This document is a detailed set of technical specifications for the Jumbo Evans Sports Park Infield Artificial Turf Installation project in Comal County, Texas. The project involves comprehensive artificial turf installation across six baseball/softball fields (Fields A through F), with each field requiring specific sub-grade preparation, drainage system installation, and turf implementation. The specifications include excavating 4 inches deep centered on the pitcher's mound, installing drainage trenches, placing a plastic barrier, installing perforated pipes, and laser grading with limestone. Each field requires installing composite nailer boards, inlaying white lines, and spreading specific amounts of SBR rubber and silica sand infill.
The artificial turf must meet precise technical specifications, including a KMTXProF 50 oz turf with a 1 ¾" pile height, UV stabilization, polyurethane backing, and specific performance characteristics like water permeability and fiber thickness. The project includes warranty requirements, with 2-year warranties on seam work and base work, and an 8-year warranty on the artificial turf itself. The contractor is responsible for adjusting irrigation systems, installing base plugs, and leaving cut turf pieces for future repairs. Each field has slightly different dimensions and base configurations, ranging from standard Little League fields to larger playing areas, with pitcher's mounds located at varying distances from home plate.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Jumbo Evans Sports Park Infield Artificial Turf Installation
Artificial Turf Requirements:
• KMTXProF Artificial Turf 50 oz 1 ¾” pile height, or equivalent, as approved by Comal County.
• Thatch zoom required, slit-film PE
• Primary Yarn Polymer – Polyethylene / Polypropolene
• UV Stabalized
• Primary Backing – Polyurethane
• Perforated
• Denier/Ends – 4600/8 Texturized PP
• Total Yard Linear Density Tensiile – 12,600
• Stregnth Silt PE Tensile 8 lbs
• Strength Texturized PP Stitch3.7 lbs
• Machine Gauge 1/2 inch
• Water Permeability > 30 in/hr
• Fiber Thickness 9.4 mils fiber thickness
A
B
C
D
E
F
Field A Sub-Grade, Drainage and
Base Preparation
Exit Point for perforated drainage system.
Final location to be approved by Comal County.
• Excavate 10,085 SF to a depth of 4” centered on pitchers mound, located 50’ from home plate, standard 50-70 Little League field
• Where radius intersects foul line, excavation shall extend perpendicular to the fence line
• Compact and laser grade sub-grade to level surface
• Install 4” deep trenches every 20’ O.C. throughout excavated area
• Install 6 millimeter plastic barrier on top of compacted sub-grade and in trenches.
• Install 4” perforated pipes within trenches with outfall point at location identified.
• Install, compact and laser grade 2” of #57 and #67 clean limestone, including in drainage trenches.
• Adjust, cap, and move existing irrigation lines/sprinkler heads/valve boxes, as needed, during excavation and reroute any necessary lines to ensure proper irrigation coverage of existing grass.
Excavation Area
Field A Turf Install
• Install 2” x 2” composite nailer boards around the perimeter of the infield to secure turf edges
• Install infield with the colors shown below. All white lines should be inlaid as part of installation; not painted
• Spread/broom 1.5 lbs per square foot of SBR rubber infill and 2.5 lbs per square foot of silica sand infill onto the turf
• Adjust/repair any portions of fence as needed to install nailer boards at the edges of the fence line
• Install base plugs for bases at both 60’ and 70’ as well as home plate
Turf Install
Field B
Base Preparation
Exit Point for perforated drainage system.
Final location to be approved by Comal County.
• Excavate 10,075 SF to a depth of 4” centered on pitchers mound located 50’ from home plate, standard 50-70 Little League field
• Where radius intersects foul line, excavation shall extend perpendicular to the fence line
• Compact and laser grade sub-grade to level surface
• Install 4” deep trenches every 20’ O.C. throughout excavated area
• Install 6 millimeter plastic barrier on top of compacted sub-grade and in trenches.
• Install 4” perforated pipes within trenches with outfall point at location identified.
• Install, compact and laser grade 2” of #57 and #67 clean limestone, including in drainage trenches.
• Adjust, cap, and move existing irrigation lines/sprinkler heads/valve boxes, as needed, during excavation and reroute any necessary lines to ensure proper irrigation coverage of existing grass.
Excavation
Field B
Turf Install Area
• Install 2” x 2” composite nailer boards around the perimeter of the infield to secure turf edges
• Install infield with the colors shown below. All white lines should be inlaid as part of installation; not painted
• Spread/broom 1.5 lbs per square foot of SBR rubber infill and 2.5 lbs per square foot of silica sand infill onto the turf
• Adjust/repair any portions of fence as needed to install nailer boards at the edges of the fence line
• Install base plugs for bases at both 60’ and 70’ as well as home plate
Field C
Base Preparation
• Excavate 13,965 SF to a depth of 4” centered on pitchers mound located 46’ from home plate, standard Little League field
• Where radius intersects foul line, excavation shall extend perpendicular to the fence line
• Compact and laser grade sub-grade to level surface
• Install 4” deep trenches every 20’ O.C. throughout excavated area
• Install 6 millimeter plastic barrier on top of compacted sub-grade and in trenches.
• Install 4” perforated pipes within trenches with outfall point at location identified.
• Install, compact and laser grade 2” of #57 and #67 clean limestone, including in drainage trenches.
