This is a Solicitation, Offer, and Award (Standard Form 1442) for a construction contract issued by the Federal Bureau of Prisons to replace switchgear at the Federal Correctional Institution (FCI) Estill in Estill, South Carolina. The solicitation number is 15BFA025B00000036, with a bid opening date of 10/21/2025 at 13:00 US Central time. The contract is a firm-fixed-price construction contract with a performance period of 430 calendar days, requiring the contractor to begin work within 10 calendar days of award and complete the project within 430 calendar days.

Key requirements include providing all materials, labor, and equipment to replace the switchgear, with a project magnitude between $1,000,000 and $5,000,000. The contractor must submit a bid guarantee of 20% of the bid price, not to exceed $3,000,000, and will be required to furnish performance and payment bonds within 10 calendar days of award. The solicitation includes extensive provisions for contractor security clearances, safety requirements, insurance (including workers' compensation, general liability, and automobile liability), and compliance with various federal regulations. Contractors must complete detailed background investigations and security screening procedures to work at the federal correctional facility.

View the file

Other files

File Type Posted
Amendment 0004 .pdf PDF
Abstract.pdf PDF
Amendment 0003.pdf PDF
Amendment 0002.pdf PDF
Amendment 0001.pdf PDF
1 - Instructions to Bidders.pdf PDF
7 - SF24-Bid Bond 10-2023.pdf PDF
6 - Construction Wage Determination SC20250013 03-14-2025.pdf PDF
8 - Criminal History Check Form.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

15BFA025B00000036 Page 1 of 51

SOLICITATION,OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NUMBER

15BFA025B00000036

X SEALED BID (IFB)

INVITATION FOR BID

NEGOTIATED (RFP)

REQUEST FOR PROPOSAL

2. TYPE OF SOLICITATION 3. DATE ISSUED

09/09/2025

PAGE OF PAGES

1 51

IMPORTANT -The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NUMBER 5. REQUISITION/PURCHASE REQUEST NUMBER

15B30525PR000039

6. PROJECT NUMBER

23Z3AR1

CODE 15BFA0

Federal Bureau of Prisons Field Acquisition Office U.S. Armed Forces Reserve Complex 346 Marine Forces Drive Grand Prairie, TX 75051

7. ISSUED BY 8. ADDRESS OFFER TO

9. FOR

INFORMATION CALL:

a. NAME

Julie Bergami

b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

(202) 598-6019

SOLICITATION

NOTE: In sealed bid solicitations "offer" and "offeror" means "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)

The selected contractor shall provide all materials, labor, and equipment for the project titled Replace Switchgear at the Federal Correctional Institution (FCI) Estill located in Estill, South Carolina in accordance with the attached Statement of Work, Specifications, and Drawings.

PLEASE COMPLETE THE FOLLOWING ITEMS:

UNIQUE ENTITY IDENTIFIER (UEI):__________________________________

TAX IDENTIFICATION NUMBER: _________________________________

CAGE CODE:___________________________________

CONTRACTOR E-MAIL:_____________________________________

11. The Contractor shall begin performance within calendar days and complete it within calendar days after receiving10 430 award, X notice to proceed. This performance period is X mandatory negotiable. (See 52.211-10.)

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS? (If "YES," indicate within how many calendar days after award in Item 12b).

X YES NO

12b. CALENDAR DAYS

Sealed offers in original and copies to perform the work required are due at the place specified in item 8 by (hour) local time (date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

1 13:00US/

Central a.

10/21/2025

b. An offer guarantee X is, is not required.

All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.c.

90d. Offers providing less than calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

13. ADDITIONAL SOLICITATION REQUIREMENTS:

STANDARD FORM 1442 (REV. 12/2022)

Prescribed by GSA - FAR (48 CFR) 53.236-1(d) bop01431 Highlight bop01431 Typewritten Text Upload bids electronically to JEFS App Box:

https://jefs.app.box.com/f/e96a52c8b4c84338838521376778d611 Single PDF document.

Bid Opening: Held on Microsoft Teams, see Instruction to Bidders Section, V. ELECTRONIC BID SUBMISSION & BID OPENING

15BFA025B00000036 Page 2 of 51

OFFER (Must be fully completed by offeror)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NUMBER (Include area code)

16. REMITTANCE ADDRESS (Include only if different than Item 14.)

CODE FACILITY CODE

The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ___________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

17.

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT

NUMBER

DATE

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)

20b. SIGNATURE 20c. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified) 27

ITEM

10 U.S.C. 3204(a) ( ) 41 U.S.C. 3304(a) ( )

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE

UNITED STATES CODE AT

26. ADMINISTERED BY 15B305

Federal Bureau of Prisons FCI Estill

100 PRISON ROAD

Estill, SC 29918

Federal Bureau of Prisons FCI Estill

100 PRISON ROAD

Estill, SC 29918

27. PAYMENT WILL BE MADE BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return __________ copies to issuing office.) Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30a.NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)

Julie Bergami

31a. NAME OF CONTRACTING OFFICER (Type or print)

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA

BY

31c. DATE

STANDARD FORM 1442 (REV. 12/2022) BACK

bop01431 Highlight bop01431 Highlight bop01431 Highlight bop01431 Highlight bop01431 Highlight bop01431 Highlight bop01431 Highlight

15BFA025B00000036 Page 3 of 51

Table of Contents

Section Description Page Number

1 Solicitation, Offer and Award 2 Commodity or Services Schedule 3 Special Contract Requirements 4 Contract Clauses 5 Attachments 6 Solicitation Provisions 7 Representations and Certifications

15BFA025B00000036 Page 4 of 51

Section 2 - Commodity or Services Schedule

Firm Fixed Price

SCHEDULE OF SUPPLIES/SERVICES

CONTINUATION SHEET

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 The selected contractor shall provide all materials, labor, and equipment to complete the project "Replace Switchgear" at FCI Estill in accordance with attached Statement of Work, Specifications, and Drawings.

