20M061CN Building HP445-HP465-HP485 Roof Repairs SR.pdf

PDF 88 KB Posted

Attached to
Roof Repairs Bldgs HP445, HP465, & HP485
Solicitation number
N40085-26-R-9048
Issued by

About this file

This is a Submittal Register form used to track and manage contractor submissions throughout a federal construction contract lifecycle. The form serves as a control document for monitoring preconstruction submittals, test reports, certificates, product data, and closeout documentation from the contractor to the approving authority.

The register requires tracking of multiple submittal categories organized by specification section codes (SD-01 through SD-11). Preconstruction submittals include the Accident Prevention Plan, Quality Control Plan, Construction Schedule, Equipment Delivery Schedule, Activity Hazard Analysis, crane-related plans and operator certifications, traffic control plans, and environmental documentation such as environmental protection plans, preconstruction surveys, storm water discharge permits, and notices of intent. Test reports and certificates encompass backflow preventer testing and certification, confined space entry permits, third-party crane certifications, and certificates of compliance. Product data submittals cover backflow preventers and MSDS documentation for Class I ozone-depleting substances. Closeout submittals include the submittal register, complete submittal package, interim DD Form 1354 for transfer and acceptance, and quality control plan documentation. The form contains columns for tracking action codes, dates of submission, approval dates, material needed dates, dates forwarded to approving authority and other reviewers, and dates received from each entity, with a remarks column for additional notes. This template allows federal agencies to systematically monitor contractor compliance with contractual documentation requirements throughout project execution and completion.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTRACT NO.

CONTRACTOR

SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

(a) (b) (c) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)

01 20 00

1.3

01 30 00

1.4.1

01 31 50

1.2

01 32 16

1.2

1.3

01 33 00

1.4.1

1.6.1

01 35 29

1.9

1.10

1.9.1

1.9.1

1.7.1.4

1.14

1.14.1

1.14.3

1.14.4

1.14.5

1.11

1.14.6

1.14.7

01 45 10

1.6

01 50 00

1.6.2.1

2.1

3.1

SD-03 PRODUCT DATA

Backflow Preventers (If Applicable)

SD-06 TEST REPORTS

SD-07 CERTIFICATES

SD-01 PRECONSTRUCTION SUBMITTALS

Traffic Control Plan (If Applicable)

Crane Critical Lift Plan (If Applicable)

Crane Operators (If Applicable)

Reports

Accident Reports

Monthly Exposure Reports

Regulatory Citations and Violations

Crane Reports

(Enter Contract No. Here)

SD-01 PRECONSTRUCTION SUBMITTALS

Accident Prevention Plan (APP)

SD-01 PRECONSTRUCTION SUBMITTALS

Equipment Delivery Schedule

SD-01 PRECONSTRUCTION SUBMITTALS

SUBMITTAL REGISTER

P A R A G R A P H

N O

S P E C

S E C T

C L A S S I F I C A T I O N

G O V T

O R

A E

R E V W R

(Enter Contractor Name Here)

Qaulity Control Plan (QC Plan)

Crane Work Plan (If Applicable)

Activity Hazard Analysis (AHA)

SD-06 TEST REPORTS

Certificate of Compliance

SD-01 PRECONSTRUCTION SUBMITTALS

TITLE AND LOCATION

(Enter Contract Title and Locaiton Here)

Schedule of Prices

List of Contact Personnel

Construction Schedule of Military Real Property (If Applicable)

A C T I V I T Y

N O

T R A N S M I T T A L

N O

(d)

DESCRIPTION ITEM SUBMITTED

SD-11 CLOSEOUT SUBMITTALS

SD-11 CLOSEOUT SUBMITTALS

Interim DD1354, Transfer & Acceptance

SD-11 CLOSEOUT SUBMITTALS

Submittal Register

Complete Submittal Package

Backflow Preventer Tests (If Applicable)

SD-07 CERTIFICATES

Third Party Certification of Barge-

Mounted Movile Cranes

Confined Space Entry Permit

Approving AuthorityContractor Schedule Dates

Contractor Action

1.3

01 57 19

1.6.1

1.6.4

1.7.2

1.7

1.7

PAGE 1 OF _

Backflow Preventers Certificate (If Applicable)

SUBMITTAL FORM, JAN 96 PREVIOUS EDITION OBSOLETE

MSDS for Class I ODS Waivered Product

SD-01 PRECONSTRUCTION SUBMITTALS

Permit for Storm Water Discharge (If applicable)

Environmental Protection Plan

Preconstruction Survey

Notice of Intent (If applicable)

Backflow Tester Certification (If Applicable)