This is Addendum #1 to Bid #2027-02 issued by the Town of Stratford, Connecticut on August 6, 2026, for the Stratford Arboretum Project located at Ketcham Road and Philo Street. The addendum addresses two requests for information submitted during the vendor question-and-answer period, which closes on August 14, 2026 at 12:00 p.m. EDT, with bids due on August 25, 2026 at 10:00 a.m. EDT. The first clarification concerns bid form item #38, which requests a lump sum cost for installation of a bus shelter. The Town has clarified that the prefabricated bus shelter will be purchased by the Town of Stratford and installed by the Contractor. The shelter is specified as a 5' x 12' Slimline Series Aluminum Structure manufactured by Brasco International, featuring a reverse barrel roof with white acrylic glazing, clear anodized aluminum finish, four-sided design with full rear and side walls, front-centered windscreen with two ADA openings, and 1/4" clear tempered safety glass wall panels. The manufacturer has indicated a 30-week lead-time from order approval. The second clarification addresses catch basin sump depths, confirming that all catch basins shall use 2-foot sumps rather than the standard 4-foot sumps for single catch basins and 2-foot sumps for double catch basins.
The addendum contains no information regarding pricing terms, set-asides, contract value, contract term, or renewal options. All requests for information must be submitted in writing to Phillip Ryan, Purchasing Agent, at pryan@townofstratford.com, and verbal communication is not accepted. Hard copy bid submission is required; electronic bid submission is prohibited.
View the file
Other files
Show all 24
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ADDENDUM #1
BID #2027-02
STRATFORD ARBORETUM PROJECT
KETCHAM ROAD & PHILO STREET
6th August, 2026 – It is intended that this Addendum incorporating the following corrections, revisions, additions, deletions and clarifications become part of the Contract Documents.
Requests for Information (RFI):
1. Summary of work spec section 01 11 00 1.5A states “WORK BY OTHERS A. Work associated with installation of Bus Shelter. This is not NIC (not in contract) and is the responsibility of the Town of Stratford.”
There is a bid form item #38 asking for LS cost for installation of bus shelter.
Please clarify bus shelter.
Who is purchasing?
Who is installing?
Response: The bus shelter will be purchased by the Town of Stratford to be installed by the Contractor.
Shelter will be prefabricated by Brasco International to meet GBT specifications. Details below.
Note there is 30-week lead-time from order approval.
Item #: SL-0512-F-C-RB-AC-TG-0-0-0
Description: 5’ x 12’ Slimline Series Aluminum Structure with Heavy Duty Anchor Boots Four- Sided; Full Rear and Side Walls; Front-Centered Windscreen with Two ADA Openings Clear Anodized Aluminum Finish Reverse Barrel Roof with White Acrylic Glazing and 2.5” Fascia with Integral Gutter 1/4” Clear Tempered Safety Glass Wall Panels.
2. Standard CB have 4’ sump. Double CB have 2’ sump.
Please verify sump depths.
Response: Please use 2’ sumps for all catch basins.
Name and Title of Authorized Rep (Printed) Signature Date
PURCHASING
mailto:purchasing@townofstratford.com http://www.townofstratford.com/
File details come from the government source that posted it. Updated .