2025-07-14_PCWRA Specifications Review Set - R_F.pdf

PDF 6 MB Posted

Attached to
Reuse Reservoir Rehabilitation and Reuse Pump Station Project
Solicitation number
2025-2
Issued by
Douglas County, Colorado

About this file

This is a comprehensive bid specification document for the Plum Creek Water Reclamation Authority (PCWRA) for the Reuse Reservoir Rehabilitation and Reuse Pump Station Project located in Douglas County, Colorado. The project involves two bid options for rehabilitating a 33 million-gallon reuse reservoir and constructing a new reuse pump station. The project scope includes site preparation, selective demolition, construction of a new pump station building (Building 4), installation of new reuse water distribution pipelines, construction of a new intake structure and slide gate, removal and replacement of existing reservoir liner and underdrain systems, installation of a new aeration system, and revegetation of disturbed areas. The bid documents were issued in July 2025, with sealed bids to be received by August 13, 2025, at 10:00 am. PCWRA anticipates a Notice of Award around August 27, 2025, with a construction duration of 365 calendar days from the Notice to Proceed.

The project will be funded through multiple potential mechanisms, including a State Revolving Fund (SRF), with compliance requirements for Davis-Bacon prevailing wage and American Iron and Steel provisions. The bid includes two options with varying levels of work and potential costs, allowing flexibility for PCWRA. Bidders are required to attend a mandatory pre-bid meeting on July 24, 2025, at 1:00 pm, and electronic bid documents will be available after July 15, 2024. The project requires performance and labor/material payment bonds, with a 5% retainage pursuant to Colorado Revised Statutes. Contractors must provide detailed qualifications, including experience, financial information, and references. The work will be performed at the PCWRA site at 4255 N. US Highway 85 in Castle Rock, Colorado.

View the file

Other files

File Type Posted
2025-07-14_PCWRA Review Set - Reduced.pdf PDF
Addendum 1 Question Responses.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SPECIFICATIONS

for Reuse Reservoir Rehabilitation and

Reuse Pump Station Project

Douglas County, Colorado

OWNER:

Plum Creek Water Reclamation Authority

ENGINEER:

July 2025

Issued For Bid

Reuse Reservoir Rehabilitation and Reuse Pump Station Project

Douglas County, Colorado

OWNER: PLUM CREEK WATER RECLAMATION AUTHORITY

4255 N. US Highway 85, Castle Rock, CO 80108

ENGINEER: GEI CONSULTANTS, INC.

4601 DTC Boulevard, Suite 325, Denver, CO 80237

These plans have been prepared by me or under my supervision.

Margaret Provencher, P.E.

Colorado P.E. No. 61410

7/14/2025

PLUM CREEK WATER RECLAMATION AUTHORITY REUSE RESERVOIR AND PUMP STATION

REUSE RESERVOIR AND PUMP STATION SECTION 00 01 10

JULY 2025 (ISSUED FOR BID) TABLE OF CONTENTS

CONTRACTING REQUIREMENTS AND

TECHNICAL SPECIFICATIONS

SECTION 00 01 10

TABLE OF CONTENTS

DIVISION 00 – PROCUREMENT AND CONTRACTING REQUIREMENTS

00 01 10 Table of Contents 00 11 16 Invitation to Bid 00 21 19 Information and Instructions to Bidders 00 31 19 Existing Condition Information 00 31 32 Geotechnical Data 00 41 09 Bid Proposal 00 70 03 Sample Contract Forms 00 70 13 Agreement for Construction Contract 00 72 00 General Conditions 00 73 00 Supplementary Conditions

DIVISION 01 – GENERAL REQUIREMENTS

01 11 00 Summary of Work 01 22 10 Measurement and Payment 01 31 00 Project Management and Coordination 01 33 00 Submittal Procedures 01 35 27 Site Safety 01 40 00 Quality Requirements 01 50 00 Temporary Facilities and Controls 01 57 13 Temporary Erosion and Sediment Control 01 71 23.16 Construction Surveying 01 77 00 Closeout Procedures

FACILITY CONSTRUCTION SUBGROUP

DIVISION 02 – EXISTING CONDITIONS

02 41 13 Selective Site Demolition

PLUM CREEK WATER RECLAMATION AUTHORITY SECTION 00 01 10

JULY 2025 (ISSUED FOR BID) TABLE OF CONTENTS

DIVISION 03 – CONCRETE

03 30 00 Cast-in-Place Concrete 03 41 09 Tilt-up Precast Building Construction 03 62 00 Non-Shrink Grouting

DIVISION 04 – MASONRY (NOT USED)

DIVISION 05 – METALS

05 10 13 Structural Steel and Miscellaneous Metalwork 05 50 00 Metal Fabrications

DIVISION 06 – WOOD, PLASTICS, AND COMPOSITES (NOT USED)

DIVISION 07 – THERMAL AND MOISTURE PROTECTION

07 10 00 Dampproofing and Waterproofing 07 71 00 Roof Specialties 07 72 33 Roof Hatches 07 92 00 Joint Sealants

DIVISION 08 – OPENINGS

08 11 16 Aluminum Doors and Frames 08 51 14 Glass Block Windows 08 70 50 Finish Hardware

DIVISION 09 – FINISHES

09 28 13 Concrete Hardener 09 62 53 Concrete Floor Toppings 09 90 00 Painting and Coating

DIVISION 10 – SPECIALTIES

10 40 00 Identification Devices 10 44 00 Fire Protection Specialties

DIVISION 11 – EQUIPMENT (NOT USED)

DIVISION 12 – FURNISHINGS (NOT USED)

DIVISION 13 – SPECIAL CONSTRUCTION (NOT USED)

DIVISION 14 – CONVEYING EQUIPMENT (NOT USED)

DIVISION 21 – FIRE SUPPRESSION (NOT USED)

DIVISION 22 – PLUMBING (NOT USED)

DIVISION 23 – HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)

23 01 00 Basic Mechanical Requirements 23 05 13 Common Motor Requirements for HVAC Equipment 23 05 14 Enclosed Controllers 23 05 93 Testing, Adjusting, And Balancing for HVAC 23 31 00 HVAC Ducts and Casings 23 34 23 HVAC Exhaust Fans 23 37 00 Air Outlets and Inlets 23 81 27 Small Split-System Heating and Cooling 23 82 00 Convection Heating and Cooling Units

DIVISION 25 – INTEGRATED AUTOMATION (NOT USED)

