICKASHA
3E
3W
99177
48377
75 169
GAGE
N
FEBRUARY 2025
AAR APRON REHABILITATION
P lo t S ty le : a e.
ct b La st S av ed
B y:
c tu ck er
5/
/2
PROJECT NO.
DRAWN BY
CHECKED BY
REVISIONS
DATE
DATE
DATE
DESIGNED BY DATE
W at er fo rd B lv d.
S ui te
O kl ah om a C ity , O kl ah om a
P
.7
.6 w w w .h w lo ch ne r.c om
L B
J Fr ee w ay
S ui te
D al la s, T ex as
, 7
P
.8
.7 w w w .rs an dh
.c om
21343
O K
LA
H
O M
A C
IT
Y
A
IR
P O
R T
TR
U
S T
O K
LA
H
O M
A C
IT
Y
, O K
LA
H
O M
A
R E
H A
B
IL
IT
A
TE
A
A R
R A
M P
P
H A
S E
I
WILL ROGERS
INTERNATIONAL AIRPORT
ADD ALTERNATE 1:
ADDITIONAL APRON REHABILITATION
OKLAHOMA CITY
ISSUE FOR BID
CZT
PJB
CZT
01-31-25
01-31-25
01-31-25
SHEET LIST TABLE
Sheet Number Sheet Title
G100 TITLE SHEET
G101 SURVEY CONTROL PLAN
G102 GENERAL LAYOUT
G103 GENERAL NOTES
G104 AIRPORT LAYOUT DRAWING
G200 SUMMARY OF QUANTITIES
G201 - G202 PAY ITEM NOTES
G300 CONSTRUCTION SAFETY AND PHASING PLAN PHASE 1
G301 CONSTRUCTION SAFETY AND PHASING PLAN PHASE 2
G302 CONSTRUCTION SAFETY AND PHASING PLAN PHASE 3
G303 - G305 CONSTRUCTION SAFETY AND PHASING PLAN NOTES
G306 - G310 CONSTRUCTION SAFETY AND PHASING PLAN DETAILS
D100 GEOTECHNICAL BORING LOCATIONS
D103 EXISTING CONDITIONS
D104 DEMOLITION PLAN
D105 DEMOLITION PLAN NOTES
D106 DEMOLITION DETAILS
S100 STORMWATER AND EROSION CONTROL PLAN
S101 STORMWATER AND EROSION CONTROL DETAILS
C201 - C202 PROPOSED GEOMETRY
C211 - C212 JOINT LAYOUT PLAN
C221 TYPICAL PAVEMENT SECTIONS AND DETAILS
C222 PCC SPALL REPAIR DETAILS
C223 - C224 JOINT DETAILS
C501 - C502 GRADING PLAN
C601 - C602 SPOT ELEVATION PLAN
C701 - C702 PAVEMENT MARKINGS
C711 PAVEMENT MARKING DETAILS
CU001 STORM SEWER NOTES
CU011 - CU012 STORM SEWER DEMO PLAN
CU021 - CU022 STORM SEWER PLAN
CU051 - CU055 STORM SEWER PROFILE
CU101 - CU109 STORM SEWER DETAILS
X101 CROSS SECTIONS OVERVIEW
X111 - X113 CROSS SECTIONS
E001 ELECTRICAL NOTES & ABBREVIATIONS
E101 PROPOSED ELECTRICAL PLAN
E111 - E115 ELECTRICAL DETAILS
D101 - D102 GEOTECHNICAL BORING LOGS
AT
REHABILITATE AAR RAMP - PHASE I
LI
C
EN
SE
D
PROFESSIONAL
ENG
IN
EER
OKLA HOMA
PATRICK J.
BARNAS
28896
RS&H, INC
Certificate of Authorization License No. 6048 Expires: 6-30-2025
W W W W W
SS
SS
M H
M H
GM
CO
M H
W
D
Y H
SPIG
SPIG
WM
GM
CO
SS
SS
W W
SS
CO
SS
W
W
D
Y H
W
SPIG
FO
WM
SS
M H
M H
SPIG
SS
M H
W
W
CO
W W
CO
W
CO
SS
SS
SS
W
D
Y H
CO
D Y H
T
SPIG
GM
SPIG
CO
SPIG
SPIG
W
WM
D Y H
WM
WM
W
FO
SS
W
W
W
W
D
Y H
W
D
Y H
PLPL
PL
PL PL
PL
PL
PL
W
W W
W
W
W
W
SS
DY
H
T
SPIG
CO
CO
CO
SPIG
CO
CO
CO
CO
CO
CO CO
SPIG
CO
CO CO
CO
T
CO
X
PL
PL PL
PL
PL
PL
PL
PL
G G
G
G
D Y H
W
W
D
Y H
PL
SS SS SS
SS
SS
SSSS
T
T
T
T
T
T
WMWM W
WM
DY
H
W
CO
PL
GM
WM
SS
T
GM
G
CO
SS
SS
SS
WM
GM GM
SPIG
W
SS
T
T
W
W
T
T
D
Y H
DY
H
W
T
D
Y H
W
WM
DY
H
GM
DY
H
W
D
Y H
D
Y H
W
W
D
Y H
DY
H
W
W
SSSS
SS
SS
SSSS
SS
SS
SCV
SCV
WM
D
Y H
WM
SCV
SCV
GM
T
T
W D
Y H
GM
T
T
T
GM
WD
Y H
W
SS
PL
GM
D
Y H
W
TT
SS
T
D
Y H
W
W
T
GM
W
GM
CO
G
TV
TV
GRAV
PL
TV
W
T
T
TV
TV
W
W
W
DY
H
W
RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA
RSARSARSARSARSARSARSARSARSARSARSARSARSARSARSARSARSARSARSARSARSARSARSARSARSARSARSARSARSARSARSARSARSARSARSARSARSARSARSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
R-O
FZ
R-O
FZ
R-O
FZ
R-O
FZ
R-O
FZ
R-O
FZ
R-O
FZ
R-O
FZ
R-O
FZ
R-O
FZ
R-O
FZ
R-O
FZ
R-O
FZ
R-O
FZ
R-O
FZ
R-O
FZ
R-O
FZ
R-O
FZ
R-O
FZ
R-O
FZ
R-O
FZ
R-O
FZ
R-OFZ
R-OFZ
R-OFZ
R-OFZ
R-OFZ
R-OFZ
R-OFZ
R-OFZ
R-OFZ
R-OFZ
R-OFZ
R-OFZ
R-OFZ
R-OFZ
R-OFZ
R-OFZ
R-OFZ
R-OFZ
R-OFZ
R-OFZ
R -O
FZ
R
-O
FZ
R-OFZR-OFZR-OFZR-OFZR-OFZR-OFZR-OFZR-OFZR-OFZR-OFZR-OFZR-OFZR-OFZR-OFZR-OFZR-OFZR-OFZR-OFZR-OFZR-OFZR-OFZR-OFZR-OFZR-OFZR-OFZR-OFZR-OFZR-OFZR-OFZR-OFZR-OFZ
R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ
R-OFAR-OFAR-OFAR-OFAR-OFAR-OFAR-OFAR-OFAR-OFAR-OFAR-OFAR-OFAR-OFAR-OFAR-OFAR-OFAR-OFAR-OFAR-OFAR-OFAR-OFAR-OFAR-OFAR-OFAR-OFAR-OFAR-OFAR-OFAR-OFAR-OFAR-OFAR-OFA
R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA
R-O
FA
R-O
FA
R-O
FA
R-O
FA
R-O
FA
R-O
FA
R-O
FA
R-O
FA
R-O
FA
R-O
FA
R-O
FA
R-O
FA
R-O
FA
R-O
FA
R-O
FA
R-O
FA
R-O
FA
R-O
FA
R-OFA
R-OFA
R-OFA
R-OFA
R-OFA
R-OFA
R-OFA
R-OFA
R-OFA
R-OFA
R-OFA
R-OFA
R-OFA
R-OFA
R-OFA
R-OFA
R-OFA
R-OFA
R-OFA
R-OFA
R-OFA
R-OFA
Runway 17R-35L (9,801 x 150')
Runway 17R-35L Object Free Area (ROFA) (11,801' x 800')
Runway 17R-35L Safety Area (RSA) (11,801' x 500')
Runway 17R-35L Obstacle Free Zone (ROFZ) (10,201' x 400')
Run way
-31
(7 ,80
0 x
0')Run way
-31
O bje ct Free
A rea
(R
OFA) (
9,8
' x
0')
Run way
-31
S afe ty Area
(R
SA) (
9,8
' x
0')
Run way
-31
O bs tac le
Free Zon e (
ROFZ) (
8,2
' x
0')
MERIDIAN AVE.
BASE BID
RECONSTRUCT APRON
BASE BID
REMOVE EXISTING PAVEMENT
AND INSTALL DRAINAGE AND SOD
ADD ALTERNATE 1
RECONSTRUCT ADDITIONAL APRON
Hangar
Hangar 1B
Hangar 1C
OLD ARFF
BUILDING
CURRENT ARFF
BUILDING
GENERAL AVIATION
TERMINAL
Hangar
Hangar 3 Hangar
3A/3B GAS
GAS
GAS
D ra w in g N am e:
C :\p w _w or ki ng \lo ch ne r-pw
-0 1\ d0
\2
G E
N L
A Y
.d w g Fe b
,2
- 9
:4 2a m
G101
SURVEY CONTROL PLAN
P lo t S ty le : a e.
ct b La st S av ed
B y:
c tu ck er
5/
/2
PROJECT NO.
DRAWN BY
CHECKED BY
REVISIONS
DATE
DATE
DATE
DESIGNED BY DATE
W at er fo rd B lv d.
S ui te
O kl ah om a C ity , O kl ah om a
P
.7
.6 w w w .h w lo ch ne r.c om
L B
J Fr ee w ay
S ui te
D al la s, T ex as
, 7
P
.8
.7 w w w .rs an dh
.c om
21343
O K
LA
H
O M
A C
IT
Y
A
IR
P O
R T
TR
U
S T
O K
LA
H
O M
A C
IT
Y
, O K
LA
H
O M
A
R E
H A
B
IL
IT
A
TE
A
A R
R A
M P
P
H A
S E
I
Point Table
Point #
Description
CP / SACS OKC ARP 4 DISK IN CONCRETE
CP / SET 1/2IN IP W/ CP CAP
BM / FND CUT X TOP CURB
BM / SET CUT X TOP CURB
BM / FND CUT X TOP CURB
BM / FND CUT X TOP CURB
CP / 3/4IN IP
BM / CUT "X" TOP OF CURB
BM / 3/4IN IP
CP / CITY OKC ALUMINUM CAP STA 313
CP / L 218 STAINLESS STEEL ROD IN SLEEVE
Northing
143,563.1700
144,910.6675
145,501.6036
145,993.0120
146,654.0972
148,096.9772
148,053.9028
147,368.9406
147,195.3033
148,192.2400
143,061.7300
Easting
2,087,758.6000
2,087,407.1520
2,087,372.8730
2,087,180.1500
2,087,203.1740
2,087,459.1010
2,087,131.5051
2,087,150.9150
2,087,386.4781
2,087,390.3680
2,085,708.7000
Elevation
1,285.99
1,285.62
1,282.16
1,278.61
1,280.88
1,287.54
1,286.94
1,283.32
1,282.36
1,287.50
1,274.80
ISSUE FOR BID
CZT
PJB
CZT
01-31-25
01-31-25
01-31-25
SURVEY CONTROL GENERAL NOTES:
1. HORIZONTAL AND VERTICAL CONTROL MONUMENT IDENTIFICATION, EXISTING TOPOGRAPHY,
ELEVATIONS, CONTROL POINTS, UTILITY INFORMATION, AND PAVEMENT MARKINGS WERE TAKEN
FROM SURVEYS PERFORMED BY FRONTIER LAND SURVEY, AS PROVIDED ON JANUARY 11, 2024.
