The document is a comprehensive set of bidding specifications for the Orange County Senior Center and Innovation Lab project in Orlando, Florida, solicited by Orange County Government. The project involves the construction of a new senior center and innovation facility, with an estimated total cost of $14,000,000. Sealed electronic bids will be accepted through the OpenGov e-Procurement Platform until 4:00 pm EST on Tuesday, September 24, 2024. Potential bidders are required to submit electronic responses and can ask questions through the platform's question and answer module by Monday, August 12, 2024, at 5:00 pm EST.
The bidding documents include detailed technical specifications covering multiple divisions of construction, including structural elements, architectural components, mechanical and electrical systems, and finishing work. The project requires comprehensive documentation, including shop drawings, product data, material certifications, and compliance with various building and safety standards. Funding appears to be from county sources, potentially including grant funding, and the project emphasizes sustainable design practices, quality control, and adherence to local building codes. Bidders must demonstrate technical expertise, provide comprehensive documentation, and comply with specific installation, fabrication, and quality assurance requirements outlined in the extensive technical specifications.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
R+B 23010-0001 July 03, 2024
OOrraannggee CCoouunnttyy SSeenniioorr CCeenntteerr aanndd
IInnnnoovvaattiioonn LLaabb 77114499 WWeesstt CCoolloonniiaall DDrriivvee,, OOrrllaannddoo FFLL 3322881188
Orange County Government Orange County, Florida
SSPPEECCIIFFIICCAATTIIOONNSS -- VVoolluummee -- 11
Divisions 1 Through 12
Client:
400 East South Street, Suite 500 Orlando, Florida 32801
Owner:
400 East South Street, Suite 500 Orlando, Florida 32801
BIDDING DOCUMENTS
605 E. Robinson St. Ste 750 Orlando, FL 32801
407.648.7288 phone
AA0002809
http://www.orangecountyfl.net/cms/
R+B 23010-0001 July 03, 2024
THIS PAGE INTENTIONALLY LEFT BLANK
ORANGE COUNTY SENIOR CENTER AND INNOVATION LAB BIDDING DOCUMENTS
ORANGE COUNTY GOVERNMENT RHODES+BRITO 23010-0001
TABLE OF CONTENTS TOC - 1
VOLUME - 1
COVER PAGE
TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
011000 SUMMARY
012300 ALTERNATES
012500 SUBSTITUTION PROCEDURES
012600 CONTRACT MODIFICATION PROCEDURES
012900 PAYMENT PROCEDURES
013100 PROJECT MANAGEMENT AND COORDINATION
013119 PROJECT MEETINGS
013200 CONSTRUCTION PROGRESS DOCUMENTATION
013230 PHOTOGRAPHIC DOCUMENTATION
013300 SUBMITTAL PROCEDURES
014000 QUALITY REQUIREMENTS
014200 REFERENCES
015000 TEMPORARY FACILITIES AND CONTROLS
016000 PRODUCT REQUIREMENTS
017300 EXECUTION
017329 CUTTING AND PATCHING
017419 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
017700 CLOSEOUT PROCEDURES
017800 WARRANTIES AND BONDS
017823 OPERATION AND MAINTENANCE DATA
017839 PROJECT RECORD DOCUMENTS
017900 DEMONSTRATION AND TRAINING
019113 GENERAL COMMISSIONING REQUIREMENTS
DIVISION 02 - EXISTING CONDITIONS
023000 SUB-SURFACE CONDITIONS
024100 DEMOLITION
024113 PAVEMENT REMOVAL
024119 SELECTIVE DEMOLITION
DIVISION 03 - CONCRETE
030000 CAST-IN-PLACE CONCRETE
033543 SEALED CONCRETE FINISHING
DIVISION 04 - MASONRY
042000 UNIT MASONRY
042223 DECORATIVE CONCRETE UNIT MASONRY
TABLE OF CONTENTS TOC - 2
DIVISION 05 - METALS
051200 STRUCTURAL STEEL FRAMING
054000 COLD-FORMED METAL FRAMING
055000 METAL FABRICATIONS
055213 PIPE AND TUBE RAILINGS
057500 DECORATIVE FORMED METAL
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
061053 MISCELLANEOUS ROUGH CARPENTRY
064023 INTERIOR ARCHITECTURAL WOODWORK
064116 PLASTIC-LAMINATE-FACED ARCHITECTURAL CABINETS
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
072100 BUILDING INSULATION
074213 METAL WALL PANELS
076200 SHEET METAL FLASHING AND TRIM
078413 PENETRATION FIRESTOPPING
078443 JOINT FIRESTOPPING
079200 JOINT SEALANTS
DIVISION 08 - OPENINGS
081113 HOLLOW METAL DOORS AND FRAMES
081416 FLUSH WOOD DOORS
083113 ACCESS DOORS AND FRAMES
083800 TRAFFIC DOORS
084113 ALUMINUM-FRAMED ENTRANCES AND STOREFRONTS
084229 SLIDING AUTOMATIC ENTRANCES
087100 DOOR HARDWARE
088000 GLAZING
088413 DECORATIVE PLASTIC GLAZING
088300 MIRRORS
088836 SWITCHABLE GLASS
089119 FIXED LOUVERS
TABLE OF CONTENTS TOC - 3
DIVISION 09 - FINISHES
092216 NON-STRUCTURAL METAL FRAMING
092900 GYPSUM BOARD
093000 TILING
095113 ACOUSTICAL PANEL CEILINGS
095153 DIRECT-APPLIED ACOUSTICAL CEILINGS
095423 LINEAR METAL CEILINGS
096513 RESILIENT BASE AND ACCESSORIES
096516 RESILIENT SHEET FLOORING
096536 STATIC-CONTROL RESILIENT FLOORING
096540 LUXURY VINYL TILE
096566 RESILIENT ATHLETIC FLOORING
096723 RESINOUS FLOOR COATINGS
096813 TILE CARPETING
097200 WALL COVERINGS
097813 DECORATIVE INTERIOR METAL WALL PANELS
