2020-06-01 Addendum No 4.pdf

PDF 133 KB Posted

Attached to
JROTC Fieldhouse Phase II
Solicitation number
RFP GIS 200000001755 4
Issued by
Genesee County, Michigan

About this file

This is an addendum to contract documents for the Genesee Intermediate School District (GISD) located in Flint, Michigan, issued by Construction Manager DCC Construction, Architect MAYOTTEgroup Architects, and MEP Engineer Clark Trombley Randers. Addendum No. 4, issued on June 1, 2020, modifies the original contract documents for the GISD JROTC Fieldhouse Phase 2 project at 5081 Torrey Road in Flint, Michigan. The addendum clarifies and amplifies contract requirements through two specific modifications: mechanical work requiring factory-installed BACnet controllers for packaged HVAC units and a BACnet thermostat for split system HVAC equipment, and electrical work requiring that Panel HP be fed from an existing 200-ampere circuit breaker in the main distribution panel located in the GCI building's main mechanical room.

The addendum contains no attachments and does not address pricing terms, set-asides, funding sources, or contract duration. This document serves solely to modify technical specifications and clarify equipment locations and electrical connections for bidders on the Phase 2 project, with electrical panel location details referenced on sheet E002 of the Phase 1 bid drawing set.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Addendum No. 4 2019-046 – GISD JROTC Fieldhouse Phase 2 mjm

ADDENDUM TO THE CONTRACT DOCUMENTS FOR:

CLIENT:

Genesee Intermediate School District

2413 W. Maple Ave.

Flint, MI. 48507

PROJECT:

GISD JROTC Fieldhouse - Phase 2

5081 Torrey Road

Flint, MI. 48507

CONSTRUCTION MANAGER:

DCC Construction

9100 Lapeer Road, Suite #A

Davison, MI 48423

ARCHITECT:

MAYOTTEgroup Architects

6240 W. Mt. Hope

Lansing, MI 48917

MEP ENGINEER:

Clark Trombley Randers

504 S. Creyts Rd., Suite B

Lansing, MI 48917

PURPOSE: This addendum is issued to amplify, clarify, and modify the original contract documents and shall take precedence over them.

DATE ISSUED: June 1, 2020

ATTACHMENTS: None

To All Bidders

MECHANICAL

Item 1 Provide factory-installed BACnet controller for the packaged HVAC unit and a

BACnet thermostat for the split system HVAC unit.

ELECTRICAL

Item 2 Panel HP is to be fed from an existing 200A circuit breaker in the MDP in the main mechanical room located in the GCI building. Location shown on sheet E002 in

Phase 1 bid drawing set (see partial plan below).

END OF ADDENDUM NO. 4