20GR21 - Sunshine Park Trails Expansion - Construction Plans.pdf

PDF 23 MB Posted

Attached to
Project No. 20GR21 - Sunshine Park Trails Expansion
Solicitation number
S-KR1079-00015675
Issued by
Douglas County, Oregon

About this file

This construction plans document is prepared by the City of Roseburg Public Works Department for Project No. 20GR21, the Sunshine Park Trails Expansion. The project involves the construction of expanded trail systems within Sunshine Park, located in Roseburg, Oregon. The plans include site plans, topography maps for both the west and east sides of the park, detailed trail sections, and specifications for culvert and armoring installations. The document references the 2024 Edition of the Oregon Standard Specifications for Construction as the governing standard and indicates that the contractor will receive KML and shape files from the city to assist with trail route staking. Key contractor responsibilities include field verification of culvert and armoring locations and lengths, replacement of any survey monuments affected by construction at the contractor's expense with a licensed land surveyor, and obtaining all required permits for work in public rights-of-way from ODOT, the city, and the county. The construction plans are dated December 2025 and contain multiple sheets detailing general notes, construction notes, and technical specifications for trail construction.

The construction specifications indicate that trails will be constructed with varying widths and slopes, with beginner and blue flow trails featuring a 4-foot tread width and an 8-foot clear width. Trail sections include typical in-sloped turns and require excavation of minimum 6-8 inches for tread preparation. Culvert installations must match existing stream channel slopes with corrugated metal pipe buried at depths specified in the construction details, including geotextile fabric and compacted bedding aggregate. Contractors are required to call 811 before digging to identify underground utilities. The document does not specify pricing, contract term, funding sources, or bid submission requirements, as these details would be contained in accompanying bid documents or solicitation materials.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

GENERAL NOTES:

1. THE 2024 EDITION OF THE OREGON STANDARD

SPECIFICATIONS FOR CONSTRUCTION PREPARED BY THE

OREGON DEPARTMENT OF TRANSPORTATION AND THE

AMERICAN PUBLIC WORKS ASSOCIATION OREGON

CHAPTER WILL BE CONSIDERED THE STANDARD

SPECIFICATIONS.

2.THE CONTRACTOR SHALL REPLACE ANY AND ALL SURVEY

MONUMENTS WHICH ARE AFFECTED BY THE

CONSTRUCTION. ALL MONUMENTS WILL BE RESET BY A

LICENSED LAND SURVEYOR AT CONTRACTORS EXPENSE.

3.LOCATIONS SHOWN ON ENGINEERING DRAWINGS ARE

APPROXIMATE. CONTRACTOR IS RESPONSIBLE FOR

STAKING TRAIL ROUTES. kML FILE AND SHAPE FILE WILL

BE SUPPLIED TO CONTRACTOR BY THE CITY.

4.CONTRACTOR TO FIELD VERFIY CULVERT AND

ARMORING LOCATIONS AND LENGTHS.

5.CONTRACTOR RESPONSIBLE FOR OBTAINING ALL

REQUIRED PERMITS FOR WORKING IN PUBLIC

RIGHT-OF-WAYS. (I.E. ODOT, CITY, COUNTY).

SUNSHINE PARK TRAILS EXPANSION

Call before you dig.

Know what's below.

ATTENTION:

LINE IS 1 INCH

AT FULL SCALE

DESIGNED: DRAWN: REVISIONS

IF NOT 1-INCH - SCALE ACCORDINGLY

DRAWING NO.

SHEET NO.

OF

DATE

PROJECT NO.

CITY OF ROSEBURG

Public Works Department

900 SE Douglas Ave.

Roseburg OR 97470

SUNSHINE PARK TRAILS

6COVER

EXPANSION

cov

DEC 2025

20GR21AB

GENERAL

VICINITY MAP

Not To Scale

GENERAL

DRAWING INDEX

LINE IS 1 INCH

AT FULL SCALE

DESIGNED: DRAWN: REVISIONS

IF NOT 1-INCH - SCALE ACCORDINGLY

DRAWING NO.

SHEET NO.