098413 FIXED SOUND ABSORPTIVE PANELS
098436 SUSPENDED CEILING BAFFLES
099100 PAINTING
DIVISION 10 - SPECIALTIES
101100 VISUAL DISPLAY UNITS
101416 PLAQUES
101423 PANEL SIGNAGE
102113 PLASTIC TOILET COMPARTMENTS
102226 OPERABLE PARTITIONS
102600 WALL PROTECTION
102813 TOILET ACCESSORIES
104413 FIRE PROTECTION CABINETS
104416 FIRE EXTINGUISHERS
105113 METAL LOCKERS
107316 ALUMINUM CANOPIES
DIVISION 11 - EQUIPMENT
114000 FOOD SERVICE EQUIPMENT
116123 PORTABLE STAGES
116133 RIGGING SYSTEMS
116143 MASKING CURTAINS
DIVISION 12 - FURNISHINGS
123661.16 SOLID SURFACE COUNTERTOPS
123661.19 QUARTZ AGGLOMERATE COUNTERTOPS
123661.23 TERRAZZO COUNTERTOPS
TABLE OF CONTENTS TOC - 4
VOLUME - 2
COVER PAGE
TABLE OF CONTENTS
DIVISION 21 - FIRE SUPPRESSION
210513 COMMON MOTOR REQUIREMENTS FOR FIRE SUPPRESSION EQUIPMENT
210517 SLEEVES AND SLEEVE SEALS FOR FIRE-SUPPRESSION PIPING
210518 ESCUTCHEONS FOR FIRE-SUPPRESSION PIPING
210553 IDENTIFICATION FOR FIRE-SUPPRESSION PIPING AND EQUIPMENT
211100 FACILITY FIRE-SUPPRESSION WATER-SERVICE PIPING
211313 WET-PIPE SPRINKLER SYSTEMS
DIVISION 22 - PLUMBING
220500 COMMON WORK RESULTS FOR PLUMBING
220519 METERS AND GAGES FOR PLUMBING PIPING
220523 GENERAL-DUTY VALVES FOR PLUMBING PIPING
220529 HANGERS AND SUPPORTS FOR PLUMBING PIPING AND EQUIPMENT
220553 IDENTIFICATION FOR PLUMBING PIPING AND EQUIPMENT
220700 PLUMBING INSULATION
221116 DOMESTIC WATER PIPING
221119 DOMESTIC WATER PIPING SPECIALTIES
221316 SANITARY WASTE AND VENT PIPING
221319 SANITARY WASTE PIPING SPECIALTIES
223300 ELECTRIC DOMESTIC WATER HEATERS
224000 PLUMBING FIXTURES
224700 DRINKING FOUNTAINS AND WATER COOLERS
TABLE OF CONTENTS TOC - 5
DIVISION 23 - HEATING VENTILATING AND AIR CONDITIONING
230500 COMMON WORK RESULTS FOR MECHANICAL
230510 BASIC MECHANICAL MATERIALS AND METHODS
230513 COMMON MOTOR REQUIREMENTS FOR HVAC EQUIPMENT
230517 SLEEVES AND SLEEVE SEALS FOR HVAC PIPING
230529 HANGERS AND SUPPORTS FOR HVAC PIPING AND EQUIPMENT
230548 VIBRATION AND SEISMIC CONTROLS FOR HVAC PIPING AND EQUIPMENT
230553 IDENTIFICATION FOR HVAC PIPING AND EQUIPMENT
230593 TESTING, ADJUSTING, AND BALANCING
230713 DUCT INSULATION
230716 HVAC EQUIPMENT INSULATION
230719 HVAC PIPING INSULATION
230800 COMMISSIONING OF HVAC
230900 INSTRUMENTATION AND CONTROL FOR HVAC
230923 BUILDING AUTOMATION SYSTEM
232123 HYDRONIC PUMPS
233113 METAL DUCTS
233300 DUCT ACCESSORIES
233423 POWER VENTILATORS
233600 AIR TERMINALS
233713 DIFFUSERS, REGISTERS, AND GRILLES
233723 HVAC GRAVITY VENTILATORS
234400 AIR PURIFICATION SYSTEM
238126 SPLIT-SYSTEM AIR-CONDITIONERS
DIVISION 26 - ELECTRICAL
260500 COMMON WORK RESULTS FOR ELECTRICAL
260501 INVESTIGATION OF EXISTING ELECTRICAL SYSTEMS
260519 LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES
260526 GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS
260529 HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS
260533 RACEWAY AND BOXES FOR ELECTRICAL SYSTEMS
260536 CABLE TRAYS FOR ELECTRICAL SYSTEMS
260553 IDENTIFICATION FOR ELECTRICAL SYSTEMS
260573 OVERCURRENT DEVICE COORDINATION WITH ARC FLASH ANALYSIS
260800 COMMISSIONING OF ELECTRICAL
260816 DEMONSTRATION OF COMPLETED ELECTRICAL SYSTEMS
260923 STAND ALONE LIGHTING CONTROL DEVICES
262200 LOW-VOLTAGE TRANSFORMERS
262416 PANELBOARDS
262726 WIRING DEVICES
262813 FUSES
262913 ENCLOSED CONTROLLERS
262923 VARIABLE-FREQUENCY MOTOR CONTROLLERS
264113 LIGHTNING PROTECTION FOR STRUCTURES
264313 SURGE PROTECTION DEVICES
265100 INTERIOR LIGHTING
265600 EXTERIOR LIGHTING
TABLE OF CONTENTS TOC - 6
DIVISION 27 - COMMUNICATIONS
270500 COMMON WORK RESULTS FOR COMMUNICATIONS
271000 VOICE-DATA CABLE INFRASTRUCTURE
271015 NETWORK ELECTRONICA
274113 AUDIO VIDEO SYSTEMS
275800 TV DISTRIBUTION SYSTEM
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
280500 COMMON WORK RESULTS FOR ELECTRONIC SAFETY AND SECURITY
282210 ACCESS CONTROL SYSTEM
282510 CCTV SYSTEM
283100 FIRE ALARM SYSTEM
DIVISION 31 - EARTHWORK
310000 EARTHWORK
311000 SITE CLEARING
312300 EARTHWORK - UNDERGROUND UTIL
312500 EROSION AND SEDIMENTATION
313200 SUBGRADE STABILIZATION
DIVISION 32 - EXTERIOR IMPROVEMENTS
321200 ASPHALTIC CONCRETE PAVING
321600 CONCRETE CURBS, WALKS, DRIVEWAYS
321723 PAVEMENT MARKINGS
323113 CHAIN LINK GATES
323116 WELDED WIRE FENCES AND GATES
323119 DECORATIVE ALUMINUM GATES
DIVISION 33 - UTILITIES
331000 POTABLE WATER SYSTEMS
333000 SEWAGE COLLECTION SYSTEM
334000 STORM SEWER SYSTEM
END OF TABLE OF CONTENTS
SUMMARY OF WORK 011000 - 1
SECTION 011000 - SUMMARY OF WORK
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
B. When the titles such as Engineer, Project Engineer, or Owner are used throughout the specification, this implies Orange County as property Owner and/or an officially appointed County Representative.
1.2 PROJECT INFORMATION
A. Project Identification: Senior Center and Center for Innovation and Design.
