2_Submittal Schedule.pdf
PDF 265 KB Posted
- Attached to
- Repair MAF Roofs Federal contract opportunity
- Solicitation number
- FA462626R0002
About this file
This document is an Attachment 2 Schedule of Materials Submittals for a project titled "Repair MAF Roofs" with project number NZAS 25-6002. The schedule outlines 21 different submittal requirements for the roofing project, detailing the type of documentation, number of copies required, and specific submission timing for each item. Key submittals include Work Schedule, Quality Control Plan, Operation and Maintenance Instructions, Contractor Furnished Equipment List, and various product data and sample submissions related to roofing materials.
The schedule uses standardized abbreviations to indicate submission timing, such as PTSW (Prior to Start Work), PTCW (Prior to Concrete Work), and PTFI (Prior to Final Inspection). Contractors are required to provide multiple copies of each submittal, ranging from 1 to 4 copies depending on the specific document. The schedule is designed to track and manage the documentation process throughout the roofing repair project, ensuring proper review and approval of all critical project materials and documentation.
View the file
Other files for this federal contract opportunity
Show all 26
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATTACHMENT 2 REPAIR MAF ROOFS
FA4626-26-R-0002
SCHEDULE OF MATERIALS SUBMITTALS Project Number Project Title: Solicitation/Contract No.
NZAS 25-6002 REPAIR MAF ROOFS
TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACTOR/ADMINISTRATOR
L
IN
E
N U
M B
E R
ITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTAL
C E
R T
IF
IC
A T
IO
N
O F
C O
M
PL
IA
N
C E
SH
O
P D
R A
W
IN
G S
SA
M
PL
E
S
C O
LO
R
S
EL
EC
TI
O N
M A
N U
FA
C
T U
R E
R 'S
E C
O M
M E
N D
A T
IO
N
S
M A
N U
FA
C
T U
R E
W
A R
R A
N T
Y
C A
T A
L O
G D
A T
A
O
PE
R A
T
IN
G
ST
R U
C T
IO
N
S
N O
T
IF
IC
A
T
IU
O N
O T
H E
R
R E
Q U
IR
E
D S
U B
M
IS
SI
O
N
D
T
T E
R E
C E
IV
E
C
N
T R
A C
T
IN
G
D A
T E
T O
C
IV
IL
EN
IN
EE
R
IN
G
R E
T U
R N
S U
SP
E
N
SE
D A
T E
SU
B
M
IT
T A
L N
U M
B E
R S
DATE CONTRACTOR NOTIFIED
C O
N T
R A
C T
SU
B M
IT
T
L
FI
A L
A
PP
R O
V A
L
REMARKS
APPROVED DIS- APPROVED
1 Submittals (AF Form 3000) 01 00 00 - 3.4 4 4 10
ACA
2 Work Schedule 01 00 00 - 3.6 1 ACA
3 Start of Work Notification 01 00 00 - 3.8 1 7
ANTP
4 Quality Control Plan 01 00 00 - 3.13 1 10
PTNP
5 Supervision 01 00 00 - 3.14 1 10
PTNT
6 Operation and Maintenance Instructions 01 00 00 -
3.16 4 10
PTCW
7 Contractor Furnished Equipment List 01 00 00 -
3.17 1 10
PTCW
8 Work Clearance Request (AF Form 103) 01 00 00 -
3.22 1 10 SN
9 Notice of Final Acceptance and Report 01 00 00 -
3.25 1 14
PTFI
10 Contract Progress Schedule and Report 01 00 00 -
3.26 1 SN
11 Missile Field Entry Authority List (EAL) 01 10 00 -
1.5 1 15
PTSW
D - Days CD - Calendar Days PBC - Prior to Beginning Construction AFA- After Final Acceptance EOM - End Of Month PFI - Prior to Final Inspection AFI - After Final Inspection PSW - Prior to Start Work PPC - Prior to Project Completion ANP - After Notice to Proceed BBCW - Before Beginning Concrete Work PT - Prior to Testing ATT - After Test is Taken BD - Before Delivery WD- Working Days
Number of Copies Required
AF Form 66
02: 000510_AC01_00_90-
Submittal Schedule - Repair MAF Roof-9/24/2025 SS-1 of 2
Attachment 2 FA4626-26-R-0002
SCHEDULE OF MATERIALS SUBMITTALS Project Number Project Title: Solicitation/Contract No.
NZAS 25-6002 REPAIR MAF ROOFS
TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACTOR/ADMINISTRATOR
L
IN
E
N U
M B
E R
ITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTAL
C E
R T
IF
IC
A T
IO
N
O F
C O
M
PL
IA
N
C E
SH
O
P D
R A
W
IN
G S
SA
M
PL
E
S
C O
LO
R
S
EL
EC
TI
O N
M A
N U
FA
C
T U
R E
C
O M
M E
N D
A T
IO
N
S
M A
N U
FA
C
T U
R E
W
R
R A
N T
Y
C A
T A
L O
G D
A T
A
O
PE
R A
T
ST
R U
C T
IO
N
S
N O
T
IF
IC
A
T
IU
O N
O T
H E
R
R E
Q U
IR
E
D S
U B
M
IS
SI
T
T E
R E
C E
IV
E
C
N
T R
A C
T
IN
G
D A
T E
T O
C
IV
IL
EN
IN
EE
R
IN
G
R E
T U
R N
S U
SP
E
N
SE
D A
T E
SU
B
M
IT
T A
L N
U M
B E
R S
DATE CONTRACTOR NOTIFIED
C O
N T
R A
C T
SU
B M
IT
T
L
FI
A L
A
PP
R O
V A
L
REMARKS
APPROVED DIS- APPROVED
Number of Copies Required
12 Environmental Deliverables 01 36 00 - 2.3 1 5
PTSW
13 Product Data 07 31 13 - 1.05.A 1 PTCW
14 Samples for Verification 07 31 13 - 1.05.B 4 PTSW
15 Warranty 07 31 13 - 1.05.C 4 PTSW
16 Product Data 07 42 93 1.4.A 4 PTSW
17 Samples for Initial Selection 07 42 93 1.4.C 4 PTSW
18 Samples for Verification 07 42 93 1.4.D 4 PTSW
19 Product Data 07 62 00 - 1.4.A 4 PTSW
20 Samples for Initial Selection 07 62 00 - 1.4.B 4 PTSW
21 Samples for Verification 07 62 00 - 1.4.C 4 PTSW
AF Form 66
02: 000510_AC01_00_90-
Submittal Schedule - Repair MAF Roof-9/24/2025 SS-2 of 2