OF

DATE

PROJECT NO.

CITY OF ROSEBURG

Public Works Department

900 SE Douglas Ave.

Roseburg OR 97470

SUNSHINE PARK TRAILS

6SITE PLAN

EXPANSION

C1

DEC 2025

20GR21AB

CONSTRUCTION

SITE NOTESNO.

DIAMOND LAKE BOULEVARD

SU

N

SH

IN

E R

O A

D

C

EM

ET

A

R Y

NORDIC VENEER

WETLAND

PARK BOUNDARY

PA

R

K B

O U

N D

A R

Y

PARKING LOT

PARK BOUNDARY

PARK BOUNDARY

PARK BOUNDARY

PARK BOUNDARY

PARK BOUNDARY

EX

IS

TI

NG

EX

IS

TI

NG

TRAIL

TR

A

IL

DESIGNED: DRAWN: REVISIONS

IF NOT 1-INCH - SCALE ACCORDINGLY

DRAWING NO.

SHEET NO.

OF

DATE

PROJECT NO.

CITY OF ROSEBURG

Public Works Department

900 SE Douglas Ave.

Roseburg OR 97470

SUNSHINE PARK TRAILS

6TOPOGRAPHY- WEST SIDE

EXPANSION

C2

DEC 2025

20GR21AB

CONSTRUCTION

CONSTRUCTION NOTESNO.

EXISTING CREEK

WETLAND

PARKING LOT

PARK BOUNDARY

PARK BOUNDARY

PARK BOUNDARY

PARK BOUNDARY

PA

R

K B

O U

N D

A R

Y

SU

N

SH

IN

E R

O A

D

NORDIC VENEER

DESIGNED: DRAWN: REVISIONS

IF NOT 1-INCH - SCALE ACCORDINGLY

DRAWING NO.

SHEET NO.

OF

DATE

PROJECT NO.

CITY OF ROSEBURG

Public Works Department

900 SE Douglas Ave.

Roseburg OR 97470

SUNSHINE PARK TRAILS

6TOPOGRAPHY - EAST SIDE

EXPANSION

G3

DEC 2025

20GR21AB

GENERAL

CONSTRUCTION NOTESNO.

WETLAND

PARK BOUNDARY

PARK BOUNDARY

PA

R

K B

O U

N D

A R

Y

PARK BOUNDARY

PARK BOUNDARY

C

EM

ET

A

R Y

DESIGNED: DRAWN: REVISIONS

IF NOT 1-INCH - SCALE ACCORDINGLY

DRAWING NO.

SHEET NO.

OF

DATE

PROJECT NO.

CITY OF ROSEBURG

Public Works Department

900 SE Douglas Ave.

Roseburg OR 97470

SUNSHINE PARK TRAILS

6TRAIL SECTIONS

EXPANSION

D1

DEC 2025

20GR21AB

DETAIL

D1

1 IN-SLOPED TURN TYPICAL

D1

2 TYPICAL TRAIL SECTION

DESIGNED: DRAWN: REVISIONS

IF NOT 1-INCH - SCALE ACCORDINGLY

DRAWING NO.

SHEET NO.

OF

DATE

PROJECT NO.

CITY OF ROSEBURG

Public Works Department

900 SE Douglas Ave.

Roseburg OR 97470

SUNSHINE PARK TRAILS

6CULVERT AND ARMORING

EXPANSION

D2

DEC 2025

20GR21AB

DETAIL

EXCAVATE

MINIMUM 6-8"

TREAD 4'

BEGINNER & BLUE FLOW TRAILS

OUTSLOPE

GEOTEXTILE

FABRIC

D2

1CULVERT

D2

2ARMORING TYPICAL

CLEAR WIDTH 8'

TREAD 4'

TRENCH BACKFILL DEPTH VARIES

PIPE ZONE BACKFILL

3" LIFT OF COMPACTED BEDDING

AGGREGATE

CORRUGATED METAL PIPE

MAX SLOPE

SLOPED TO MATCH EXISTING

STREAM CHANNEL

STREAM BED

TREAD 4'

STREAMBED PIPE BURRY