PSC: Z2FF

Delivery Schedule:

Quantity: 1.000000

Delivery Address: Federal Bureau of Prisons FCI Estill

100 PRISON ROAD

Estill, SC 29918

1 JB $________ $_________________

NOTE: The successful contractor shall be responsible for all applicable federal, state, and local taxes. No tax exemption certification will be issued by the Federal Bureau of Prisons. THE TOTAL PURCHASE PRICE SHALL BE WRITTEN IN BLOCK 17 OF SF 1442.

bop01431 Highlight

15BFA025B00000036 Page 5 of 51

Section 3 - Special Contract Requirements

Clauses By Full Text

FAO-0001 Bonds

(a) Bid Guarantee. Each bidder shall submit with his bid a Bid Bond (Standard Form 24) with good and sufficient surety or sureties acceptable to the Government, or other security as provided in provision 52.228-1, in the form of twenty percent (20) of the bid price or not to exceed $3,000,000. The bid bond penalty may be expressed in terms of a percentage of the bid price or may be expressed in dollars and cents. A bid bond is not required for bids of $150,000 or less. (FAR 28.102-1)

(b) Performance and Payment Bonds. Within 10 days after award the contractor shall execute and submit to the Contracting Officer two bonds, each with good and sufficient surety or sureties acceptable to the Government, as follows;

a Performance Bond (Standard Form 25) and a Payment Bond (Standard Form 25A). The penal sums of such bonds will be as follows: (Not required for contracts of $150,000 or less)

(1) Performance Bond: The penal sum of performance bonds at the time of contract award shall be 100 percent of the original contract price.

(2) Payment Bond: The penal amount of payment bonds at the time of contract award shall be 100 percent of the original contract price.

(c) For construction contracts greater than $35,000 but not greater than $150,000, the Contracting Officer shall select two or more of the following payment protections, giving particular consideration to inclusion of an irrevocable letter of credit as one of the selected alternatives (FAR 28.102-1(b)(1)):

(1) A Payment Bond;

(2) An irrevocable letter of credit (ILC);

(3) A tripartite escrow agreement;

(4) A Certificate of Deposit; or

(5) A deposit of the types of security listed in 28.204-1 and 28.204-2.

(d) Individual Sureties.

(1) Bidders may elect to furnish individual surety bonds. If individual surety bonds are furnished for bid guarantees, payment or performance bonds, the individual sureties must submit their bonds proof of ownership and value of the assets which they claim in their net worth at time of bid opening. The Government's preferred method of proof is to have a statement of net worth prepared by a Certified Public Accountant (CPA) in accordance with Generally Accepted Accounting Principles (GAAP). Statements from a CPA that contain disclaimers are not acceptable. The statement of net worth on the Standard Form 28, Affidavit of Individual Surety, is insufficient and will not be accepted without additional proof of value and ownership.

(2) Bidders are cautioned that individual sureties must provide complete and detailed information in Block 9 of Standard Form 28 concerning other contracts on which they have provided bonds. This information shall include contract number, contract location, amount, and type of bond and telephone number of the involved contracting office. Failure to provide the proof and information required may result in rejection of the bid or termination of the contract for failure to provide adequate bonds.

FAO-0002 Magnitude

The magnitude of this project is between $1,000,000.00 and $5,000,000.00.

15BFA025B00000036 Page 6 of 51

FAO-0003 Required Insurance

See FAR 52.228-5, Insurance - Work on a Government Installation.

The Contractor shall, at its own expense, provide and maintain during the entire performance period of this contract, at least the kinds and minimum amounts of insurance required in the Schedule or elsewhere in the contract.

TYPE AMOUNT

(1) WORKERS COMPENSATION & EMPLOYER'S LIABILITY $100,000

The required Workmen's Compensation Insurance shall extend to cover employee's liability for accidental bodily injury or death and for occupational disease with a minimum liability of $100,000.

(2) COMPREHENSIVE GENERAL LIABILITY with a minimum limit of:

PER ACCIDENT OR OCCURRENCE FOR BODILY INJURY $500,000

This insurance shall include contractor's protective and contractual liability.

(3) COMPREHENSIVE AUTOMOBILE LIABILITY with the following minimum limits:

PER PERSON $200,000

PER OCCURRENCE FOR BODILY INJURY $500,000

PER OCCURRENCE FOR PROPERTY DAMAGE $ 20,000

FAO-0004 Pre-Construction Conference

(a) Prior to the start of construction, Contracting Officers shall call a conference with the contractor, subcontractor(s), Warden, Controller/Business Administrator, Safety Manager, Facilities Administrator, Project Representative, A&E firm, Captain and other interested personnel to discuss the statutory labor standards, prevailing wage requirements, submission of the contractor's payrolls, subcontractor's responsibilities, institution work schedules, local policies, contraband, parking, storage of vehicles and equipment, etc.

Minutes of the conference shall be recorded, listing the names and titles of all attendees, and the subject matter of all items covered. The minutes shall be signed by the contractor and the Contracting Officer, and a signed copy placed in the contract file.

(b) The Contractor shall familiarize himself/herself with all procedures involved in normal institution routines. Any requirements which may constitute a problem or result in conflict, will be brought to the attention of the Contracting Officer or his representative for determination.