• Adjust, cap, and move existing irrigation lines/sprinkler heads/valve boxes, as needed, during excavation and reroute any necessary lines to ensure proper irrigation coverage of existing grass.
Exit Point for perforated drainage system.
Final approval to be approved by Comal County.
Excavation
Field C
Turf Install Area
• Install 2” x 2” composite nailer boards around the perimeter of the infield to secure turf edges
• Install infield with the colors shown below. All white lines should be inlaid as part of installation; not painted
• Spread/broom 1.5 lbs per square foot of SBR rubber infill and 2.5 lbs per square foot of silica sand infill onto the turf
• Adjust/repair any portions of fence as needed to install nailer boards at the edges of the fence line
• Install base plugs for bases at both 60’ as well as home plate
Field D
Base Preparation
• Excavate 13,965 SF to a depth of 4” centered on pitchers mound located 46’ from home plate, standard Little League field
• Where radius intersects foul line, excavation shall extend perpendicular to the fence line
• Compact and laser grade sub-grade to level surface
• Install 4” deep trenches every 20’ O.C. throughout excavated area
• Install 6 millimeter plastic barrier on top of compacted sub-grade and in trenches.
• Install 4” perforated pipes within trenches with outfall point at location identified.
• Install, compact and laser grade 2” of #57 and #67 clean limestone, including in drainage trenches.
• Adjust, cap, and move existing irrigation lines/sprinkler heads/valve boxes, as needed, during excavation and reroute any necessary lines to ensure proper irrigation coverage of existing grass.
Exit Point for perforated drainage system.
Final approval to be approved by Comal County.
Excavation Area
Excavation
Field D
Turf Install Area
• Install 2” x 2” composite nailer boards around the perimeter of the infield to secure turf edges
• Install infield with the colors shown. All white lines should be inlaid as part of installation; not painted
• Spread/broom 1.5 lbs per square foot of SBR rubber infill and 2.5 lbs per square foot of silica sand infill onto the turf
• Adjust/repair any portions of fence as needed to install nailer boards at the edges of the fence line
• Install base plugs for bases at both 60’ as well as home plate
Turf Install
Field E
Base Preparation
• Excavate 26,905 SF to a depth of 4” centered on pitchers mound located 60’-6” from home plate.
• Where radius intersects foul line, excavation shall extend perpendicular to the fence line
• Compact and laser grade sub-grade to level surface
• Install 4” deep trenches every 20’ O.C. throughout excavated area
• Install 6 millimeter plastic barrier on top of compacted sub-grade and in trenches.
• Install 4” perforated pipes within trenches with outfall point at location identified.
• Install, compact and laser grade 2” of #57 and #67 clean limestone, including in drainage trenches.
• Adjust, cap, and move existing irrigation lines/sprinkler heads/valve boxes, as needed, during excavation and reroute any necessary lines to ensure proper irrigation coverage of existing grass.
Exit Point for perforated drainage system.
Final approval to be approved by Comal County.
Excavation
Field E
Turf Install Area
• Install 2” x 2” composite nailer boards around the perimeter of the infield to secure turf edges
• Install infield with the colors shown. All white lines should be inlaid as part of installation; not painted
• Spread/broom 1.5 lbs per square foot of SBR rubber infill and 2.5 lbs per square foot of silica sand infill onto the turf
• Adjust/repair any portions of fence as needed to install nailer boards at the edges of the fence line
• Install base plugs for bases at both 60’, 70’, 80’ and 90’ as well as home plate
Turf Install
Field F
Base Preparation
• Excavate 13,965 SF to a depth of 4” centered on pitchers mound located 46’ from home plate.
• Where radius intersects foul line, excavation shall extend perpendicular to the fence line
• Compact and laser grade sub-grade to level surface
• Install 4” deep trenches every 20’ O.C. throughout excavated area
• Install 6 millimeter plastic barrier on top of compacted sub-grade and in trenches.
• Install 4” perforated pipes within trenches with outfall point at location identified.
• Install, compact and laser grade 2” of #57 and #67 clean limestone, including in drainage trenches.
• Adjust, cap, and move existing irrigation lines/sprinkler heads/valve boxes, as needed, during excavation and reroute any necessary lines to ensure proper irrigation coverage of existing grass.
Exit Point for perforated drainage system.
Final approval to be approved by Comal County.
Excavation
Field F Turf Install
• Install 2” x 2” composite nailer boards around the perimeter of the infield to secure turf edges
• Install infield with the colors shown. All white lines should be inlaid as part of installation; not painted
• Spread/broom 1.5 lbs per square foot of SBR rubber infill and 2.5 lbs per square foot of silica sand infill onto the turf
• Adjust/repair any portions of fence as needed to install nailer boards at the edges of the fence line
• Install base plugs for bases at both 60’ as well as home plate
| Slide Number 1 |
| Slide Number 2 |
| Slide Number 3 |
| Slide Number 4 |
| Slide Number 5 |
| Slide Number 6 |
| Slide Number 7 |
| Slide Number 8 |
| Slide Number 9 |
| Slide Number 10 |
| Slide Number 11 |
| Slide Number 12 |
| Slide Number 13 |
| Slide Number 14 |
| Slide Number 15 |
File details come from the government source that posted it. Updated .