B. Architect: Rhodes + Brito Architects.
1.3 SCOPE OF WORK
A. Summary of Work: As indicated on the Drawings.
1.4 CONTRACTOR RESPONSIBILITIES
A. The contractor shall have all submittals approved by the Engineer and accepted by the Owner prior to the start of active construction.
B. The contractor shall have all equipment and material onsite prior to the start of active construction.
C. The contractor shall submit to the Owner prior to the project pre-construction meeting the following:
• Schedule of Values
• Construction Schedule
• Submittal Schedule
• Emergency Telephone List including subcontractors and suppliers
D. The contractor shall field verify existing conditions of construction prior to start of active construction.
SUMMARY OF WORK 011000 - 2
E. The contractor shall coordinate with the Owner on the operation of the existing fire alarm system prior to the start of active construction. There shall be an action plan for the operation of the fire alarm system during construction submitted by the contractor to the Owner for acceptance. This action plan shall be in place prior to the start of active construction. Any false fire alarms that occur during construction and deemed by the Owner to be the fault of the contractor, the contractor shall pay all costs incurred from the local fire department for responding to a false alarm.
F. The contractor is responsible for moving furniture and/or equipment if necessary to perform the work included in the contract. The contractor is responsible for placing the furniture and/or equipment back in its original location. The contractor is responsible for any damages to furniture, equipment, etc., which occur during construction. The contractor shall provide protection for floors, walls, furniture, equipment and any other items that may be subject to damage during the construction periods and will be required to repair or replace to original or better condition.
G. The contractor shall coordinate with the Owner on the operation of the security alarm system prior to the start of active construction. The contractor shall submit an action plan for operation of the security alarm system during construction to the Owner for acceptance prior to start of active construction. This action plan shall be in place prior to the start of active construction.
Any false security alarms that occur during construction and deemed by the Owner to be the fault of the contractor, the contractor shall pay all cost incurred from the local police and/or sheriff department for responding to a false alarm.
H. The contractor shall take digital pictures or video of pre-existing conditions of the interior and exterior of the building prior to the start of active construction. Failure to provide digital pictures or video prior to start of construction places the responsibility on the Contractor to complete the necessary replacement, repairs, and/or cleaning as determined by the Owner, at no additional cost to the Owner. One CD copy of digital pictures or video of the existing site conditions shall be submitted to the Owner.
I. The contractor shall at all times maintain daily cleanup of construction areas. Costs for work areas that are not cleaned by the contractor will be cleaned by the Owner and those costs shall be charged back to the contractor via change order.
J. The contractor shall provide a construction schedule to the Owner's Project Manager prior to the pre-construction meeting.
K. The contractor shall update the construction schedule weekly and submit it to the Owner's Project Manager for review.
1.5 WORK COVERED BY CONTRACT DOCUMENTS
A. Type of Contract:
1. Project will be constructed under a single prime contract.
1.6 WORK UNDER OTHER CONTRACTS
A. Separate contracts may be issued to perform certain construction operations at the site. The contractor of this project will allow reasonable access and coordination to the other contractor/s.
SUMMARY OF WORK 011000 - 3
1.7 WORK SEQUENCE
A. Work Hours shall be fully coordinated in writing with Orange County Project Manager prior to commencement of work.
B. The contractor may work on the weekends at his or her discretion with prior written approval from Orange County Project Manager. Weekend work shall not be an additional cost to the Owner. The contractor will coordinate with the Orange County Project Manager for access to the building on weekends and after hours work.
1.8 CONTRACTOR USE OF PREMISES
A. Unrestricted Use of Site: Contractor shall have full use of Project site for construction operations during construction period. Contractor's use of Project site is limited only by Owner's right to perform work or to retain other contractors on portions of Project.
B. Limits on Use of Site: Limit use of Project site to areas within the Contract limits indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.