FAO-0005 Submittals

Within 10 calendar days after commencement of work or as otherwise established by the Contracting Officer, all materials and articles requiring approval, as contemplated by the Materials and Workmanship clause, shall be submitted by the contractor.

The submittal process is in place to allow the Government the opportunity to determine whether materials or procedures used by the contractor are in accordance with contract requirements. It is ultimately the Contractor's responsibility via the quality control process to ensure submittal items installed under the contract and work performed on site are in accordance with industry standards and general practices.

(a) The types of submittal requirements specified in this contract may include, but is not limited to; shop drawings, product data, samples, certificates of conformance or compliance, certified test or inspection reports, equipment, materials, and miscellaneous work related submittals for construction. Individual submittal requirements are generally specified in applicable sections for each unit of work in the specifications and/or as a whole in one section in the statement of work.

15BFA025B00000036 Page 7 of 51

(b) The Bureau of Prisons (BOP) Contracting Officer’s Representative (COR) shall act for the Contracting Officer in the review and acceptance of all submittals. The Contractor shall submit submittals as required by the contract/ specifications to the COR for transmittal to the Contracting Officer. Fabrication of any work or purchase or use of any submittals (such as materials for which samples are required or equipment, etc.) shall not take place until written acceptance is given by the COR, except at the Contractor's own risk.

(c) The Contractor shall submit all shop drawings and submittals sufficiently in advance (unless otherwise specified in the specifications) of the construction requirements to allow ample time for checking, re-submitting, and re-checking.

(d) Failure of any materials to pass their specified tests shall be sufficient cause for refusal to consider, under this contract, any further samples of the same brand or make of that material. The Government reserves the right to disapprove any material or equipment which has previously proven unsatisfactory in service.

(e) The Contracting Officer’s or designee’s approval or acceptance of submittals is not to be construed as a complete check. Approval or acceptance will not relieve the Contractor of the responsibility for any error which may exist, as the Contractor is responsible for the satisfactory construction of all work. The Contractor is responsible for delivering a final product/system that is operational as intended by the contract requirements, regardless of any Government approvals or acceptance of submittals. The Government assumes no liability during the submittal approval/acceptance process. It is the sole responsibility of the Contractor to deliver a properly functioning product or system.

FAO-0006 Contractor Use of Premises

Work Hours The project schedule is based on a normal forty (40) hour work week, eight (8) hours per day, Monday through Friday, excluding Federal holidays. The Contracting Officer’s Representative (COR) shall establish the work hour time frames for the duration of the project, subject to the approval of the Contracting Officer. Work hours and work days may be altered only with a 48 hour advance approval of the Contracting Officer.

NOTE: Access to the site will be available during normal working hours except during emergencies. It shall be the responsibility of the Contractor to familiarize himself, his employees, and his subcontractors of the working hours and conditions in the correctional facility, as working hours may not constitute a full eight hour day. The Government assumes no responsibility to the Contractor, nor to any of his subcontractors, for shorter hours due to institutional emergencies or entry and/or exit of workers necessitated by normal institution routines. The procedures and institutional entrance/ exit routines applicable to this project will be explained at both the pre-bid conference/site visit and the pre-construction meeting.

Contraband The Contractor shall inform his employees that intoxicating beverages, drugs, weapons, etc., will not be allowed on the site. Introduction of contraband shall be subject to the penalties prescribed by Title 18 USC-1791.

Explosives The use of explosives is absolutely forbidden without written authorization from the Contracting Officer.

Parking and Temporary Office Parking will be available at the site to the extent it does not interfere with construction activities. Otherwise, parking shall be provided for by the Contractor, at his expense, off the site for workmen employed on the project. Any temporary field office used by the Contractor shall be located in an area approved by the COR.

Safety and Accident Prevention In performing work under this contract the contractor shall:

(a) Conform to the specific safety requirements established by this contract;

(b) Comply with the safety rules of the Government institution that concern related activities not directly addressed in this contract;

(c) Take all reasonable steps and precautions to prevent accidents and preserve the life and health of contractor and Government personnel performing or in any way coming in contact with the performance of this contract; and

15BFA025B00000036 Page 8 of 51

(d) Take such additional immediate precautions as the Contracting Officer and/or COR may reasonably require for safety and accident prevention purposes.

FAO-0007 Payment Services

(a) Original application for payment shall be prepared on AIA (American Institute of Architects) Form G-702 "Application and Certificate for Payment" and submitted to the Contracting Officer. The contractor may use another form;

however, it shall contain similar information as the AIA Form G-702. The Contracting Officer’s Representative (COR) will approve the amount of payment by signing. The approved application for payment shall be forwarded as follows: Original to Accounting; Copy for Contract Award File.

(b) All small business contractors are required to self-certify on all invoices their small business status.

(c) The following information is required with each application for payment:

• Name and address of contractor

• Contract number

• Contractor invoice/application for payment number

• Description, price, and quantity of construction completed/rendered

• Payment terms (reference the contract payment clause)

• Other substantiating documentation or information required by the contract

• Name, title, and phone number of official to be notified in the event of a defective invoice

• Contractor TIN (Tax ID Number)

FAO-0008 Request for Final Inspection

The Contractor shall give the Contracting Officer’s Representative (COR) a minimum of ten (10) working days advanced written notice of the date on which the work will be fully completed and ready for the Government’s final inspection.