2. GRID DATA IS BASED ON THE NAD 83 DATUM.
3. VERTICAL DATA IS BASED ON NAVD88 DATUM.
4. THE SURVEY CONTROL MONUMENT / BENCHMARK COORDINATES SHOWN ON THIS DRAWING
WILL BE USED AS THE BASIS OF CONSTRUCTION VERIFICATION SURVEYS PERFORMED BY THE
CONTRACTOR.
5. TEMPORARY BENCHMARK INFORMATION OBTAINED FROM TOPOGRAPHIC SURVEY PERFORMED
BY FRONTIER LAND SURVEYING, LLC IN JANUARY, FEBRUARY AND MAY OF 2024. THESE POINTS
ARE PROVIDED FOR REFERENCE ONLY. THEIR EXISTENCE, ACCURACY, AND RELIABILITY MUST
BE CONFIRMED BY THE CONTRACTOR IF UTILIZED.
6. ALL PROJECT CONTROL AND CONSTRUCTION STAKEOUT MUST BE PERFORMED BY THE
CONTRACTOR. THE WORK MUST BE COMPLETED BY A PROFESSIONAL LAND SURVEYOR,
REGISTERED IN THE STATE OF OKLAHOMA.
7. PROTECT SURVEY CONTROL MONUMENTS IN PLACE. ALL DISTURBED, DAMAGED, AND/OR
DESTROYED SURVEY CONTROL MONUMENTS MUST BE REPLACED BY A PROFESSIONAL LAND
SURVEYOR, LICENSED IN THE STATE OF OKLAHOMA, AT NO ADDITIONAL EXPENSE TO THE
OWNER.
8. LOCATIONS OF UNDERGROUND UTILITIES AS SHOWN IN THE DRAWINGS ARE BASED ON
ABOVEGROUND STRUCTURES, AS WERE VISIBLE AT THE TIME OF SURVEY.
9. SUBSURFACE AND ENVIRONMENTAL CONDITIONS WERE NOT INCLUDED IN THE SURVEY.
10. PRIOR TO ANY LAYOUT FOR THE PROPOSED WORK, VERIFY EXISTING SURVEY CONTROL POINTS.
NOTIFY THE RESIDENT PROJECT REPRESENTATIVE (RPR) OF DISCREPANCIES IMMEDIATELY IF
FOUND. IT IS THE SOLE RESPONSIBILITY OF THE CONTRACTOR TO SET ADDITIONAL CONTROL
POINTS, AS NECESSARY, TO FACILITATE ACCURATE LAYOUT FOR THE PROPOSED WORK.
11. CONTROL POINTS WITHIN 250 FEET OF RUNWAY CENTERLINE AND WITHIN 130 FEET OF TAXIWAY
CENTERLINE NEED ADVANCE COORDINATION TO LOCATE / STAKEOUT. CONTRACTOR MUST
REQUEST PERMISSION THROUGH THE RPR TO SURVEY THESE POINTS AT ANY TIME DURING
CONSTRUCTION.
12. CONTRACTOR MUST BE FAMILIAR WITH SURVEY LAYOUT NEEDS AND EQUIPMENT PRIOR TO
ENTERING ANY ACTIVE RSA OR TOFA FOR SURVEYING NEEDS, WITH THE INTENT OF REDUCING
THE DURATION OF SURVEYOR PERSONNEL NEEDS INSIDE ANY ACTIVE RSA OR TOFA.
13. CONTRACTOR SURVEY AND STAKEOUT MUST BE PERFORMED IN ACCORDANCE WITH FAA
GENERAL PROVISION 50-07, CONSTRUCTION LAYOUT AND STAKES, AND ITEM X-202, SURVEY AND
STAKEOUT.
14. PROJECT SURVEY AND STAKEOUT IS THE RESPONSIBILITY OF THE CONTRACTOR AND WILL BE
PAID FOR UNDER LUMP SUM BID ITEM X-202, SURVEY AND STAKEOUT.
Scale in Feet
0 400200200
LI
C
EN
SE
D
PROFESSIONAL
ENG
IN
EER
OKLA HOMA
PATRICK J.
BARNAS
28896
W W W
SS
SS
M H
M H
GM
CO
M H
W
D
YH
SPIG
SPIG
WM
GM
CO
SS
SS
W
W
SS
CO
SS
W
W
D Y
H
W
SPIG
FO
WM
SS
M H
M H
SPIG
SS
M H
W
W
CO
W W
CO
W
CO
SS
SS
SS
W
D
Y H
CO
D Y
H
T
SPIG
GM
SPIG
CO
SPIG
SPIG
W
WM
D
Y
H
WM
WM
W
FO
SS
W
W
W
W
D Y H
W
D
Y
H
PLPL
PL
PL PL
PL
PL
PL
W
W
W
W
W
W
W
SS
D
Y H
T
SPIG
CO
CO
CO
SPIG
CO
CO
CO
CO
CO
CO CO
SPIG
CO
CO CO
CO
T
CO
PL
PL PL
PL
PL
PL
PL
PL
G
G
G
G
CO
D Y
H W
W
D Y
H
PL
W
W
D
Y
H
GM
D
Y H
G
D
Y
H
W
W W
WM
W W
D
Y
H
WW
W
W
D
Y
H
W W
W
W
W
GM
CO
SS SS SS
SS
SS
SS
SS
SS
SSSS
T
T
T
T
T
T
T
T
T
TV
TV
WMWM W
WM
D
Y
H
W
CO
PL
GM
WM
SS
T
GM
G
CO
SS
SS
SS
WM
GM GM
SPIG
W
SS
T
T
W
W
T T
D
Y H
D Y H W
T
D
Y H
W
WM
D
Y H
GM
D Y
H
W
D
Y
H
D Y
H
W
W
D Y
H
D Y H W
W
SSSS
SS
SS
SSSS
SS
SS
SCV
SCV
WM
D Y
H
WM
SCV
SCV
GM
T
T
W
D
Y H
GM
T
T
T
GM
WD
Y H
W
SS
PL
GM
D
Y
H
W
T
T
SS
T
D Y
H
W
W
T
GM
W
GM
CO
G
TV
TV
GRAV
PL
TV
W
T
T
TV
TV
W
W
W
D Y H
W
RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA RSA
R S
A R
S A
RSARSARSARSARSARSARSARSARSARSARSARSARSARSARSARSARSARSARSARSARSARSARSARSARSARSARSARSARSARSARSARSARSARSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
RSA
R-O
FZ
R-O
FZ
R-O
FZ
R-O
FZ
R-O
FZ
R-O
FZ
R-O
FZ
R-O
FZ
R-O
FZ
R-O
FZ
R-O
FZ
R-O
FZ
R-O
FZ
R-O
FZ
R-O
FZ
R-O
FZ
R-O
FZ
R-O
FZ
R-O
FZ
R-O
FZ
R-O
FZ
R-O
FZ
R-O
FZ
R-O
FZ
R-O
FZ
R-O
FZ
R-OFZ
R-OFZ
R-OFZ
R-OFZ
R-OFZ
R-OFZ
R-OFZ
R-OFZ
R-OFZ
R-OFZ
R-OFZ
R-OFZ
R-OFZ
R-OFZ
R-OFZ
R-OFZ
R-OFZ
R-OFZ
R-OFZ
R-OFZ
R-OFZ
R-OFZ
R-OFZ
R-OFZ
R-OFZ
R-OFZ
R -O
FZ
R-OFZR-OFZR-OFZR-OFZR-OFZR-OFZR-OFZR-OFZR-OFZR-OFZR-OFZR-OFZR-OFZR-OFZR-OFZR-OFZR-OFZR-OFZR-OFZR-OFZR-OFZR-OFZR-OFZR-OFZR-OFZ
R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ R-OFZ
R-OFAR-OFAR-OFAR-OFAR-OFAR-OFAR-OFAR-OFAR-OFAR-OFAR-OFAR-OFAR-OFAR-OFAR-OFAR-OFAR-OFAR-OFAR-OFAR-OFAR-OFAR-OFAR-OFAR-OFAR-OFAR-OFAR-OFAR-OFA
R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA R-OFA
R -O
FA
R
-O
FA
R -O
FA
R-O
FA
R-O
FA
R-O
FA
R-O
FA
R-O
FA
R-O
FA
R-O
FA
R-O
FA
R-O
FA
R-O
FA
R-O
FA
R-O
FA
R-O
FA
R-O
FA
R-O
FA
R-O
FA
R-O
FA
R-O
FA
R-O
FA
R-O
FA
R-O
FA
R-O
FA
R-O
FA
R-O
FA
R-O
FA
R-O
FA
R-OFA
R-OFA
R-OFA
R-OFA
R-OFA
R-OFA
R-OFA
R-OFA
R-OFA
R-OFA
R-OFA
R-OFA
R-OFA
R-OFA
R-OFA
R-OFA
R-OFA
R-OFA
R-OFA
R-OFA
R-OFA
R-OFA
R-OFA
R-OFA
R-OFA
R-OFA
R-OFA
R-OFA
R-OFA
R-OFA
X
Runway 17R-35L (9,801 x 150')
Runway 17R-35L Object Free Area (ROFA) (11,801' x 800')
Runway 17R-35L Safety Area (RSA) (11,801' x 500')
Runway 17R-35L Obstacle Free Zone (ROFZ) (10,201' x 400')
Run way
-31
(7 ,80
0 x
0')
Run way
-31
O bje ct Free
A rea
(R
OFA) (
9,8
' x
0')
Run way
-31
S afe ty Area
(R
SA) (
9,8
' x
0')
Run way
-31
O bs tac le
Free Zon e (
ROFZ) (
8,2
' x
0')
MERIDIAN AVE.
TERMINAL DR.
A M
E
LI
A E
A R
H A
R T
LN
TERMINAL BUILDING
OLD ARFF
BUILDING
CURRENT ARFF
BUILDING
GENERAL AVIATION
TERMINAL
HANGAR 1C HANGAR 1B
HANGAR 1
HANGAR 2 HANGAR 3
HANGAR 3A/3B
BASE BID
GATE 139 ACCESS FOR EXCESS
EXCAVATION DUMP SITE
ADD ALTERNATE 1
AIR CARGO RD.
SW
4T H
ST
CONTRACTOR SHALL UTILIZE DIRT PERIMETER
ROAD FOR DUMPING EXCAVATED MATERIAL
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
GAS
APPROXIMATE LOCATION OF PHILLIPS 66 GAS LINE.
CONTRACTOR TO COORDINATE WITH PHILLIPS 66
TWO WEEKS BEFORE UTILIZING DUMP SITE.
CONTRACTOR SHALL INSTALL TEMPORARY EROSION
CONTROL AROUND THE EXCESS EXCAVATION SITE,
SPREAD THE FINAL EXCESS EXCAVATION TO SMOOTH
GRADES, GRADE IT TO DRAIN, AND ESTABLISH
PERMANENT VEGETATIVE COVER. THIS WORK SHALL
BE CONSIDERED SUBSIDIARY TO OTHER ITEMS BID.
EXCESS EXCAVATION
DUMP SITE
SEE TABLES THIS SHEET.
1A
2A
3A
D ra w in g N am e:
C :\p w _w or ki ng \lo ch ne r-pw
-0 1\ d0
\2
G E
N L
A Y
.d w g Fe b
,2
- 8
:3 1a m
G102
GENERAL LAYOUT
P lo t S ty le : a e.
ct b La st S av ed
B y:
c tu ck er
5/
/2
PROJECT NO.
