20M057CN Building HP215-HP225-HP235-HP245 Roof Repairs PD.pdf

PDF 62 KB Posted

Attached to
Roof Repairs Bldgs HP225, HP235, HP245, HP275, HP285, & HP295
Solicitation number
N4008526R9017
Issued by

About this file

This is a Project Description and Scope of Work document for a roofing replacement project at Camp Lejeune, North Carolina. The contractor is required to replace existing shingle roof systems with standing seam metal roofing systems on four Bachelor Enlisted Quarters (BEQ) buildings: HP215, HP225, HP235, and HP245. The contractor assumes responsibility for moving any furniture and other objects within the project area as necessary to complete the work.

The project must be executed while the facility remains operational, requiring the contractor to minimize interference with normal operations. Supervision requirements allow for a single qualified individual to serve as Superintendent, Quality Control Manager, and Safety & Health Officer, provided that person meets all qualifications as defined in the project specifications.

View the file

Other files

Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROJECT DESCRIPTION

This scope of work is to be accomplished in BEQ buildings HP215, HP225, HP235,HP245 located on Camp Lejeune, North Carolina. Contractor shall Provide the following: Replace existing shingle roof systems with standing seam metal roofing systems on all noted Bachelor Enlisted Quarters noted.

SPECIAL SCHEDULING

The facility/activity will remain in operation during the entire construction period. The Contractor shall conduct his operations so as to cause the least possible interference with normal operations of the facility/activity. The furniture and other objects in the project area are to be moved by the contractor if required.

SUPERVISION

One person may fill the roles of Superintendent, Quality Control Manager, and Safety & Health Officer, if duly qualified for all three positions as defined in the project specification.