C. Burial of Waste Materials: Do not dispose of organic and hazardous material on site, either by burial or by burning.
D. Provide protection and safekeeping of material and equipment stored on premises.
E. Comply with Owner's requirements for ingress and egress procedures, prohibitions against firearms, procedures for transportation of workers, safety and fire prevention requirements and all applicable pollution control requirements. Refer to the following reference requirements:
1. Orange County Safety and Health Manual http://www.orangecountyfl.net/VendorServices/OrangeCountySafetyandHe althManual.aspx#.Wql6OU2oupo
2. Orange County Policy Manual page 96 regarding Firearms http://www.orangecountyfl.net/portals/0/resource%20library/employment% 20- %20volunteerism/Policy%20Manual.pdf
F. Contractor to require all employees and subcontractors to wear non- objectionable clothing;
prohibit revealing clothing and articles of clothing with offensive writings displayed. The contractor shall require offending personnel to leave the premises until such clothing is changed.
G. Contractor employees and subcontractors will not fraternize with County employees or the general public during the entire construction period.
H. Use of sound equipment (such as boom boxes, stereos, radios, etc.) is not allowed.
I. Contractor and their personnel shall abide to Orange County Tobacco free policy while on any Orange County property. This policy shall apply to building, parking lots, parks, break areas and worksites. Tobacco is defined as tobacco products, including but not limited to:
Cigars, cigarettes, pipes, chewing tobacco and snuff. Failure to abide by the policy may result in civil penalties levied under Chapter 386, Florida Statutes and/or Contract enforcement remedies. Refer to the following documents:
http://www.orangecountyfl.net/VendorServices/OrangeCountySafetyandHe http://www.orangecountyfl.net/portals/0/resource%20library/employment%25
SUMMARY OF WORK 011000 - 4
1. Orange County Smoking Policy:
http://www.orangecountyfl.net/Portals/0/resource%20library/employment% 20- %20volunteerism/Employee%20Handbook.pdf
J. Conduct that is disrespectful, abusive or otherwise objectionable to the Owners' employees or general public will not be allowed at any time during the construction period. Repetitive complaints and violations of the requirements listed above will be cause for dismissal and or permanent removal of offending personnel from the project.
K. Contractor to coordinate with the Owner the site location for storage of equipment, machinery, materials, tools and a construction waste dumpster.
L. Contractor shall at all times keep the premises free of all waste or surplus materials, rubbish and debris, which is caused by contractor employees or subcontractors resulting from their work. Contractor shall maintain a safe work environment to all building occupants during the construction period.
1.9 SECURITY AND IDENTIFICATION
A. All costs for background investigations will be Contractor's responsibility. The County shall have the right to request any additional investigative background information including, but limited to, the employment record, Right-To-Know records, E-Verify system records (if the Contractor uses this service as a means to determine employment eligibility, available through www.uscis.gov), training records, payroll records, position for which hired including site location of any personnel assigned to perform the services. The Contractor shall furnish, in writing, such information to the extent allowed by law, prior to commencement of services. The County reserves the right to conduct its own investigation of any employee of the Contractor.
B. A Level 1 (5 years) Background Check for the contractor's staff must be approved by Orange County's Security team prior to working in any County facility. Contractors are responsible for obtaining the necessary forms for background checks for work at the .
1. For security purposes and to maintain privacy when submitting FDLE Background Checks via e-mail the subject line of the email must contain the following
**EXEMPT**.
2. The County will inform the contractor of their Background Check results.
3. Upon Background Check approval the contractor's staff shall arrange an appointment with the County staff to obtain an Orange County photo ID badge. An affidavit of Identity form (issued by the contractor) and a State of Florida ID or Drivers License will be required.
C. Contractor's employees will not be allowed in Orange County facilities without completed and approved background investigations.
1.10 DISTRIBUTION OF RELATED DOCUMENTS
A. The Contractor is solely responsible for the distribution of ALL related documents/drawings to ALL appropriate vendors/subcontractors to ensure proper coordination of all aspects of the project and its related parts during bidding and construction.
http://www.orangecountyfl.net/Portals/0/resource%20library/employment%25
SUMMARY OF WORK 011000 - 5
1.11 CONTRACT DOCUMENT FILE
A. Copies of the Contract Documents, Plans, Specifications, Addenda, Change Orders, Engineers Supplemental Instructions, approved Shop Drawings, Substitution Acceptances, etc. shall be placed and maintained at the project site by the Contractor throughout the entire contract period. These said documents shall be filed in a manner that allows for ease of retrieval.
Documents shall be made available to the Engineer and the County's representatives throughout this same period.
1.12 SPECIFICATION AND DRAWING CONVENTIONS
A. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations.
These conventions are as follows:
1. Imperative mood and streamlined language are generally used in the Specifications.
The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.
2. Specification requirements are to be performed by Contractor unless specifically stated otherwise.
B. Division 01 General Requirements: Requirements of Sections in Division 01 apply to the Work of all Sections in the Specifications.
PART 2 - PRODUCTS
2.1 ASBESTOS FREE MATERIAL
A. Contractor shall provide a written and notarized statement on company letterhead(s) to certify and warrant that ONLY ASBESTOS FREE MATERIALS AND PRODUCTS were provided AS REQUIRED BY THE Engineer. Such statement shall be submitted with the final payment request. Final payment shall not be made until such statement is submitted. Contractor agrees that if materials containing asbestos are subsequently discovered at any future time to have been included in the construction, the Contractor shall be liable for all costs related to the redesign or modification of the construction of the project so that materials containing asbestos are removed from the facility. If construction has begun or has been completed pursuant to a design that includes asbestos containing materials, the Contractor shall also be liable for all costs related to the abatement of such asbestos.
PART 3 - EXECUTION (Not applicable).