DIVISION 26 – ELECTRICAL

26 05 00 Common Work Results for Electrical 26 05 19 Low-Voltage Power Conductors and Cables 26 05 26 Grounding and Bonding for Electrical 26 05 29 Hangers and Supports for Electrical 26 05 33 Raceways and Boxes for Electrical 26 05 53 Identification for Electrical 26 08 00 Testing for Electrical 26 22 00 Low-Voltage Transformers 26 24 13 Switchboards 26 24 16 Panelboards 26 27 26 Wiring Devices 26 28 16 Enclosed Switches and Breakers 26 29 23 Variable Frequency Motor Controllers 26 43 00 Surge Protection Devices

DIVISION 27 – COMMUNICATIONS (NOT USED)

DIVISION 28 – ELECTRONIC SAFETY AND SECURITY (NOT USED)

SITE AND INFRASTRUCTURE SUBGROUP

DIVISION 31 – EARTHWORK

31 10 13 Site Clearing, Grubbing, and Stripping 31 23 13 Subgrade Preparation 31 23 16 Excavation 31 23 19 Dewatering 31 23 23 Fill and Backfill 31 66 15 Helical Foundation Piles

DIVISION 32 – EXTERIOR IMPROVEMENTS

32 05 19.13 Geotextiles for Exterior Improvements 32 05 19.16 Geomembranes for Exterior Improvements 32 31 00 Fences and Gates 32 90 13 Site Reclamation

DIVISION 33 – UTILITIES

33 05 04 Reuse Reservoir Underdrain System

DIVISION 34 – TRANSPORTATION (NOT USED)

DIVISION 35 – WATERWAY AND MARINE CONSTRUCTION

35 21 34 HDPE Trash Racks 35 22 11 Slide Gates

PROCESS EQUIPMENT SUBGROUP

DIVISION 40 – PROCESS INTERCONNECTIONS

40 05 04 Process Mechanical Piping Systems 40 05 06 Couplings, Adapters, and Specials for Process Piping 40 05 07 Hangers and Supports for Process Piping 40 05 19 Ductile Iron Process Piping

40 05 23 Stainless Steel Process Pipe and Tubing 40 05 60 Manually-Actuated Valves and Check Valves 40 05 68 Surge Relief Valves 40 05 97 Identification for Process Equipment 40 61 13 Process Control System General Provisions 40 61 21 Process Control System Testing 40 61 26 Process Control System Training 40 61 93 Process Control System IO List 40 61 96 Process Control Descriptions 40 62 63 Operator Interface Terminals (OIT) 40 63 43 Programmable Logical Controllers 46 66 13 Switches and Routers 40 66 33 Fiber-Optic Communication Cabling and Connectors 40 67 16 Free-Standing Panels 40 67 63 Control Panel Uninterruptible Power Supply 40 68 13 Process Control HMI Software 40 68 63 Configuration of HMI Software 40 68 66 Programming of Controller Software 40 71 13 Magnetic Flow Meters 40 72 76 Level Switches 40 73 14 Meters and Gauges 40 73 26 Pressure Transmitters 40 74 63 Temperature Transmitters 40 78 53 Relays 40 78 56 Isolation Safe Barriers, and Surge Suppressors 40 78 59 Power Supplies 40 91 14 Actuated Valves

DIVISION 41 – MATERIAL PROCESSING AND HANDLING EQUIPMENT (NOT

USED)

DIVISION 42 – PROCESS HEATING, COOLING AND DRYING EQUIPMENT (NOT

USED)

DIVISION 43 – PROCESS GAS AND LIQUID HANDLING, PURIFICATION AND

STORAGE EQUIPMENT

43 24 30 Vertical Turbine Pumps

DIVISION 44 – POLLUTION AND WASTE CONTROL EQUIPMENT (NOT USED)

DIVISION 45 – INDUSTRY-SPECIFIC MANUFACTURING EQUIPMENT (NOT USED)

DIVISION 46 – WATER AND WASTEWATER EQUIPMENT

46 51 19 Fine Bubble Diffusers

DIVISION 48 – ELECTRICAL POWER GENERATION (NOT USED)

ATTACHMENTS

A Colorado State Revolving Fund Required Specifications

B Certification Regarding Debarment, Suspension, and Other Responsibility Matters

C Davis-Bacon Act WD# CO20250002

END OF CONTENTS

SECTION 00 11 16

INVITATION TO BID

Reuse Reservoir Rehabilitation and New Reuse Pump Station

Plum Creek Water Reclamation Authority (PCWRA), will receive sealed Bids for The Reuse Reservoir Rehabilitation and New Pump Station Project until August 13, 2025, 10:00 am at:

4255 N. US Hwy 85

CASTLE ROCK, CO 80108

At that time and place, Bids will be opened and publicly read aloud. Bids must be received prior to the above stated time and date. Any Bids received after this time and date will be returned, unopened.

Clearly mark your Bid Envelope showing the Project Name, the Bid Opening date and YOUR COMPANY NAME. In the Case of No Bid, please return your Bidding Documents indicating No Bid on the form and on the outside of the return envelope.

If any information/material is to accompany the Bid, please attach it to the Bid Forms.

This project consists of various wastewater infrastructure improvements. Work items to be completed in accordance with Plum Creek Water Reclamation Authority specifications.

Principal items of work include:

1. Site preparation;

2. Selective demolition of structures at the reuse reservoir and reuse pump station location based on selected Bid Option;

3. Construction of a replacement pump station building (Building 4) and wet well within the

PCWRA plant site, including all structural, mechanical, electrical, and instrumentation equipment for Bid Option 2 if selected;

4. Installation of new reuse water distribution pipelines and tie-ins (8-inch-diameter and 12-inch-diameter ductile iron) from new reuse pump station to existing reuse distribution pipes to Pond 6A, Pond 17, and Red Hawk Ridge for Bid Option 2 if selected;

5. Construction of new intake structure and slide gate within the reuse reservoir;

6. Installation of 30-inch-diameter ductile iron outlet pipeline from the reuse reservoir per the selected Bid Option;

7. Removal, hauling, and spreading of existing soil and muck from within the reuse reservoir;

8. Removal of existing HDPE liner, underdrain, and aeration systems within the reuse reservoir;

9. Re-grading, subgrade preparation, and installation of a new geomembrane liner at the existing reuse reservoir;

10. Installation of a new aeration and underdrain system at the reuse reservoir;

11. Replacement of the existing trashracks on the inlet and outlet structures and replacement of the gate valve on the outlet conduit;

12. As part of Bid Option 2, selective demolition of mechanical equipment in PCWRA Building 6;

13. As part of Bid Option 2, installation of associated aeration equipment within Building 6;

14. Revegetation of disturbed areas and other restoration items as described in the Project

Specifications; and

15. SRF Funding Requirement Compliance if Bid Item 19 (Bid Alternative 19) is selected.

All bidders are expected to be present at the Pre-Bid Meeting to be held on July 24, 2025 at 1:00 pm. Prospective bidders are to meet on site. PCWRA authority staff will be on site to direct bidders.