DRAWN BY
CHECKED BY
REVISIONS
DATE
DATE
DATE
DESIGNED BY DATE
W at er fo rd B lv d.
S ui te
O kl ah om a C ity , O kl ah om a
P
.7
.6 w w w .h w lo ch ne r.c om
L B
J Fr ee w ay
S ui te
D al la s, T ex as
, 7
P
.8
.7 w w w .rs an dh
.c om
21343
O K
LA
H
O M
A C
IT
Y
A
IR
P O
R T
TR
U
S T
O K
LA
H
O M
A C
IT
Y
, O K
LA
H
O M
A
R E
H A
B
IL
IT
A
TE
A
A R
R A
M P
P
H A
S E
I
ISSUE FOR BID
CZT
PJB
CZT
01-31-25
01-31-25
01-31-25
WARNING!!!!!!
THERE ARE A NUMBER OF AIRPORT, PUBLIC UTILITIES, FAA LIGHTING,
COMMUNICATIONS, UNDERGROUND CABLES, AND PIPES TRAVERSING THE AIRFIELD
PAVEMENT AREAS. THE ENGINEER HAS MADE EVERY ATTEMPT TO SHOW TO
APPROXIMATE LOCATION OF ALL ITEMS. HOWEVER, THE ENGINEER IS NOT
RESPONSIBLE FOR SHOWING OR LOCATING EVERY ITEM CURRENTLY IN PLACE. IT IS
THE RESPONSIBILITY OF THE CONTRACTOR TO HAVE EVERY ITEM LOCATED, FLAGGED
AND IDENTIFIED PRIOR TO STARTUP OF CONSTRUCTION. REPAIRS TO ANY DAMAGE
DONE TO ANY EXISTING ITEMS NOT DESIGNATED FOR REMOVAL OR
RECONSTRUCTION WILL BE THE RESPONSIBILITY OF THE CONTRACTOR. THE
CONTRACTOR MUST REPAIR ANY DAMAGES, CAUSED BY HIS/HER ACTIONS, WITH NO
ADDITIONAL COMPENSATION.
Scale in Feet
0 600300300
LI
C
EN
SE
D
PROFESSIONAL
ENG
IN
EER
OKLA HOMA
PATRICK J.
BARNAS
28896
EXCESS EXCAVATION DUMP SITE LIMITS
Point Latitude Longitude
1A N35° 23' 52.68" W97° 36' 17.04" 2A N35° 24' 03.74" W97° 36' 17.05" 3A N35° 24' 03.74" W97° 36' 11.98"
EXCESS EXCAVATION DUMP SITE QUANTITIES
Approx. Volume of
Unclassified Excavation to be
Spread (C.Y.)
Approx. Area of Unclassified
Excavation to be Spread (S.Y.)
Height of Unclassified
Excavation to be Spread (ft.)
650 1,950 1
NOTE: VALUES IN TABLE ARE APPROXIMATIONS OF
EXCESS EXCAVATION NOT NEEDED AS EMBANKMENT FOR
SITE GRADING, BASED ON THE ASSUMED DEPTHS IN PAY
ITEM NOTE 17.
ra w in g N am e:
C :\p w _w or ki ng \lo ch ne r-pw
-0 1\ d0
\2
G E
N L
A Y
.d w g Fe b
,2
- 9
:4 3a m
G103
GENERAL NOTES
P lo t S ty le : a e.
ct b La st S av ed
B y:
c tu ck er
5/
/2
PROJECT NO.
DRAWN BY
CHECKED BY
REVISIONS
DATE
DATE
DATE
DESIGNED BY DATE
W at er fo rd B lv d.
S ui te
O kl ah om a C ity , O kl ah om a
P
.7
.6 w w w .h w lo ch ne r.c om
L B
J Fr ee w ay
S ui te
D al la s, T ex as
, 7
P
.8
.7 w w w .rs an dh
.c om
21343
O K
LA
H
O M
A C
IT
Y
A
IR
P O
R T
TR
U
S T
O K
LA
H
O M
A C
IT
Y
, O K
LA
H
O M
A
R E
H A
B
IL
IT
A
TE
A
A R
R A
M P
P
H A
S E
I
GENERAL NOTES:
1. THE EXISTING FEATURES SHOWN ON THESE PLANS ARE THOSE NOTED IN THE FIELD AND THOSE TAKEN FROM RECORD DRAWINGS. THIS DOES NOT GUARANTEE THAT ALL FEATURES ARE SHOWN ON THE PLANS. THERE WILL BE NO ADDITIONAL PAYMENT TO THE CONTRACTOR DUE TO VARIATIONS IN SIZE, QUANTITY, OR LOCATION OF EXISTING FEATURES. THE EXISTING CONDITIONS SHOWN WITHIN THE PROJECT AREAS MAY HAVE BEEN ALTERED PRIOR DUE TO CONSTRUCTION BY OTHERS. IT IS THE CONTRACTOR'S RESPONSIBILITY TO WORK WITH THE EXISTING CONDITIONS OF THE PROJECT AT THE TIME OF CONSTRUCTION. VERIFY EXISTING CONDITIONS AND NOTIFY THE RPR OF DISCREPANCIES IMMEDIATELY IF FOUND, PRIOR TO PERFORMING CONSTRUCTION ACTIVITIES.
2. EXTREME CAUTION SHALL BE USED WHEN WORKING NEAR EXISTING LIGHT FIXTURES, UNDERGROUND ELECTRICAL DUCTS, UNDERGROUND ELECTRICAL CABLE AND ANY OTHER AIRPORT FIXTURES. SHOULD DAMAGE OCCUR TO ANY OF THESE ITEMS, THEY WILL BE REPLACED IMMEDIATELY AT THE CONTRACTOR'S EXPENSE TO THE
SATISFACTION OF THE ENGINEER.
3. THE CONTRACTOR SHALL BE RESPONSIBLE FOR LOCATING ANY UNDERGROUND UTILITIES PRIOR TO BEGINNING CONSTRUCTION. CONTACT OKLAHOMA ONE CALL AT 1-800-522-OKIE OR 811 A MINIMUM OF 48 HOURS PRIOR TO ANY CONSTRUCTION ACTIVITIES TO ALLOW ONE CALL SUFFICIENT TIME TO LOCATE AND MARK ANY EXISTING UTILITIES WHICH MIGHT BE AFFECTED BY THIS PROJECT. CONTRACTOR SHALL PROVIDE THE ONE CALL REPORT/CASE INFORMATION TO THE ENGINEER AND AIRPORT PERSONNEL PRIOR TO BEGINNING EXCAVATION. SHOULD DAMAGE OCCUR TO ANY OF THESE ITEMS, THEY WILL BE REPLACED IMMEDIATELY AT THE CONTRACTOR'S EXPENSE TO THE SATISFACTION OF THE ENGINEER. AIRPORT UTILITIES NOT LOCATED BY ONE CALL SHALL BE LOCATED BY THE CONTRACTOR AT NO COST TO THE OWNER. THE CONTRACTOR WILL BE RESPONSIBLE FOR REPAIRS OF ANY DAMAGES RESULTING FROM THEIR FAILURE TO LOCATE UTILITIES AS SPECIFIED AT NO ADDITIONAL EXPENSE TO
THE OWNER.
4. ONLY RUBBER-TIRED VEHICLES UNDER 60,000 LBS GROSS VEHICLE WEIGHT RATING (GVWR) WILL BE ALLOWED ON
AIRPORT PAVEMENT SURFACES WITHOUT PRIOR ENGINEER APPROVAL.
5. THE CONTRACTOR SHALL BE RESPONSIBLE FOR THE RESTORATION AND SEEDING OF THE CONTRACTOR'S STAGING AREA, ACCESS, EXCAVATION DISPOSAL AREA, AND HAUL ROADS IF DAMAGE HAS OCCURRED DUE TO CONSTRUCTION ACTIVITIES. NO DIRECT PAYMENT WILL BE MADE FOR THESE ITEMS. SEEDING AND SODDING SHALL BE DONE AS REQUIRED IN ACCORDANCE WITH ITEMS T-901: SEEDING AND T-904: SODDING OF THE PROJECT MANUAL, RETURNING THE AREA TO ORIGINAL OR BETTER CONDITION. ALL OF THE CONTRACTOR'S EQUIPMENT AND MATERIALS SHALL BE REMOVED FROM THE AIR OPERATIONS AREA (AOA) PRIOR TO REOPENING THE AIRFIELD PAVEMENT. THE AIRPORT MAINTENANCE PERSONNEL SHALL BE RESPONSIBLE FOR MOWING THE AIRFIELD.
6. WASTE MATERIALS RESULTING FROM THIS PROJECT SHALL BE DISPOSED OF OFF AIRPORT PROPERTY UNLESS SHOWN OTHERWISE ON THESE PLANS. CLEAN EXCESS UNCLASSIFIED EXCAVATION SHALL BE DISPOSED ON
AIRPORT PROPERTY AT A LOCATION DETERMINED BY THE AIRPORT.
7. THE CONSTRUCTION SAFETY AND PHASING PLAN (CSPP) DRAWINGS DEPICT HAUL ROUTES FOR ACCESS FROM SURROUNDING PUBLIC ROADWAYS AND HAUL ROUTE THROUGH THE AIRPORT PERIMETER FENCE. CONTRACTOR ACCESS AND HAULING OPERATIONS ARE STRICTLY LIMITED TO THE HAUL ROUTES SHOWN. ANY TIME AN EXISTING AIRFIELD PAVEMENT IS TRAVERSED OR CROSSED, THE CONTRACTOR SHALL PROVIDE PROTECTION TO THE PAVEMENT EDGES. THE CONTRACTOR IS REQUIRED TO SWEEP AND MAINTAIN THE PAVEMENT AS DIRECTED BY
THE RESIDENT PROJECT REPRESENTATIVE (RPR).
8. THE CONTRACTOR WILL BE REQUIRED TO REPAIR ANY DAMAGE TO PUBLIC AND AIRPORT ROADS AND AIRFIELD PAVEMENTS CAUSED BY THE CONTRACTOR'S TRUCKS AND EQUIPMENT DURING THE CONSTRUCTION OF THE PROJECT. REPAIRS SHALL BE ADEQUATE TO RETURN THE PAVEMENTS TO A CONDITION EQUAL TO OR BETTER THAN THE CONDITION PRIOR TO DAMAGE. ALL REPAIR WORK SHALL BE AT THE CONTRACTOR'S EXPENSE. THE AIRPORT ENTRANCE ROAD AND HAUL ROUTES SHALL BE VIDEOED AND PHOTOGRAPHED BY THE CONTRACTOR IN THE PRESENCE OF THE ENGINEER OR THE RPR PRIOR TO CONSTRUCTION IN ORDER TO DOCUMENT THEIR
EXISTING CONDITION.
9. CONTRACTOR RADIOS AND/OR MOBILE PHONES MUST ONLY BE USED FOR THE CONTRACTOR'S INTERNAL COMMUNICATIONS TO COMMUNICATE CLEARANCE FOR MOVEMENT OF EQUIPMENT, PERSONNEL, ETC., ON OR ACROSS ACTIVE AOA AREAS. USE OF RADIOS MUST NOT INTERFERE WITH FREQUENCIES USED BY THE AIR TRAFFIC CONTROL TOWER (ATCT) OR THE AIRPORT. USE OF MOBILE PHONES IS RESTRICTED TO WORK-RELATED CALLS WITHIN THE AOA; NO PERSONAL CALLS WILL BE ALLOWED. CONTRACTOR SUPERVISORY PERSONNEL, CONTRACTOR GATE GUARDS, CONTRACTOR VEHICLE ESCORTS, AND CONTRACTOR FLAGMEN ARE REQUIRED TO MONITOR RADIOS AND/OR MOBILE PHONES AND BE CAPABLE OF SENDING AND RECEIVING INSTRUCTIONS AT ALL
TIMES WHEN INSIDE THE AOA.