END OF SECTION 011000
SUMMARY OF WORK 011000 - 6
ALTERNATES 012300 - 1
SECTION 012300 - ALTERNATES
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative and procedural requirements for alternates.
1.3 DEFINITIONS
A. Alternate: An amount proposed by bidders and stated on the Bid Form for certain work defined in the bidding requirements that may be added to or deducted from the base bid amount if the Owner decides to accept a corresponding change either in the amount of construction to be completed or in the products, materials, equipment, systems, or installation methods described in the Contract Documents.
1. Alternates described in this Section are part of the Work only if enumerated in the Agreement.
2. The cost or credit for each alternate is the net addition to or deduction from the Contract Sum to incorporate alternates into the Work. No other adjustments are made to the Contract Sum.
1.4 PROCEDURES
A. Coordination: Revise or adjust affected adjacent work as necessary to completely integrate work of the alternate into Project.
1. Include, as part of each alternate, miscellaneous devices, accessory objects, and similar items incidental to or required for a complete installation, whether or not indicated as part of alternate.
B. Execute accepted alternates under the same conditions as other Work of the Contract.
C. Schedule: A Part 3 "Schedule of Alternates" Article is included at the end of this Section.
Specification Sections referenced in schedule contain requirements for materials necessary to achieve the work described under each alternate.
ALTERNATES 012300 - 2
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 SCHEDULE OF ALTERNATES
A. The Base Bid includes the complete set of documents with design of the Gathering Space (Room 114) as a shell space with no internal walls, interior partitioning, finishes, and equipment. The space will be prepared (utilities stubbed up) for receiving new future equipment and finishes while only providing the minimum code required utility for life safety systems, such as a fire protection system, lighting, HVAC (no distribution), fire alarm, and other assets needed to maintain the integrity of the space for future build-out. Add Alt. No.
1 and Add Alt No. 2 describe the level of interior equipment and finish upgrades within Gathering Space (Room 114), whereas Add Alt. No. 3 will address exterior improvements.
1. Add Alt No. 1 (Partial Build-Out Gathering Space (Room 114)) - Includes a level of finish for the space to be move in ready to include internal walls and interior space partitioning for Green Rooms 113A and 113B.
2. Improvements include:
a. Epoxy flooring
b. Drywall at perimeter
c. Wall partitions
d. Painted walls
e. Acoustical wall panels
f. Painted exposed ceiling
g. Linear ambient lighting
h. Fire protection system
i. Fire alarm
j. HVAC with distribution
k. Plumbing (stubbed up)
l. Low voltage infrastructure for future build-out
m. Electrical power as required and conduit for future equipment
3. Add Alt 2 No. 2 (Complete Build-Out Gathering Space (Room 114)) - As described in the construction documents, Add Alt No. 2 is the complete build-out of the space with owner and contractor provided and installed furnishings and equipment. Items omitted in Add Alt No. 1 will be included with this alternate bid.
4. Improvements include:
a. Demountable stage with associated wheel chair lift and stairs
b. Operable partition with associated soffits and lighting
c. Theatrical lighting and sound with associated equipment
d. Millwork
e. Video monitors
5. Add Alt No. 3 (Patio) - Located east of the site within parking, Add Alt No. 3 will include an exterior patio build-out with associated civil and landscape improvements. The exterior patio will include a tensile canopy structure along with a wood plank deck on wood framing with galvanized steel guardrails.
END OF SECTION 012300
SUBSTITUTION PROCEDURES 012500 - 1
SECTION 012500 - SUBSTITUTION PROCEDURES
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. This Section specifies administrative and procedural requirements for handling request for substitutions made during bidding and after award of the Contract.
B. The Contractor's Installation Schedule and the Schedule of Submittals are included under Section "Submittal Procedures".
1.3 DEFINITIONS
A. Definitions used in this Article are not intended to change or modify the meaning of other terms used in the Contract Documents.
B. Substitutions: The Contract will be awarded based on the design, methods, materials and/or equipment as addressed in the Contract Drawings and/or described in the Contract Specifications. Addressing, describing or naming an item is intended to establish the type, function, characteristics and quality required in order to establish a base for bidding.
1. During bidding, the Contractor may submit for approval substitutes for any equipment and/or material. In addition to the product documents, a written certification shall accompany the documentation indicating that the proposed substitute will have the same characteristics, will perform in accordance with the design requirements and that complies with all the requirements set for in the Contract. Any additional information required by the Owner or County Representative shall be provided by the Contractor.
Rejection of any proposed substitute will be considered final and the Contractor shall not get into any agreement with manufacturers or providers until the submittal has been finally approved.
2. The basis design shall establish the minimum standard of quality.
3. Any substitution requested made after contract award will not be considered.
1.4 SUBMITTALS
A. Substitution Request Submittal: Request for substitution will be considered if received within thirty (30) days after contract award. As long as this time allowance will not impact the construction schedule.
1. Submit three (3) copies of each request for substitution for consideration. Submit requests in the form and in accordance with procedures required for Change Order proposals.