FAO-0009(a) Construction Contract Security

(Program Statement 3732.01 BOP Identifications and Background Investigation)

In addition to the information contained in clause “DOJ-03 Personnel Security Requirements For Contractor Employees (Nov 2021); (Alt. I) -- Classified Information – Cleared Contractors”, the following additional security is required to be completed and submitted for all contract employees who will be working under the terms of the contract:

Criminal History Check – BP-A0660 (May 2018) CJIS Name Check Request Form BOP Contractor Pre-employment Questionnaire BOP Authority for Release of Information

The contactor should be aware that the time required for contractor security clearances to be completed may vary. For the purposes of this solicitation, 30 calendar days have been included in the performance period specified in FAR clause 52.211-10. The number of days listed above is contingent upon the contractor providing completed clearance packages for their employees within 10 calendar days of the Notice to Proceed. For any subsequently awarded subcontract, completed security clearance packages for subcontractor workers shall be submitted in conjunction with the completed

SF-1413.

**A form package will be issued by the Administrative Contracting Officer or Contracting Officer's Representative (COR) at the institution upon contract award. Completed packages shall be submitted by the PRIME CONTRACTOR ONLY to obtain clearance for each prime and sub-contract employee. Security Clearance packages will NOT be accepted from sub-contractors. Upon clearance being obtained the contractor will be notified. Should a contract employee NOT be cleared to enter the facility for this project, the contractor will be notified immediately. The contractor will be responsible to submit another contract employee as soon as possible for clearance. Be advised, the Federal Bureau of Prisons cannot disclose why an individual does not pass the security clearance process, as it is a violation of law.**

15BFA025B00000036 Page 9 of 51

FAO-0010 Assignment of Contract Administration Office and Functions

Pursuant to FAR 42.201 and 42.202, the assigned Contract Administration Office is listed in Block 26 of the Standard Form 1442 Back. This assignment carries with it the authority to perform all of the contract administration functions listed in FAR 42.302(a) and 42.302(b) to the extent that those functions apply to the contract.

The Contract Administration Office is required, however, to obtain written authorization from the Procuring Contracting Officer (PCO) to perform any function listed under 42.302(b). Specifically, the Administrative Contracting Officer (ACO) is required to obtain written authorization to perform the below referenced functions FOR CONSTRUCTION CONTRACT AWARDS:

1. Negotiate or negotiate and execute supplemental agreements incorporating contractor proposals resulting from change orders issued under the Changes clause. Before completing negotiations, coordinate any delivery schedule change with the contracting office.

2. Negotiate prices and execute priced exhibits for unpriced orders issued by the contracting officer under basic ordering agreements.

3. Negotiate or negotiate and execute supplemental agreements changing contract delivery schedules.

4. Complete Contractor Performance Assessment Report System (CPARS) evaluations of contractor performance in accordance with FAR Subpart 42.15.

Should any other function under FAR Subpart 42.15 not listed above be required, the ACO is required to contact the PCO for authority.

FAO-0011 Schedule of Values

The Contractor shall prepare a Schedule of Values (SOV) for the project and submit to the Contracting Officer for approval prior to submitting the first application for payment. The SOV shall be correlated with the construction schedule.

The SOV shall be formatted per the Construction Specification Institute Master Format structure. The Contractor may propose an alternate organizational format to the Contracting Officer for approval.

(a) The SOV shall include:

(1) Project name, location, and contract number;

(2) Contractor’s name and address;

(3) Date of submittal.

(b) The SOV shall be arranged in a tabular form with separate columns to indicate the following for each item listed:

(1) Description of Work or Material;

(2) Related specification section, if applicable;

(3) Name of subcontractor, if applicable;

(4) Name of manufacturer or fabricator, if applicable;

(5) Name of supplier, if applicable;

(6) Change orders (modifications) that have affected value, if applicable;

(7) Dollar value;

(8) Percentage of Contract sum rounded to the nearest percent, adjusted to total 100 percent.

(c) The SOV shall breakdown the contract sum in sufficient detail to facilitate continued evaluation of applications for payment and progress reports. The contractor should separate principal subcontract amounts down into several line items.

(d) SOV amounts shall be rounded to the nearest whole dollar. The total of all SOV amounts shall equal the total contract amount.

(e) The contractor shall progress the percentage of completion, with the concurrence of the Contracting Officer’s Representative, for each value in conjunction with the preparation of each monthly application for payment. The progressed value percentages shall directly correlate to the calculated total amount due for each monthly progress payment.

15BFA025B00000036 Page 10 of 51

(f) The SOV shall remain fixed for the duration of contract performance. Any revisions to the SOV must be requested in writing, with justification, for approval by the Contracting Officer.

FAO-0012 Progress Meetings

The Administrative Contracting Officer (ACO) shall conduct progress meetings at the project site on a monthly basis, or at intervals as determined by the ACO.

(a) At a minimum, the attendees shall include but is not limited to:

(1) FBOP: Administrative Contracting Officer, Contracting Officer’s Representative (COR), Facility Administrator/Manager, Architect/Engineer (if applicable), Other Personnel (Executive Staff, Captain, Safety Manager, etc.).

(2) Contractor: Project Manager, Superintendent, and technical support disciplines as appropriate (Subcontractors, Manufacturers, Suppliers, etc.).

(b) The meeting should include, but is not limited to issues such as:

Administrative Contracting Officer:

(1) Old business from previous progress meeting(s);

(2) Status of modifications, certified payrolls, submittals, requests for information (RFI);

(3) Review of payments made to date and review/approve current payment request;

(4) Status of modification proposal requests;

(5) Discuss new business.

COR:

(1) Status of escort coverage;

(2) Review gate or sallyport entrance/exit issues;

(3) Discuss other delays contractor may be experiencing;

(4) Discuss performance/quality issues.