10. NO CHANGES TO THE APPROVED SAFETY AND PHASING PLAN WILL BE ALLOWED WITHOUT PRIOR APPROVAL AND
CONCURRENCE FROM THE RPR, AIRPORT, AND FAA.
11. THE CONTRACTOR SHALL PROVIDE THE AIRPORT WITH THE CONTACT INFORMATION OF THE SUPERVISOR ON SITE.
THE CONTRACTOR'S PROJECT SUPERINTENDENT OR SHIFT LEADERS MUST BE ON SITE DURING ALL WORK ACTIVITIES. THE CONTRACTOR'S PROJECT SUPERINTENDENT IS THE DESIGNATED RESPONSIBLE CONTRACTOR
REPRESENTATIVE AND MUST BE AVAILABLE IN CASE OF EMERGENCIES ON A 24-HOUR BASIS.
12. THE CONTRACTOR HAS THE OPTION OF INSTALLING TEMPORARY DRAINAGE STRUCTURES FOR CONSTRUCTION OF TEMPORARY ACCESS DRIVES DURING CONSTRUCTION. ONCE CONSTRUCTION IS COMPLETE, THE DRIVES AND DRAINAGE STRUCTURES SHALL BE REMOVED AND THE AREA RESTORED TO ITS ORIGINAL CONDITION. THIS WORK
SHALL BE CONSIDERED SUBSIDIARY TO OTHER BID ITEMS IN THE CONTRACT.
13. CONTRACTOR SHALL BE RESPONSIBLE FOR OBTAINING WATER, AS REQUIRED FOR COMPLETION OF THE PROJECT, AND SHALL COORDINATE WITH THE LOCAL WATER PROVIDER FOR PRICING, OBTAINING A WATER METER, AND DETERMINING A LOCATION FOR WATER ACCESS. THE COST OF THIS WORK SHALL BE CONSIDERED SUBSIDIARY TO
OTHER ITEMS BID.
14. CONTRACTOR SHALL PROVIDE SANITARY PORTABLE TOILET(S) FOR USE ON THE JOBSITE, WHICH SHALL BE SECURED TO PREVENT MOVEMENT, FOR TOILET QUANTITY, SEE OSHA 1915.88(D)(2). CONTRACTOR SHALL COORDINATE MAINTENANCE OF POTABLE TOILET(S) AND SHALL ESCORT THE MAINTENANCE VEHICLES TO THE
TOILET(S) LOCATION(S). USE OF OWNERS FACILITIES IS PROHIBITED.
15. EXCESS EXCAVATION SHALL BE DISPOSED OF AT THE LOCATION INDICATED ON SHEET G102. THE CONTRACTOR SHALL STRIP TOPSOIL PRIOR TO SPREADING EXCESS EXCAVATION AND SAVE IT TO PLACE OVER THE EXCESS EXCAVATION. TOPSOILING AND ESTABLISHMENT OF GRASS OF THE DUMP SITE SHALL BE INCIDENTAL TO P-152 "UNCLASSIFIED EXCAVATION (INCLUDES ONSITE EMBANKMENT AND EXCESS STOCKPILING)". THE CONTRACTOR SHALL SPREAD WASTED SOIL TO SMOOTH, UNIFORM GRADES, AND VEGETATION SHALL BE RE-ESTABLISHED. THE ACCESS ROUTE SHALL BE MAINTAINED THROUGHOUT THE PROJECT AS REQUIRED, AND THE ROUTE SHALL BE BROUGHT TO ITS ORIGINAL CONDITION OR BETTER PRIOR TO THE PROJECT'S COMPLETION. CONTRACTOR SHALL ONLY ACCESS EXCESS EXCAVATION DUMP SITE VIA GATE 139 ON MERIDIAN AVE. CONTRACTOR SHALL NOT CROSS THE AAR RAMP TO ACCESS DUMP SITE. A GATE GUARD SHALL BE PROVIDED AT THE ACCESS GATE. GATE GUARD REQUIREMENTS ARE LISTED IN CONTRACTOR ACCESS OF THE CONSTRUCTION SAFETY AND PHASING PLAN NOTES. ISSUE FOR BID
CZT
PJB
CZT
01-31-25
01-31-25
01-31-25
WARNING!!!!!!
THERE ARE A NUMBER OF AIRPORT, PUBLIC UTILITIES, FAA LIGHTING,
COMMUNICATIONS, UNDERGROUND CABLES, AND PIPES TRAVERSING THE AIRFIELD
PAVEMENT AREAS. THE ENGINEER HAS MADE EVERY ATTEMPT TO SHOW TO
APPROXIMATE LOCATION OF ALL ITEMS. HOWEVER, THE ENGINEER IS NOT
RESPONSIBLE FOR SHOWING OR LOCATING EVERY ITEM CURRENTLY IN PLACE. IT IS
THE RESPONSIBILITY OF THE CONTRACTOR TO HAVE EVERY ITEM LOCATED, FLAGGED
AND IDENTIFIED PRIOR TO STARTUP OF CONSTRUCTION. REPAIRS TO ANY DAMAGE
DONE TO ANY EXISTING ITEMS NOT DESIGNATED FOR REMOVAL OR
RECONSTRUCTION WILL BE THE RESPONSIBILITY OF THE CONTRACTOR. THE
CONTRACTOR MUST REPAIR ANY DAMAGES, CAUSED BY HIS/HER ACTIONS, WITH NO
ADDITIONAL COMPENSATION.
DEMOBILIZATION NOTES:
1. CONDITIONS OF THE PROJECT AREA UPON COMPLETION OF THE JOB SHALL BE AS
GOOD AS OR BETTER THAN THE CONDITIONS PRIOR TO STARTING WORK, IN
ADDITION TO THE WORK ITEMS LISTED.
2. THE PROJECT AREA SHALL BE FREE OF ANY CONTRACTOR STOCKPILE MATERIALS
UPON COMPLETION OF THE PROJECT UNLESS OTHERWISE DIRECTED THE RPR.
3. UPON COMPLETION OF THE PROJECT, ALL THE HAUL ROUTES SHALL BE
PROPERLY CLEANED TO PREVENT OBSTRUCTION AND/OR CAUSE INCONVENIENCE
TO NORMAL REGULAR TRAFFIC. ALL TEMPORARY HAUL ROUTES SHALL BE
REMOVED AND BROUGHT BACK TO ORIGINAL CONDITION OR BETTER.
4. CONTRACTOR'S JOBSITE OFFICE TRAILER, JOB TRAILER, ALL OF THE
CONSTRUCTION EQUIPMENT, AND ANY FACILITIES TEMPORARILY PLACED ONSITE
FOR THE PROJECT SHALL BE REMOVED FROM THE SITE.
5. ANY PROPERTIES BELONGING TO THE AIRPORT SHALL BE RETURNED TO THE
AIRPORT OWNER.
6. PROPER DRAINAGE (NO LOCALIZED PONDING) SHALL BE MAINTAINED, PRIOR TO,
DURING AND AFTER MOBILIZATION.
7. DEMOBILIZATION SHALL BE DONE TO THE SATISFACTION OF THE RPR.
8. DEMOBILIZATION SHALL BE DONE IN A MANNER THAT WILL NOT CAUSE ANY
INCONVENIENCE TO AIRPORT OPERATIONS.
9. ANY DAMAGE TO THE AIRPORT PROPERTIES DURING DEMOBILIZATION SHALL BE
REPAIRED AND PAID FOR AT THE CONTRACTOR'S OWN EXPENSE.
10. SAFETY REGULATIONS SHALL BE OBSERVED AT ALL TIMES DURING
DEMOBILIZATION.
11. THE COST FOR DEMOBILIZATION SHALL BE CONSIDERED SUBSIDIARY TO THE
MOBILIZATION BID ITEM.
12. THE CONTRACTOR SHALL VIDEO THE ENTIRE WORK AREA AFTER THE
CONSTRUCTION ACTIVITIES HAVE BEEN COMPLETED. THE CONTRACTOR SHALL
PROVIDE ONE (1) COPY OF THIS VIDEO TO THE AIRPORT MANAGER AND THE RPR.
13. THE CONTRACTOR SHALL REMOVE ANY SILT FENCE AND ALL STORM WATER
POLLUTION PROTECTION DEVICES ONCE A STAND OF GRASS HAS BEEN
ESTABLISHED.
14. ALL DISTURBED AREAS WITHIN THE GRADING LIMITS SHALL BE SODDED. ALL
OTHER DISTURBED AREAS SHALL BE SEEDED OR SODDED. FINAL PAYMENT SHALL
NOT BE MADE UNTIL A STAND OF GRASS HAS BEEN ESTABLISHED ON ALL
DISTURBED AREAS INCLUDING ANY AREAS WHERE DISPOSED SOIL IS PLACED FOR
STOCKPILING.
LI
C
EN
SE
D
PROFESSIONAL
ENG
IN
EER
OKLA HOMA
PATRICK J.
No. No.Date
AVIGATION EASEMENT
OIL/GAS WELLS
AIRFIELD PAVEMENT
PRECISION APPROACH PATH INDICATOR (PAPI)
VISUAL APPROACH SLOPE INDICATOR
RUNWAY END IDENTIFIER LIGHTS (REILS)
LIGHTED WIND CONE & SEGMENTED CIRCLE
RUNWAY PROTECTION ZONE
BUILDING RESTRICTION LINE
AIRPORT PROPERTY LINE
MIL, STOL, TACTICAL
FUTURE
PREC./PREC.
500' X 14,000'
800' X 14,000'
HIRL & CL
150' X 12,000'
PRECISION
RIGID & FLEX
350+ (DT)
MALSR, PAPI
ASR, ILS, ALS
% WIND COVERAGE (16 KNOTS)
AIRPLANE DESIGN GROUP
EFFECTIVE RUNWAY GRADIENT %
PAVEMENT STRENGTH(IN 1000 LBS.)
RUNWAY SHOULDERS
LANDING AIDS
PAVEMENT TYPE
APPROACH SURFACES
NAVIGATIONAL AIDS
35'
99.8
V
350+ (DT)
RIGID & FLEX
0.18
ASR,ILS,VOR,NDB
ALSF-2, VASI
50 : 1
RUNWAY OBJECT FREE AREA
RUNWAY WIDTH AND LENGTH
APPROACH TYPE
RUNWAY SAFETY AREA
RUNWAY LIGHTING
RUNWAY MARKING
150' X 9800'
500' X 11,800'
N.P. / PREC.
800' X 11,800'
HIRL & CL
PRECISION
EXISTING
17L/35R
ALSF-2, PAPI
ASR, ILS, ALS
99.8
35'
99.8
V
35'
V
99.8
V
35'
MALSR, VASI, REILS
350+ (DT)
0.18
RIGID
50 : 1
ASR,ILS,ALS,NDB
0.18
50 : 1
0.18
RIGID
350+ (DT)
50 : 1
99.3
NONE
V
99.3
NONE
V
0.13
350+ (DT)
RIGID & FLEX
NONE
VASI, REILS
20 : 1
0.13
350+ (DT)
RIGID & FLEX
50 : 1
ILS, ASR
MALSR, PAPI, REILS
PREC. / PREC.
500' X 14,000'
150' X 12,000'
800' X 14,000'
150' X 9800'
PREC. / N. P.
500' X 11,500'
800' X 11,800'
HIRL
PRECISION PRECISION
HIRL & CL
EXISTING
17R/35L (1)
FUTURE
150' X 10,000'150' X 7800'
500' X 9700'
VIS. / VIS.