PCWRA anticipates a Notice of Award on or around August 27, 2025.

The construction duration will be 365 calendar days from Notice to Proceed to final completion.

Work within the reservoir must be limited to less than 45 days. Scheduling of the outage is to be coordinated with PCWRA with a preference to occur during the off season (October through March).

Direct questions regarding bidding procedures and/or technical questions on the project scope of work to GEI Consultants. Email: mprovencher@geiconsultants.com.

All requests for clarification and/or questions must be received by email, fax or submission through Bidnet (no phone requests) by August 1, 2025. All requests for additional information must identify the person/vendor requesting the information. All clarifications will be for the benefit of all potential bidders.

Electronic copies of Bidding Documents will be available through an FTP site hosted by GEI Consultants after July 15, 2024 by request. Hard copies of Contract Documents, complete with plans and specifications, may be obtained at the office of Plum Creek Water Reclamation Authority, 4255 N. US Hwy 85, Castle Rock, CO 80108, upon receipt of a non-refundable fee of Twenty Dollars ($20) per set of documents. Checks only (NO CASH) for the fee shall be payable to Plum Creek Water Reclamation Authority.

If awarded the project, a Performance Bond and a Labor and Material Payment Bond are required within ten (10) days of the date the written Notice of Award, each for the total amount of the Contract Price. No Bidder may withdraw a Bid for a period of thirty (30) days after the date fixed for opening the Bids. Additionally, the contract for this project will be subject to a 5% retainage pursuant to CRS 24-91-103.

PCWRA reserves the right to cancel this Invitation to Bid; reject any Bid, in whole or in part; to adjust the quantity of Work to be done as mandated by budgetary requirements; and to waive informalities or irregularities in the Bids received; when it is in PCWRA's best interest to do so.

IT IS UNLAWFUL AND UNETHICAL FOR ANY PERSON TO OFFER, GIVE OR AGREE TO GIVE

ANY PCWRA EMPLOYEE, PCWRA OFFICIAL OR FORMER PCWRA EMPLOYEE, OR FOR ANY

PCWRA EMPLOYEE, PCWRA OFFICIAL OR FORMER PCWRA EMPLOYEE TO SOLICIT,

DEMAND, ACCEPT OR AGREE TO ACCEPT FROM ANOTHER PERSON, A GRATUITY OR AN

OFFER OF EMPLOYMENT IN CONNECTION WITH ANY DECISION, APPROVAL, DISAPPROVAL,

RECOMMENDATION OR PREPARATION OF ANY PART OF A PROGRAM REQUIREMENT OR A

PURCHASE REQUEST, INFLUENCING THE CONTENT OF ANY SPECIFICATION OR

PROCUREMENT STANDARD, RENDERING OF ADVICE, INVESTIGATION, AUDITING OR IN ANY

OTHER ADVISORY CAPACITY IN ANY PROCEEDING OR APPLICATION, REQUEST FOR

RULING, DETERMINATION, CLAIM OR CONTROVERSY, OR OTHER PARTICULAR MATTER,

PERTAINING TO ANY PROGRAM REQUIREMENT OR A CONTRACT OR SUBCONTRACT, OR

TO ANY SOLICITATION OR PROPOSAL THEREFORE.

IT IS UNLAWFUL AND UNETHICAL FOR ANY PAYMENT, GRATUITY OR OFFER OF

EMPLOYMENT TO BE MADE BY OR ON BEHALF OF A SUBCONTRACTOR UNDER A

CONTRACT TO THE PRIME CONTRACTOR OR HIGHER TIER SUBCONTRACTOR OF ANY

PERSON ASSOCIATED THEREWITH, AS AN INDUCEMENT FOR THE AWARD OF A

SUBCONTRACT OR ORDER.

PCWRA

mailto:mprovencher@geiconsultants.com

1 | P a g e

SECTION 00 21 19

INFORMATION AND INSTRUCTIONS TO BIDDERS

INDEX

1.0 DATE OF RECEIVING BIDS

2.0 BID FORMS .................................................................................................................................. 2,3

3.0 FAMILIARIZATION WITH THE WORK AND SITE CONDITIONS

4.0 REQUESTS FOR EXPLANATION

5.0 ADDENDA

6.0 BID GUARANTEE ......................................................................................................................... 3,4

7.0 BONDS

8.0 SUBMISSION OF BIDS ................................................................................................................ 4,5

9.0 TAXES

10.0 BID PRICING

11.0 BIDS .............................................................................................................................................. 5,6

12.0 AWARD OF CONTRACTS

13.0 ACCEPTANCE OF BID AND ITS EFFECT

14.0 TIME FOR EXECUTING CONTRACT AND DAMAGES FOR FAILURE TO EXECUTE ............. 6,7

15.0 POST-BID INFORMATION

16.0 EXAMINATION OF BIDS

17.0 REJECTION OF BIDS

18.0 RIGHT TO INSPECT

19.0 LAWS TO BE OBEYED ................................................................................................................ 7,8

20.0 EQUAL OPPORTUNITY

21.0 LOCAL LABOR AND MATERIALS

22.0 TIME OF COMPLETION

2 | P a g e

INFORMATION AND INSTRUCTIONS TO BIDDERS

1. DATE OF RECEIVING BIDS

1.1 Bids will be received as directed in the Invitation to Bid and then will be publicly read. Bids received after the time specified will not be accepted.