SUBSTITUTION PROCEDURES 012500 - 2
2. Identify the product, or the fabrication or installation method to be replaced in each request. Include related Specification Section number and Drawing numbers and titles. Provide complete documentation showing compliance with the requirements for substitution, and the following information, as appropriate:
a. Statement indicating why specified product or fabrication or installation cannot be provided, if applicable.
b. Coordination information, including a list of changes or modifications needed to other parts of the Work and to construction performed by Owner and separate contractors that will be necessary to accommodate proposed substitution.
c. Product Data, including Drawings, and descriptions of products, fabrication and installation procedures.
d. Samples, where applicable or requested.
e. A detailed comparison of significant qualities of the proposed substitution with those of the Work specified. Significant qualities may include elements such as size, weight, durability, performance and visual effect.
f. Coordination information, including a list of changes or modifications needed to other parts of the Work and to construction performed by the Owner and separate Contractors that will become necessary to accommodate the proposed substitution.
g. A statement indicating the substitution's effect on the Contractor's construction schedule compared to the schedule without approval of the substitution. Indicate the effect of the proposed substitution on overall Contract Time.
h. Cost information, including a proposal of the net change, if any in the Contract Sum.
i. Certificates and qualification data, where applicable or requested. Certification by the Contractor that the Substitution proposed is equal-to or better in every significant respect to that required by the Contract Documents, and that it will perform adequately in the application indicated. Include the contractor's waiver of rights to additional payment or time that may subsequently become necessary because of the failure of the substitution to perform adequately.
j. List of similar installations for completed projects with project names and addresses and names and addresses of architects and owners.
k. Material test reports from a qualified testing agency indicating and interpreting test results for compliance with requirements indicated.
l. Research reports evidencing compliance with building code in effect for Project.
m. Detailed comparison of Contractor's construction schedule using proposed substitution with products specified for the Work, including effect on the overall Contract Time. If specified product or method of construction cannot be provided within the Contract Time, include letter from manufacturer, on manufacturer's letterhead, stating date of receipt of purchase order, lack of availability, or delays in delivery.
n. Cost information, including a proposal of change, if any, in the Contract Sum.
o. Contractor's certification that proposed substitution complies with requirements in the Contract Documents except as indicated in substitution request, is compatible with related materials, and is appropriate for applications indicated.
p. Contractor's waiver of rights to additional payment or time that may subsequently become necessary because of failure of proposed substitution to produce indicated results.
3. Engineer's Action: Within two weeks of receipt of the request for substitution, the Engineer will request additional information or documentation necessary for evaluation of the request if needed. Within two (2) weeks of receipt of the request, or one week of receipt of the additional information or documentation, whichever is later, the Engineer will notify the Contractor of acceptance or rejection of the proposed substitution. If a decision on use of a proposed substitute cannot be made or obtained
SUBSTITUTION PROCEDURES 012500 - 3
within the time allocated, use the project specified by name. Decision on the use of a product substitution or its rejection by the Engineer is considered final. Acceptance will be in the form of a Change Order.
4. Architect's Action: If necessary, Architect will request additional information or documentation for evaluation within 10 days of receipt of a request for substitution.
Architect will notify Contractor of acceptance or rejection of proposed substitution within 5 days of receipt of request, or 7 days of receipt of additional information or documentation, whichever is later.
a. Forms of Acceptance: Change Order, Construction Change Directive, or Architect's Supplemental Instructions for minor changes in the Work.
b. Use product specified if Architect does not issue a decision on use of a proposed substitution within time allocated.
1.5 QUALITY ASSURANCE
A. Compatibility of Substitutions: Investigate and document compatibility of proposed substitution with related products and materials. Engage qualified testing agency to perform compatibility tests recommended by manufacturers.
PART 2 - PRODUCTS
2.1 SUBSTITUTIONS
A. Conditions: The Contractor's substitution request will be received and considered by the Engineer when one or more of the following conditions are satisfied, as determined by the Engineer; otherwise request will be returned without action except to record noncompliance with these requirements.
1. Extensive revisions to Contract Documents are not required.
2. Proposed changes are in keeping with the general intent of Contract Documents.
3. The request is timely, fully documented and properly submitted.
4. The specified product or method of construction cannot be provided within the
Contract Time. The request will not be considered if the product or method cannot be provided as a result of failure to pursue the work promptly or coordinate activities properly.
5. The specified product or method of construction cannot receive necessary approval by a governing authority, and the requested substitution can be approved.
6. A substantial advantage is offered to the Owner, in terms of cost, time, energy conservation or other considerations of merit, after deducting offsetting responsibilities the Owner may be required to bear. Additional responsibilities for the Owner may include additional compensation to the Engineer for redesign and evaluation services, increased cost of other construction by the Owner or separate Contractors, and similar consideration.
7. The specified product or method of construction cannot be provided in a manner that is compatible with other materials, and where the Contractor certifies that the substitution will overcome the incompatibility.
8. The specified product or method of construction cannot be coordinated with other materials, and where the Contractor certifies that the proposed substitution can be coordinated.
SUBSTITUTION PROCEDURES 012500 - 4
9. The specified product or method of construction cannot provide a warranty required by the Contract Documents and where the Contractor certifies that the proposed substitution provide the required warranty.
B. The Contractor's submittal and Project Manager's acceptance of Shop Drawings, Product Data or Samples that relate to construction activities not complying with the Contract Documents does not constitute an acceptable or valid request for substitution, nor does it constitute approval.
C. Substitution request constitutes a representation that the Contractor:
1. Has investigated proposed product and determined that it meets or exceeds, in all respects, specified product.
2. Will provide the same warranty for substitution as for specified product.
3. Will coordinate installation and make other changes which may be required for work to be complete in all respects.
4. Waives claims for additional costs which may subsequently become apparent. All costs associated with the substitution will be paid by the Contractor regardless of approvals given, and regardless of subsequent difficulties experienced as a result of substitutions.
END OF SECTION 012500
CONTRACT MODIFICATION PROCEDURES 012600 - 1
SECTION 012600 - CONTRACT MODIFICATION PROCEDURES
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. This section specifies administrative and procedural requirements for handling and processing Contract modifications.
1.3 MINOR CHANGES IN THE WORK
A. Supplemental instructions authorizing minor changes in the work, not involving an adjustment to the Contract Sum or Contract Time, will be issued by the Project Manager.