800' X 9500'
MIRL
VISUAL
500' X 12,000'
800' X 12,000'
PREC. / N.P.
MIRL
PRECISION
13/31
EXISTING FUTURE
NPIAS CATEGORY
UNICOM (MHz)
AIRPORT REFERENCE POINT (ARP)
MEAN MAX. TEMP. HOTTEST MONTH (°F)
AIRPORT PROPERTY (ACRES)
AIRPORT ELEVATION (AMSL)
BECOME 17C-35C.
TAXIWAY LIGHTING
OF THE SW CORNER SEC. 26, T-11-N, R-4-W.
(2) MIN. T/W SAFETY AREA 320' ALL TAXIWAYS.
AIRPLANE APPROACH CATEGORY
AIRPORT REFERENCE CODE
CONTROL TOWER (MHz)
(1) UPON CONSTRUCTION OF FUTURE R/W 17R-35L, EXISTING R/W 17R-35L TO
(3) R/W 17L-35R EQUIPPED WITH CL & TOUCHDOWN LIGHTING ALSO DESIGNATED CAT II.
* NOTE: EXISTING AIRPORT REFERENCE POINT IS LOCATED 750' NORTH & 400' EAST
77 (DT)
99.8
NONE
IV
99.8
NONE
IV
FLEX
240 (DTW)
REILS
NONE
20 : 1
FLEX
0.18
NONE
NONE
20 : 1
IV
99.8
35'
ALS, PAPI, REILS
RIGID & FLEX
350+ (DT)
0.18
ASR, ILS
100 : 1
17R/35L (NEW)
500' X 7000'
800' X 7000'
VIS. / VIS.
100' X 5000'75' X 3090'
500' X 5090'
800' X 5090'
VIS. / VIS.
VISUAL VISUAL
MIRL
FUTURE EXISTING
18/36
INITIAL
150' X 9800'
PREC. / PREC.
800' X 11,800'
500' X 11,800'
PRECISION
HIRL & CL
ULTIMATE
118.3
MIRL-ALL
D D
D-V D-V
ASOS
MIRL-ALL
119.35
BEACON
122.95
1295.19
LON. 97° 36' 00.37"
PRIM. COMM. SERV.
EXISTING
LAT. 35° 23' 34.72"
ITEM
1295.19
PRIM. COMM. SERV.
LAT. 35° 23' 27.77"
LON. 97° 36' 06.79"
122.95
BUILDINGS
FENCE
FUTURE
RUNWAY SAFETY AREA LENGTH-RUNWAY 35L
RUNWAY OBJECT FREE AREA LENGTH-RUNWAY 13
RUNWAY SAFETY AREA LENGTH-RUNWAY 13
ITEM
D-V D-V
D-V D-V
D-V D-V
AIRPLANE DESIGN GROUP
EXISTING FUTURE
STANDARD
1000'
1000'
1000'
EXISTING
1000'
1000'
1000'
FUTURE
NOTE: THIS DRAWING SHOULD NOT BE USED AS A STANDARD FOR PLANNING OR DESIGN.
ITEM
BRLBRL
X
P L
EXISTING FUTURE
ORIGINAL DATE
APRIL, 1993 1" = 800'
SCALE
REVISION DATE: MAY, 1998
REVISIONS BY WILL ROGERS WORLD AIRPORT
MAGNETIC DECLINATION OBTAINED FROM UNITED STATES GEOLOGICAL SURVEY.
TOPOGRAPHICAL INFORMATION OBTAINED FROM CITY OF OKLAHOMA CITY, OKLAHOMA.
DIRECTOR OF AIRPORTS DATE
MAGNETIC
RUNWAY EXTENSION
RUNWAY EXTENSION
RUNWAY EXTENSION
MODIFICATION
700'
700'
900'
EXISTING
1000'
1000'
1000'
FUTURE
CORRECTED WITH
CORRECTED WITH
CORRECTED WITH
REMARKS
APPROVAL
DATE
-5.2° ANN. CHANGE
AUGUST 1992
6° 32.6'
GRAPHIC SCALE IN FEET
0 400 1600 2400
TRUE
PERIOD OF RECORD 1981-1990 WILL ROGERS WORLD AIRPORT.
NATIONAL CLIMATIC DATA CENTER STATION 13967
NATIONAL OCEANIC AND ATMOSPHERIC ADMINISTRATION.
13-31 17-35
13-31 17-35
ALL
83.8 93.7 97.5
99.3 99.8
ALL
RUNWAY
OKLAHOMA CITY, OKLAHOMA
100.0
% COVERAGE
10.5 KNOTS
10.5 KNOTS
10.5 KNOTS
20 KNOTS
20 KNOTS
CROSSWIND
20 KNOTS
2.5
.81
240 .2
SW230
S
SSW
.2.1 .1
.6
W
SW
W
.1
.5
.1
.2
.1
.1
.4
3.2
.3
.7 1 1.6 3.1
.6 .4
.1
.1
.2
.3
.2
.1
59.3
0-10 KNOTS
.1
SSE
SE 130
110.2
.8
.4
.1
.5
1.9
.3
1.4
ESE
.2
.2
.2
.2
.2 .3
E
US 77
W
SW
.4 1.9 ESE
.6
.2
NW
W
N W
.1.2
.4
.4
.1
.1
.7
.5
.2
.1
.1
.7 .9
.3
1.4
.8 .6
.1
1.3 .4
NNW
N
RUNWAY
13-31 17-35
ALL
100.0
% COVERAGE
99.8 99.3
50NE
.5
.1 .1
EN
E
NNE
CROSSWIND
20 KNOTS
20 KNOTS
20 KNOTS
2.5
NATIONAL CLIMATIC DATA CENTER STATION 13967
NATIONAL OCEANIC AND ATMOSPHERIC ADMINISTRATION.
PERIOD OF RECORD 1981-1990 WILL ROGERS WORLD AIRPORT.
OKLAHOMA CITY, OKLAHOMA
SW230
SSW
210 S
.5 .1
.1
.2
3.2
1 .8
.1 .1
.7
.2 .3
.6
1.6 3.1
SSE
.2
.1
.5 .3
SE 130
.2
.6
.5 17
W
W N
W
.2 0-10 KNOTS
.1 .2
.1
.1
.1
59.3
.3
.6 .4
.4
.2
.4 .7.1
.1
.1
.7 .91.4
1.3
NW
NNW
.1
.1 .2
.3
.1
.8 .6
.2
.4
.1
N
.2
.8
.2
.2
.4
.11.4
E
.2
.2
.5 .3
.1
.1 EN
E
NNE
NE
1" = 20 MILES
CHICKASHA
SH 39
SH 59
PURCELL
SH 39
I-35
S H
U S
U S
S H
S H
I-3
OKLA. CITY
PAGE
SH 152
H.E. B
AILEY
WORLD
AIRPORT
U S
AIRPORT
WILL ROGERS
TUTTLE
BLANCHARD
SH 37
MUSTANG
EL RENO
CLARENCE E.
I-40
AIRPORT
US 66
I-40
YUKON
WILEY POST
EDMOND
AIRPARK
MAX WESTHEIMER
SH 9NORMAN
I-240
SHAWNEE
I-40 N
TURNER
US 62
US 66 CHANDLER
KINGFISHER
SH 33
GUTHRIE SH 105
CLOSEDCLOSED
97°36'43"
97°36'43"
97°36'25.501"
97°36'25.542"
35L
17R
35°22'40"
35°23'36.282"
35°23'06.863"
35°23'30"
35°21'52"
SAME
CLOSED
97°36'43"
SAME
CLOSED
INITIAL
LONGITUDE
97°36'18.319"
97°36'18.225"
97°35'17.915"
97°35'17.834"
97°35'48.435"
97°36'54.977"13 35°24'16.155"
35R
17R (1)
35L (1)
17L
35°22'41.199"
35°22'44.061"
35°24'20.982"
35°23'21.545"
35°24'18.134"
RUNWAY
LATITUDE
EXISTING/
97°37'14.70"35°24'31.73"
35°22'19.64"
35°22'44.05"
SAME
SAME
SAME
97°35'18.85"
97°36'19.24"
SAME
SAME
SAME
FUTURE/ULTIMATE
LATITUDE LONGITUDE
No. No.Date
AVIGATION EASEMENT
OIL/GAS WELLS
AIRFIELD PAVEMENT
PRECISION APPROACH PATH INDICATOR (PAPI)
VISUAL APPROACH SLOPE INDICATOR
RUNWAY END IDENTIFIER LIGHTS (REILS)
LIGHTED WIND CONE & SEGMENTED CIRCLE
RUNWAY PROTECTION ZONE
BUILDING RESTRICTION LINE
AIRPORT PROPERTY LINE
MIL, STOL, TACTICAL
FUTURE
PREC./PREC.
500' X 14,000'
800' X 14,000'
HIRL & CL
150' X 12,000'
PRECISION
RIGID & FLEX
350+ (DT)
MALSR, PAPI
ASR, ILS, ALS
% WIND COVERAGE (16 KNOTS)
AIRPLANE DESIGN GROUP
EFFECTIVE RUNWAY GRADIENT %
PAVEMENT STRENGTH(IN 1000 LBS.)
RUNWAY SHOULDERS
LANDING AIDS
PAVEMENT TYPE
APPROACH SURFACES
NAVIGATIONAL AIDS
35'
99.8
V
350+ (DT)
RIGID & FLEX
0.18
ASR,ILS,VOR,NDB
ALSF-2, VASI
50 : 1
RUNWAY OBJECT FREE AREA
RUNWAY WIDTH AND LENGTH
APPROACH TYPE
RUNWAY SAFETY AREA
RUNWAY LIGHTING
RUNWAY MARKING
150' X 9800'
500' X 11,800'
N.P. / PREC.
800' X 11,800'
HIRL & CL
PRECISION
EXISTING
17L/35R
ALSF-2, PAPI
ASR, ILS, ALS
99.8
35'
99.8
V
35'
V
99.8
V
35'
MALSR, VASI, REILS
350+ (DT)
0.18
RIGID
50 : 1
ASR,ILS,ALS,NDB
0.18
50 : 1
0.18
RIGID
350+ (DT)
50 : 1
99.3
NONE
V
99.3
NONE
V
0.13
350+ (DT)
RIGID & FLEX
NONE
VASI, REILS
20 : 1
0.13
350+ (DT)
RIGID & FLEX
50 : 1
ILS, ASR
MALSR, PAPI, REILS
PREC. / PREC.
500' X 14,000'
150' X 12,000'
800' X 14,000'
150' X 9800'
PREC. / N. P.
500' X 11,500'
800' X 11,800'
HIRL
PRECISION PRECISION
HIRL & CL
EXISTING
17R/35L (1)
FUTURE
150' X 10,000'150' X 7800'
500' X 9700'
VIS. / VIS.
800' X 9500'
MIRL
VISUAL
500' X 12,000'
800' X 12,000'
PREC. / N.P.
MIRL
PRECISION
13/31
EXISTING FUTURE
NPIAS CATEGORY
UNICOM (MHz)
AIRPORT REFERENCE POINT (ARP)
MEAN MAX. TEMP. HOTTEST MONTH (°F)
AIRPORT PROPERTY (ACRES)
AIRPORT ELEVATION (AMSL)
BECOME 17C-35C.
TAXIWAY LIGHTING
OF THE SW CORNER SEC. 26, T-11-N, R-4-W.
(2) MIN. T/W SAFETY AREA 320' ALL TAXIWAYS.
