This document is a project specification for a generator installation at the Washington County Courthouse located in Sandersville, Georgia. The project involves a comprehensive electrical infrastructure upgrade, specifically the installation of a new 150 kW three-phase diesel generator with a comprehensive set of associated electrical work. The scope includes removing existing infrastructure, installing a new 600-amp service entrance rated transfer automatic switch, establishing new underground and overhead electrical conduits, setting a concrete pad for the generator, and performing required NFPA 110 startup and load bank testing.
The project includes all labor and materials, with specific technical requirements for the generator and transfer switch to meet NFPA 110 emergency power standards. The total bid price covers permit fees and includes 20 gallons of diesel fuel. The installation will occur at 132 West Haynes St., involving precise electrical modifications including new wire pulls, conduit installations, and connections from the generator to the courthouse's main electrical systems. The specification indicates a comprehensive turnkey approach to upgrading the courthouse's emergency power infrastructure, with attention to technical specifications, safety standards, and complete system integration.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 2025 BID Invitation EMA Dept GENERATORS.docx | DOCX document | |
| 2025 Washington County Health Dept_ Generator.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Washington County Courthouse 132 West Haynes St. Sandersville, Ga. 31082 150 Kw Generator install
Price includes labor and materials to install the following tasks:
1. Remove existing weather heads and wire to main panel on exterior wall at service.
2. Install new 600 amp service entrance rated transfer automatic transfer switch 120/208v to meet NFPA 110 on exterior wall at existing service location.
3. Install new conduit and wire weatherproof from transfer switch to existing main breaker panel inside electrical room.
4. Pull new feeder wire parallel 350 mcm copper from transfer switch to existing main.
5. Install underground conduit from existing overhead service pole in ground to new ATS with parallel 500 mcm aluminum leaving enough slack for utility company termination up pole.
6. Install concrete pad for new 150 kw 3 phase 120/208 v generator
7. Provide, offload, and set new 150 kw 3 phase 120/208 v diesel generator commercial grade to meet NFPA110
8. Install conduit and cable from generator to front door desk and install remote annunciator.
9. Perform NFPA 110 start up and 4 hr. load bank test on generator after completion.
Notes:
1. Generator and transfer switch must meet NFPA 110 for emergency power
2. Bid includes permit fees
3. Bid includes 20 gallons of diesel fuel