2027004-PU-DB_Addendum 02_10-26-26.pdf

PDF 2 MB Posted

Attached to
Water Treatment Plant Sedimentation Basin Plate Settlers Project RFP (2027004-PU-DB)
Solicitation number
DB-129405
Issued by
Hanover County, Virginia

About this file

This Addendum #2 modifies the City of Harrisonburg's Request for Proposal (RFP 2027004-PU-DB) for the Water Treatment Plant Sedimentation Basin Plate Settlers Project, a Design-Build procurement issued October 6, 2026. The project involves the design and construction of four sedimentation basins (110 feet long, 27.5 feet wide, 14 feet deep) equipped with inclined plate settlers and sludge removal systems (vacuum or scrapers) meeting Virginia Department of Health-Office of Drinking Water (VDH-ODW) requirements under 12VAC9-590-872. The scope includes project management, design, construction, installation, commissioning, and obtaining VDH-ODW certificates to construct and operate. A non-mandatory virtual pre-proposal meeting was held October 22, 2026, with recorded login sheets and PowerPoint presentations attached. The RFP uses a two-phase Design-Build selection process with at least two firms short-listed following Step 1 Statement of Qualifications submissions. Key dates include a deadline for questions and site visits of November 26, 2026, proposal closing December 10, 2026 at 3:00 PM through the eva.virginia.gov platform, proposal review December 11-31, 2026, and one-on-one presentation meetings January 2-31, 2027. Addendum #2 clarifies that no line stop, hot tap, or line freeze work is required; any tapping will occur on empty pipes only.

Pricing and cost information are submitted separately through Proposal Part 2, Section 7, using Cost Proposal Form M. Proposals are evaluated on a 100-point system addressing technical components including project scope, design requirements, construction requirements, project planning, and ancillary design requirements outlined in Attachments I through M. Four informational concept documents from different vendors are provided for reference but are non-comprehensive, non-binding, and for informational purposes only. All submittals must be made through the eva platform with bidders required to be registered vendors; faxed, emailed, and hard copy submittals are not accepted. Authorized signatures confirming receipt of the addendum must accompany all bid/proposal submissions. No set-asides, incumbent information, or specific funding sources are identified in this addendum document.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ADDENDUM #2

ITB/RFP NUMBER: 2027004-PU-DB

Water Treatment Plant Sedimentation Basin Plate Settlers Project RFP

DATE: October 26, 2026

TO: All Potential Bidders/Offerors

City of Harrisonburg’s RFP, is modified as follows:

On October 22, 2026 at 1:30pm local time a non-mandatory, virtual pre-proposal meeting was held for the above-referenced solicitation. The recorded log-in sheet and PowerPoint presentation slides from this meeting are attached and made part of this addendum. Below is a question and answer received prior to the pre-proposal meeting.

1. Question: What is the Line Stop, Hot Tap or Line Freeze scope of work for this project?

Answer: There is no need to hot tap or to freeze any lines. Any tapping that will be required will be on an empty pipe.

All other requirements, terms and conditions of the ITB/RFP remain unchanged.

Addendum page must be signed and returned with your bid/proposal to acknowledge receipt of this addendum.

Authorized Signature

By: Shane B. Smith Procurement Manager

City of Harrisonburg, VA - Water Treatment Plant Sedimentation Basin Plate Settlers Project RFP (2027004-PU-DB) Addendum #2 Page 1 of 23 display userName John Thornton, DBIA jthornton@meb.group John Thornton, DBIA jthornton@meb.group Joshua L. Baughman joshua.baughman@harrisonburgva.gov Dave Gray dave.gray@harrisonburgva.gov Arnold, Roger rarnold@hazenandsawyer.com Aaron Tice atice@wileywilson.com Josh Clifton jclifton@englishconst.com Delphos, Paul J pjdelphos@burnsmcd.com Sue Griffin svgriffin@crowderusa.com Rick Prosser rprosser@crowderusa.com Tabor, Chris ctabor@hazenandsawyer.com Rebecca L. Kibler rebecca.kibler@harrisonburgva.gov Margo Waisanen mwaisanen@crowderusa.com Rob Mangrum rob@mangrumconsulting.com Jeremy Harrison jharrison@crowderusa.com Shane B. Smith shane.smith@harrisonburgva.gov Sara Sipe sara.sipe@harrisonburgva.gov Balbina Penaloza balbina.penaloza@harrisonburgva.gov Balbina Penaloza balbina.penaloza@harrisonburgva.gov Mike Collins mike.collins@harrisonburgva.gov Mike Collins mike.collins@harrisonburgva.gov