2 BID FORMS

2.1 PCWRA shall provide the Bidder access to the Bidding Documents which will state the location and description of the proposed Work and will show the estimate of the various quantities of work to be performed and materials to be furnished, the time in which the work must be completed, the amount of the "Bid Guarantee" (which must accompany the Bid) and the date and time of the reading of the Bids. It will also state any special provisions or requirements, which vary from or are not contained in the Standard Specifications. All forms bound with or submitted with the Bid Forms are a necessary part thereof and must not be detached. Bids must be printed or electronically submitted to Bidnet. No Bid alterations or interlineations will be permitted, unless made before submission and initialed and dated. If initialed, PCWRA may require the Bidder to identify the alteration so initialed. PCWRA will give the Bidder an additional set of Bid Forms. No partial sets of Contract Documents and Specifications will be issued.

2.2 Each Bid must contain the full name(s) and post office address of the Bidder(s), and any person signing any Bid as agent of another, or of a firm, must furnish legal evidence of authority to do so.

2.3 A person who submits a Bid and affixes "President," "Secretary," "Agent," or other designation to his or her signature, without disclosing the principal, may be personally held to the Bid.

2.4 PCWRA will not consider more than one Bid from an individual, firm, partnership, or corporation under the same or different names. Evidence that any Bidder is interested in more than one Bid for the same work will be cause for rejection of all such Bids. Collusion between the Bidders will be considered sufficient cause for the rejection of all affected Bids. A party quoting prices to a Bidder is not thereby disqualified from quoting prices to other Bidders or from submitting a direct Bid on the Bidder's own behalf.

2.5 Discrepancies: In the event of a difference between extended price and unit price of the Proposal, the unit price governs.

2.6 Modifications: Modifications to Bids already submitted will be allowed if received prior to the time specified in the Invitation to Bid. Modifications shall be submitted as such and shall not reveal the total amount of either the original or revised Bids. The modifications shall be in writing and shall be signed in the same manner and by the same person(s) who signed the Proposal.

2.7 Withdrawal of Proposal: A Bidder may withdraw a Bid at any time prior to the time Bids are to be read, by written request of the Bidder. Any such request shall be signed in the same manner as, and by the same person(s) who signed the Bid Proposal.

2.8 Alternate Bids: Whenever Alternate Bids are called for specifying the use of several different classes of materials or types of improvements for the same work, all Bidders are requested to submit prices for use of each of the several classes of materials or types of improvements as specified. The material to be used or the type of improvement to be adopted will be selected by PCWRA after the Bids have been read. Unless otherwise specifically provided in the specifications for the improvement, Bids shall be made upon each and every item shown on the Bid Schedule.

3 | P a g e

2.9 Variation in Estimated Quantities: The Contractor must reasonably expect a variation in the estimated quantities from the actual quantities and no claims will be allowed for anticipated profits, for loss of profits or for damage of any sort because of a difference between the estimate of any item and the amount of the item actually required. PCWRA reserves the right to eliminate items from the Bid Schedule when PCWRA deems it in its best interest.

3 FAMILIARIZATION WITH THE WORK AND SITE CONDITIONS

3.1 Before submitting Bids, prospective Bidders shall familiarize themselves with the work, the site where the work is to be performed, local labor conditions and all laws, regulations and other factors affecting performance of the work. Bidders shall carefully correlate their observations with requirements of the Contract and otherwise satisfy themselves as to the expense and difficulties attending performance of the work. The submission of a Bid constitutes a representation of compliance by the Bidder. There will be no subsequent financial adjustment for lack of such familiarization.

3.2 Site Conditions: Bidders shall visit the site of the work and completely inform themselves relative to construction hazards and procedures, the availability of lands, the character and quantity of surface and sub-surface materials, and utilities to be encountered, the arrangement and condition of existing structures and facilities, the procedures necessary for maintenance of uninterrupted operation of existing sewers and other utilities, the character of construction equipment and facilities needed for performance of the work, and facilities for transportation, handling, and storage of materials and equipment. All such factors shall be properly investigated and considered in the preparation of Bids.

4. REQUESTS FOR EXPLANATION

4.1 Bidders should notify PCWRA of any discrepancies in or omissions from the Drawings or Specifications.

Any Bidder may submit a written request for an explanation or correction of any part of the Contract, to GEI Consultants a minimum of seven days prior to the Bid reading. The person submitting the request shall be responsible for its prompt delivery.

5 ADDENDA

5.1 Any explanations or corrections shall be made as Addenda to the documents and shall be furnished to all Bidders who shall acknowledge receipt of all Addenda in the appropriate spaces provided in the Proposal Form. Oral explanations and interpretations made prior to the Bid Reading will not be binding. No telephone Addenda will be made within the four days just prior to the Bid Reading, unless the Bid Reading is postponed or canceled.

6 BID GUARANTEE

6.1 Each Bid shall be accompanied by a certified check or Bid Bond payable to Plum Creek Water Reclamation Authority in an amount not less than five percent of the total amount of the Bid as a Bid Guarantee, when required in the Invitation to Bid. No Bid will be considered unless accompanied by the Bid Guarantee. No personal or business checks will be accepted as Bid Guarantees.

6.2 When Alternate Bids are called for, providing for the use of several different classes of materials or types of improvements for the same work, one Bid Guarantee in the amount of five percent of the total amount of the highest Bid will be sufficient for all Bids.

6.3 The Bid Guarantee of the Bidder(s) to whom a contract award is made may be returned when the successful Bidder executes a contract and files a Labor and Material Payment Bond, and a Performance Bond. The Bid Guarantee of the next best Bidder may be retained for a period not to exceed 45 days and may be

4 | P a g e returned after the execution of the contract and bonds by the successful Bidder. The Bid Guarantee of all other Bidders may be returned after the contract is awarded. However, surety forms provided with the Bid will not be returned unless specifically requested by the Bidder. Certified Checks (used as Bid Guarantees) will be returned immediately following the Bid reading, at the discretion of PCWRA, to those who are not the apparent best Bidders. However, Certified Checks as Bid Guarantee of the best three Bidders may be retained until award of contract is made.

6.4 If the Successful Bidder fails to enter into a contract according to the Bidder's accepted Bid or fails to furnish the required bonds within ten days from Notice of Award, the Bid Guarantee shall be forfeited to Plum Creek Water Reclamation Authority as liquidated damages.

6.5 The next best Bid shall then be considered the successful Bid and, at the discretion of PCWRA, the contract may be awarded to the Bidder submitting that Bid.

7 BONDS

7.1 Bonds shall be executed on the forms included in the Contract Documents (or a form acceptable to PCWRA) by a corporate bonding company licensed to do business in the State of Colorado and acceptable as Surety to PCWRA. The forms must be countersigned by the Colorado agent.