Contractor:

(1) Review/discuss updated progress schedule;

(2) Provide 30 day outlook;

(3) Discuss other issues affecting performance.

FAO-0013 Contract Closeout Procedures (for construction contracts exceeding SAT)

Contract Closeout must be completed within six (6) months of physical completion of the work.

Prior to payment of final invoice:

The contractor shall submit the following documents:

(1) Contractor’s Affidavit of Release of Liens (AIA Document G706A);

(2) Contractor’s Affidavit of Payment of Debts and Claims (AIA Document G706);

(3) All as-built drawings/shop drawings, if applicable;

(4) Contractor’s final invoice;

(5) Release of Claims (GSA Form 1142);

(6) Consent of Surety to Final Payment (AIA Document G707);

(7) Letter establishing warranty dates;

(8) Complete list of subcontractors with telephone numbers and points of contact;

(9) Guarantees and warranties;

(10) All balance and test reports;

(11) All operation/maintenance manuals;

(12) All permits and certifications.

AIA forms can be obtained from The American Institute of Architects at www.aiabookstore.com. GSA forms can be obtained from the General Services Administration at www.gsa.gov (click on the “Forms Library” link).

15BFA025B00000036 Page 11 of 51

Section 4 - Contract Clauses

Clauses By Reference

52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.acquisition.gov

Clause Title Fill-ins (if applicable)

52.202-1 Definitions (Jun 2020)

52.203-3 Gratuities (Apr 1984)

52.203-5 Covenant Against Contingent Fees (May 2014)

52.203-6 Restrictions on Subcontractor Sales to the Government

(Jun 2020)

52.203-7 Anti-Kickback Procedures (Jun 2020)

52.203-8 Cancellation, Rescission, and Recovery of Funds for

Illegal or Improper Activity (May 2014)

52.203-10 Price or Fee Adjustment for Illegal or Improper Activity

(May 2014)

52.203-12 Limitation On Payments to Influence Certain Federal

Transactions (Jun 2020)

52.203-17 Contractor Employee Whistleblower Rights (Nov 2023)

52.203-19 Prohibition on Requiring Certain Internal Confidentiality

Agreements or Statements (Jan 2017)

52.204-2 Alt II Security Requirements (Mar 2021) - Alternate II (Apr

1984)

52.204-9 Personal Identity Verification of Contractor Personnel

(Jan 2011)

52.204-10 Reporting Executive Compensation and First-Tier

Subcontract Awards (Jun 2020)

52.204-13 System for Award Management Maintenance (Oct 2018)

15BFA025B00000036 Page 12 of 51

Clause Title Fill-ins (if applicable)

52.204-14 Service Contract Reporting Requirements (Oct 2016)

52.204-18 Commercial and Government Entity Code Maintenance

(Aug 2020)

52.204-19 Incorporation by Reference of Representations and

Certifications (Dec 2014)

52.204-21 Basic Safeguarding of Covered Contractor Information

Systems (Nov 2021)

52.204-23 Prohibition on Contracting for Hardware, Software, and

Services Developed or Provided by Kaspersky Lab

Covered Entities (Dec 2023)

52.204-25 Prohibition on Contracting for Certain

Telecommunications and Video Surveillance Services or

Equipment (Nov 2021)

52.204-27 Prohibition on a ByteDance Covered Application (Jun

2023)

52.204-30 Federal Acquisition Supply Chain Security Act Orders-

Prohibition (Dec 2023)

52.209-6 Protecting the Government's Interest When

Subcontracting with Contractors Debarred, Suspended, Proposed for Debarment, or Voluntarily Excluded (Jan

2025)

52.209-9 Updates of Publicly Available Information Regarding

Responsibility Matters (Oct 2018)

52.209-10 Prohibition on Contracting with Inverted Domestic

Corporations (Nov 2015)

52.211-12 Liquidated Damages-Construction (Sept 2000) (a): "$1,482.96"

52.219-6 Notice of Total Small Business Set-Aside (Nov 2020)

52.219-8 Utilization of Small Business Concerns (Jan 2025)

52.219-14 Limitations on Subcontracting (Oct 2022) (f)(1) End of Base Term: "X"

52.219-28 Postaward Small Business Program Rerepresentation

(Jan 2025)

15BFA025B00000036 Page 13 of 51

52.222-1 Notice to the Government of Labor Disputes (Feb 1997)

52.222-3 Convict Labor (June 2003)

52.222-4 Contract Work Hours and Safety Standards--Overtime

Compensation (May 2018)

52.222-6 Construction Wage Rate Requirements (Aug 2018)

52.222-7 Withholding of Funds (May 2014)

52.222-8 Payrolls and Basic Records (Jul 2021)

52.222-10 Compliance with Copeland Act Requirements (Feb

1988)

52.222-11 Subcontracts (Labor Standards) (May 2014)

52.222-12 Contract Termination - Debarment (May 2014)

52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations (May 2014)

52.222-14 Disputes Concerning Labor Standards (Feb 1988)

52.222-15 Certification of Eligibility (May 2014)

52.222-35 Equal Opportunity for Veterans (Jun 2020)

52.222-36 Equal Opportunity for Workers with Disabilities (Jun

2020)

52.222-37 Employment Reports on Veterans (Jun 2020)

52.222-40 Notification of Employee Rights Under the National

Labor Relations Act (Dec 2010)

52.222-50 Combating Trafficking in Persons (Nov 2021)

52.222-54 Employment Eligibility Verification (Jan 2025)

52.222-55 Minimum Wages for Contractor Workers Under

Executive Order 14026 (Jan 2022)

52.222-62 Paid Sick Leave Under Executive Order 13706 (Jan

2022)