B. Architect will issue supplemental instructions authorizing Minor Changes in the Work, not involving adjustment to the Contract Sum or the Contract Time, on AIA Document "Architect's Supplemental Instructions."
1.4 CHANGE ORDER PROPOSAL REQUESTS
A. Owner-Initiated Proposal Requests: Architect will issue a detailed description of proposed changes in the work that will require adjustment to the Contract Sum or Contract Time will be issued by the Project Manager, with a detailed description of the proposed change and supplemental or revised Drawings and Specifications, if necessary.
1. Proposal requests issued by the Architect are for information only. Do not consider them instruction either to stop work in progress, or to execute the proposed change.
2. Unless otherwise indicated in the proposal request, within 5 days of receipt of the proposal request, submit to the Project Manager from the Owner's review, an estimate of cost necessary to execute the proposed change.
a. Include a list of quantities of products to be purchased and unit costs, along with the total amount of purchases to be made. Where requested, furnish survey data to substantiate quantities.
b. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.
c. Include a statement indicating the effect the proposed change in the work will have on the Contract Time. Include an updated Contractor's Construction Schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.
d. Contractor and subcontractors will provide a complete detailed labor and material breakdown to justify change order request amount. Include costs of labor and supervision directly attributable to the change.
CONTRACT MODIFICATION PROCEDURES 012600 - 2
B. Contractor-Initiated Change Order Proposal Requests: When latent or other unforeseen conditions in mutual accord with the Owner Representatives findings require modifications to the Contract, the Contractor may propose changes by submitting a request for a change to the Engineer/Architect.
1. Include a statement outlining the reasons for the change and the effect of the change on the Work. Provide a complete description of the proposed change. Indicate the effect of the proposed change on the Contract Sum and Contract Time.
2. Include a list of quantities of products required or eliminated and unit costs, with total amount of to be purchased and unit costs along with the total amount of purchases to be made. Where requested, furnish survey data to substantiate quantities.
3. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.
4. Include costs of labor and supervision directly attributable to the change.
5. Comply with requirements in Section 012500 "Substitution Procedures" - if the proposed change in the work requires that substitution of one product or system for a product or system not specified.
6. Contractor and subcontractors will provide a complete detailed labor and material breakdown to justify change order request amounts.
7. Include an updated Contractor's Construction Schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.
C. Proposal Request Form: Project Manager will transfer the information to the appropriate forms for approval. Use AIA Document G 709 for Change Order Proposal Requests.
D. Proposal Request Form: Use forms provided by the Owner for Change Order Proposals.
1.5 CONSTRUCTION CHANGE DIRECTIVE
A. Construction Change Directive: When the Owner and Contractor are not in total agreement on the terms of a Change Order Proposal Request, the Project Manager may issue a Construction Change Directive instructing the Contractor to proceed with a change in the Work, for subsequent inclusion in a Change Order.
1. The Construction Change Directive will contain a complete description of the change in the Work and designate the method to be followed to determine change in the Contract Sum or Contract Time.
B. Documentation: Maintain detailed records on a time and material basis of work required by the Construction Change Directive.
1. After completion of the change, submit an itemized account and supporting data necessary to substantiate cost and time adjustments to the Contract.
1.6 CHANGE ORDER PROCEDURES
A. Upon the Owner's approval of a Change Order Proposal Request, the Project Manager will issue a Change Order for signatures of the Owner and Contractor on County's Change Order form, as provided in the Conditions of the Contract.
CONTRACT MODIFICATION PROCEDURES 012600 - 3
PART 2 - PRODUCTS (Not Applicable)
PART 3 - EXECUTION (Not Applicable)
END OF SECTION 012600
CONTRACT MODIFICATION PROCEDURES 012600 - 4
PAYMENT PROCEDURES 012900 - 1
SECTION 012900 - PAYMENT PROCEDURES
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative and procedural requirements necessary to prepare and process Applications for Payment.
B. The Contractor's Construction Schedule and Submittal Schedule are included in Section 0133 00 - “Submittal Procedures".
1.3 SCHEDULE OF VALUES
A. Coordinate preparation of the Schedule of Values with preparation of Contractor's Construction Schedule.
1. Correlate line items in the Schedule of Values with other required administrative forms and schedules, including Application for Payment forms with Continuation Sheets, Submittals Schedule, and Contractor's Construction Schedule.
2. Submit the Schedule of Values to the Owner at the earliest feasible date, but in no case later than Preconstruction Meeting. Submit the Schedule of Values to Architect 10 days after receipt of Notice to Proceed.
3. Sub-Schedules: Where the Work is separated into phases that require separately phased payments, provide sub-schedules showing values correlated with each phase of payment.
B. Format and Content: Use the Project Manual Table of Contents as a guide to establish the format for the Schedule of Values. Provide at least one line item for each Specification Section.
1. Identification: Include the following project identification on the Schedule of Values:
a. Project name and location.
b. Name of the Engineer/Architect
c. Architect's Project Number
d. Contractor's name and address
e. Date of submittal
2. Arrange the Schedule of Values in a tabular form with separate columns to indicate the following for each item listed:
a. Generic name
b. Related Specification Section
c. Change Orders (numbers) that have affected value
d. Dollar Value
PAYMENT PROCEDURES 012900 - 2
e. Percentage of Contract Sum to the nearest one-hundredth percent, adjusted to total 100 percent
3. Submit AIA Document G703 Continuation Sheets
4. Provide a breakdown of the Contract Sum in sufficient detail to facilitate continued evaluation of Applications for Payment and progress reports. Coordinate with the Project Manual table of contents. Break principal subcontract amounts down into several line items:
a. A value will be given for at least every major specification section (subsections can logically be grouped together).
b. A single material subcontractor will not be required to be broken down into labor and material unless it is anticipated the materials will be stored and invoiced prior to installation.
c. All multiple item subcontracts or work items (i.e. mechanical, electrical items, etc.) will be shown broken down at least in labor and material (all taxes, burden and overhead and profit included).
d. Mobilization (move-on, bond, insurance, temporary office and sanitary service installation) shall not exceed 2 1/2% of contract price.
e. For multi-story work all items broken down per floor.
f. HVAC: Typically shown per specification section, labor and material, per floor.
g. Electrical: same as HVAC.
h. Logical grouping of specification subsections are permitted.