7.2 A "Power of Attorney" authorizing the attorney-in-fact to bind the surety company and certified to include the date of the bond shall accompany the bond.

7.3 The Performance Bond and Labor and Material Payment Bond must remain in full force and effect during the entire period of the guarantee.

7.4 The successful Bidder shall give a Performance Bond equal to the amount of the Contract Price. The Performance Bond shall guarantee: (a) the faithful performance and completion of the work in strict accordance with the terms of the Contract, and each and every covenant, condition and part thereof, according to the true intent and meaning of the Contract Documents, as defined in the Contract and (b) the repair or replacement where required, or the cost thereof, for a period of one year after the issuance of the Certificate of Acceptance or until all warranty work is completed, whichever occurs last, of all work performed under the Contract. A separate Labor and Material Payment Bond equal to the amount of the Contract Price is required to ensure the payments of laborers, materialmen, suppliers, and subcontractors in connection with the work performed under the Contract and to satisfy the requirements of §§ 38-26-105 and 38-26-106, C.R.S., as amended. WHEN BONDS ARE REQUIRED, THE NEED AND THE NATURE

OF THE BONDS SHALL BE STATED IN THE ADVERTISEMENT FOR BIDS.

7.5 Plum Creek Water Reclamation Authority reserves the right to waive bond requirements if the Total Bid amount does not exceed $50,000. In the event the Performance or Payment Bonds are waived, cost of the bonds shall be reflected as a deduction from the total Bid Price, when so indicated on the Bid Form. There will be a Unit Price deduction for the waiver indicated on the Bid Schedule, when necessary.

8 SUBMISSION OF BIDS

8.1 One copy of the completed Bid Forms and the Bid Guarantee must be submitted in the Bidder's own envelope or electronically through Bidnet. The second copy of the Bid Forms contained in the Bidding Documents is for the Bidder's records.

8.2 All copies of the Bid Forms, the Bid Guarantee and any other documents required to be submitted with the Bid shall be submitted electronically or enclosed in a sealed, opaque envelope bearing the following address and information:

5 | P a g e

a) Plum Creek Water Reclamation Authority 4255 N US Highway 85 Castle Rock, CO 80108 Attn: Weston Martin

b) PROJECT, BIDDER, OPENING DATE & TIME

8.3 If the Bid is sent by mail, the sealed envelope shall be enclosed in a separate mailing envelope, having proper postage for delivery, and clearly marked "BID ENCLOSED FOR PROJECT NAME" on the outside of the envelope. Send Bids early enough to be received prior to the time and date established for the Bid reading. Bids with insufficient postage will not be accepted.

It is the Bidders' responsibility to ensure mailed and electronic Bids are received prior to the time and date of advertised opening.

8.4 Bidders may bring Bids to Plum Creek Water Reclamation Authority at 4255 N US Highway 85, Castle Rock, CO 80108 before the time and date for receipt of Bids in the Invitation to Bid. Bids received after the time and date for receipt of Bids will not be accepted. Once Bids are submitted, they may not be withdrawn except as stipulated below.

Timely delivery of Bids is the Bidder's responsibility.

8.5 Oral, telephone or fax Bids are invalid and will not receive consideration.

8.6 Withdrawal of Proposal: A Bidder may withdraw his Proposal at any time prior to the bid submission deadline by written request. The written request must be signed in the same manner and by the same person(s) who signed the Proposal. If, within 24 hours after the Bid reading, any Bidder files a duly signed written notice with the Owner and promptly thereafter demonstrates to the reasonable satisfaction of the Owner that there was a material and substantial mistake in the preparation of its Bid, that Bidder may withdraw its Bid and the Bid security will be returned. Thereafter, if the Work is rebid, that Bidder will be disqualified from further bidding on the Work.

9 TAXES

9.1 Materials and equipment purchased solely for PCWRA projects, that will become a permanent part of the final project, are tax exempt. Contractors must obtain their own tax-exempt number from the Colorado State Department of Revenue for each project. PCWRA will furnish its tax-exempt numbers for the Contractor to reference when applying for its own tax-exempt number.

10 BID PRICING

10.1 Unit Price Bid Schedule: When PCWRA requests Unit Prices, the Bidder shall fully complete the schedule of unit prices included in the Bid Proposal Form.

10.2 When PCWRA includes an additional amount on the bid schedule for minor contract revisions and PCWRA has estimated bid quantities on the schedule, Bidders shall include that additional amount in the total Bid price.

10.3 The total of all the unit prices bid multiplied by the estimated quantity of each item shall be the total Bid price. PCWRA will pay for the final measured, used, or delivered quantities at unit prices in the Bid.

11 BIDS

6 | P a g e

11.1 Opening of Bids: The submitted Bids will be publicly read aloud at the time, date, and place set in the Invitation to Bid.

11.2 Irregular Bids: Bids may be rejected if they show any omission, alteration of form, additions not called for, conditional Alternate Bids, or irregularities of any kind which, in the opinion of PCWRA, tend to make the Bid indefinite or ambiguous.

PCWRA will reject Bid Proposals with prices, which are obviously unbalanced as determined by PCWRA.

Contracts will be awarded only to responsible Bidders capable of performing the class of work contemplated. The Bidder shall furnish a complete statement of the Bidder's experience and of the amount of capital and equipment available for the proposed work on the Bidder's Qualification and Data form provided in the Bid Forms.

11.3 Collusion: Bids will be rejected if there is reason for believing that collusion exists among the Bidders.

Participants in such collusion are subject to suspension and debarment.

For certain projects, PCWRA may require potential bidders to submit information regarding the bidders' qualifications in addition to the Qualification Application for Contractors and Professional Services. The requirement for such information will be identified in the Invitation to Bid or elsewhere in the Bid Documents.

Any information requested by or on file with PCWRA may be used to qualify or disqualify potential bidders.

12 AWARD OF CONTRACTS

12.1 Any or all Bids may be rejected or informalities in bids may be waived at the option of PCWRA.

12.2 The award of the Contract is contingent upon securing an acceptable Bid which will fall within the amount of funds available for construction of the project, or the acquisition of contracted services.

13 ACCEPTANCE OF BIDS AND ITS EFFECT

13.1 PCWRA will act upon the Bids with reasonable promptness after the opening of the Bids. The acceptance of a Bid will be a written Notice of Award signed by the duly authorized representative of PCWRA. No other act of PCWRA shall be necessary to constitute acceptance of a Bid. The acceptance of a Bid binds the successful Bidder to execute the required Agreement for Construction Contract and take all action necessary to fulfill the Contract.