52.223-5 Pollution Prevention and Right-to-Know Information

(May 2024)

15BFA025B00000036 Page 14 of 51

52.223-11 Ozone-Depleting Substances and High Global Warming

Potential Hydrofluorocarbons (May 2024)

52.223-20 Aerosols (May 2024)

52.223-21 Foams (May 2024)

52.225-9 Buy American-Construction Materials (Oct 2022) (b)(2): "None"

52.225-13 Restrictions on Certain Foreign Purchases (Feb 2021)

52.226-7 Drug-Free Workplace (May 2024)

52.226-8 Encouraging Contractor Policies To Ban Text

Messaging While Driving (May 2024)

52.227-1 Authorization and Consent (Jun 2020)

52.227-2 Notice and Assistance Regarding Patent and Copyright

Infringement (Jun 2020)

52.227-4 Patent Indemnity-Construction Contracts (Dec 2007)

52.228-2 Additional Bond Security (Oct 1997)

52.228-5 Insurance-Work on a Government Installation (Jan

1997)

52.228-11 Individual Surety-Pledge of Assets (Feb 2021)

52.228-12 Prospective Subcontractor Requests for Bonds (Dec

2022)

52.228-14 Irrevocable Letter of Credit (Nov 2014)

52.228-15 Performance and Payment Bonds-Construction (Jun

2020)

52.232-5 Payments under Fixed-Price Construction Contracts

(May 2014)

52.232-17 Interest (May 2014)

52.232-23 Assignment of Claims (May 2014)

52.232-27 Prompt Payment for Construction Contracts (Jan 2017)

52.232-33 Payment by Electronic Funds Transfer-System for

Award Management (Oct 2018)

52.232-39 Unenforceability of Unauthorized Obligations (Jun 2013)

15BFA025B00000036 Page 15 of 51

52.232-40 Providing Accelerated Payments to Small Business

Subcontractors (Mar 2023)

52.233-1 Alt I Disputes (May 2014) - Alternate I (Dec 1991)

52.233-3 Protest after Award (Aug 1996)

52.233-4 Applicable Law for Breach of Contract Claim (Oct 2004)

52.236-2 Differing Site Conditions (Apr 1984)

52.236-3 Site Investigation and Conditions Affecting the Work

(Apr 1984)

52.236-5 Material and Workmanship (Apr 1984)

52.236-6 Superintendence by the Contractor (Apr 1984)

52.236-7 Permits and Responsibilities (Nov 1991)

52.236-8 Other Contracts (Apr 1984)

52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements (Apr 1984)

52.236-10 Operations and Storage Areas (Apr 1984)

52.236-11 Use and Possession Prior to Completion (Apr 1984)

52.236-12 Cleaning Up (Apr 1984)

52.236-13 Alt I Accident Prevention (Nov 1991) - Alternate I (Nov 1991)

52.236-14 Availability and Use of Utility Services (Apr 1984)

52.236-15 Schedules for Construction Contracts (Apr 1984)

52.236-17 Layout of Work (Apr 1984)

52.236-21 Alt II Specifications and Drawings for Construction (Feb 1997)

- Alternate II (Apr 1984)

(g) desired amount: "2 sets"

52.240-1 Prohibition on Unmanned Aircraft Systems

Manufactured or Assembled by American Security

Drone Act-Covered Foreign Entities (Nov 2024)

52.242-13 Bankruptcy (July 1995)

52.242-14 Suspension of Work (Apr 1984)

52.243-4 Changes (June 2007)

52.246-12 Inspection of Construction (Aug 1996) bop01431 Typewritten Text See Statement of Work, page 2, Section D

15BFA025B00000036 Page 16 of 51

52.246-21 Warranty of Construction (Mar 1994)

52.248-3 Value Engineering-Construction (Oct 2020)

52.249-2 Alt I Termination for Convenience of the Government (Fixed-

Price) (Apr 2012) - Alternate I (Sept 1996)

52.249-10 Default (Fixed-Price Construction) (Apr 1984)

52.253-1 Computer Generated Forms (Jan 1991)

Clauses By Full Text

52.215-21 Alt IV Requirements for Certified Cost or Pricing Data and Data Other Than Certified Cost or Pricing Data- Modifications (Nov 2021) - Alternate IV (Oct 2010)

(a) Submission of certified cost or pricing data is not required.

(b) Provide data described below:

Modification proposal breakdown formatted as a listing of individual costs for labor, materials, equipment, overhead, profit, bond increase, and any additional information requested by the Contracting Officer. [Insert description of the data and the format that are required, including the access to records necessary to permit an adequate evaluation of the proposed price in accordance with 15.403-3.]

(End of clause)

52.222-9 (DEV) Apprentices and Trainees (July 2005) (DEVIATION FEB 2025)

(a) Apprentices.

(1) An apprentice will be permitted to work at less than the predetermined rate for the work performed when employed -

(i) Pursuant to and individually registered in a bona fide apprenticeship program registered with the U.S. Department of Labor, Employment and Training Administration, Office of Apprenticeship Training, Employer, and Labor Services (OATELS) or with a State Apprenticeship Agency recognized by the OATELS; or

(ii) In the first 90 days of probationary employment as an apprentice in such an apprenticeship program, even though not individually registered in the program, if certified by the OATELS or a State Apprenticeship Agency (where appropriate) to be eligible for probationary employment as an apprentice.

(2) The allowable ratio of apprentices to journeymen on the job site in any craft classification shall not be greater than the ratio permitted to the Contractor as to the entire work force under the registered program.