5. Round amounts off the nearest whole dollar, the total shall equal the Contract Sum.
6. For each part of the Work where an Application for Payment may include materials or equipment, purchased or fabricated and stored, but not yet installed, provide separate line items on the Schedule of Values for initial cost of the materials, for each subsequent stage of completion, and for total installed value of that part of the Work.
7. Margins of Cost: Show line items for indirect costs, and margins on actual costs, only to the extent that such items will be listed individually in Applications for Payment.
Each item in the Schedule of Values and Applications for Payment shall be complete including its total cost and proportionate share of general overhead and profit margin.
a. At the Contractor's option, temporary facilities and other major cost items that are not direct cost of actual work-in-place may be shown as separate line items in the Schedule of Values or distributed as general overhead expense.
8. Schedule Updating: Update and resubmit the Schedule of Values before the next Applications for Payment when Change Orders or Construction Change Directives result in a change in the contract sum.
1.4 APPLICATIONS FOR PAYMENT
A. Each Application for Payment shall be consistent with previous applications and payments ascertified by the Owner's representative and paid for by the Owner.
1. The initial Application for Payment, the Application for Payment at time of Substantial Completion, and the Final Application for Payment involve additional requirements.
See items G, I, J and K of this section.
PAYMENT PROCEDURES 012900 - 3
B. Payment Application Times: The date for each progress payment is indicated in the Agreement between Owner and Contractor. The period of construction Work covered by each Application for Payment is the period indicated in the Agreement.
C. Payment Application Forms: Use the County's most updated form as the form for Application for Payment. Form given at the Preconstruction Conference. The date for each progress payment is indicated in the Agreement between Owner and Contractor. The period of construction Work covered by each Application for Payment is the period indicated in the Agreement.
D. Payment Application Times: Progress payments shall be submitted to Architect on the 5th of the month. The period covered by each Application for Payment is one month, ending on the last day of the month.
E. Payment Application Forms: Use AIA Document G702 and AIA Document G703 Continuation Sheets as form for Applications for Payment.
F. Application Preparation: Complete every entry on the form, including notarization and execution by person authorized to sign legal documents on behalf of the Owner. Architect will return incomplete applications will be returned without action.
1. Entries shall match data on the Schedule of Values and Contractor's Construction Schedule. Use updated schedules if revisions have been made.
2. Include amounts of Change Orders and Construction Change Directives issued prior to the last day of the construction period covered by the application.
G. Transmittal: Submit four (3) original executed copies of each Application for Payment to the Project Manager/Architect by method ensuring receipt within 24 hours; one copy shall be complete, including waivers of lien and similar attachments, when required.
1. Transmit each copy with a transmittal form listing attachments, and recording appropriate information related to the application in a manner acceptable to the Project Manager.
H. Waivers of Mechanics Lien: With each Application for Payment submit waivers of mechanics liens (lien from every entity who is lawfully entitled to file a mechanic's lien arising out of the Contract and related to the Work covered by the payment.) from subcontractors of sub-subcontractors and suppliers for the construction period covered by the previous application.
1. Submit partial waivers on each item for the amount requested, prior to deduction for retainage on each item.
2. When an application shows completion of an item, submit final or full waivers.
3. The Owner reserves the right to designate which entities involved in the work must submit waivers.
4. Waiver Forms: Submit waivers of lien on forms, executed in a manner acceptable to Owner.
5. List all Subcontractor's start and finish dates to substantiate any Notice to Owner received by the Project Manager.
I. Initial Application for Payment: Administrative actions and submittals that must precede or coincide with submittal of the first Application for Payment include the following:
1. List of principal subcontractors
2. List of principal suppliers and fabricators
3. Schedule of Values
4. Approved Contractor's Construction Schedule (preliminary if not final)
PAYMENT PROCEDURES 012900 - 4
5. Schedule of principal products
6. Schedule of unit prices (if applicable)
7. Submittal schedule (preliminary if not final)
8. List of Contractor's staff assignments
9. List of Contractor's principal consultants
10. Copies of building permits for trades requiring separate permits
11. Copies of authorizations and licenses from governing authorities for performance of the Work
12. Initial progress report
13. Report of Pre-construction Meeting
14. Initial settlement survey and damage report, (if required)
15. Listing of all long lead procurement items monthly applications for payment will be accompanied with updated schedule and review of as- built drawings
16. Certificates of insurance and insurance policies.
J. Interim Application for Payment: Payment will be processed once a month. No applications will be processed without receipt of previous month's waiver of lien described in subsection F above. Payment for item will be based on percentage completed as determined and approved by the County Project Manager or invoice for stored materials. Retainage (5%) will be held for all interim applications.
K. Application for Payment at Substantial Completion: Following issuance of the Certificate of Substantial Completion, submit an Application for Payment showing 100 percent completion for portion of the Work claimed as substantially complete. Application shall also include all items listed in Part H. above.
1. Include documentation supporting claim that the Work is substantially complete and a statement showing an accounting of changes to the Contract Sum.
2. This application shall reflect Certificates of Partial Substantial Completion issued previously for Owner occupancy of designated portions of the Work.
L. Administrative actions and submittals that shall proceed or coincide with Substantial Completion Payment.