14 TIME FOR EXECUTING CONTRACT AND DAMAGES FOR FAILURE TO EXECUTE

14.1 Any Bidder whose Bid is accepted will be required to execute the Contract and furnish the Contractor's Bonds required under Section 6, Bid Guarantee, within ten days after written notice that the Contract has been awarded to the Bidder, or by such time as modified by Special Conditions. Failure to do so shall constitute a breach of the Contract effected by the acceptance of the Bid.

14.2 The damages to PCWRA for such breach will include loss from interference with the construction program and other items whose accurate amount will be difficult or impossible to compute. The amount of the Bid Guarantee accompanying the Bid shall be retained by PCWRA as reasonable liquidated damages and not as a penalty for such breach.

14.3 PCWRA is authorized, the same as if the Bid Guarantee or Bid contained an expressed stipulation to that effect, to cause such work to be done, or complete the work in-house, or contract with some other Contractor to do so, and/or compute the difference between actual cost to PCWRA of such improvements and the sum which it would cost if the defaulting Bidder complied with the Bid.

7 | P a g e

15 POST-BID INFORMATION

15.1 Unless previously requested or unless waived by PCWRA, the Bidder shall, within ten days of receiving the Notice of Award, submit the following information to PCWRA:

15.1.1 A designation of the work to be performed by the Bidder with the Bidder's own forces;

15.1.2 The proprietary names and the suppliers of principal items or systems of material and equipment proposed for the work;

15.1.3 A list of names of the Subcontractors or other persons or organizations (including those who are to furnish materials or equipment fabricated to a special design) proposed for the principal portions of the work;

15.1.4 A proposed schedule of construction and estimated monthly payments.

15.2 The Bidder will be required to establish to the satisfaction of PCWRA, the reliability and responsibility of the proposed Subcontractors to furnish and perform the Work described in the Sections of the Specifications pertaining to such proposed Subcontractor's respective trade.

15.3 Prior to the Award of Contract, PCWRA will notify the Bidder in writing if PCWRA, after due investigation, has reasonable objection to any person or organization on such list. If PCWRA, in its sole discretion, has a reasonable objection to any person or organization on such list, and refuses in writing to accept such person or organization, the Bidder shall submit an acceptable substitute Subcontractor.

16 EXAMINATION OF BIDS

16.1 All Bids submitted shall be made available for examination by interested parties within a reasonable time following the Bid reading. All information in the Bid Documents will be available for public scrutiny, unless the Bidder specifically requests confidential treatment of some or all of its commercial data.

Requests for confidentiality shall be in writing, and the portions of the commercial data for which confidentiality is requested shall be clearly identified.

Procurement information shall be a public record to the extent provided by Article 24.72, C.R.S., as amended, and shall be available to the public as provided in the statute.

16.2 The Final Bid Price and the means by which that price was determined are not commercial data and may not be included in any request for confidentiality.

17 REJECTION OF BIDS

17.1 Plum Creek Water Reclamation Authority reserves the right to cancel this Invitation to Bid; reject any Bid, in whole or in part; to adjust the quantity of Work to be done as mandated by budgetary requirements; and to waive informalities or irregularities in the Bids received; when it is in PCWRA's best interest to do so.

Plum Creek Water Reclamation Authority reserves the right to accept the Bid, which in the opinion of PCWRA will best suit PCWRA's purpose.

18 RIGHT TO INSPECT

18.1 PCWRA may, at reasonable times, inspect the part of the plant, place of business or worksite of the Bidder or the Bidder's subcontractors at any tier which is pertinent to the performance of the award of the Contract.

19 LAWS TO BE OBEYED

8 | P a g e

19.1 Bidders shall familiarize themselves with the provisions of the laws of the State of Colorado and the Federal Government, and with all local laws and all regulations made which are pertinent to the proposed work and shall comply with the same.

19.2 Contractor shall abide by the PCWRA Smoking Policy which states “Smoking in buildings, in company vehicles, or on the plant site is forbidden. Smoking is only allowed in the designated and posted smoking area located between the administration and maintenance buildings.”

20 EQUAL OPPORTUNITY

20.1 The Contractor will not discriminate against any employee or applicant for employment because of race, color, religion, age, sex, or national origin, or other reason prohibited by applicable federal, state or local law, ordinance or regulation. The Contractor shall abide by all federal laws in effect during the Contract period, which govern Equal Opportunity Employment.

21 LOCAL LABOR AND MATERIALS

21.1 Preference shall be given to employment of Colorado labor pursuant to § 8-17-101 and 102, C.R.S., as amended.

21.2 Pursuant to statutory authority, preference shall be given to materials, supplies, and provisions produced, manufactured, or grown in Colorado, quality being equal to articles offered by competitor outside the state (§§ 8-18-101 through 103, C.R.S., as amended).

22 TIME OF COMPLETION

22.1 This is a 365 calendar day project from Notice to Proceed to final completion. Work within the reservoir must be limited to less than 45 days. Scheduling of the outage is to be coordinated with PCWRA with a preference to occur during the off season (October through March).

22.2 TIME IS OF THE ESSENCE and the Bidder agrees to comply with all partial completion dates and to substantially complete the Project within the stated time beginning on the date of Notice to Proceed.

REUSE RESERVOIR AND PUMP STATION SECTION 00 31 19

JULY 2025 (ISSUED FOR BID) EXISTING CONDITIONS

SECTION 00 31 19

EXISTING CONDITIONS

GENERAL

1.01 SCOPE

A. Existing site information, including design and as-built drawings of the construction of the reuse reservoir, pump facilities, and reuse water distribution pipelines, is provided as attachments to this section or is shown on the Drawings. Bidders are encouraged to review the available information and to attend the site visit following the pre-bid meeting to familiarize themselves with existing site conditions. If a bidder chooses not to attend the site visit, the bidder will nevertheless be charged with knowledge of conditions which reasonable inspection would have disclosed.

B. Bidders and the Contractor shall assume all responsibility for deductions and conclusions as to the difficulties in performing the work.