(3) Any worker listed on a payroll at an apprentice wage rate, who is not registered or otherwise employed as stated in paragraph (a)(1) of this clause, shall be paid not less than the applicable wage determination for the classification of work actually performed. In addition, any apprentice performing work on the job site in excess of the ratio permitted under the registered program shall be paid not less than the applicable wage rate on the wage determination for the work actually performed.

(4) Where a Contractor is performing construction on a project in a locality other than that in which its program is registered, the ratios and wage rates (expressed in percentages of the journeyman's hourly rate) specified in the Contractor's or subcontractor's registered program shall be observed. Every apprentice must be paid at not less than

15BFA025B00000036 Page 17 of 51 the rate specified in the registered program for the apprentice's level of progress, expressed as a percentage of the journeyman hourly rate specified in the applicable wage determination.

(5) Apprentices shall be paid fringe benefits in accordance with the provisions of the apprenticeship program. If the apprenticeship program does not specify fringe benefits, apprentices must be paid the full amount of fringe benefits listed on the wage determination for the applicable classification. If the Administrator determines that a different practice prevails for the applicable apprentice classification, fringes shall be paid in accordance with that determination.

(6) In the event OATELS, or a State Apprenticeship Agency recognized by OATELS, withdraws approval of an apprenticeship program, the Contractor will no longer be permitted to utilize apprentices at less than the applicable predetermined rate for the work performed until an acceptable program is approved.

(b) Trainees.

(1) Except as provided in 29 CFR 5.16, trainees will not be permitted to work at less than the predetermined rate for the work performed unless they are employed pursuant to and individually registered in a program which has received prior approval, evidenced by formal certification by the U.S. Department of Labor, Employment and Training Administration, Office of Apprenticeship Training, Employer, and Labor Services (OATELS). The ratio of trainees to journeymen on the job site shall not be greater than permitted under the plan approved by OATELS.

(2) Every trainee must be paid at not less than the rate specified in the approved program for the trainee's level of progress, expressed as a percentage of the journeyman hourly rate specified in the applicable wage determination.

Trainees shall be paid fringe benefits in accordance with the provisions of the trainee program. If the trainee program does not mention fringe benefits, trainees shall be paid the full amount of fringe benefits listed in the wage determination unless the Administrator of the Wage and Hour Division determines that there is an apprenticeship program associated with the corresponding journeyman wage rate in the wage determination which provides for less than full fringe benefits for apprentices. Any employee listed on the payroll at a trainee rate who is not registered and participating in a training plan approved by the OATELS shall be paid not less than the applicable wage rate in the wage determination for the classification of work actually performed. In addition, any trainee performing work on the job site in excess of the ratio permitted under the registered program shall be paid not less than the applicable wage rate in the wage determination for the work actually performed.

(3) In the event OATELS withdraws approval of a training program, the Contractor will no longer be permitted to utilize trainees at less than the applicable predetermined rate for the work performed until an acceptable program is approved.

(End of clause)

52.223-2 (DEV) Reporting of Biobased Products Under Service and Construction Contracts (May 2024) (DEVIATION

FEB 2025)

(a) Definitions. As used in this clause--

Biobased product means a product determined by the U.S. Department of Agriculture (USDA) to be a commercial product or industrial product (other than food or feed) that is composed, in whole or in significant part, of biological products, including renewable domestic agricultural materials and forestry materials, or that is an intermediate ingredient or feedstock. The term includes, with respect to forestry materials, forest products that meet biobased content requirements, notwithstanding the market share the product holds, the age of the product, or whether the market for the product is new or emerging. (7 U.S.C. 8101) (7 CFR 4270.2).

USDA-designated product category means a generic grouping of products that are or can be made with biobased materials--

(1) That are listed by USDA in a procurement guideline available at https://www.biopreferred.gov/resources/ categories.html; and

(2) For which USDA has provided purchasing recommendations (available at https://www.biopreferred.gov or 7 CFR part 4270).

15BFA025B00000036 Page 18 of 51

(b) The Contractor shall report to https://www.sam.gov, with a copy to the Contracting Officer, on the product types and dollar value of any biobased products in USDA-designated product categories purchased by the Contractor during the previous Government fiscal year, between October 1 and September 30; and

(c) Submit this report no later than--

(1) October 31 of each year during contract performance; and

(2) At the end of contract performance.

(End of clause)

52.223-23 (DEV) Sustainable Products and Services (May 2024) (DEVIATION FEB 2025)

(a) Definitions. As used in this clause--

Biobased product means a product determined by the U.S. Department of Agriculture (USDA) to be a commercial product or industrial product (other than food or feed) that is composed, in whole or in significant part, of biological products, including renewable domestic agricultural materials and forestry materials, or that is an intermediate ingredient or feedstock. The term includes, with respect to forestry materials, forest products that meet biobased content requirements, notwithstanding the market share the product holds, the age of the product, or whether the market for the product is new or emerging. (7 U.S.C. 8101) (7 CFR part 4270.2).

Recovered material means waste materials and by-products recovered or diverted from solid waste, but the term does not include those materials and by-products generated from, and commonly reused within, an original manufacturing process.

(42 U.S.C. 6903).

Sustainable products and services means:

(1) Products containing recovered material designated by the U.S. Environmental Protection Agency (EPA) under the Comprehensive Procurement Guidelines (42 U.S.C. 6962) (40 CFR part 247) (https://www.epa.gov/smm/ comprehensiveprocurement-guideline-cpgprogram#products).

(2) Energy- and water-efficient products that are ENERGY STAR® certified or Federal Energy Management Program (FEMP)-designated products (42 U.S.C. 8259b) (10 CFR part 436, subpart C) (https://www.energy.gov/eere/femp/search-energyefficient-products and https://www.energystar.gov/products?s=mega).