AIRPLANE APPROACH CATEGORY
AIRPORT REFERENCE CODE
CONTROL TOWER (MHz)
(1) UPON CONSTRUCTION OF FUTURE R/W 17R-35L, EXISTING R/W 17R-35L TO
(3) R/W 17L-35R EQUIPPED WITH CL & TOUCHDOWN LIGHTING ALSO DESIGNATED CAT II.
* NOTE: EXISTING AIRPORT REFERENCE POINT IS LOCATED 750' NORTH & 400' EAST
77 (DT)
99.8
NONE
IV
99.8
NONE
IV
FLEX
240 (DTW)
REILS
NONE
20 : 1
FLEX
0.18
NONE
NONE
20 : 1
IV
99.8
35'
ALS, PAPI, REILS
RIGID & FLEX
350+ (DT)
0.18
ASR, ILS
100 : 1
17R/35L (NEW)
500' X 7000'
800' X 7000'
VIS. / VIS.
100' X 5000'75' X 3090'
500' X 5090'
800' X 5090'
VIS. / VIS.
VISUAL VISUAL
MIRL
FUTURE EXISTING
18/36
INITIAL
150' X 9800'
PREC. / PREC.
800' X 11,800'
500' X 11,800'
PRECISION
HIRL & CL
ULTIMATE
118.3
MIRL-ALL
D D
D-V D-V
ASOS
MIRL-ALL
BEACON
122.95
1295.19
LON. 97° 36' 00.37"
PRIM. COMM. SERV.
EXISTING
LAT. 35° 23' 34.72"
ITEM
1295.19
PRIM. COMM. SERV.
LAT. 35° 23' 27.77"
LON. 97° 36' 06.79"
122.95
BUILDINGS
FENCE
FUTURE
RUNWAY SAFETY AREA LENGTH-RUNWAY 35L
RUNWAY OBJECT FREE AREA LENGTH-RUNWAY 13
RUNWAY SAFETY AREA LENGTH-RUNWAY 13
ITEM
D-V D-V
D-V D-V
D-V D-V
AIRPLANE DESIGN GROUP
EXISTING FUTURE
STANDARD
1000'
1000'
1000'
EXISTING
1000'
1000'
1000'
FUTURE
NOTE: THIS DRAWING SHOULD NOT BE USED AS A STANDARD FOR PLANNING OR DESIGN.
ITEM
BRLBRL
X
P L
EXISTING FUTURE
ORIGINAL DATE
APRIL, 1993 1" = 800'
SCALE
REVISION DATE: MAY, 1998
REVISIONS BY WILL ROGERS WORLD AIRPORT
MAGNETIC DECLINATION OBTAINED FROM UNITED STATES GEOLOGICAL SURVEY.
TOPOGRAPHICAL INFORMATION OBTAINED FROM CITY OF OKLAHOMA CITY, OKLAHOMA.
DIRECTOR OF AIRPORTS DATE
MAGNETIC
RUNWAY EXTENSION
RUNWAY EXTENSION
RUNWAY EXTENSION
MODIFICATION
700'
700'
900'
EXISTING
1000'
1000'
1000'
FUTURE
CORRECTED WITH
CORRECTED WITH
CORRECTED WITH
REMARKS
APPROVAL
DATE
-5.2° ANN. CHANGE
AUGUST 1992
6° 32.6'
GRAPHIC SCALE IN FEET
0 400 1600 2400
TRUE
PERIOD OF RECORD 1981-1990 WILL ROGERS WORLD AIRPORT.
NATIONAL CLIMATIC DATA CENTER STATION 13967
NATIONAL OCEANIC AND ATMOSPHERIC ADMINISTRATION.
13-31 17-35
13-31 17-35
ALL
83.8 93.7 97.5
99.3 99.8
ALL
RUNWAY
OKLAHOMA CITY, OKLAHOMA
100.0
% COVERAGE
10.5 KNOTS
10.5 KNOTS
10.5 KNOTS
20 KNOTS
20 KNOTS
CROSSWIND
20 KNOTS
2.5
.81
240 .2
SW230
S
SSW
.2.1 .1
.6
W
SW
W
.1
.5
.1
.2
.1
.1
.4
3.2
.3
.7 1 1.6 3.1
.6 .4
.1
.1
.2
.3
.2
.1
59.3
0-10 KNOTS
.1
SSE
SE 130
110.2
.8
.4
.1
.5
1.9
.3
1.4
ESE
.2
.2
.2
.2
.2 .3
E
US 77
W
SW
.4 1.9 ESE
.6
.2
NW
W
N W
.1.2
.4
.4
.1
.1
.7
.5
.2
.1
.1
.7 .9
.3
1.4
.8 .6
.1
1.3 .4
NNW
N
RUNWAY
13-31 17-35
ALL
100.0
% COVERAGE
99.8 99.3
50NE
.5
.1 .1
EN
E
NNE
CROSSWIND
20 KNOTS
20 KNOTS
20 KNOTS
2.5
NATIONAL CLIMATIC DATA CENTER STATION 13967
NATIONAL OCEANIC AND ATMOSPHERIC ADMINISTRATION.
PERIOD OF RECORD 1981-1990 WILL ROGERS WORLD AIRPORT.
OKLAHOMA CITY, OKLAHOMA
SW230
SSW
210 S
.5 .1
.1
.2
3.2
1 .8
.1 .1
.7
.2 .3
.6
1.6 3.1
SSE
.2
.1
.5 .3
SE 130
.2
.6
.5 17
W
W N
W
.2 0-10 KNOTS
.1 .2
.1
.1
.1
59.3
.3
.6 .4
.4
.2
.4 .7.1
.1
.1
.7 .91.4
1.3
NW
NNW
.1
.1 .2
.3
.1
.8 .6
.2
.4
.1
N
.2
.8
.2
.2
.4
.11.4
E
.2
.2
.5 .3
.1
.1 EN
E
NNE
NE
1" = 20 MILES
CHICKASHA
SH 39
SH 59
PURCELL
SH 39
I-35
S H
U S
U S
S H
S H
I-3
OKLA. CITY
PAGE
SH 152
H.E. B
AILEY
WORLD
AIRPORT
U S
AIRPORT
WILL ROGERS
TUTTLE
BLANCHARD
SH 37
MUSTANG
EL RENO
CLARENCE E.
I-40
AIRPORT
US 66
I-40
YUKON
WILEY POST
EDMOND
AIRPARK
MAX WESTHEIMER
SH 9NORMAN
I-240
SHAWNEE
I-40 N
TURNER
US 62
US 66 CHANDLER
KINGFISHER
SH 33
GUTHRIE SH 105
110'
P L
P L
P L
P L
P.L.
PL
P L
PL
P L
PL
PL
PL
PL
PL
PL
P L
PL
P L
PL
PL
PL
PL
PL
PL
P
L P
L P
L
P L
P.L.
PL
P L
PL
P L
PL
PL
PL
PL
PL
PL
P L
PL
P L
PL
PL
PL
PL
PL
PL
X X X
XXXXXX
X
X X
X
X
X X
X X
X X X
X
X
X X
X
X
X
X X
XXX
X
X
X
X X
X
X
X
X
X
X
X
XX
X
X
X
X
X
X
X
X
X
X
XX
X
X X
X
X
X
X
X
X
X X
X X
X
X
X
X
X
X X
X X
X
X
X
X
X
X X
X
X
X
XXXXXX
X
X
X
X
X X
X X
X
X
X
X
X
X X
X
X
X X
X X
X X
X X
X
X
X
X
X
X
30' DITCH
110'ABANDONED SEWAGE
TREATMENT PLANT
VORTAC
ASR-9
ASR-8
X
( C
LO
S E
D
X
X
X X
X
X
X
X
X
X
X
X
X X
BURLING
TO
N NO
RTHERN RAILRO
AD
X
X
X X
X X X
STATE HIG
HW
AY 152
RADAR
X
XX
X
X
X
X
X X
X
X
XX
X
X
X
X
X X
XX X
BASE
POND
POND
x
POND
C S
.W . 59th S
TR
E
E T
L
GP
LOADING DOCK
RAMP
ALUM.
POST
RAMP LOADING DOCK
FLUME
RAMP
LOADING
RAMP
RAMP
TILE
RAMP
BRASS CAP 1275.81
XY COORDS NOT VERIFIED!
N=147753.766 E=2081690.945
PAD M.L.S. CONC.
CONC. FLUME
S .W
. 59th S
TR
E E
T
NEWPORT HEIGHTS ADDN. W/2, NE/4
VACATED ORDINANCE 12633, 5-27-70 BK.
3937, PG. 1348. ALSO VACATION OF PLAT
BK. 5932, PG. 1465 DATED 4-4-89
S .W
. 59th S
TR
E E
T
OIL FIELD PIPE YARD (NOT
SURVEYED)
T.D.W.R.
BUILDING
STAFFORD
BUILDING
M
IK
E M
O N
R O
N E
Y B
LV
D
M
IKE M
O N
R O
N
EY BLVD
S .W
. 61st S
TR
E E
T
FOSTER DRIVE
FOSTER DRIVE
S .W
. 61st S
TR
E E
T
HALABY DR.
DENNING AVENUE
H elm s S treet
HALABY DR.
S .W
. 59th S t
LC ROCKWELL AVE.
S. DENNING AVENUE
CHRISTIAN AVE.
S .W
. 68th S
TR
E E
T S
.W . 68th S
TR
E
E T
S .W
. 61st S
TR
E E
T
S .W
. 62nd S
TR
E E
T
MULTI-PURPOSE
BUILDING
TOWER
CENTER
T.D .W
.R . - 2
PROGRAM
SUPPORT
FACILITY
SYSTEM
SUPPORT
FACILITY
LARGE AREA TRACON
TRAINING FACILITY
LARGE AREA TRACON
ENGINE BUILDING
DASR-11
(#219)
CONC.
CONC.
CONC.
VENTS
VENT
COOLING
TOW
ER
WEATHER
STATION
DW-2
SHED
GARDEN
RAMP
RAMP
RAMP
METAL
BUILDING
HAZARD
MATERIALS
SHIPS
LADDER
VENT
TOWER
S .W
. 68th S
TR
E E
T
CHRISTIAN AVE.
RAMP
DOCK
MOTOR
RAMP
O
NE STO
RY
GATE
METAL PAD FOR
ELEVATOR
PIT
CONC.
CONC.
RAMP GRATED PIT
TOWER BASE CABLE
CAGES
PIPE
CONC.
RAMP
RAMP
RAMP
RAMP W/GUARD RAIL
CONC.
RAMP
RAMP
ROCK WALL
CONCRETE WALL
CONC.
GRAVEL
STORAGE TANK
CONC. DOCK W/OVERHANG
WOOD POLE
WATER MANHOLE ON CONC. PAD TR:
1270.89
RAMP
CONC.
GATE
MEMORIAL MONUMENT
CONC.
GATE
6' CH. LK.
DOCK
CONC.
AIRPORT TRUST "B-28-1"
MARATHON OIL CO.
RAMP
RAMP
RAMP
RAMP
RAMP
CONC.
TOWER
COOLING
CONC.
ASPHALT
ASPHALT
GRAVEL
PIT
RAMP
RAMP
PIPE
GRAVEL
POST
STATION OBSERVATION
RAMP
TOWER RADAR
ARSR-3
RADAR
TOWER RADAR
WATER TOWER
4' CH. LK. FENCE
4' CH. LK. FENCE
6' CH. LK. FENCE
x
GATE
GATE
GATE
6' CH. LK. FENCE W/3 B.W.
6' CH. LK. FENCE W/3 B.W.
6' CH. LK. FENCE W/3 B.W.
GATE
GATE
GATE
GATE
GATE
6' CH. LK. FENCE W/3 B.W.
LC ROCKWELL AVE.