END OF SECTION

PLUM CREEK WATER RECLAMATION AUTHORITY SECTION 00 31 19

REUSE RESERVOIR AND PUMP STATION SECTION 00 31 19

JULY 2025 (ISSUED FOR BID) EXISTING CONDITIONS

THIS PAGE INTENTIONALLY LEFT BLANK

REUSE RESERVOIR AND PUMP STATION SECTION 00 31 32

JULY 2025 (ISSUED FOR BID) GEOTECHNICAL DATA

SECTION 00 31 32

GEOTECHNICAL DATA

GENERAL

1.01 SITE INFORMATION

A. A geotechnical investigation was conducted at the site in 2020. Results of the investigation are provided in the Drawings. Bidders are encouraged to review the available information and to attend the site visit following the pre-bid meeting to familiarize themselves with observable geotechnical conditions and to discuss interpreted geotechnical conditions with the Owner’s Representative.

B. Subsurface information and reports from previous geotechnical investigations in the vicinity of the reuse reservoir and reuse pump station is provided as attachments to this section.

END OF SECTION

PLUM CREEK WATER RECLAMATION AUTHORITY SECTION 00 31 32

REUSE RESERVOIR AND PUMP STATION SECTION 00 31 32

JULY 2025 (ISSUED FOR BID) GEOTECHNICAL DATA

SECTION 00 41 09

BID PROPOSAL

Project Name Reuse Reservoir Rehabilitation and New Reuse Pump Station

1. In compliance with your Invitation to Bid, and subject to all conditions thereof, the undersigned:

a Corporation incorporated in the State of

-OR- , a partnership, / limited partnership, (select one), registered in the State of , whose general partner(s) is/are

-OR-

a sole proprietor, whose trade name is in the Town of , State of , offers this Bid Proposal for the construction of all items listed at the prices shown on the following Bid Schedule. (The attached Bid Schedule lists the various divisions of construction contemplated in the Plans and Specifications, together with an estimate of the units of each. With these units as the basis, extend each item, using the cost inserted in the unit column. Any total cost found inconsistent with the unit cost when the Bids are examined will be deemed in error and corrected to agree with the unit cost. Alternate Bids are optional.)

2. The undersigned Bidder declares and stipulates that this Bid is made in good faith, without collusion or connection with any other person or persons bidding for the same Work, and that it is made subject to all the terms and conditions of the Invitation to Bids, Information and Instruction for Bidders, Construction Contract, General Conditions, the Agreement for a Construction Contract, the Technical Specifications, and the Plans pertaining to the Work to be done, all of which have been examined by the undersigned.

3. Accompanying this Bid is a Bid Guarantee for 5% of the total Bid amount according to the Invitation to Bid and Information and Instructions to Bidders.

4. The undersigned Bidder agrees to execute the Agreement for a Construction Contract, a Performance

Bond and a Labor and Material Payment Bond within ten days from the date when the written Notice of Award is delivered at the address given on this Bid Proposal. The Performance Bond and Labor and Material Payment Bond shall each be for the amount of the total of this Bid and shall be from the same surety. The name and address of the corporate surety through which the Bidder proposes to furnish the specified Bonds is as follows:

5. The submission of the Bid constitutes an agreement, and it shall not be withdrawn after the Bid Opening for a period of thirty days.

6. All the various phases of work enumerated in the Contract with individual jobs and overhead, whether specifically mentioned or not, are included by implication or appurtenance in the Contract. The Contractor shall perform all the various phases of work under one of the items listed in the Bid Schedule, irrespective of whether it is named in the Schedule.

7. Payment for the Work performed will be according to the Bid Schedule, subject to changes as provided in the Contract.

8. The undersigned Bidder hereby acknowledges receipt of addenda numbers ___ through ___.

RETURN BID TO: Plum Creek Water Reclamation Authority 4255 N. US Hwy 85

Castle Rock, CO 80108

The undersigned, being familiar with the existing conditions on the project area affecting the cost of the Work and the Contract Documents, and having verified the quantities and the availability of materials and labor, hereby proposes to furnish all supervision, labor, materials, machinery, tools, appurtenances, equipment, supplies, and services, including utility and transportation service required to construct and complete the Project listed above, according to the Contract, within the time specified, and at the prices stated below.

These prices are to cover all expenses incurred in performing the Work required under the Contract of which this Bid is a part.

(The approximate quantities of Work to be completed in-place under the Contract are identified in the Bid Schedule and are for the purpose of comparing Bids. These quantities have been estimated and the quantities used are for the general information of the Bidder, representing the major items of the Work to be done. Minor details are not listed but shall be part of the complete Contract.)

9. The undersigned agrees to hold firm the Bid for thirty (30) days for the purpose of PCWRA reviewing the

Bids and investigating the qualifications of the Bidders prior to award of Contract. Mutually agreed upon extensions of time may be made if necessary.

This proposal is submitted by:

CONTRACTOR: BY:

ADDRESS: TITLE:

Attest:

SECRETARY: DATE:

(if corporation)

BID SCHEDULE – BID OPTION 1

Item No.

Item Quantity Unit Unit Price

Item Cost

1 General Conditions, Mobilization and Demobilization 1 LS $ 11 Reuse Reservoir - Haul and Spread Muck 8,000 CY $ 12 Reuse Reservoir - LLDPE Liner System 245,000 SF $ 13 Reuse Reservoir - Underdrain System 2,200 LF $ 14 Reuse Reservoir - Outlet Structure 1 LS $ 15 Reuse Reservoir - 30” Diameter Outlet Conduit Stub Out through Embankment

130 LF $

16 Reuse Reservoir - Replacement of Existing Equipment 1 LS $ 17 Reuse Reservoir - Aeration System and Blowers 1 LS $ 19 SRF Funding Requirement Compliance

(BID ALTERNATE)

1 LS $

LS = Lump Sum CY = Cubic Yards SF = Square Feet LF = Linear Feet

BID AMOUNT – BID OPTION 1

Total Base Bid in Words (Items 1, 11 – 18)

Total Base Bid In Figures

Total Alternate Bid in Words (Items 1, 11 – 19)

Total Alternate Bid In Figures

BID SCHEDULE – BID OPTION 2

Item No.