City of Harrisonburg, VA - Water Treatment Plant Sedimentation Basin Plate Settlers Project RFP (2027004-PU-DB) Addendum #2 Page 2 of 23

City of Harrisonburg, Virginia

Water Treatment Plant Enhancements

Clarification Basin Plate Settlers & Sludge Removal Systems

10.22.2026

City of Harrisonburg, VA - Water Treatment Plant Sedimentation Basin Plate Settlers Project RFP (2027004-PU-DB) Addendum #2 Page 3 of 23

Owner Design Builder EJCDC Format

Project Work Scope

Procurement Format and Schedule

Offerors Submittal Contents

Technical Component

City of Harrisonburg, VA - Water Treatment Plant Sedimentation Basin Plate Settlers Project RFP (2027004-PU-DB) Addendum #2 Page 4 of 23

Owner Design Builder EJCDC Format

City of Harrisonburg, VA - Water Treatment Plant Sedimentation Basin Plate Settlers Project RFP (2027004-PU-DB) Addendum #2 Page 5 of 23

Available Upon Request-Edited

City of Harrisonburg, VA - Water Treatment Plant Sedimentation Basin Plate Settlers Project RFP (2027004-PU-DB) Addendum #2 Page 6 of 23

Available Upon Request - Unedited

City of Harrisonburg, VA - Water Treatment Plant Sedimentation Basin Plate Settlers Project RFP (2027004-PU-DB) Addendum #2 Page 7 of 23

Project Work Scope

City of Harrisonburg, VA - Water Treatment Plant Sedimentation Basin Plate Settlers Project RFP (2027004-PU-DB) Addendum #2 Page 8 of 23

3.0 SCOPE DOCUMENTS

ATTACHMENT I: DESIGN REQUIREMENTS FOR INCLINED PLATE SETTLERS

ATTACHMENT J: DESIGN REQUIREMENTS FOR SLUDGE SYSTEM

ATTACHMENT K: VIRGINIA ADMINISTRATIVE CODE 12VAC9-590-872

ATTACHMENT L: ANCILLARY PROJECT REQUIREMENTS

OTHER:

o Provided are 4 concept documents from 4 different vendors.

o They are not comprehensive to use for construction.

o They are not binding in any way for this project.

o They are informational only.

City of Harrisonburg, VA - Water Treatment Plant Sedimentation Basin Plate Settlers Project RFP (2027004-PU-DB) Addendum #2 Page 9 of 23

4.0 PROJECT SCOPE

4.1 PROJECT MANAGEMENT

Integration, scope, schedule, cost, quality, resources, communication, risk , procurement, and stakeholder management

4.2 DESIGN REQUIREMENTS

Meet HPU design requirements and obtain VDH-ODW certificate to construct

4.3 CONSTRUCTION REQUIREMENTS

Partner with Harrisonburg’s plant operations team, complete the installation, commission the final product, and obtain VDH-ODW certificate to operate.

City of Harrisonburg, VA - Water Treatment Plant Sedimentation Basin Plate Settlers Project RFP (2027004-PU-DB) Addendum #2 Page 10 of 23

Procurement Format and Schedule

City of Harrisonburg, VA - Water Treatment Plant Sedimentation Basin Plate Settlers Project RFP (2027004-PU-DB) Addendum #2 Page 11 of 23

The City of Harrisonburg will use a two-phased selection process for the selection of a Design-Builder for the Project.

The RFQ represents the first phase in the selection process, during which Offerors will submit Statements of Qualifications for the project. Upon completion of this Step 1, the City intends to short-list at least two (2) Offerors.

Only the short-listed Offerors will receive the Request for Proposal (RFP) and be allowed to submit a proposal. In the event the SOQs of fewer than two (2) Offerors are determined to be responsive, then the City reserves the right to not proceed to Step 2 of the D-B process.

1.1. CITY’S DESIGN-BUILD PROCUREMENT PROCESS

City of Harrisonburg, VA - Water Treatment Plant Sedimentation Basin Plate Settlers Project RFP (2027004-PU-DB) Addendum #2 Page 12 of 23

6.0 ANTICIPATED SCHEDULE

PROJECT EVENT DATE

Issue date for RFP October 6, 2026

Virtual Pre-Proposal Meeting October 22, 2026, 1:30 PM

Last Day for Questions & Site Visits November 26, 2026

Closing on EVA December 10, 2026, 3:00 PM

Review of Proposals December 11, 2026 – December 31, 2026

One-on-One Presentation Meetings January 2, 2027- January 31, 2027

City of Harrisonburg, VA - Water Treatment Plant Sedimentation Basin Plate Settlers Project RFP (2027004-PU-DB) Addendum #2 Page 13 of 23

5.0 PRE-PROPOSAL MEETING (VIRTUAL) & SITE TOURS

City of Harrisonburg, VA - Water Treatment Plant Sedimentation Basin Plate Settlers Project RFP (2027004-PU-DB) Addendum #2 Page 14 of 23

9.0 INSTRUCTIONS TO OFFERORS

All submittals this RFP shall be submitted through the eva platform (https://eva.virginia.gov/).