Quesada Drive
DENNING AVENUE
CHRISTIAN AVE.
S .W
. 63rd S
TR
E E
T
S .W
. 66th S
TR
E E
T
S .W
. 64th S T.
S .W
. 62nd S T
EDDIE AVE.
EDDIE AVE.
S .W
. 64th S T.
EDDIE AVE.
S .W
. 66th S
TR
E E
T
S. DENNING AVENUE
EDDIE AVENUE
S .W
. 66th S
TR
E E
T
Quesada Drive
H elm s S treet
HALABY DR.
QUESADA
HALABY DR.
M cLU
C A
S D
R M cLU C
A S
S T.
SHAFFER ST
11'59" W 2648.20' N 00
ROCKWELL AVE.
FOSTER DRIVE
HALABY DR.
ROCKWELL AVE.
4' CONC.
FLUME
CONCRETE PAD
CONC. FLUME
RAMP
AC's
AC
ACAC
ASR-11CMU
RADAR SUPPORT
FACILITY
(#217)
ARSR-4
POWER SUB
STATION
GROUND
MAINTENANCE
BLDG.
Airport Trust
28-1 RATLIFF
EXPLORATION
CO.
STEEL
FRAME
SHED
DIGITAL
REMOTE
SWITCHING
CENTER
BLDG. 122
DAY CAREMETAL BLDG.
AOS BLDG.
CSF BLDG.
BASE
MAINTENANCE
BLDG.
SHED
T.S.I. LAB
DWT
AIRCRAFT TITLE
INSURED
SERVICE
(#30)
S H
E D
REGISTRY
BUILDING
METAL
BUILDING
BLDG. 50
2 STORY 7.8
x 20.8 METAL
BLDG. F.F.
1282.18
ARSR-3
TRAINING
METAL BLDG.
GENERATOR
TRAILER
ASR-9
ARSR-8
TR
A
ILE
R
CIVIL
AERO-MEDICAL
INSTITUTE
SHED
PORTABLE
SHED
POSITIONER
1 STORY
METAL BLDG.
PRIMATE BLDG.
COOLING
TOWER
O N
E S
TO
R
Y
O
O D
B
LD
G
BUILDING
COOLING
TOWER
GNAS TRAINING
FACILITY
SYSTEMS
BLDG.
ENVIRONMENTAL
SUPPORT
FPS-66
ARSR-1/2
AIR NAVIGATION FACILITIES NO. 2
AVIATION
RECORDS
CAFETERIA
METAL BLDG.
ONE STORY
C O
O
LIN
G
TO
E R
SYSTEMS
TRAINING
GUARD POSTS (TYP.)
WEATHER TOWER
4' WALL
CONC.
VENTS
VENT
VENT
POLE
RAMP
RAMP
CONCRETE PADCONCRETE PADCONCRETE PAD
CONCRETE PAD
METAL
BUILDING
CONCRETE PAD
CONCRETE PADRAMP
JCT. FOR ANTENNA
TOWER BASE W/ 3-METAL
TOWER LEGS 3'X3'X3'
RAMP
TILE
S E
C U
R
ITY
TR
A
ILE
R
GP GP
GP GP
GARDENGARDEN
GARDEN
GARDEN
6' CH. LK. FENCE W/3 B.W.
W/3 B.W.
CONC. FLUME
CONC. FLUME
CONC. FLUME
W O
O
D BLDG
RAMP
RAMP
RAMP
RAMP
GATE
TOWER BASE W/ 3-METAL
TOWER LEGS 3'X3'X3'
GATE
PIT
PIT
CONCRETE WALL
CONCRETE WALL
CONCRETE WALL
ROCK WALL
ROCK WALL
ROCK WALL
ROCK WALL
ROCK WALL
ROCK WALL
ROCK WALL
ROCK WALL
ROCK WALL
RAMP
GATE
RAMP RAMP
RAMP
CONC.
RAMP
DOCK
PIT
GRAVEL
GRAVEL
GARDEN
GARDEN
GARDEN
GARDEN
PIT
PIT
PIT
PIT
VENT
GRAVEL
GRAVEL
GRAVEL
GRAVEL
AN-WALL-HEADAN-WALLAN-DOOR
ASDE
END FIRE
TOWER
GLIDE SLOPE
INTERFACE BOX INTERFACE BOX
GLIDE SLOPE
TOWER
END FIRE
BARBED WIRE FENCE
Quesada Drive
VOR DME TACAN
GUARD
SHACK
RADAR REPAIR
FACILITY
(#218)
Quesada Drive
BUILDING 1
BUILDING 2
LSTC
BUILDING 3
BUILDING 4
VOR-700
ASR-9
RCV TOWER
STAIR BLDG
MAINTENANCE
BUILDING
ATCBI
RMM
OIL TANK BATTERY
SNOW EQUIPMENT BUILDING
AIRPORT MAINTENANCE FACILITY
CORPORATE AVIATION FACILITIES
MUSTANG FUEL DEPOT
PARKING TOLL BOOTHS
SURFACE PARKING
TAXIWAY LIGHTING VAULT
OKLAHOMA CITY AVIATION
CAREER CENTER-METRO TECH
BOP FEDERAL TRANSFER CENTER
FUEL SATELLITE
NINETY NINE'S INC. 801
804A
FUEL STORAGE FACILITY
FBO & MAINTENANCE AREA
FIRE RESCUE FACILITY (ARFF)
NATIONAL WEATHER BUREAU
FIRE PUMP FACILITY
ORGANON TEKNIKA
ONG & OKC WATER DEPT.
CEMETARY
5-LEVEL PARKING GARAGE
FEDERAL MARSHAL HANGAR
EMPLOYEE & OVERFLOW PARKING
AIRFIELD LIGHTING ELECT. VAULT
20TERMINAL BUILDING
AIR TRAFFIC CONTROL TOWER
2-LEVEL PARKING GARAGE
CAR RENTAL FACILITIES
AIR CARGO FACILITIES
AIR NATIONAL GUARD AREA
MMAC CENTER/FAA
FUEL SATELLITE
FBO BUILDING
NINETY NINE'S INC. 33
FUEL STORAGE FACILITY
FBO & MAINTENANCE AREA
FIRE RESCUE FACILITY (ARFF)
NATIONAL WEATHER BUREAU
FIRE PUMP FACILITY
ORGANON TEKNIKA
27 44
ONG & OKC WATER DEPT.
CEMETARY
5-LEVEL PARKING GARAGE
FEDERAL MARSHAL HANGAR
EMPLOYEE & OVERFLOW PARKING
AIRFIELD LIGHTING ELECT. VAULT
20TERMINAL BUILDING
AIR TRAFFIC CONTROL TOWER
2-LEVEL PARKING GARAGE
US POST OFFICE
CAR RENTAL FACILITIES
AIR CARGO FACILITIES
AIR NATIONAL GUARD AREA
MMAC CENTER/FAA
MAINTENANCE FACILITY BUILDING
413 STORAGE FENCING SUPPLY
STORAGE BUILDING
LIGHT PLANT BUILDING
STORAGE MASONARY SUPPLY
TRUCK WASH BUILDING
PARKING GARAGE (ONE TONE)
STORAGE BUILDING
423 STORAGE CHEMICAL SUPPLY
804B LUMBER STORAGE BUILDING
804C PARKING GARAGE (4700)
804D PAINT AND TIRE BUILDING
804E PARKING GARAGE
943 MAIN SHOP BUILDING
(LARGE TRUCKS)
943A PUMP BUILDING
943B THINNER BUILDING
AIRPORT HOTEL
CORPORATE AVIATION FACILITIESDISTRIBUTION CENTER-USPS
CORPORATE AVIATION FACILITIES
CUSTOM NATIONAL AVIAION CENTER
SW SIRLINES RESERVATIONS CENTER
AREA A
AREA B
AREA C
HERTZ
26,872 S.F.
AREA D
X X X X
X
X X X
X
XX
X
D ra w in g N am e:
C :\p w _w or ki ng \lo ch ne r-pw
-0 1\ d0
\2
A R
P R
T D
A
TA
.d w g Fe b
,2
- 9
:4 3a m
G104
AIRPORT LAYOUT DRAWING
CZT
PJB
CZT
01-31-25
01-31-25
01-31-25
P lo t S ty le : a e.
ct b La st S av ed
B y:
c tu ck er
5/
/2
PROJECT NO.
DRAWN BY
CHECKED BY
REVISIONS
DATE
DATE
DATE
DESIGNED BY DATE
W at er fo rd B lv d.
S ui te
O kl ah om a C ity , O kl ah om a
P
.7
.6 w w w .h w lo ch ne r.c om
L B
J Fr ee w ay
S ui te
D al la s, T ex as
, 7
P
.8
.7 w w w .rs an dh
.c om
21343
O K
LA
H
O M
A C
IT
Y
A
IR
P O
R T
TR
U
S T
O K
LA
H
O M
A C
IT
Y
, O K
LA
H
O M
A
R E
H A
B
IL
IT
A
TE
A
A R
R A
M P
P
H A
S E
I
ISSUE FOR BIDNOTE: This Airport Layout Drawing is a copy from the Airport Layout Plan draft dated April 1993 and is supplied for reference only. The accuracy of the data in the Airport Layout Plan draft was not verified. This sheet has been reduced to fit within this project title block thus it is not to scale.
LI
C
EN
SE
D
PROFESSIONAL
ENG
IN
EER
OKLA HOMA
PATRICK J.
w in g N am e:
C :\p w _w or ki ng \lo ch ne r-pw
-0 1\ d0
\2
S O
Q .d w g
Fe b
,2
- 9 :4
3a m
G200
SUMMARY OF QUANTITIES
P lo t S ty le : a e.
ct b La st S av ed
B y:
c tu ck er
5/
/0
PROJECT NO.
DRAWN BY
CHECKED BY
REVISIONS
DATE
DATE
DATE
DESIGNED BY DATE
W at er fo rd B lv d.
S ui te
O kl ah om a C ity , O kl ah om a
P
.7
.6 w w w .h w lo ch ne r.c om
L B
J Fr ee w ay
S ui te
D al la s, T ex as
, 7
P
.8
.7 w w w .rs an dh
.c om
21343
O K
LA
H
O M
A C
IT
Y
A
IR
P O
R T
TR
U
S T
O K
LA
H
O M
A C
IT
Y
, O K
LA
H
O M
A
R E
H A
B
IL
IT
A
TE
A
A R
R A
M P
P
H A
S E
I
ISSUE FOR BID
CZT
PJB
CZT
01-31-25
01-31-25
01-31-25
LI
C
EN
SE
D
PROFESSIONAL
ENG
IN
EER
OKLA HOMA
PATRICK J.
BARNAS
28896
Schedule of Materials Acceptance Lots
Spec Lot/Sublot/Sample Frequency Total
Lots/Sublots Base Bid
P-152 Sets of Tests / 3,000 S.Y. 7 P-156 Sets of Tests / 1,000 S.Y. 10 P-209/
P-306/P-306 Sets of Tests / 1,200 S.Y. 8
P-403 400 Tons / Sublot - Stabilized Base 10 400 Tons / Sublot - Base Course 9
P-501 400 C.Y. / Sublot 9 Add Alternate 1
P-152 Sets of Tests / 3,000 S.Y. 2 P-156 Sets of Tests / 1,000 S.Y. 4 P-209/
P-306/P-306 Sets of Tests / 1,200 S.Y. 4
P-403 400 Tons / Sublot - Stabilized Base 5 400 Tons / Sublot - Base Course 4
P-501 400 C.Y. / Sublot 4
SUMMARY OF QUANTITIES
ITEM NO. SPEC ITEM DESCRIPTION UNIT
QUANTITY
ESTIMATED AS-CONST.