Item Quantity Unit Unit Price

Item Cost

1 General Conditions, Mobilization and Demobilization 1 LS $ 2 Building 4 – Excavation and Excavation Support 1 LS $ 3 Building 4 - Backfill 1,000 CY $ 4 Building 4 - Structural 1 LS $ 5 Building 4 – Mechanical 1 LS $ 6 Building 4 – Electrical 1 LS $ 7 Building 4 – I&C 1 LS $ 8 Building 4 – HVAC 1 LS $ 9 12” Diameter Reuse Water Distribution Piping and Tie-ins

(Pond 6A and Pond 17)

100 LF $

10 8” Diameter Reuse Water Distribution Piping and Tie-ins (Red Hawk)

50 LF $

11 Reuse Reservoir - Haul and Spread Muck 8,000 CY $ 12 Reuse Reservoir - LLDPE Liner System 245,000 SF $ 13 Reuse Reservoir - Underdrain System 2,200 LF $ 14 Reuse Reservoir - Outlet Structure 1 LS $ 15 Reuse Reservoir - 30” Diameter Outlet Conduit 370 LF $ 16 Reuse Reservoir - Replacement of Existing Equipment 1 LS $ 17 Reuse Reservoir - Aeration System and Blowers 1 LS $ 18 Building 6 - Aeration System and Blower 1 LS $ 19 SRF Funding Requirement Compliance

(BID ALTERNATE)

1 LS $

LS = Lump Sum CY = Cubic Yards SF = Square Feet LF = Linear Feet

BID AMOUNT – BID OPTION 2

Total Base Bid in Words (Items 1 – 18)

Total Base Bid In Figures

Total Alternate Bid in Words (Items 1 – 19)

Total Alternate Bid In Figures

BIDDER'S QUALIFICATIONS AND DATA

All questions must be answered clearly and comprehensively. If necessary, separate sheets may be attached. The Bidder may submit additional information.

1. Name of Bidder:

2. Permanent main office address: _____________________________________________________

3. Phone: Fax #

4. Bidder's federal tax identification number

5. The Bidder is organized as a .

6. The date the Bidder was organized in its current form:

7. If a corporation, the state where it is incorporated:

8. How many years have you been engaged in the contracting business under your present firm or trade name?

9. Contract(s) on hand: (Schedule these, showing amount of each contract and the appropriate anticipated dated of completion.)

Job: $: Completion Date:

10. General character or work performed by your company:

11. Have you ever been debarred or suspended by a government from consideration for the award of contracts? If so, where and why?

12. Have you ever been charged liquidated damages on a contract? If so, where and why?

13. List your major equipment AVAILABLE FOR THIS PROJECT:

14. Experience in construction work similar in contract price to this project:

a. Job/$ /

Contact Name/Phone

b. Job/$ /

c. Job/$ /

15. Background and experience of the principal members of your organization, including officers:

16. Bonding Limit: $

17. Bonding Company: Phone #

Address:

18. Bank Reference(s):

19. Will you, upon request, complete a detailed financial statement and furnish any other information that may be required by PCWRA?

20. The undersigned hereby authorizes and requests any person, firm or corporation to furnish any information requested by PCWRA in verification of the recitals in this statement of Bidder's Qualifications and Data.

ADDRESS: ITS:

Title Attest:

SECRETARY: DATE:

BIDDER'S OFFICIALS DATA

Bidder's name For each officer of a corporation, partner of a firm, or owner of a sole proprietorship, provide the following information: (Use additional sheets as necessary.)

Name

Title Social Security Number

Home address

Town, State, Zip

Other companies with whom this person has been affiliated in last 10 years

Has that company ever been disbarred or suspended from participation in the award of contracts with a government?

Home address

Has that company ever been disbarred or suspended from participation in the award of contracts with a

Home address

Has that company ever been disbarred or suspended from participation in the award of contracts with a

Home address

Town, State, Zip

Other companies with whom this person has been affiliated in last 10 years

Has that company ever been disbarred or suspended from participation in the award of contracts with a

BID BOND

(insert the full name and address or legal title of the Contractor) as Principal, and, (insert the legal title of the Surety) as Surety, a corporation organized under the laws of the State of

, and authorized to transact business in the State of Colorado, with a general office at , are hereby bound by Plum Creek Water Reclamation Authority, (PCWRA) as Obligee, in the amount of DOLLARS, in United States currency, for the payment of which amount the Contractor and Surety bind themselves, their heirs, executors, administrators, successors, and assigns, jointly and severally. The Principal has submitted the accompanying Bid dated , 20__, for _____Reuse Reservoir Rehabilitation and New Reuse Pump Station_____.

PCWRA requires, as a condition for receiving the Bid, that the Principal deposit with PCWRA a Bid Guaranty, of at least five percent of the amount of the Bid, conditioned so that if the Principal fails to execute the Agreement for Construction Contract, and furnish the required Bonds if the Principal is awarded the Contract, that the sum be paid immediately to PCWRA, as liquidated damages and not as a penalty, for the Principal's failure to perform.

If the Principal, within the specified period, executes the Agreement for Construction Contract with PCWRA according to the Bid, as accepted, and furnishes a Performance Bond and a Labor and Material Payment Bond with good and sufficient Surety or Sureties, upon the forms prescribed by PCWRA for the faithful performance and proper fulfillment of the Contract, or pays to PCWRA the proper amount of liquidated damages, then this obligation shall be null and void; otherwise it shall remain in full force and effect.

Executed this day of , 20__.

WITNESS PRINCIPAL

By its President

WITNESS SURETY

TITLE

BY:

Its Attorney-in-fact

I, , certify that I am the (title) of the Corporation named as Surety; that ________________________________________, who signed the bond on behalf of the Principal, was then (title) of the Corporation; that I know his or her signature, and the signature thereto is genuine; and that the bond was duly signed, sealed, and attested to for and on behalf of the Corporation by authority of this governing body.

(CORPORATE SEAL) Signed:

Title:

NON-COLLUSION AFFIDAVIT OF PRIME BIDDER

State of ) ss

County of )

, being duly sworn deposes and says that:

(Insert name)

1. He/She is the (Title) of , the Bidder that has submitted the attached Bid;

2. He/She is fully informed respecting the preparation and content of the attached Bid and of all pertinent circumstances respecting such Bid;

3. Such Bid is genuine and is not a collusive or sham Bid:

4. Neither the Bidder nor any of its officers, partners, owners, agents, representatives, employees or parties in interest, including this affiant, has in any way colluded, conspired, connived or agreed, directly or indirectly with any other Bidder, subcontractor, mechanic, materialman, suppliers, firm or person to submit a collusive or sham Bid in connection with the Contract for which the attached Bid has been submitted, or to refrain from bidding in connection with such Contract, or has in any manner, directly or indirectly, sought agreement, collusion, communication or conference in the attached Bid or any other Bidder, or to fix any overhead, profit or cost element of the…