20260520_Asset_Protection_Project_Schedule.pdf

PDF 1010 KB Posted

Attached to
Asset Protection - Painting and Coating
Solicitation number
630-0923-27
Issued by
Trinity County, California

About this file

This is a project schedule document for the Solano County Asset Protection project, a multi-phase construction initiative administered by the County of Solano, Department of General Services - Capital Projects Division. The project encompasses protection of multiple county properties located at Union Avenue, Clay Street, Delaware Street, and Texas Street from stormwater damage through the installation of barrier walls, berms, landscaping, hardscape, flood gates, underground utility reconfiguration, and pump systems. The overall project schedule spans from April 2, 2026, through May 21, 2027, with substantial completion targeted for April 12, 2027. The project is structured in ten phased construction components plus a FEMA closeout phase, with individual phases scheduled between May 2026 and April 2027. Work activities include site preparation, utility management, drainage installation, pavement work, electrical systems, landscaping, security fencing, and finishing operations. The schedule identifies critical milestones for each phase, including Phase 1 completion by August 19, 2026; Phase 4 completion by September 11, 2026; Phase 3 completion by November 30, 2026; and Phase 10 completion by April 8, 2027, with final project completion and FEMA closeout documentation due by May 21, 2027.

The schedule includes detailed procurement activities for multiple bid packages covering demolition, site utilities, concrete, electrical work, earthwork, and fencing and gates, with award periods occurring between April and July 2026. Long-lead procurement items include pump submittals and lead times extending from June through October 2026. The project incorporates level-of-effort activities across ten phases, with concurrent construction execution allowing for parallel work streams. The related contract opportunity specifically solicits proposals for painting and coating services as part of this multi-prime procurement structure. FEMA funding sources this asset protection project, which addresses recurring seasonal flooding impacts to county properties, with the FEMA closeout phase scheduled from April 12, 2027, through May 21, 2027, including final billings, reimbursement requests, and closeout documentation requirements.

View the file

Other files

File Type Posted
20260819_Revision_5_Asset_Protection_Volume_1_Approved.pdf PDF
20260925_Asset_Protection_Painting_and_Coating_-_Project_Manual.pdf PDF
20251211_Volume_2_Parking_and_Security_Improvements_IFC_Rev_1_Drawing_Set_Building_Div_Approved.pdf PDF
20260806_Revision_2_Asset_Protection_Volume_1_Approved.pdf PDF
20251208_Volume_1_Asset_Protection_IFC_Drawing_Set_Building_Div_Approved.pdf PDF
20260811_Revision_3_Asset_Protection_Volume_1_Approved.pdf PDF
20260819_Revision_4_Asset_Protection_Volume_1_Approved.pdf PDF
20260806_Revision_1_Asset_Protection_Volume_1_Approved.pdf PDF
20210903_Geotech_Report_CE&G.pdf PDF
Hazard_Mitigation_Assistance_Contracting_Guidance_for_FEMA-Eligible_Projects,_Non-State_Subrecipients.pdf PDF
Access_Requirements.pdf PDF
20260223_Revised_Section_31_00_00_Embankment_Construction.pdf PDF
20260430_SI_099000-1_Painting_and_Coating_Supplemental_Instruction.pdf PDF
20260819_Revision_4_Asset_Protection_Volume_2_Sheet_C-637_Approved.pdf PDF
20260223_Revised_Section_31_23_16_Structure_Excavation_and_Backfill.pdf PDF
20260819_Revision_4_Asset_Protection_Volume_2_Sheet_C-630_Approved.pdf PDF
20260303_Revised_Section_09_90_00_Painting_and_Coating.pdf PDF
PO_TERMS_CONDITIONS.pdf PDF
Exhibit_C_-_General_Terms_6_12_18.pdf PDF
Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Activity ID Activity Name Start Finish

Solano County Asset Protection - Live FileSolano County Asset Protection - Live File 04-02-26 A 05-21-27

MILESTONESMILESTONES 05-06-26 A 05-21-27

LOE-100 Phase 1 Level of Effort 05-06-26 A 08-19-26

LOE-160 Phase 6 Level of Effort 05-06-26 A 12-15-26

LOE-170 Phase 2 Level of Effort 05-06-26 A 01-27-27

LOE-180 Phase 9 Level of Effort 05-06-26 A 04-09-27

LOE-190 Phase 3 Level of Effort 05-06-26 A 11-30-26

LOE-150 Phase 4 Level of Effort 06-02-26 09-11-26

MILE-110 Phase 6C Completion 07-16-26

MILE-190 Phase 1 Completion 08-19-26

MILE-140 Phase 6A Completion 09-10-26

MILE-130 Phase 4 Completion 09-11-26

LOE-110 Phase 7 Level of Effort 10-19-26 01-08-27

LOE-120 Phase 8 Level of Effort 10-19-26 01-12-27

LOE-140 Phase 5 Level of Effort 10-19-26 01-18-27

MILE-160 Phase 3 Completion 11-30-26

MILE-200 Phase 6 Completion 12-15-26

MILE-210 Phase 6B Completion 12-15-26

MILE-170 Phase 7 Completion 01-08-27

MILE-100 Phase 8 Completion 01-12-27

LOE-130 Phase 10 Level of Effort 01-18-27 04-08-27

MILE-150 Phase 5 Completion 01-18-27

MILE-220 Phase 2 Completion 01-27-27

MILE-180 Phase 10 Completion 04-08-27

MILE-120 Phase 9 Completion 04-12-27

MILE-240 Substantial Completion 04-12-27*

MILE-230 Project Completion 05-21-27

ASSET PROTECTION - FEMAASSET PROTECTION - FEMA 04-02-26 A 05-21-27

AwardsAwards 04-02-26 A 07-07-26

Bid Packages 1 - Demo PackageBid Packages 1 - Demo Package 04-13-26 A 05-29-26

AWARD-220 Submittals and Review Period - Demo Packages 04-13-26 A 05-29-26

Bid Packages 2 - Site UtilitiesBid Packages 2 - Site Utilities 04-02-26 A 05-26-26

AWARD-280 Submittals and Review Period - Site Utilities 04-02-26 A 05-26-26

Bid Packages 3 - ConcreteBid Packages 3 - Concrete 04-02-26 A 05-26-26

AWARD-520 Submittals and Review Period - Concrete 04-02-26 A 05-26-26

Bid Packages 4 - ElectricalBid Packages 4 - Electrical 05-12-26 A 07-07-26

AWARD-450 NTP - Electrical 05-12-26 A 05-22-26

AWARD-460 Submittals and Review Period - Electrical 05-26-26 07-07-26

Bid Packages 5 - Earth WorkBid Packages 5 - Earth Work 04-02-26 A 05-29-26

AWARD-400 Submittals and Review Period - Earth Work 04-02-26 A 05-29-26

Bid Packages 6 - Fencing and GatesBid Packages 6 - Fencing and Gates 04-28-26 A 05-26-26

AWARD-340 Submittals and Review Period - Fencing and Gate 04-28-26 A 05-26-26

ProcurementProcurement 05-04-26 A 10-29-26

PRO-110 Long Lead Pump Submittals and Review 05-04-26 A 06-26-26

PRO-140 Pump Lead Time 06-29-26 10-29-26

PRO-130 Pump Vault Lead Time 06-29-26 10-29-26

PRO-150 Pumps/Electrical/Controls Lead Time 06-29-26 10-29-26

ConstructionConstruction 05-02-26 A 04-10-27

Phased WorkPhased Work 05-02-26 A 04-10-27

Phase 1Phase 1 05-20-26 08-19-26

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug 2026 2027

Phase 1 Level of Effort

Phase 6 Level of Effort

Phase 2 Level of Effort

Phase 9 Level of Effort

Phase 3 Level of Effort

Phase 4 Level of Effort

Phase 6C Completion

Phase 1 Completion

Phase 6A Completion

Phase 4 Completion

Phase 7 Level of Effort

Phase 8 Level of Effort

Phase 5 Level of Effort

Phase 3 Completion

Phase 6 Completion

Phase 6B Completion

Phase 7 Completion

Phase 8 Completion

Phase 10 Level of Effort

Phase 5 Completion

Phase 2 Completion

Phase 10 Completion

Phase 9 Completion

Substantial Completion

Project Completion

Submittals and Review Period - Demo Packages

Submittals and Review Period - Site Utilities

Submittals and Review Period - Concrete

NTP - Electrical

Submittals and Review Period - Electrical

Submittals and Review Period - Earth Work

Submittals and Review Period - Fencing and Gate

Long Lead Pump Submittals and Review

Pump Lead Time

Pump Vault Lead Time

Pumps/Electrical/Controls Lead Time

Data Date: 05-19-26 Print Date: 05-20-26 13:24

SOLANOC-ASSET-LF-1-1-2-1 | #

123 Complete

Milestone

Critical Milestones

Summary Milestones

Actual Work

Remaining Work

Critical Remaining Work

Remaining Level of Effort

Actual Level of Effort

Solano County Asset Protection - Live File

Full Schedule

P1-CON-150 Cap Off Utilities and Irrigation Lines 05-20-26 05-21-26

P1-CON-170 Excavate and Remove Storm Drain Pipes and Basin 05-22-26 06-03-26

P1-CON-180 Rough Grade From 00+00 to 01+75 06-04-26 06-09-26

P1-CON-190 Rough Grade From 01+75 to 05+52 06-10-26 06-15-26

P1-CON-200 Install New Storm Drainage Lines and Basins 06-16-26 06-26-26

P1-CON-210 Fine Grade and Build Berm 06-27-26 07-21-26

P1-CON-220 Install Irrigatiion Mains 07-22-26 07-29-26

P1-CON-230 Install Irrigation Branches 07-30-26 08-01-26

P1-CON-240 Form and Pour Mow Bands at Berm 07-30-26 08-04-26

P1-CON-250 Install Landscaping 08-05-26 08-15-26

P1-CON-260 Remove Construction Fencing and Barriers 08-17-26 08-19-26

Phase 2Phase 2 05-02-26 A 01-27-27

Clay StreetClay Street 05-20-26 01-27-27

P2-CON-CLAY-160 Excavate and Remove Storm Drain Pipes and Basin 05-20-26 05-26-26

P2-CON-CLAY-170 Setup Dewatering 05-20-26 05-22-26

P2-CON-CLAY-180 Rough Grade 05-30-26 06-04-26

P2-CON-CLAY-190 Install New Storm Drainage Lines and Basins 06-05-26 06-18-26

P2-CON-CLAY-200 Excavate Retaining Wall Footings and Flood Gate 06-05-26 06-12-26

P2-CON-CLAY-210 Install New Sewer Line (Add Alt) 06-05-26 06-18-26

P2-CON-CLAY-220 Install Retaining Wall Footings and Flood Gate 06-13-26 06-24-26

P2-CON-CLAY-230 Backfill Retaining Wall Footings and Form Retaining Walls 06-13-26 06-24-26

P2-CON-CLAY-240 Inspect Underground Utilities 07-08-26 07-09-26

P2-CON-CLAY-250 Backfill Storm Drain Trenches Backfill to Grade 07-10-26 07-21-26

P2-CON-CLAY-260 Trench for Electrical 07-22-26 07-27-26

P2-CON-CLAY-270 Install Underground Conduits 07-28-26 08-01-26

P2-CON-CLAY-280 Inspect Underground Electrical 08-03-26 08-04-26

P2-CON-CLAY-290 Backfill Electrical Trench 08-05-26 08-11-26

P2-CON-CLAY-300 Complete Fine Grade 08-12-26 08-25-26

P2-CON-CLAY-310 Pour Retaining Walls 08-12-26 08-13-26

P2-CON-CLAY-320 Form and Pour Curbs 08-26-26 09-09-26

P2-CON-CLAY-330 Pull Electrical 08-26-26 08-31-26

P2-CON-CLAY-340 Form and Pour Sidewalks 09-10-26 09-21-26

P2-CON-CLAY-350 Place AC Pavement 01-12-27 01-18-27

P2-CON-CLAY-360 Paint Striping 01-18-27 01-21-27

P2-CON-CLAY-370 Install Signage 01-18-27 01-23-27

P2-CON-CLAY-390 Paint and Coatings 01-18-27 01-23-27

P2-CON-CLAY-380 Remove Construction Fencing and Barriers 01-23-27 01-27-27

Texas StreetTexas Street 05-02-26 A 09-23-26

Washington Street SewerWashington Street Sewer 05-02-26 A 07-27-26

P2-CON-TEXAS-410Wait ing on School Closure 05-02-26 A 06-03-26

P2-CON-TEXAS-100Call 811 and Markout Utilities 06-04-26 06-06-26

P2-CON-WASH-100Setup Construction Fencing and Barriers 06-08-26 06-08-26

P2-CON-WASH-110Setup Temporary Access 06-08-26 06-08-26

P2-CON-WASH-120Setup SWPPP 06-09-26 06-09-26

P2-CON-WASH-130Demo Existing Pavement 06-10-26 06-12-26

P2-CON-WASH-140Excavate and Remove New Sewer Line (Add Alt) 06-13-26 06-18-26

P2-CON-WASH-150Setup Dewatering 06-13-26 06-13-26

P2-CON-WASH-160Rough Grade 06-19-26 06-20-26

P2-CON-WASH-170Install New Sewer Line (Add Alt) 06-22-26 07-15-26

P2-CON-WASH-180Complete Fine Grade 07-16-26 07-17-26

P2-CON-WASH-190Place AC Pavement 07-18-26 07-20-26

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug 2026 2027

Cap Off Utilities and Irrigation Lines

Excavate and Remove Storm Drain Pipes and Basin

Rough Grade From 00+00 to 01+75

Rough Grade From 01+75 to 05+52

Install New Storm Drainage Lines and Basins

Fine Grade and Build Berm

Install Irrigatiion Mains

Install Irrigation Branches

Form and Pour Mow Bands at Berm

Install Landscaping

Remove Construction Fencing and Barriers

Excavate and Remove Storm Drain Pipes and Basin

Setup Dewatering

Rough Grade

Install New Storm Drainage Lines and Basins

Excavate Retaining Wall Footings and Flood Gate

Install New Sewer Line (Add Alt)

Install Retaining Wall Footings and Flood Gate

Backfill Retaining Wall Footings and Form Retaining Walls

Inspect Underground Utilities

Backfill Storm Drain Trenches Backfill to Grade

Trench for Electrical

Install Underground Conduits

Inspect Underground Electrical

Backfill Electrical Trench

Complete Fine Grade

Pour Retaining Walls

Form and Pour Curbs

Pull Electrical

Form and Pour Sidewalks

Place AC Pavement

Paint Striping

Install Signage

Paint and Coatings

Remove Construction Fencing and Barriers

Wait ing on School Closure

Call 811 and Markout Utilities

Setup Construction Fencing and Barriers

Setup Temporary Access

Setup SWPPP

Demo Existing Pavement

Excavate and Remove New Sewer Line (Add Alt)

Setup Dewatering

Rough Grade

Install New Sewer Line (Add Alt)

Complete Fine Grade

Place AC Pavement

Data Date: 05-19-26 Print Date: 05-20-26 13:24

SOLANOC-ASSET-LF-1-1-2-1 | #

123 Complete

Milestone

Critical Milestones

Summary Milestones

Actual Work

Remaining Work

Critical Remaining Work

Remaining Level of Effort

Actual Level of Effort

P2-CON-WASH-200Paint Striping 07-21-26 07-22-26

P2-CON-WASH-210Install Signage 07-21-26 07-22-26

P2-CON-WASH-220Paint and Coatings 07-21-26 07-24-26

P2-CON-WASH-230Remove Construction Fencing and Barriers 07-25-26 07-27-26

Texas SewerTexas Sewer 06-04-26 07-30-26

P2-CON-TEXAS-260Setup Construction Fencing and Barriers 06-04-26 06-04-26

P2-CON-TEXAS-270Setup Temporary Access 06-04-26 06-04-26

P2-CON-TEXAS-280Setup SWPPP 06-05-26 06-05-26

P2-CON-TEXAS-290Demo Existing Pavement 06-10-26 06-12-26

P2-CON-TEXAS-310Setup Dewatering 06-13-26 06-13-26

P2-CON-TEXAS-300Excavate and Remove New Sewer Line (Add Alt) 06-19-26 06-24-26

P2-CON-TEXAS-330Install New Sewer Line (Add Alt) 06-25-26 07-18-26

P2-CON-TEXAS-320Rough Grade 07-20-26 07-21-26

P2-CON-TEXAS-340Complete Fine Grade 07-20-26 07-21-26

P2-CON-TEXAS-350Place AC Pavement 07-22-26 07-23-26

P2-CON-TEXAS-360Paint Striping 07-24-26 07-25-26

P2-CON-TEXAS-370Install Signage 07-24-26 07-25-26

P2-CON-TEXAS-400Paint and Coatings 07-24-26 07-28-26

P2-CON-TEXAS-380Remove Construction Fencing and Barriers 07-29-26 07-30-26

Storm DrainStorm Drain 07-31-26 09-23-26

P2-CON-TEXAS-110Setup Construction Fencing and Barriers 07-31-26 07-31-26

P2-CON-TEXAS-120Setup Temporary Access 07-31-26 07-31-26

P2-CON-TEXAS-130Setup SWPPP 08-01-26 08-01-26

P2-CON-TEXAS-140Clear and Grub 08-03-26 08-04-26

P2-CON-TEXAS-150Demo Existing Pavement 08-05-26 08-07-26

P2-CON-TEXAS-160Excavate and Remove Storm Drain Pipes and Basin 08-08-26 08-13-26

P2-CON-TEXAS-170Setup Dewatering 08-08-26 08-08-26

P2-CON-TEXAS-180Rough Grade 08-14-26 08-15-26

P2-CON-TEXAS-190Install New Storm Drainage Lines and Basins 08-17-26 08-29-26

P2-CON-TEXAS-200Backfill Storm Drain Trenches and Fine Grade 08-31-26 09-11-26

P2-CON-TEXAS-210Complete Fine Grade 09-12-26 09-14-26

P2-CON-TEXAS-220Place AC Pavement 09-15-26 09-16-26

P2-CON-TEXAS-230Paint Striping 09-17-26 09-18-26

P2-CON-TEXAS-240Install Signage 09-17-26 09-18-26

P2-CON-TEXAS-390Paint and Coatings 09-17-26 09-21-26

P2-CON-TEXAS-250Remove Construction Fencing and Barriers 09-22-26 09-23-26

Phase 3Phase 3 05-06-26 A 11-30-26

P3-CON-150 Demo Existing Pavement and Sidewalk 05-06-26 A 06-16-26

P3-CON-460 Wait ing on Temporary Gates 05-06-26 A 06-01-26

P3-CON-120 Setup Temporary Access 06-02-26 06-04-26

P3-CON-140 Cap Off Utilities and Irrigation Lines 06-17-26 06-18-26

P3-CON-160 Rough Grade 06-19-26 06-24-26

P3-CON-170 Excavate and Remove Storm Drain Pipes and Basin 06-25-26 06-30-26

P3-CON-180 Install New Storm Drainage Lines and Basins 07-01-26 07-18-26

P3-CON-190 Backfill Storm Drain Trenches and to Grade 07-20-26 07-30-26

P3-CON-200 Trench for Shallow Underground Electrical 07-31-26 08-07-26

P3-CON-210 Excavate Retaining Wall Footings and Flood Gate 07-31-26 08-07-26

P3-CON-220 Install Underground Electrical Conduit 08-08-26 08-13-26

P3-CON-230 Install Retaining Wall Footings and Flood Gate 08-08-26 08-15-26

P3-CON-250 Backfill Electrical Trench to Grade 08-14-26 08-25-26

P3-CON-260 Pull Electrical Wire 08-14-26 08-27-26

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug 2026 2027

Paint Striping

Install Signage

Paint and Coatings

Remove Construction Fencing and Barriers

Setup Construction Fencing and Barriers

Setup Temporary Access

Setup SWPPP

Demo Existing Pavement

Setup Dewatering

Excavate and Remove New Sewer Line (Add Alt)

Install New Sewer Line (Add Alt)

Rough Grade

Complete Fine Grade

Place AC Pavement

Paint Striping

Install Signage

Paint and Coatings

Remove Construction Fencing and Barriers

Setup Construction Fencing and Barriers

Setup Temporary Access

Setup SWPPP

Clear and Grub

Demo Existing Pavement

Excavate and Remove Storm Drain Pipes and Basin

Setup Dewatering

Rough Grade

Install New Storm Drainage Lines and Basins

Backfill Storm Drain Trenches and Fine Grade

Complete Fine Grade

Place AC Pavement

Paint Striping

Install Signage

Paint and Coatings

Remove Construction Fencing and Barriers

Demo Existing Pavement and Sidewalk

Waiting on Temporary Gates

Setup Temporary Access

Cap Off Utilities and Irrigation Lines

Rough Grade

Excavate and Remove Storm Drain Pipes and Basin

Install New Storm Drainage Lines and Basins

Backfill Storm Drain Trenches and to Grade

Trench for Shallow Underground Electrical

Excavate Retaining Wall Footings and Flood Gate

Install Underground Electrical Conduit

Install Retaining Wall Footings and Flood Gate

Backfill Electrical Trench to Grade

Pull Electrical Wire

Data Date: 05-19-26 Print Date: 05-20-26 13:24

SOLANOC-ASSET-LF-1-1-2-1 | #

123 Complete

Milestone

Critical Milestones

Summary Milestones

Actual Work

Remaining Work

Critical Remaining Work

Remaining Level of Effort

Actual Level of Effort

P3-CON-270 Install Irrigations Mains 08-14-26 08-21-26

P3-CON-240 Backfill Retaining Wall Footings and Form Retaining Walls 08-17-26 08-25-26

P3-CON-290 Install Irrigation Branches 08-22-26 09-02-26

P3-CON-280 Complete Fine Grade 08-26-26 08-31-26

P3-CON-300 Form and Pour Curbs 09-01-26 09-12-26

P3-CON-310 Form and Pour Sidewalks 09-14-26 09-24-26

P3-CON-320 Set Fence Pole Bases and Poles 09-14-26 09-24-26

P3-CON-330 Excavate for Light Pole Bases 09-14-26 09-18-26

P3-CON-340 Set Cages and Finish Conduit 09-19-26 09-24-26

P3-CON-350 Install Fencing 09-25-26 10-03-26

P3-CON-360 Form and Pour Light Pole Bases 09-25-26 10-05-26

P3-CON-370 Set Light Poles 10-06-26 10-10-26

P3-CON-380 Place AC Pavement 10-12-26 10-17-26

P3-CON-390 Pull Wire for Security 10-19-26 10-22-26

P3-CON-400 Install Landscaping 10-23-26 10-30-26

P3-CON-410 Install Vehicle Gates and Card Readers 10-23-26 10-30-26

P3-CON-420 Paint Parking Striping 10-31-26 11-12-26

P3-CON-450 Paint and Coatings 10-31-26 11-05-26

P3-CON-430 Set Wheel Stops 11-13-26 11-24-26

P3-CON-440 Remove Construction Fencing and Barriers 11-25-26 11-30-26

Phase 4Phase 4 06-02-26 09-11-26

P4-CON-100 Call 811 and Markout Utilities 06-02-26 06-05-26

P4-CON-110 Setup Construction Fencing and Barriers 06-06-26 06-06-26

P4-CON-120 Setup Temporary Access 06-06-26 06-06-26

P4-CON-130 Setup SWPPP 06-08-26 06-08-26

P4-CON-140 Clear and Grub 06-09-26 06-10-26

P4-CON-150 Cap Off Utilities and Irrigation Lines 06-11-26 06-12-26

P4-CON-160 Demo Existing Pavement and Sidewalk 06-13-26 06-16-26

P4-CON-170 Excavate and Remove Storm Drain Pipes and Basin 06-17-26 06-19-26

P4-CON-180 Rough Grade 06-20-26 06-22-26

P4-CON-190 Install New Storm Drainage Lines and Basins 06-23-26 06-25-26

P4-CON-200 Trench for Electrical for Gate 06-23-26 06-23-26

P4-CON-210 Install Electrical Conduit for Electrical for Gate 06-24-26 06-26-26

P4-CON-220 Backfill Storm Drain Trenches and Fine Grade 06-26-26 07-08-26

P4-CON-230 Install Footing for Retaining Wall and Fencing 06-27-26 07-06-26

P4-CON-240 Trench for Electrical 07-09-26 07-10-26

P4-CON-250 Install Underground Electrical Conduit 07-11-26 07-13-26

P4-CON-260 Install Irrigations Mains 07-11-26 07-14-26

P4-CON-270 Backfill Electrical Trench 07-14-26 07-17-26

P4-CON-280 Complete Fine Grade 07-18-26 07-20-26

P4-CON-290 Form and Pour Perimeter Fencing Posts 07-18-26 07-23-26

P4-CON-300 Form and Pour Curbs 07-24-26 08-04-26

P4-CON-310 Set Lightpoles Bases, Light Poles and Bollards 08-05-26 08-07-26

P4-CON-320 Form and Pour Sidewalks 08-08-26 08-19-26

P4-CON-330 Place AC Pavement 08-20-26 08-21-26

P4-CON-340 Pull Electrical Wire and Security Wire 08-20-26 08-21-26

P4-CON-350 Paint Parking Striping 08-22-26 08-26-26

P4-CON-360 Install Landscaping 08-22-26 08-26-26

P4-CON-370 Pull Wire for Lights and Security 08-22-26 08-24-26

P4-CON-430 Paint and Coatings 08-22-26 08-27-26

P4-CON-380 Install Security Fencing and Gates 08-27-26 09-08-26

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug 2026 2027

Install Irrigations Mains

Backfill Retaining Wall Footings and Form Retaining Walls

Install Irrigation Branches

Complete Fine Grade

Form and Pour Curbs

Form and Pour Sidewalks

Set Fence Pole Bases and Poles

Excavate for Light Pole Bases

Set Cages and Finish Conduit

Install Fencing

Form and Pour Light Pole Bases

Set Light Poles

Place AC Pavement

Pull Wire for Security

Install Landscaping

Install Vehicle Gates and Card Readers

Paint Parking Striping

Paint and Coatings

Set Wheel Stops

Remove Construction Fencing and Barriers

Call 811 and Markout Utilities

Setup Construction Fencing and Barriers

Setup Temporary Access

Setup SWPPP

Clear and Grub

Cap Off Utilities and Irrigation Lines

Demo Existing Pavement and Sidewalk

Excavate and Remove Storm Drain Pipes and Basin

Rough Grade

Install New Storm Drainage Lines and Basins

Trench for Electrical for Gate

Install Electrical Conduit for Electrical for Gate

Backfill Storm Drain Trenches and Fine Grade

Install Footing for Retaining Wall and Fencing

Trench for Electrical

Install Underground Electrical Conduit

Install Irrigations Mains

Backfill Electrical Trench

Complete Fine Grade

Form and Pour Perimeter Fencing Posts

Form and Pour Curbs

Set Lightpoles Bases, Light Poles and Bollards

Form and Pour Sidewalks

Place AC Pavement

Pull Electrical Wire and Security Wire

Paint Parking Striping

Install Landscaping

Pull Wire for Lights and Security

Paint and Coatings

Install Security Fencing and Gates

Data Date: 05-19-26 Print Date: 05-20-26 13:24

SOLANOC-ASSET-LF-1-1-2-1 | #

123 Complete

Milestone

Critical Milestones

Summary Milestones

Actual Work

Remaining Work

Critical Remaining Work

Remaining Level of Effort

Actual Level of Effort

P4-CON-390 Install Irrigation Branches 08-28-26 08-29-26

P4-CON-400 Set Wheel Stops 08-31-26 09-03-26

P4-CON-410 Install Card Readers 09-09-26 09-10-26

P4-CON-420 Remove Construction Fencing and Barriers 09-11-26 09-11-26

Phase 5Phase 5 10-19-26 01-18-27

P5-CON-100 Call 811 and Markout Utilities 10-19-26 10-22-26

P5-CON-110 Setup Construction Fencing and Barriers 10-23-26 10-23-26

P5-CON-120 Setup Temporary Access 10-23-26 10-23-26

P5-CON-130 Setup SWPPP 10-24-26 10-24-26

P5-CON-140 Clear and Grub 10-26-26 10-27-26

P5-CON-150 Cap Off Utilities and Irrigation Lines 10-28-26 10-29-26

P5-CON-160 Demo Existing Pavement and Sidewalk 10-30-26 11-02-26

P5-CON-170 Excavate and Remove Storm Drain Pipes and Basin 11-03-26 11-07-26

P5-CON-180 Rough Grade 11-09-26 11-12-26

P5-CON-190 Install New Storm Drainage Lines and Basins 11-13-26 11-18-26

P5-CON-200 Backfill Storm Drain Trenches and Fine Grade 11-19-26 12-02-26

P5-CON-210 Trench for Electrical 12-03-26 12-08-26

P5-CON-220 Install Underground Electrical Conduit 12-09-26 12-11-26

P5-CON-230 Install Irrigations Mains 12-09-26 12-11-26

P5-CON-240 Backfill Electrical Trench 12-12-26 12-15-26

P5-CON-250 Complete Fine Grade 12-16-26 12-17-26

P5-CON-260 Form and Pour Curbs 12-18-26 12-26-26

P5-CON-270 Form and Pour Sidewalks 12-28-26 01-04-27

P5-CON-280 Place AC Pavement 01-05-27 01-06-27

P5-CON-290 Paint Parking Striping 01-07-27 01-08-27

P5-CON-300 Install Landscaping 01-07-27 01-07-27

P5-CON-310 Pull Wire and Makeup for Lights and Security 01-07-27 01-11-27

P5-CON-350 Paint and Coatings 01-07-27 01-12-27

P5-CON-320 Install Irrigation Branches 01-13-27 01-13-27

P5-CON-330 Set Wheel Stops 01-14-27 01-15-27

P5-CON-340 Remove Construction Fencing and Barriers 01-16-27 01-18-27

Phase 6Phase 6 05-12-26 A 12-15-26

Phase 6A North Oval and PlatformPhase 6A North Oval and Platform 05-12-26 A 09-10-26

P6A-CON-160 Demo Existing Pavement and Sidewalk 05-12-26 A 05-20-26

P6A-CON-150 Cap Off Utilities and Irrigation Lines 05-21-26 05-22-26

P6A-CON-170 Rough Grade 05-30-26 06-04-26

P6A-CON-180 Trench for Electrical 06-05-26 06-06-26

P6A-CON-190 Install Underground Electrical Conduit 07-08-26 07-09-26

P6A-CON-200 Set Pull and Junction Boxes 07-10-26 07-13-26

P6A-CON-210 Backfill Electrical Trench 07-14-26 07-17-26

P6A-CON-220 Set Lightpoles Bases, Light Poles and Bollards 07-18-26 07-20-26

P6A-CON-230 Trench and Install Storm Drain Line 07-18-26 07-21-26

P6A-CON-240 Install Irrigations Mains 07-21-26 07-22-26

P6A-CON-250 Backfill Storm Drain Line 07-22-26 07-23-26

P6A-CON-260 Form and Pour Curbs 07-23-26 08-03-26

P6A-CON-270 Form and Pour Foundations for Stairs and Walls 07-24-26 08-04-26

P6A-CON-280 Form and Pour Slab 08-04-26 08-14-26

P6A-CON-290 Backfill Foundations 08-05-26 08-08-26

P6A-CON-300 Form and Pour Stairs 08-10-26 08-17-26

P6A-CON-310 Fine Grade Site 08-15-26 08-17-26

P6A-CON-320 Form and Pour Sidewalks 08-18-26 08-24-26

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug 2026 2027

Install Irrigation Branches

Set Wheel Stops

Install Card Readers

Remove Construction Fencing and Barriers

Call 811 and Markout Utilities

Setup Construction Fencing and Barriers

Setup Temporary Access

Setup SWPPP

Clear and Grub

Cap Off Utilities and Irrigation Lines

Demo Existing Pavement and Sidewalk

Excavate and Remove Storm Drain Pipes and Basin

Rough Grade

Install New Storm Drainage Lines and Basins

Backfill Storm Drain Trenches and Fine Grade

Trench for Electrical

Install Underground Electrical Conduit

Install Irrigations Mains

Backfill Electrical Trench

Complete Fine Grade

Form and Pour Curbs

Form and Pour Sidewalks

Place AC Pavement

Paint Parking Striping

Install Landscaping

Pull Wire and Makeup for Lights and Security

Paint and Coatings

Install Irrigation Branches

Set Wheel Stops

Remove Construction Fencing and Barriers

Demo Existing Pavement and Sidewalk

Cap Off Utilities and Irrigation Lines

Rough Grade

Trench for Electrical

Install Underground Electrical Conduit

Set Pull and Junction Boxes

Backfill Electrical Trench

Set Lightpoles Bases, Light Poles and Bollards

Trench and Install Storm Drain Line

Install Irrigations Mains

Backfill Storm Drain Line

Form and Pour Curbs

Form and Pour Foundations for Stairs and Walls

Form and Pour Slab

Backfill Foundations

Form and Pour Stairs

Fine Grade Site

Form and Pour Sidewalks

Data Date: 05-19-26 Print Date: 05-20-26 13:24

SOLANOC-ASSET-LF-1-1-2-1 | #

123 Complete

Milestone

Critical Milestones

Summary Milestones

Actual Work

Remaining Work

Critical Remaining Work

Remaining Level of Effort

Actual Level of Effort

P6A-CON-330 Pull Wire and Makeup for Lights and Security 08-25-26 08-27-26

P6A-CON-340 Install Pre-Fab Seats 08-25-26 08-27-26

P6A-CON-350 Install Landscaping 08-28-26 09-02-26

P6A-CON-360 Install Irrigation Branches 09-03-26 09-05-26

P6A-CON-370 Remove Construction Fencing and Barriers 09-08-26 09-10-26

Phase 6B South OvalPhase 6B South Oval 09-11-26 12-15-26

P6B-CON-100 Setup Construction Fencing and Barriers 09-11-26 09-14-26

P6B-CON-110 Setup Temporary Access 09-15-26 09-19-26

P6B-CON-120 Setup SWPPP 09-21-26 09-21-26

P6B-CON-130 Clear and Grub 09-22-26 09-23-26

P6B-CON-140 Cap Off Utilities and Irrigation Lines 09-24-26 09-25-26

P6B-CON-150 Demo Existing Pavement and Sidewalk 09-26-26 09-29-26

P6B-CON-160 Rough Grade 09-30-26 10-10-26

P6B-CON-170 Trench for Electrical 10-12-26 10-14-26

P6B-CON-180 Install Underground Electrical Conduit 10-15-26 10-17-26

P6B-CON-190 Set Pull and Junction Boxes 10-19-26 10-20-26

P6B-CON-200 Backfill Electrical Trench 10-21-26 10-24-26

P6B-CON-210 Set Lightpoles Bases, Light Poles and Bollards 10-26-26 10-30-26

P6B-CON-220 Install Irrigations Mains 10-31-26 11-04-26

P6B-CON-230 Fine Grade Site 10-31-26 11-02-26

P6B-CON-240 Form and Pour Curbs 11-05-26 11-10-26

P6B-CON-250 Form and Pour Sidewalks 11-12-26 11-23-26

P6B-CON-260 Pull Electrical Wire and Security Wire 11-24-26 11-30-26

P6B-CON-270 Install Landscaping 12-01-26 12-08-26

P6B-CON-280 Install Irrigation Branches 12-09-26 12-11-26

P6B-CON-290 Remove Construction Fencing and Barriers 12-12-26 12-15-26

Phase 6C Law and Justice CenterPhase 6C Law and Justice Center 05-20-26 07-16-26

P6C-CON-100 Setup Construction Fencing and Barriers 05-20-26 05-20-26

P6C-CON-110 Setup Temporary Access 05-21-26 05-21-26

P6C-CON-120 Setup SWPPP 05-22-26 05-22-26

P6C-CON-130 Clear and Grub 05-23-26 05-26-26

P6C-CON-140 Cap Off Utilities and Irrigation Lines 05-27-26 05-28-26

P6C-CON-150 Demo Existing Pavement and Sidewalk 05-29-26 06-01-26

P6C-CON-160 Rough Grade 06-02-26 06-03-26

P6C-CON-170 Fine Grade Site 06-04-26 06-05-26

P6C-CON-180 Form and Pour Curbs and Wall 06-06-26 06-23-26

P6C-CON-190 Form and Pour Sidewalks 06-24-26 07-06-26

P6C-CON-200 Install Expansion Joints 07-07-26 07-09-26

P6C-CON-210 Install Landscaping 07-10-26 07-11-26

P6C-CON-220 Install Signage 07-13-26 07-13-26

P6C-CON-230 Remove Construction Fencing and Barriers 07-14-26 07-16-26

Phase 7Phase 7 10-19-26 01-08-27

P7-CON-100 Call 811 and Markout Utilities 10-19-26 10-19-26

P7-CON-110 Setup Construction Fencing and Barriers 10-20-26 10-20-26

P7-CON-120 Setup Temporary Access 10-20-26 10-20-26

P7-CON-130 Setup SWPPP 10-21-26 10-21-26

P7-CON-140 Clear and Grub 10-22-26 10-23-26

P7-CON-150 Cap Off Utilities and Irrigation Lines 10-24-26 10-26-26

P7-CON-160 Demo Existing Pavement and Sidewalk 10-27-26 10-29-26

P7-CON-170 Excavate and Remove Storm Drain Pipes and Basin 10-30-26 11-04-26

P7-CON-180 Rough Grade 11-05-26 11-06-26

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug 2026 2027

Pull Wire and Makeup for Lights and Security

Install Pre-Fab Seats

Install Landscaping

Install Irrigation Branches

Remove Construction Fencing and Barriers

Setup Construction Fencing and Barriers

Setup Temporary Access

Setup SWPPP

Clear and Grub

Cap Off Utilities and Irrigation Lines

Demo Existing Pavement and Sidewalk

Rough Grade

Trench for Electrical

Install Underground Electrical Conduit

Set Pull and Junction Boxes

Backfill Electrical Trench

Set Lightpoles Bases, Light Poles and Bollards

Install Irrigations Mains

Fine Grade Site

Form and Pour Curbs

Form and Pour Sidewalks

Pull Electrical Wire and Security Wire

Install Landscaping

Install Irrigation Branches

Remove Construction Fencing and Barriers

Setup Construction Fencing and Barriers

Setup Temporary Access

Setup SWPPP

Clear and Grub

Cap Off Utilities and Irrigation Lines

Demo Existing Pavement and Sidewalk

Rough Grade

Fine Grade Site

Form and Pour Curbs and Wall

Form and Pour Sidewalks

Install Expansion Joints

Install Landscaping

Install Signage

Remove Construction Fencing and Barriers

Call 811 and Markout Utilities

Setup Construction Fencing and Barriers

Setup Temporary Access

Setup SWPPP

Clear and Grub

Cap Off Utilities and Irrigation Lines

Demo Existing Pavement and Sidewalk

Excavate and Remove Storm Drain Pipes and Basin

Rough Grade

Data Date: 05-19-26 Print Date: 05-20-26 13:24

SOLANOC-ASSET-LF-1-1-2-1 | #

123 Complete

Milestone

Critical Milestones

Summary Milestones

Actual Work

Remaining Work

Critical Remaining Work

Remaining Level of Effort

Actual Level of Effort

P7-CON-190 Install New Storm Drainage Lines and Basins 11-07-26 11-19-26

P7-CON-200 Install Footing for Barrier Wall 11-07-26 11-19-26

P7-CON-210 Backfill Storm Drain Trenches and Fine Grade 11-20-26 11-25-26

P7-CON-230 Trench for Electrical 11-20-26 11-21-26

P7-CON-220 Form and Pour Barrier Wall 1A and 1B 11-20-26 11-28-26

P7-CON-240 Install Underground Electrical Conduit 11-28-26 11-30-26

P7-CON-250 Backfill Electrical Trench 12-01-26 12-02-26

P7-CON-280 Install Irrigations Mains 12-01-26 12-02-26

P7-CON-260 Complete Fine Grade 12-03-26 12-04-26

P7-CON-270 Form and Pour Footings for Fencing 12-03-26 12-05-26

P7-CON-290 Backfill Around Footings 12-07-26 12-07-26

P7-CON-300 Form and Pour Curbs 12-08-26 12-14-26

P7-CON-310 Set Lightpoles Bases, Light Poles and Bollards 12-15-26 12-18-26

P7-CON-320 Form and Pour Sidewalks 12-15-26 12-21-26

P7-CON-330 Pull Electrical Wire and Security Wire 12-19-26 12-22-26

P7-CON-340 Place AC Pavement 12-22-26 12-28-26

P7-CON-350 Paint Parking Striping 12-29-26 12-29-26

P7-CON-360 Install Landscaping 12-29-26 12-31-26

P7-CON-370 Pull Wire for Lights and Security 12-29-26 12-30-26

P7-CON-410 Paint and Coatings 12-29-26 01-02-27

P7-CON-380 Install Irrigation Branches 01-02-27 01-04-27

P7-CON-390 Set Wheel Stops 01-05-27 01-05-27

P7-CON-400 Remove Construction Fencing and Barriers 01-06-27 01-08-27

Phase 8Phase 8 10-19-26 01-12-27

P8-CON-100 Call 811 and Markout Utilities 10-19-26 10-19-26

P8-CON-110 Setup Construction Fencing and Barriers 10-20-26 10-20-26

P8-CON-120 Setup Temporary Access 10-20-26 10-20-26

P8-CON-130 Setup SWPPP 10-21-26 10-21-26

P8-CON-140 Clear and Grub 10-22-26 10-23-26

P8-CON-150 Demo Existing Pavement and Sidewalk 10-24-26 10-29-26

P8-CON-160 Excavate and Remove Storm Drain Pipes and Basin 10-30-26 11-04-26

P8-CON-170 Setup Dewatering 10-30-26 10-30-26

P8-CON-180 Rough Grade 11-05-26 11-09-26

P8-CON-190 Install New Storm Drainage Lines and Basins 11-10-26 11-16-26

P8-CON-200 Backfill Storm Drain Trenches and Fine Grade 11-17-26 11-21-26

P8-CON-210 Complete Fine Grade 11-23-26 11-25-26

P8-CON-220 Install Footing for Barrier Wall 11-23-26 12-05-26

P8-CON-230 Form and Pour Barrier Wall 1A and 1B 12-07-26 12-12-26

P8-CON-240 Form and Pour Curbs 12-14-26 12-22-26

P8-CON-250 Form and Pour Sidewalks 12-23-26 12-29-26

P8-CON-260 Place AC Pavement 12-30-26 01-05-27

P8-CON-270 Paint Striping 01-06-27 01-11-27

P8-CON-280 Install Signage 01-06-27 01-08-27

P8-CON-300 Paint and Coatings 01-06-27 01-11-27

P8-CON-290 Remove Construction Fencing and Barriers 01-12-27 01-12-27

Phase 9Phase 9 05-20-26 04-10-27

Phase 9APhase 9A 05-20-26 12-29-26

P9A-CON-120 Cap Off Utilities and Irrigation Lines 05-20-26 05-21-26

P9A-CON-110 Safe Off 07-08-26 07-08-26

P9A-CON-160 Clear and Grub 07-09-26 07-09-26

P9A-CON-170 Demo Site 07-10-26 07-15-26

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug 2026 2027

Install New Storm Drainage Lines and Basins

Install Footing for Barrier Wall

Backfill Storm Drain Trenches and Fine Grade

Trench for Electrical

Form and Pour Barrier Wall 1A and 1B

Install Underground Electrical Conduit

Backfill Electrical Trench

Install Irrigations Mains

Complete Fine Grade

Form and Pour Footings for Fencing

Backfill Around Footings

Form and Pour Curbs

Set Lightpoles Bases, Light Poles and Bollards

Form and Pour Sidewalks

Pull Electrical Wire and Security Wire

Place AC Pavement

Paint Parking Striping

Install Landscaping

Pull Wire for Lights and Security

Paint and Coatings

Install Irrigation Branches

Set Wheel Stops

Remove Construction Fencing and Barriers

Call 811 and Markout Utilities

Setup Construction Fencing and Barriers

Setup Temporary Access

Setup SWPPP

Clear and Grub

Demo Existing Pavement and Sidewalk

Excavate and Remove Storm Drain Pipes and Basin

Setup Dewatering

Rough Grade

Install New Storm Drainage Lines and Basins

Backfill Storm Drain Trenches and Fine Grade

Complete Fine Grade

Install Footing for Barrier Wall

Form and Pour Barrier Wall 1A and 1B

Form and Pour Curbs

Form and Pour Sidewalks

Place AC Pavement

Paint Striping

Install Signage

Paint and Coatings

Remove Construction Fencing and Barriers

Cap Off Utilities and Irrigation Lines

Safe Off

Clear and Grub

Demo Site

Data Date: 05-19-26 Print Date: 05-20-26 13:24

SOLANOC-ASSET-LF-1-1-2-1 | #

123 Complete

Milestone

Critical Milestones

Summary Milestones

Actual Work

Remaining Work

Critical Remaining Work

Remaining Level of Effort

Actual Level of Effort

P9A-CON-180 Rough Grade Area 9A 07-16-26 07-24-26

P9A-CON-190 Excavate Underground Storm Drain 07-25-26 08-03-26

P9A-CON-200 Install Storm Drain Lines 08-04-26 08-04-26

P9A-CON-210 Install Underground Electrical 08-05-26 08-05-26

P9A-CON-220 Install New Pump Vault 10-29-26 10-30-26

P9A-CON-230 Install New Pump 10-30-26 10-31-26

P9A-CON-240 Connect Storm Drain Lines to New Pump 10-31-26 11-02-26

P9A-CON-250 Connect Electrical Lines to New Pump 11-02-26 11-03-26

P9A-CON-260 Connect Storm Drain Lines to New Pump 11-03-26 11-04-26

P9A-CON-270 Excavate Footing for Wall 11-04-26 11-07-26

P9A-CON-280 Fine Grade and Build Berm 11-04-26 11-14-26

P9A-CON-290 Install Footing for Wall 11-07-26 11-09-26

P9A-CON-300 Form and Pour Wall 11-09-26 11-21-26

P9A-CON-310 Install Security Fencing 11-21-26 11-23-26

P9A-CON-320 Pull Wire for Lights and Security 11-23-26 11-24-26

P9A-CON-330 Form and Pour Curbs 11-24-26 12-08-26

P9A-CON-340 Form and Pour Sidewalks 12-08-26 12-19-26

P9A-CON-350 Paint Parking Striping 12-19-26 12-21-26

P9A-CON-390 Paint and Coatings 12-19-26 12-24-26

P9A-CON-360 Install Landscaping 12-24-26 12-26-26

P9A-CON-370 Set Wheel Stops 12-26-26 12-28-26

P9A-CON-380 Remove Construction Fencing and Barriers 12-28-26 12-29-26

Phase 9BPhase 9B 07-08-26 04-10-27

P9B1-CON-110 Safe Off 07-08-26 07-08-26

P9B1-CON-160 Clear and Grub 07-09-26 07-09-26

P9B1-CON-130 Cap Off Utilities and Irrigation Lines 07-09-26 07-10-26

P9B1-CON-140 Setup Temporary Access 07-09-26 07-09-26

P9B1-CON-170 Demo Site 07-11-26 07-16-26

P9B1-CON-180 Install Sanitary By-Pass 07-17-26 07-22-26

Area 9B1Area 9B1 07-23-26 01-21-27

P9B1-CON-190 Excavate and Install Shoring 07-23-26 08-03-26

P9B1-CON-200 Install Foundations 08-04-26 08-08-26

P9B1-CON-210 Install Pre-Cast Rings 10-29-26 11-04-26

P9B1-CON-220 Install SD Piping 11-04-26 11-06-26

P9B1-CON-230 Install Pumps 11-06-26 11-12-26

P9B1-CON-240 Install Electrical 11-12-26 11-18-26

P9B1-CON-250 Install Waterproofing 11-18-26 11-23-26

P9B1-CON-260 Backfill and Strip Forms 11-23-26 11-28-26

P9B1-CON-270 Connect Pumps 12-24-26 01-05-27

P9B1-CON-280 Excavate Footing for Wall 01-05-27 01-07-27

P9B1-CON-290 Install Footing for Wall 01-07-27 01-12-27

P9B1-CON-300 Form and Pour Wall 01-12-27 01-21-27

Area 9B2Area 9B2 08-04-26 04-10-27

P9B2-CON-100 Excavate and Install Shoring - Pump Vaults 08-04-26 08-14-26

P9B2-CON-110 Pour Foundations - Pump Vaults 08-15-26 08-20-26

P9B2-CON-120 Install Pre-Cast Rings - Pump Vaults 10-29-26 11-04-26

P9B2-CON-130 Install SD Piping - Pump Vaults 11-04-26 11-06-26

P9B2-CON-140 Waterproof - Pump Vaults 11-06-26 11-09-26

P9B2-CON-150 Backfill Precast Vaults and Strip Forms - Pump Vaults 11-09-26 11-13-26

P9B2-CON-160 Excavate and Install Shoring - 5 SIde Vault 11-13-26 11-19-26

P9B2-CON-170 Trench for Electrical After Backfill 11-13-26 11-17-26

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug 2026 2027

Rough Grade Area 9A

Excavate Underground Storm Drain

Install Storm Drain Lines

Install Underground Electrical

Install New Pump Vault

Install New Pump

Connect Storm Drain Lines to New Pump

Connect Electrical Lines to New Pump

Connect Storm Drain Lines to New Pump

Excavate Footing for Wall

Fine Grade and Build Berm

Install Footing for Wall

Form and Pour Wall

Install Security Fencing

Pull Wire for Lights and Security

Form and Pour Curbs

Form and Pour Sidewalks

Paint Parking Striping

Paint and Coatings

Install Landscaping

Set Wheel Stops

Remove Construction Fencing and Barriers

Safe Off

Clear and Grub

Cap Off Utilities and Irrigation Lines

Setup Temporary Access

Demo Site

Install Sanitary By-Pass

Excavate and Install Shoring

Install Foundations

Install Pre-Cast Rings

Install SD Piping

Install Pumps

Install Electrical

Install Waterproofing

Backfill and Strip Forms

Connect Pumps

Excavate Footing for Wall

Install Footing for Wall

Form and Pour Wall

Excavate and Install Shoring - Pump Vaults

Pour Foundations - Pump Vaults

Install Pre-Cast Rings - Pump Vaults

Install SD Piping - Pump Vaults

Waterproof - Pump Vaults

Backfill Precast Vaults and Strip Forms - Pump Vaults

Excavate and Install Shoring - 5 SIde Vault

Trench for Electrical After Backfill

Data Date: 05-19-26 Print Date: 05-20-26 13:24

SOLANOC-ASSET-LF-1-1-2-1 | #

123 Complete

Milestone

Critical Milestones

Summary Milestones

Actual Work

Remaining Work

Critical Remaining Work

Remaining Level of Effort

Actual Level of Effort

P9B2-CON-180 Install Undergroud Electrical After Backfill 11-17-26 11-21-26

P9B2-CON-190 Form and Pour Foundation - 5 Side Vault 11-19-26 11-23-26

P9B2-CON-200 Install Undergroud Storm Drain After Backfill 11-21-26 12-05-26

P9B2-CON-210 Form and Pour Walls - 5 Side Vault 11-23-26 11-28-26

P9B2-CON-220 Setup Shoring for Lid - 5 Side Vault 11-28-26 11-30-26

P9B2-CON-230 Form and Pour Lid - 5 Side Vault 11-30-26 12-03-26

P9B2-CON-240 Install Pumps 12-03-26 12-09-26

P9B2-CON-250 Form and Pour Equipment Pads 12-05-26 12-12-26

P9B2-CON-260 Install Electrical 12-09-26 12-15-26

P9B2-CON-270 Set Electrical Equipment 12-12-26 12-15-26

P9B2-CON-280 Set Mechanical and Storm Drain Equipment 12-12-26 12-24-26

P9B2-CON-290 Install Waterproofing 12-15-26 12-17-26

P9B2-CON-300 Backfill- 5 Side Vault 12-17-26 12-21-26

P9B2-CON-310 Pull Wire and Terminate Electrical 12-22-26 01-05-27

P9B2-CON-320 Connect Pumps 12-24-26 01-05-27

P9B2-CON-330 Test and Energize Equipment 01-05-27 01-09-27

P9B2-CON-340 Excavate Footing for Wall (Continue from 9A-A) 01-21-27 01-26-27

P9B2-CON-350 Install Footing for Wall 01-26-27 02-03-27

P9B2-CON-360 Form and Pour Wall 02-03-27 02-12-27

P9B2-CON-370 Install Security Fencing 02-12-27 02-24-27

P9B2-CON-380 Install Devices and Pull Wire for Lights and Security 02-24-27 03-02-27

P9B2-CON-390 Form and Pour Curbs 03-02-27 03-11-27

P9B2-CON-400 Form and Pour Sidewalks 03-11-27 03-17-27

P9B2-CON-410 Pave Area 03-17-27 03-26-27

P9B2-CON-420 Paint Parking Striping 03-26-27 03-30-27

P9B2-CON-450 Paint and Coatings 03-26-27 04-01-27

P9B2-CON-430 Install Landscaping 04-01-27 04-07-27

P9B2-CON-440 Remove Construction Fencing and Barriers 04-07-27 04-10-27

Phase 10Phase 10 01-18-27 04-08-27

P10-CON-100 Call 811 and Markout Utilities 01-18-27 01-20-27

P10-CON-110 Setup Construction Fencing and Barriers 01-20-27 01-21-27

P10-CON-120 Setup Temporary Access 01-20-27 01-21-27

P10-CON-130 Setup SWPPP 01-21-27 01-22-27

P10-CON-140 Clear and Grub 01-22-27 01-25-27

P10-CON-150 Cap Off Utilities and Irrigation Lines 01-25-27 01-26-27

P10-CON-160 Demo Existing Sidewalk 01-26-27 01-29-27

P10-CON-170 Excavate and Remove Storm Drain Pipes and Basin 01-29-27 02-04-27

P10-CON-180 Start Dewatering 01-29-27 02-01-27

P10-CON-190 Rough Grade 02-04-27 02-08-27

P10-CON-200 Install New Storm Drainage Lines and Basins 02-08-27 02-15-27

P10-CON-210 Trench for Electrical 02-08-27 02-10-27

P10-CON-220 Install Footing for Wall 02-08-27 02-17-27

P10-CON-230 Install Underground Electrical Conduit 02-10-27 02-15-27

P10-CON-240 Backfill Electrical Trench 02-15-27 02-17-27

P10-CON-250 Fine Grade and Build Berm 02-17-27 02-24-27

P10-CON-260 Form and Pour Wall 02-17-27 02-23-27

P10-CON-270 Form and Pour Curbs 02-23-27 03-12-27

P10-CON-280 Install Irrigatiion Mains 02-24-27 03-01-27

P10-CON-290 Form and Pour Sidewalk 03-01-27 03-10-27

P10-CON-310 Install Landscaping 03-10-27 03-19-27

P10-CON-300 Set Lightpoles Bases, Light Poles and Bollards 03-12-27 03-22-27

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug 2026 2027

Install Undergroud Electrical After Backfill

Form and Pour Foundation - 5 Side Vault

Install Undergroud Storm Drain After Backfill

Form and Pour Walls - 5 Side Vault

Setup Shoring for Lid - 5 Side Vault

Form and Pour Lid - 5 Side Vault

Install Pumps

Form and Pour Equipment Pads

Install Electrical

Set Electrical Equipment

Set Mechanical and Storm Drain Equipment

Install Waterproofing

Backfill- 5 Side Vault

Pull Wire and Terminate Electrical

Connect Pumps

Test and Energize Equipment

Excavate Footing for Wall (Continue from 9A-A)

Install Footing for Wall

Form and Pour Wall

Install Security Fencing

Install Devices and Pull Wire for Lights and Security

Form and Pour Curbs

Form and Pour Sidewalks

Pave Area

Paint Parking Striping

Paint and Coatings

Install Landscaping

Remove Construction Fencing and Barriers

Call 811 and Markout Utilities

Setup Construction Fencing and Barriers

Setup Temporary Access

Setup SWPPP

Clear and Grub

Cap Off Utilities and Irrigation Lines

Demo Existing Sidewalk

Excavate and Remove Storm Drain Pipes and Basin

Start Dewatering

Rough Grade

Install New Storm Drainage Lines and Basins

Trench for Electrical

Install Footing for Wall

Install Underground Electrical Conduit

Backfill Electrical Trench

Fine Grade and Build Berm

Form and Pour Wall

Form and Pour Curbs

Install Irrigatiion Mains

Form and Pour Sidewalk

Install Landscaping

Set Lightpoles Bases, Light Poles and Bollards

Data Date: 05-19-26 Print Date: 05-20-26 13:24

SOLANOC-ASSET-LF-1-1-2-1 | #

123 Complete

Milestone

Critical Milestones

Summary Milestones

Actual Work

Remaining Work

Critical Remaining Work

Remaining Level of Effort

Actual Level of Effort

P10-CON-330 Install Irrigation Branches 03-19-27 03-24-27

P10-CON-340 Install Security Fencing and Gates 03-19-27 03-29-27

P10-CON-320 Place AC Pavement 03-22-27 03-31-27

P10-CON-350 Paint Parking Striping 03-31-27 04-02-27

P10-CON-360 Pull Wire and Makeup for Lights and Security 03-31-27 04-07-27

P10-CON-380 Paint and Coatings 03-31-27 04-06-27

P10-CON-370 Remove Construction Fencing and Barriers 04-07-27 04-08-27

FEMA CloseoutFEMA Closeout 04-12-27 05-21-27

CLOS-CON-100 Final Billings 04-12-27 04-23-27

CLOS-CON-120 Closeout Documentation 04-12-27 05-21-27

CLOS-CON-110 Reimbursement Request 04-26-27 05-14-27

May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug 2026 2027

Install Irrigation Branches

Install Security Fencing and Gates

Place AC Pavement

Paint Parking Striping

Pull Wire and Makeup for Lights and Security

Paint and Coatings

Remove Construction Fencing and Barriers

Final Billings

Closeout Documentation

Reimbursement Request

Data Date: 05-19-26 Print Date: 05-20-26 13:24

SOLANOC-ASSET-LF-1-1-2-1 | #

123 Complete

Milestone

Critical Milestones

Summary Milestones

Actual Work

Remaining Work

Critical Remaining Work

Remaining Level of Effort

Actual Level of Effort

File details come from the government source that posted it. Updated .