ADD ALTERNATE 1
ADDITIONAL APRON REHABILITATION
1 C-100 Contractor Quality Control Program (CQCP) L.S. 1 2 C-105 Mobilization L.S. 1 3 P-101 Concrete Pavement Section Removal S.Y. 2,470 4 P-152 Unclassified Excavation (Includes Onsite Embankment and Excess Stockpiling) C.Y. 830 5 P-152 Unsuitable Subgrade Removal and Replacement C.Y. 130 6 P-152 Scarify and Recompact Subgrade Soils, 8" Depth S.Y. 2,470 7 P-156 8" Cement Treated Subgrade S.Y. 2,470 8 PLANS (C221) 5" Stabilized Base Course S.Y. 2,470 9 PLANS (C221) 6" Base Course S.Y. 2,470
10 P-501 13.5" Concrete Pavement S.Y. 2,470 11 X-202 Project Survey and Stakeout L.S. 1 12 X-209 Sawcutting L.F. 10
SUMMARY OF QUANTITIES
ITEM NO. SPEC ITEM DESCRIPTION UNIT
QUANTITY
ESTIMATED AS-CONST.
BASE BID
AAR APRON REHABILITATION
1 C-100 Contractor Quality Control Program (CQCP) L.S. 1 2 C-102 Temporary Erosion Control L.S. 1 3 C-102 Stormwater Pollution Prevention Plan (SWPPP) Document L.S. 1 4 C-102 Temporary Seeding AC. 4 5 C-105 Mobilization L.S. 1 6 P-101 Removal of Existing Signs and Lighting System L.S. 1 7 P-101 Storm Pipe and Sanitary Sewer Camera Inspection L.F. 5,070 8 P-101 Asphalt Pavement Section Removal S.Y. 3,850 9 P-101 Concrete Pavement Section Removal S.Y. 13,075
10 P-101 Spall Repair S.F. 200 11 P-152 Unclassified Excavation (Includes Onsite Embankment and Excess Stockpiling) C.Y. 2,640
12 P-152 Unsuitable Subgrade Removal and Replacement C.Y. 400 13 P-152 Scarify and Recompact Subgrade Soils, 8" Depth S.Y. 8,240
14 P-156 8" Cement Treated Subgrade S.Y. 8,240 15 PLANS (C221) 5" Stabilized Base Course S.Y. 8,240 16 PLANS (C221) 6" Base Course S.Y. 8,240
17 P-501 13.5" Concrete Pavement S.Y. 8,000 18 P-620 Pavement Marking Removal S.F. 2,980 19 P-620 Reflectorized Pavement Marking S.F. 2,425 20 P-620 Non-Reflectorized Pavement Marking S.F. 2,425
21 P-632 Asphalt Pavement Rejuvenation S.Y. 500 22 D-701 Remove and Dispose of 12" RCP, Open Cut L.F. 310 23 D-701 Remove and Dispose of 18" RCP, Open Cut L.F. 230 24 D-701 Remove and Dispose of 48" RCP, Open Cut L.F. 8 25 D-701 10" PVC, SDR 35, Open Cut L.F. 20 26 D-701 6' x 6' RCB, Class Aircraft Rated, Open Cut L.F. 157 27 D-701 48" RCP, Class V, Open Cut L.F. 20 28 D-701 60" RCP, Class III, Open Cut L.F. 977 29 D-705 6" ASTM F949 Smooth-Wall, Perforated PVC Underdrain Pipe L.F. 710 30 D-705 10" ASTM F949 Smooth-Wall, Non-Perforated PVC Underdrain Outlet Pipe L.F. 41 31 D-751 Remove Existing Manhole EA. 3 32 D-751 Remove Existing Area Inlet EA. 9 33 D-751 Procure and Install Cleanout EA. 3 34 D-751 Procure and Install Handhole EA. 2 35 D-751 Procure and Install 8' x 8' Inlet EA. 8 36 D-751 Procure and Install 8' x 8' Junction Box EA. 1 37 D-751 Procure and Install 8' x 8' Conflict Structure Junction Box EA. 1 38 D-751 Procure and Install 19' x 11' Junction Box EA. 1 39 D-752 12" Concrete Pipe Plug EA. 5 40 D-752 18" Concrete Pipe Plug EA. 8 41 L-105 Temporary Airport Lighting Systems L.S. 1 42 L-108 No. 8 AWG, 5 kV, L-824, Type C Cable, Installed in Conduit L.F. 810 43 L-108 No. 6 AWG, Solid, Bare Copper Counterpoise Wire, Installed in Trench Above Conduit L.F. 340 44 L-110 1-Way, 2-Inch Schedule 40 PVC Conduit, Concrete Encased L.F. 340
45 L-125 L-861T(L) Taxiway Elevated Edge Light on New 24” Deep L-867B Base Can, in Shoulder Pavement EA. 5
46 L-125 Re-Install Sign on New Foundation EA. 2 47 L-125 Modify Existing Sign Legend EA. 2 48 T-904 Sodding S.Y. 9,100 49 T-905 Topsoil (Furnished from Offsite) S.Y. 9,100 50 X-202 Project Survey and Stakeout L.S. 1 51 X-205 Temporary Construction Items L.S. 1 52 X-209 Sawcutting L.F. 3,350 53 X-216 Aircraft Tiedown Anchors EA. 45 54 X-786 Abandon Drainage Pipe In-Place, 12" Reinforced Concrete Pipe (RCP) L.F. 320 55 X-786 Abandon Drainage Pipe In-Place, 18" Reinforced Concrete Pipe (RCP) L.F. 560 56 OKC 518 18" Steel Casing, Open Cut L.F. 20 w in g N am e:
C :\p w _w or ki ng \lo ch ne r-pw
-0 1\ d0
\2
P A
Y
IT
M S
.d w g Fe b
,2
- 9
:4 3a m
G201
PAY ITEM NOTES
CZT
PJB
CZT
01-31-25
01-31-25
01-31-25
P lo t S ty le : a e.
ct b La st S av ed
B y:
c tu ck er
5/
/2
PROJECT NO.
DRAWN BY
CHECKED BY
REVISIONS
DATE
DATE
DATE
DESIGNED BY DATE
W at er fo rd B lv d.
S ui te
O kl ah om a C ity , O kl ah om a
P
.7
.6 w w w .h w lo ch ne r.c om
L B
J Fr ee w ay
S ui te
D al la s, T ex as
, 7
P
.8
.7 w w w .rs an dh
.c om
21343
O K
LA
H
O M
A C
IT
Y
A
IR
P O
R T
TR
U
S T
O K
LA
H
O M
A C
IT
Y
, O K
LA
H
O M
A
R E
H A
B
IL
IT
A
TE
A
A R
R A
M P
P
H A
S E
I
PAY ITEM NOTES:
1. GENERAL
a. THE PROJECT PAY ITEMS PROVIDED ARE INCLUSIVE OF ALL WORK THAT MUST BE PERFORMED AS REQUIRED BY THE CONTRACT DOCUMENTS AND ALL
REQUIRED RELATED WORK THAT MAY NOT BE SPECIFICALLY IDENTIFIED IN ORDER TO PROVIDE A COMPLETED PROJECT. WORK REQUIRED BY THE CONTRACT DOCUMENTS THAT IS NOT PAID FOR DIRECTLY BY A SPECIFIC BID ITEM IS SUBSIDIARY TO THE WORK ITEMS OF THE PROJECT.
b. THE CONTRACTOR SHALL PROVIDE COPIES OF ALL SUBCONTRACTS TO THE RPR 14 DAYS PRIOR TO THE PRE-CONSTRUCTION CONFERENCE. AT A
MINIMUM, THE INFORMATION SHALL INCLUDE THE FOLLOWING:
· SUBCONTRACTOR'S LEGAL COMPANY NAME.
· SUBCONTRACTOR'S LEGAL COMPANY ADDRESS, INCLUDING COUNTY NAME.
· PRINCIPAL CONTACT PERSON'S NAME, TELEPHONE AND FAX NUMBER.
· COMPLETE NARRATIVE DESCRIPTION, AND DOLLAR VALUE OF THE WORK TO BE PERFORMED BY THE SUBCONTRACTOR.
· COPIES OF REQUIRED INSURANCE CERTIFICATES IN ACCORDANCE WITH THE SPECIFICATIONS.
· MINORITY/ NON-MINORITY STATUS.
2. SURVEY CONTROL
a. CONTRACTOR SHALL VERIFY WITH THE ENGINEER ALL USED SURVEY CONTROL POINTS PRIOR TO BREAKING GROUND. CONTRACTOR SHALL RESET ANY
DISTURBED CONTROL POINTS.
b. PRIOR TO BREAKING GROUND, CONTRACTOR SHALL PROVIDE THEIR CONSTRUCTION STAKING SURVEY TO THE RPR.
c. ALL GRADE VERIFICATIONS SHALL BE PROVIDED BY THE CONTRACTOR'S SURVEYOR TO THE RPR FOR VERIFICATION A MINIMUM OF 1-WEEK PRIOR TO
THE NEXT LAYER BEING PLACED AND PRIOR TO ACCEPTANCE.
3. PHASING
a. LIQUIDATED DAMAGES SHALL BE ASSESSED FOR EACH PHASE INDIVIDUALLY AND FOR THE PROJECT AS A WHOLE.
b. CONTRACTOR SHALL BE REQUIRED TO SCHEDULE THE CLOSURE FOR TAXIWAY A WITH THE AIRPORT AND THE RPR A MINIMUM OF 30 DAYS IN ADVANCE.
c. CONTRACTOR SHALL COMPLETE ALL WORK ITEMS WITHIN THE DEPICTED PHASE LIMITS FOR EACH PHASE IN THEIR ENTIRETY PRIOR TO MOVING TO
THE NEXT PHASE. CONTRACTOR SHALL PROVIDE PROVISIONS TO PERFORM TESTING OF THE CONCRETE PAVEMENT TO ENSURE THAT THE PAVEMENT HAS REACHED THE ACCEPTABLE COMPRESSIVE STRENGTHS PRIOR TO MOVING TO THE NEXT PHASE. CONTRACTOR WILL NOT BE
ALLOWED TO RE-MOBILIZE TO A PREVIOUS PHASE.
d. CRITICAL CONSTRUCTION LIMITS DEPICT THE AREAS IN WHICH EFFORTS TO COMPLETE THE WORK SHALL BE FOCUSED IN ORDER TO OPEN PAVEMENTS.
4. TESTING
a. CONTRACTOR SHALL EMPLOY AN ACCREDITED TESTING LABORATORY TO COMPLETE TESTING REQUIRED AS PART OF THE CONTRACTOR'S QUALITY
CONTROL PROGRAM.
b. CONTRACTOR SHALL ALSO ESTABLISH AN AGREEMENT WITH THE OWNER'S QA TESTING LABORATORY PRIOR TO BEGINNING WORK. THE CONTRACTOR
WILL BE REQUIRED TO PAY THE QA LAB FOR ALL RETESTS REQUIRED DUE TO FAILING MATERIAL TEST RESULTS AND FOR ADDITIONAL COSTS INCURRED DUE TO THE CONTRACTOR'S FAILURE TO PROPERLY SCHEDULE TESTING AND THE READINESS OF MATERIALS FOR TESTING.
c. IT IS THE CONTRACTOR'S RESPONSIBILITY TO SCHEDULE QA TESTING WITH THE OWNER'S QA LAB.
d. SEE SCHEDULE OF MATERIALS ACCEPTANCE LOTS TABLE. QA TESTING IS BASED ON THE NUMBER OF LOTS AND SUBLOTS AS DEFINED IN THE
TABLE.…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .