2026-02-04_Bid_Schedule_-_EL_PORTAL.xlsx

XLSX spreadsheet 16 KB Posted

Attached to
El Portal Vehicular Beach Access Ramp
Solicitation number
26-B-59IF
Issued by
Volusia County, Florida

About this file

This is a Bid Schedule for Volusia County, Florida's reconstruction of the El Portal Vehicular Beach Access Ramp in Daytona Beach Shores, a project that will restore safe pedestrian and vehicle access to the beach following destruction caused by Hurricane Nicole in 2022. The project encompasses demolition of existing storm-damaged infrastructure, installation of 64 linear feet of sheet-pile seawall and 104 linear feet of sheet-pile retaining walls with concrete caps, placement of 313 square yards of reinforced concrete ramp and 361 square yards of heavy-duty concrete, installation of 128 linear feet of FDOT Type D curbing and 104 square yards of sidewalk, pavement markings and signage, as-built survey certification, and complete site restoration. The bid schedule itemizes 14 line items with quantities and unit pricing, and the project requires a 150-day completion period with substantial completion in 120 days. The non-mandatory pre-bid meeting is scheduled for March 16, 2026, at 10:30 a.m. with a virtual Microsoft Teams option, the deadline for submitting questions is March 26, 2026, at 11:59 p.m., and sealed bids must be submitted electronically through the County's eProcurement Portal by April 9, 2026, at 3:00 p.m. Award will be determined by the lowest responsive and responsible bidder using combined pricing for all line items.

The estimated construction cost is $1,464,420.00 under Contract C-2075, with contractors required to submit a bid bond equal to 5 percent of total bid price and, upon award, provide Payment and Performance Bonds equal to 100 percent of contract price. The solicitation includes no local preference provisions due to FEMA funding restrictions; however, federal requirements mandate that the contractor make affirmative efforts to contract with small and minority businesses, women's business enterprises, and labor surplus area firms. The project is subject to FEMA federal compliance requirements including Davis-Bacon Act wage standards, Clean Air Act compliance, and domestic preference for materials per Florida Statute 255.0993. Contractors must comply with all federal, state, and local laws, maintain comprehensive insurance with the County named as additional insured, utilize the E-Verify system for employee verification, and integrate with existing Florida Department of Environmental Protection permits, U.S. Army Corps of Engineers authorizations, and U.S. Fish and Wildlife Service Take Permits. Marine turtle nesting season restrictions prohibit construction activity from May 1 through October 31, and required contractor training in sea turtle protection is mandatory. Liquidated damages are assessed at $1,000 per day for failure to meet completion deadlines, and payment for construction services will be made within 20 to 25 days of invoice receipt in accordance with Florida Statute 218.735.

View the file

Other files

File Type Posted
El_Portal_Vehicular_Beach_Access_Ramp_(Addendum_#2_Revision).pdf PDF
Exhibit_D_-_Construction_Plans_26-B-59IF_-_REVISED_-_REPLACES_ALL_PREVIOUS_VERSIONS.pdf PDF
El_Portal_Vehicular_Beach_Access_Ramp_(Addendum_#1_Revision).pdf PDF
El_Portal_Vehicular_Beach_Access_Ramp_(Addendum_#1_Revision).pdf PDF
Exhibit_A_-_Insurance_Requirements_26-B-59IF_-_REVISED_03.10.2026.pdf PDF
El_Portal_Vehicular_Beach_Access_Ramp.pdf PDF
Exhibit_C_-_Draft_Contract_26-B-59IF.pdf PDF
Exhibit_H_-_Geotechnical_Report_26-B-59IF.pdf PDF
Exhibit_J_-_FDEP_Permit_26-B-59IF.pdf PDF
Exhibit_C_-_Draft_Contract_26-B-59IF.pdf PDF
Exhibit_F_-_Sales_Tax_Exemption_Procedures_26-B-59IF.pdf PDF
Exhibit_J_-_FDEP_Permit_26-B-59IF.pdf PDF
Exhibit_G_-_Bid_Price_Sheet_26-B-59IF.xlsx XLSX spreadsheet
Exhibit_J_-_FDEP_Permit_26-B-59IF.pdf PDF
Exhibit_K_-_Federal_Contract_Provisions_26-B-59IF.pdf PDF
Exhibit_I_-_Survey_26-B-59IF.pdf PDF
Exhibit_A_-_Insurance_Requirements_26-B-59IF.pdf PDF
Exhibit_G_-_Bid_Price_Sheet_26-B-59IF.xlsx XLSX spreadsheet
Exhibit_E_-_Technical_Specifications_26-B-59IF.pdf PDF
Exhibit_H_-_Geotechnical_Report_26-B-59IF.pdf PDF
Exhibit_I_-_Survey_26-B-59IF.pdf PDF
Exhibit_E_-_Technical_Specifications_26-B-59IF.pdf PDF
Exhibit_H_-_Geotechnical_Report_26-B-59IF.pdf PDF
Exhibit_J_-_FDEP_Permit_26-B-59IF.pdf PDF
Exhibit_K_-_Federal_Contract_Provisions_26-B-59IF.pdf PDF
Exhibit_L_-_Installation_Floater_Affidavit_26-B-59IF.docx DOCX document
Exhibit_I_-_Survey_26-B-59IF.pdf PDF
Exhibit_K_-_Federal_Contract_Provisions_26-B-59IF.pdf PDF
Exhibit_L_-_Installation_Floater_Affidavit_26-B-59IF.docx DOCX document
Exhibit_D_-_Construction_Plans_26-B-59IF.pdf PDF
Exhibit_G_-_Bid_Price_Sheet_26-B-59IF.xlsx XLSX spreadsheet
1_-_FDEP_CCCL_VO002489_AR_FO.pdf PDF
2026-02-03_Final_Design_Tech_Specs.pdf PDF
4_-_Geotechnical_Report.pdf PDF
Drawings_-_EL_PORTAL.pdf PDF
2026-02-03_Final_Design_Tech_Specs.pdf PDF
3_-_Survey.pdf PDF
1_-_FDEP_CCCL_VO002489_AR_FO.pdf PDF
2026-02-03_Final_Design_Tech_Specs.pdf PDF
3_-_Survey.pdf PDF
PRIME-SUB_FORM_for_Contractors.xls XLS spreadsheet
2026-02-04_Bid_Schedule_-_EL_PORTAL.xlsx XLSX spreadsheet
4_-_Geotechnical_Report.pdf PDF
3_-_Survey.pdf PDF
4_-_Geotechnical_Report.pdf PDF
Drawings_-_EL_PORTAL.pdf PDF
3_-_Survey.pdf PDF
2026-02-04_Bid_Schedule_-_EL_PORTAL.xlsx XLSX spreadsheet
1_-_FDEP_CCCL_VO002489_AR_FO.pdf PDF
PRIME-SUB_FORM_for_Contractors_rev._01.15.2025_(lock_before_publishing).xls XLS spreadsheet
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Bid Schedule

Volusia County
El Portal Drive
Vehicular Beach Access Ramp
February 3, 2026
Bid Schedule
ItemDescriptionQuantity0Unit Price0Cost
1Mobilization/Demobilization1LSLS$0
2Demolition1LSLS$0
3Excavation, Grading, and Compaction1LSLS$0
4Sheet-Pile Seawall64LFLF$0
5Sheet-Pile Retaining Wall104LFLF$0
6Concrete Plugs & Chemical Grout1LSLS$0
7Reinforced Concrete Ramp313SYSY$0
8Heavy Duty Concrete361SYSY$0
9FDOT Type D Curb128LFLF$0
10Sidewalk & Transition Area104SYSY$0
11Pavement Markings & Signage1LSLS$0
12As-Built Survey1LSLS$0
13Site Restoration1LSLS$0
14Flood Insurance1LSLS$0
Total Cost:$0
Contract Time:150 Days

File details come from the government source that posted it. Updated .