Faxed, emailed and hard copies of submittals will not be accepted. Submittals shall be received by the Purchasing Office no later than the date and time listed on the Cover Page of this RFP. Any submittals received after this date and time will not be accepted.

To submit through eva, the Offeror must be a registered vendor. To register as a new vendor, visit:

https://eva.virginia.gov/register-now.html. If you have questions or issues during the process of submitting a response, contact eva Customer Care at: 1-866-289-7367.

City of Harrisonburg, VA - Water Treatment Plant Sedimentation Basin Plate Settlers Project RFP (2027004-PU-DB) Addendum #2 Page 15 of 23 https://eva.virginia.gov/

Offerors Submittal Contents

City of Harrisonburg, VA - Water Treatment Plant Sedimentation Basin Plate Settlers Project RFP (2027004-PU-DB) Addendum #2 Page 16 of 23

6.0 PROPOSAL REQUIREMENTS

PART 1

Section 1: General Section 2: Required Forms –B,C,D,G,H,W9 Section 3: Signed Addenda- Section 4: Scope of work – Docs + Power point summary Section 5: Technical Documents –Docs + Power point summary Section 6: Project Planning – Docs + Power point summary

Part 2 Section 7: Cost Proposal Form M

11.0 PROPOSAL EVALUATION CRITERIA

Proposal evaluations will be based on a 100-point system using the following minimum selection criteria.

The format of each proposal must contain the following elements organized into separate sections , as the Offeror(s) may deem appropriate

City of Harrisonburg, VA - Water Treatment Plant Sedimentation Basin Plate Settlers Project RFP (2027004-PU-DB) Addendum #2 Page 17 of 23

City of Harrisonburg, VA - Water Treatment Plant Sedimentation Basin Plate Settlers Project RFP (2027004-PU-DB) Addendum #2 Page 18 of 23

Technical Component

City of Harrisonburg, VA - Water Treatment Plant Sedimentation Basin Plate Settlers Project RFP (2027004-PU-DB) Addendum #2 Page 19 of 23

Project Scope

4 basins Length: 110” Width: 27.5’ Depth 14’

Plate settlers designed to meet

12VAC5-590-872

under VDH-ODW approval

Sludge removal system (vacuum or scrapers).

• Physical hydraulic integration

• Sludge transport layout

• Electrical layout

City of Harrisonburg, VA - Water Treatment Plant Sedimentation Basin Plate Settlers Project RFP (2027004-PU-DB) Addendum #2 Page 20 of 23

City of Harrisonburg, VA - Water Treatment Plant Sedimentation Basin Plate Settlers Project RFP (2027004-PU-DB) Addendum #2 Page 21 of 23

ATTACHMENT I. PROJECT SPECIFICATION FOR INCLINED PLATE SETTLERS

ATTACHMENT J. PROJECT SPECIFICATION FOR SLUDGE SYSTEM

ATTACHMENT K. VIRGINIA ADMINISTRATIVE CODE 12VAC9-590-872

ATTACHMENT M. PROJECT ANCILLARY DESIGN CHECKLIST

City of Harrisonburg, VA - Water Treatment Plant Sedimentation Basin Plate Settlers Project RFP (2027004-PU-DB) Addendum #2 Page 22 of 23

City of Harrisonburg, VA - Water Treatment Plant Sedimentation Basin Plate Settlers Project RFP (2027004-PU-DB) Addendum #2 Page 23 of 23

2027004-PU-DB_Addendum 02_10-26-26.pdf
ADD2_10.22.26 RFP Attendance.pdf
ADD2_Pre-RFP Meeting Final.pdf
City of Harrisonburg, Virginia��Water Treatment Plant Enhancements��Clarification Basin Plate Settlers &Sludge Removal Systems��
Slide Number 2
Slide Number 3
Slide Number 4
Slide Number 5
Slide Number 6
Slide Number 7
Slide Number 8
Slide Number 9
Slide Number 10
Slide Number 11
Slide Number 12
Slide Number 13
Slide Number 14
Slide Number 15
Slide Number 16
Slide Number 17
Slide Number 18
Slide Number 19
Slide Number 20
Slide Number 21

File details come from the government source that posted it. Updated .