This is Addendum #3 to a competitive sealed bid solicitation issued by the Town of Stratford, Connecticut, for the elevation of a two-story residential home above flood elevation at 105 Washington Parkway. The original bid due date has been postponed to 10:00 a.m. on Thursday, August 20, 2026, with sealed bids to be received at the Purchasing Department, 2725 Main Street, Room 104, Stratford, Connecticut 06615. A non-mandatory site meeting was held on July 29, 2026, to allow prospective bidders to assess site conditions. The project timeline extends from the date of award through December 31, 2026. Substantial completion is defined as achievement of five essential project elements: structural piers and foundation installation, house connection to foundation, electricity reconnection, sewer and water reconnection, and stair access with railings to door entrances, with remaining scope items allowable within a reasonable period thereafter without liquidated damages.

This addendum clarifies that neither Connecticut Department of Labor prevailing wage rates nor Federal Davis Bacon wage rates apply to the project, removing the requirement to request a lump sum amount for prevailing wage costs under the original addendum. The owner, Mr. Joseph Sansone, must be named as an additionally insured party on all insurance policies, and builder's risk insurance coverage shall remain in effect until utilities are reconnected and inspected. The project is funded by a U.S. Department of Homeland Security grant with FEMA grant requirements incorporated into the bid specifications.

View the file

Other files

Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BID #2027-01

ADDENDUM #3

ELEVATION OF TWO-STORY RESIDENCE

105 WASHINGTON PARKWAY

12th August, 2026 – It is intended that this Addendum incorporating the following corrections, revisions, additions, deletions and clarifications become part of the Contract Documents.

DUE DATE POSTPONED

Sealed bids will be received by the Purchasing Department at the office of the Purchasing Agent, 2725 Main Street, Room 104, Stratford, Connecticut 06615, up to: 10:00AM, Thursday, 20th August, 2026.

REVISED ITEMS

CT-DOL Prevailing Wage Rates do NOT apply to this project. Delete reference to requesting lump sum amount for bid to include prevailing wage rates under Addendum #1. Prevailing Wage Rates do NOT apply.

Federal Davis Bacon Wage Rates do NOT apply to this project.

Substantial Completion: The project will be deemed substantially complete when the essential elements of the project are properly completed and inspected, including:

1) Structural piers/foundation for house,

2) House properly connected to foundation,

3) Electricity reconnected,

4) Sewer and Water reconnected,

5) Stair access with railings to door entrances.

NOTE: Other scope of work items may be completed within a reasonable time period after the date that liquidated damages would apply, with no damages assigned. Time allotted for the project is from date of award to December 31, 2026.

The Owner, Mr. Joseph Sansone, shall be named additionally insured on all insurance policies.

Builder’s Risk insurance coverage should continue to be in effect until the utilities are reconnected and inspected.