(3) Biobased products meeting the content requirement of the USDA under the BioPreferred® program (7 U.S.C. 8102) (7 CFR part 4270) (https://www.biopreferred.gov).

(4) Acceptable chemicals, products, and manufacturing processes listed under EPA's Significant New Alternatives Policy (SNAP) program, which ensures a safe and smooth transition away from substances that contribute to the depletion of stratospheric ozone (42 U.S.C. 7671l) (40 CFR part 82, subpart G) (https://www.epa.gov/snap).

(b) Requirements.

(1) The sustainable products and services, including the purchasing program and type of product or service, that are applicable to this contract, and any products or services that are not subject to this clause, will be set forth in the statement of work or elsewhere in the contract.

(2) The Contractor shall ensure that the sustainable products and services required by this contract are--

(i) Delivered to the Government;

(ii) Furnished for use by the Government;

(iii) Incorporated into the construction of a public building or public work; and

15BFA025B00000036 Page 19 of 51

(iv) Furnished for use in performing services under this contract, where the cost of the products is a direct cost to this contract (versus costs which are normally applied to the Contractor's general and administrative expenses or indirect costs). This includes services performed by contractors performing management and operation of Government-owned facilities to the same extent that, at the time of award, an agency would be required to comply if an agency operated or supported the facility.

(c) Resource. The Green Procurement Compilation (GPC) available at https://sftool.gov/greenprocurement provides a comprehensive list of sustainable products and services and sustainable acquisition guidance. The Contractor should review the GPC when determining which statutory purchasing programs apply to a specific product or service.

(End of clause)

52.229-3 (DEV) Federal, State, and Local Taxes (Feb 2013) (DEVIATION AUG 2025)

(a) As used in this clause-

"After-imposed Federal tax" means any new or increased Federal excise tax or duty, or tax that was exempted or excluded on the contract date but whose exemption was later revoked or reduced during the contract period, on the transactions or property covered by this contract that the Contractor is required to pay or bear as the result of legislative, judicial, or administrative action taking effect after the contract date. It does not include social security tax or other employment taxes.

"After-relieved Federal tax" means any amount of Federal excise tax or duty, except social security or other employment taxes, that would otherwise have been payable on the transactions or property covered by this contract, but which the Contractor is not required to pay or bear, or for which the Contractor obtains a refund or drawback, as the result of legislative, judicial, or administrative action taking effect after the contract date.

"All applicable Federal, State, and local taxes and duties" means all taxes and duties, in effect on the contract date, that the taxing authority is imposing and collecting on the transactions or property covered by this contract.

"Contract date" means the date set for bid opening or, if this is a negotiated contract or a modification, the effective date of this contract or modification.

"Local taxes" includes taxes imposed by a possession or territory of the United States, Puerto Rico, or the Northern Mariana Islands, if the contract is performed wholly or partly in any of those areas.

(b)(1) The contract price includes all applicable Federal, State, and local taxes and duties, except as provided in subparagraph (b)(2)(i) of this clause.

(2) Taxes imposed under 26 U.S.C. 5000C may not be --

(i) Included in the contract price; nor

(ii) Reimbursed.

(c) The contract price shall be increased by the amount of any after-imposed Federal tax, provided the Contractor warrants in writing that no amount for such newly imposed Federal excise tax or duty or rate increase was included in the contract price, as a contingency reserve or otherwise.

(d) The contract price shall be decreased by the amount of any after-relieved Federal tax.

(e) The contract price shall be decreased by the amount of any Federal excise tax or duty, except social security or other employment taxes, that the Contractor is required to pay or bear, or does not obtain a refund of, through the Contractor's fault, negligence, or failure to follow instructions of the Contracting Officer.

(f) No adjustment shall be made in the contract price under this clause unless the amount of the adjustment exceeds $250.

15BFA025B00000036 Page 20 of 51

(g) The Contractor shall promptly notify the Contracting Officer of all matters relating to any Federal excise tax or duty that reasonably may be expected to result in either an increase or decrease in the contract price and shall take appropriate action as the Contracting Officer directs.

(h) The Government shall, without liability, furnish evidence appropriate to establish exemption from any Federal, State, or local tax when the Contractor requests such evidence and a reasonable basis exists to sustain the exemption.

(End of clause)

52.229-12 (DEV) Tax on Certain Foreign Procurements (Feb 2021) (DEVIATION AUG 2025)

(a) Definitions. As used in this clause--

Foreign person means any person other than a United States person.

United States person, as defined in 26 U.S.C. 7701(a)(30), means--

(1) A citizen or resident of the United States;

(2) A domestic partnership;

(3) A domestic corporation;

(4) Any estate (other than a foreign estate, within the meaning of 26 U.S.C. 7701(a)(31)); and

(5) Any trust if--

(i) A court within the United States is able to exercise primary supervision over the administration of the trust; and

(ii) One or more United States persons have the authority to control all substantial decisions of the trust.

(b) This clause applies only to foreign persons. It implements 26 U.S.C. 5000C and its implementing regulations at 26 CFR 1.5000C-1 through 1.5000C-7.

(c)(1) If the Contractor is a foreign person and has only a partial or no exemption to the withholding, the Contractor shall include the Department of the Treasury Internal Revenue Service Form W-14, Certificate of Foreign Contracting Party Receiving Federal Procurement Payments, with each voucher or invoice submitted under this contract throughout the period in which this status is applicable. The excise tax withholding is applied at the payment level, not at the contract level.

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .