2 - Solicitation 15BBNF26B60300001.pdf

PDF 1 MB Posted

Attached to
Upgrade Fire Detection System at FDC Honolulu, Hawaii
Solicitation number
15BBNF26B60300001
Issued by

About this file

Contract Solicitation Summary

This is a Sealed Bid Invitation for Bid (IFB) for construction services issued by the Federal Bureau of Prisons (FBP) Field Acquisition Office. The solicitation is for the upgrade of the fire detection system at the Federal Detention Center (FDC) Honolulu, located in Honolulu, Hawaii. The project is estimated between $5,000,000 and $10,000,000 in magnitude and will be awarded as a firm-fixed price contract. Bids are due on August 19, 2026 at 1:00 PM Central Time, with contract performance to begin within 10 days of award and be completed within 161 calendar days. The selected contractor must provide all materials, labor, and equipment in accordance with attached specifications and drawings, and must be responsible for all applicable federal, state, and local taxes.

The solicitation employs a two-step sealed bidding process. A 20 percent bid bond (not to exceed $3,000,000) is required, and performance and payment bonds equal to 100 percent of the original contract price must be furnished within 10 days of award. Liquidated damages are set at $1,066.13 per day. Required insurance includes workers' compensation ($100,000), comprehensive general liability ($500,000), and comprehensive automobile liability ($200,000 per person/$500,000 per occurrence/$20,000 property damage). Contractors must obtain security clearances for all employees, comply with prevailing wage requirements per Hawaii Wage Determination HI20260001, and submit past performance references and banking information directly to jbergami@bop.gov prior to bid closing. The contract administration office is assigned to FDC Honolulu, located at 351 Elliott Street, Honolulu, HI 96819.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

15BBNF26B60300001 Page 1 of 48

SOLICITATION,OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NUMBER

15BBNF26B60300001

X SEALED BID (IFB)

INVITATION FOR BID

NEGOTIATED (RFP)

REQUEST FOR PROPOSAL

2. TYPE OF SOLICITATION 3. DATE ISSUED

07/01/2026

PAGE OF PAGES

1 48

IMPORTANT -The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NUMBER 5. REQUISITION/PURCHASE REQUEST NUMBER

15BH0N26PR000083

6. PROJECT NUMBER

26Z6AU1

CODE BFAO

Federal Bureau of Prisons Field Acquisition Office U.S. Armed Forces Reserve Complex 346 Marine Forces Drive Grand Prairie, TX 75051

7. ISSUED BY

Federal Bureau of Prisons Field Acquisition Office U.S. Armed Forces Reserve Complex 346 Marine Forces Drive Grand Prairie, TX 75051

8. ADDRESS OFFER TO

9. FOR

INFORMATION CALL:

a. NAME

Julie Bergami jbergami@bop.gov

b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

202-598-6019

SOLICITATION

NOTE: In sealed bid solicitations "offer" and "offeror" means "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)

This Invitation for Bid (IFB) is using the Two-Step Sealed Bidding procurement method. The selected contractor shall provide all materials, labor, and equipment to complete the project titled Upgrade Fire Detection System at the Federal Detention Center (FDC) Honolulu, located in Honolulu, Hawaii, in accordance with the attached Specifications and Drawings.

PLEASE COMPLETE THE FOLLOWING ITEMS:

UNIQUE ENTITY IDENTIFIER (UEI):_____________________________

TAX IDENTIFICATION NUMBER: ____________________________

CAGE CODE:________________________________

CONTRACTOR E-MAIL:________________________________

System updates may lag policy updates. The System for Award Management (SAM) may continue to require entities to complete representations based on provisions that are not included in agency solicitations. Contracting officers will not consider these representations when making award decisions or enforce requirements. Entities are not required to, nor are they able to, update their entity registration to remove these representations in SAM.

11. The Contractor shall begin performance within calendar days and complete it within calendar days after receiving10 161 award, X notice to proceed. This performance period is X mandatory negotiable. (See __________________________.)

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS? (If "YES," indicate within how many calendar days after award in Item 12b).

X YES NO

12b. CALENDAR DAYS

Sealed offers in original and copies to perform the work required are due at the place specified in item 8 by (hour) local time (date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

13:00US/

Central a.

08/19/2026

b. An offer guarantee X is, is not required.

All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.c.

90d. Offers providing less than calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

13. ADDITIONAL SOLICITATION REQUIREMENTS:

STANDARD FORM 1442 (REV. 12/2022)

Prescribed by GSA - FAR (48 CFR) 53.236-1(d) bop01431 Highlight

15BBNF26B60300001 Page 2 of 48

OFFER (Must be fully completed by offeror)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NUMBER (Include area code)

16. REMITTANCE ADDRESS (Include only if different than Item 14.)

CODE FACILITY CODE

The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within ___________ calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

17.

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT

NUMBER

DATE

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)

20b. SIGNATURE 20c. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified) 27

ITEM

10 U.S.C. 3204(a) ( ) 41 U.S.C. 3304(a) ( )

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE

UNITED STATES CODE AT

26. ADMINISTERED BY 15BH0N

Federal Bureau of Prisons FDC Honolulu 351 Elliott Street Honolulu, HI 96819

Federal Bureau of Prisons FDC Honolulu 351 Elliott Street Honolulu, HI 96819

27. PAYMENT WILL BE MADE BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return __________ copies to issuing office.) Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30a.NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)

Julie Bergami

31a. NAME OF CONTRACTING OFFICER (Type or print)

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA

BY

31c. DATE

STANDARD FORM 1442 (REV. 12/2022) BACK

bop01431 Highlight bop01431 Highlight bop01431 Highlight bop01431 Highlight bop01431 Highlight bop01431 Highlight bop01431 Highlight bop01431 Highlight

15BBNF26B60300001 Page 3 of 48

Table of Contents

Section Description Page Number

1 Solicitation, Offer and Award 2 Commodity or Services Schedule 3 Special Contract Requirements 4 Contract Clauses 5 Attachments 6 Solicitation Provisions 7 Representations and Certifications

15BBNF26B60300001 Page 4 of 48

Section 2 - Commodity or Services Schedule

Upgrade Fire Detection System FDC Honolulu

Firm Fixed Price

SCHEDULE OF SUPPLIES/SERVICES

CONTINUATION SHEET

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 The selected contractor shall provide all materials, labor, and equipment for Upgrade Fire Detection System at the Federal Detention Center (FDC) Honolulu, Hawaii, in accordance with the attached Specifications and Drawings.

PSC: Z2FF

Delivery Schedule:

Quantity: 1.000000

Place of Performance Address:

Federal Bureau of Prisons FDC Honolulu 351 Elliott Street Honolulu, HI 96819

1 JB $________ $_________________

The successful contractor shall be responsible for all applicable federal, state, and local taxes. No tax exemption certification will be issued by the Federal Bureau of Prisons. THE TOTAL PRICE SHALL BE WRITTEN ON LINE ITEM 17 OF THE STANDARD FORM 1442.

bop01431 Highlight

15BBNF26B60300001 Page 5 of 48

Section 3 - Special Contract Requirements

Clauses By Full Text

FAO-0001 Bonds

(a) Bid Guarantee. Each bidder shall submit with his bid a Bid Bond (Standard Form 24) with good and sufficient surety or sureties acceptable to the Government, or other security as provided in provision 52.228-1, in the form of twenty percent (20) of the bid price or not to exceed $3,000,000. The bid bond penalty may be expressed in terms of a percentage of the bid price or may be expressed in dollars and cents. A bid bond is not required for bids of $150,000 or less. (FAR 28.102-1)

(b) Performance and Payment Bonds. Within 10 days after award the contractor shall execute and submit to the Contracting Officer two bonds, each with good and sufficient surety or sureties acceptable to the Government, as follows;

a Performance Bond (Standard Form 25) and a Payment Bond (Standard Form 25A). The penal sums of such bonds will be as follows: (Not required for contracts of $150,000 or less)

(1) Performance Bond: The penal sum of performance bonds at the time of contract award shall be 100 percent of the original contract price.

(2) Payment Bond: The penal amount of payment bonds at the time of contract award shall be 100 percent of the original contract price.

(c) For construction contracts greater than $35,000 but not greater than $150,000, the Contracting Officer shall select two or more of the following payment protections, giving particular consideration to inclusion of an irrevocable letter of credit as one of the selected alternatives (FAR 28.102-1(b)(1)):

(1) A Payment Bond;

(2) An irrevocable letter of credit (ILC);

(3) A tripartite escrow agreement;

(4) A Certificate of Deposit; or

(5) A deposit of the types of security listed in 28.204-1 and 28.204-2.

(d) Individual Sureties.

(1) Bidders may elect to furnish individual surety bonds. If individual surety bonds are furnished for bid guarantees, payment or performance bonds, the individual sureties must submit their bonds proof of ownership and value of the assets which they claim in their net worth at time of bid opening. The Government's preferred method of proof is to have a statement of net worth prepared by a Certified Public Accountant (CPA) in accordance with Generally Accepted Accounting Principles (GAAP). Statements from a CPA that contain disclaimers are not acceptable. The statement of net worth on the Standard Form 28, Affidavit of Individual Surety, is insufficient and will not be accepted without additional proof of value and ownership.

(2) Bidders are cautioned that individual sureties must provide complete and detailed information in Block 9 of Standard Form 28 concerning other contracts on which they have provided bonds. This information shall include contract number, contract location, amount, and type of bond and telephone number of the involved contracting office. Failure to provide the proof and information required may result in rejection of the bid or termination of the contract for failure to provide adequate bonds.

FAO-0002 Magnitude

The magnitude of this project is between $5,000,000 and $10,000,000.

15BBNF26B60300001 Page 6 of 48

FAO-0003 Required Insurance

See FAR 52.228-5, Insurance - Work on a Government Installation.

The Contractor shall, at its own expense, provide and maintain during the entire performance period of this contract, at least the kinds and minimum amounts of insurance required in the Schedule or elsewhere in the contract.

TYPE AMOUNT

(1) WORKERS COMPENSATION & EMPLOYER'S LIABILITY $100,000

The required Workmen's Compensation Insurance shall extend to cover employee's liability for accidental bodily injury or death and for occupational disease with a minimum liability of $100,000.

(2) COMPREHENSIVE GENERAL LIABILITY with a minimum limit of:

PER ACCIDENT OR

OCCURRENCE FOR BODILY INJURY $500,000

This insurance shall include contractor's protective and contractual liability.

(3) COMPREHENSIVE AUTOMOBILE LIABILITY with the following minimum limits:

PER PERSON $200,000

PER OCCURRENCE FOR BODILY INJURY $500,000

PER OCCURRENCE FOR PROPERTY DAMAGE $ 20,000

FAO-0004 Pre-Construction Conference

(a) Prior to the start of construction, Contracting Officers shall call a conference with the contractor, subcontractor(s), Warden, Controller/Business Administrator, Safety Manager, Facilities Administrator, Project Representative, A&E firm, Captain and other interested personnel to discuss the statutory labor standards, prevailing wage requirements, submission of the contractor's payrolls, subcontractor's responsibilities, institution work schedules, local policies, contraband, parking, storage of vehicles and equipment, etc.

Minutes of the conference shall be recorded, listing the names and titles of all attendees, and the subject matter of all items covered. The minutes shall be signed by the contractor and the Contracting Officer, and a signed copy placed in the contract file.

(b) The Contractor shall familiarize himself/herself with all procedures involved in normal institution routines. Any requirements which may constitute a problem or result in conflict, will be brought to the attention of the Contracting Officer or his representative for determination.

FAO-0005 Submittals

Within 10 calendar days after commencement of work or as otherwise established by the Contracting Officer, all materials and articles requiring approval, as contemplated by the Materials and Workmanship clause, shall be submitted by the contractor.

15BBNF26B60300001 Page 7 of 48

The submittal process is in place to allow the Government the opportunity to determine whether materials or procedures used by the contractor are in accordance with contract requirements. It is ultimately the Contractor's responsibility via the quality control process to ensure submittal items installed under the contract and work performed on site are in accordance with industry standards and general practices.

(a) The types of submittal requirements specified in this contract may include, but is not limited to; shop drawings, product data, samples, certificates of conformance or compliance, certified test or inspection reports, equipment, materials, and miscellaneous work related submittals for construction. Individual submittal requirements are generally specified in applicable sections for each unit of work in the specifications and/or as a whole in one section in the statement of work.

(b) The Bureau of Prisons (BOP) Contracting Officer’s Representative (COR) shall act for the Contracting Officer in the review and acceptance of all submittals. The Contractor shall submit submittals as required by the contract/specificat ions to the COR for transmittal to the Contracting Officer. Fabrication of any work or purchase or use of any submittals (such as materials for which samples are required or equipment, etc.) shall not take place until written acceptance is given by the COR, except at the Contractor's own risk.

(c) The Contractor shall submit all shop drawings and submittals sufficiently in advance (unless otherwise specified in the specifications) of the construction requirements to allow ample time for checking, re-submitting, and re-checking.

(d) Failure of any materials to pass their specified tests shall be sufficient cause for refusal to consider, under this contract, any further samples of the same brand or make of that material. The Government reserves the right to disapprove any material or equipment which has previously proven unsatisfactory in service.

(e) The Contracting Officer’s or designee’s approval or acceptance of submittals is not to be construed as a complete check. Approval or acceptance will not relieve the Contractor of the responsibility for any error which may exist, as the Contractor is responsible for the satisfactory construction of all work. The Contractor is responsible for delivering a final product/system that is operational as intended by the contract requirements, regardless of any Government approvals or acceptance of submittals. The Government assumes no liability during the submittal approval/acceptance process. It is the sole responsibility of the Contractor to deliver a properly functioning product or system.

FAO-0006 Contractor Use of Premises

Work Hours The project schedule is based on a normal forty (40) hour work week, eight (8) hours per day, Monday through Friday, excluding Federal holidays. The Contracting Officer’s Representative (COR) shall establish the work hour time frames for the duration of the project, subject to the approval of the Contracting Officer. Work hours and work days may be altered only with a 48 hour advance approval of the Contracting Officer.

NOTE: Access to the site will be available during normal working hours except during emergencies. It shall be the responsibility of the Contractor to familiarize himself, his employees, and his subcontractors of the working hours and conditions in the correctional facility, as working hours may not constitute a full eight hour day. The Government assumes no responsibility to the Contractor, nor to any of his subcontractors, for shorter hours due to institutional emergencies or entry and/or exit of workers necessitated by normal institution routines. The procedures and institutional entrance/ exit routines applicable to this project will be explained at both the pre-bid conference/site visit and the pre-construction meeting.

Contraband The Contractor shall inform his employees that intoxicating beverages, drugs, weapons, etc., will not be allowed on the site. Introduction of contraband shall be subject to the penalties prescribed by Title 18 USC-1791.

Explosives The use of explosives is absolutely forbidden without written authorization from the Contracting Officer.

Parking and Temporary Office Parking will be available at the site to the extent it does not interfere with construction activities. Otherwise, parking shall be provided for by the Contractor, at his expense, off the site for workmen employed on the project. Any temporary field office used by the Contractor shall be located in an area approved by the COR.

15BBNF26B60300001 Page 8 of 48

Safety and Accident Prevention In performing work under this contract the contractor shall:

(a) Conform to the specific safety requirements established by this contract;

(b) Comply with the safety rules of the Government institution that concern related activities not directly addressed in this contract;

(c) Take all reasonable steps and precautions to prevent accidents and preserve the life and health of contractor and Government personnel performing or in any way coming in contact with the performance of this contract; and

(d) Take such additional immediate precautions as the Contracting Officer and/or COR may reasonably require for safety and accident prevention purposes.

FAO-0007 Payment Services

(a) Original application for payment shall be prepared on AIA (American Institute of Architects) Form G-702 "Application and Certificate for Payment" and submitted to the Contracting Officer. The contractor may use another form;

however, it shall contain similar information as the AIA Form G-702. The Contracting Officer’s Representative (COR) will approve the amount of payment by signing. The approved application for payment shall be forwarded as follows: Original to Accounting; Copy for Contract Award File.

(b) All small business contractors are required to self-certify on all invoices their small business status.

(c) The following information is required with each application for payment:

• Name and address of contractor

• Contract number

• Contractor invoice/application for payment number

• Description, price, and quantity of construction completed/rendered

• Payment terms (reference the contract payment clause)

• Other substantiating documentation or information required by the contract

• Name, title, and phone number of official to be notified in the event of a defective invoice

• Contractor TIN (Tax ID Number)

FAO-0008 Request for Final Inspection

The Contractor shall give the Contracting Officer’s Representative (COR) a minimum of ten (10) working days advanced written notice of the date on which the work will be fully completed and ready for the Government’s final inspection.

FAO-0009(a) Construction Contract Security

FAO-0009(a) Construction Contract Security (Program Statement 3732.01 BOP Identifications and Background Investigation)

In addition to the information contained in clause “DOJ-03 Personnel Security Requirements For Contractor Employees (Nov 2021); (Alt. I) -- Classified Information – Cleared Contractors”, the following additional security is required to be completed and submitted for all contract employees who will be working under the terms of the contract:

Criminal History Check – BP-A0660 (May 2018) CJIS Name Check Request Form BOP Contractor Pre-employment Questionnaire BOP Authority for Release of Information The contractor should be aware that the time required for contractor security clearances to be completed may vary. For the purposes of this solicitation, 14 calendar days have been included in the performance period specified on box 11 of the SF1442. The number of days listed above is contingent upon the contractor providing completed clearance packages for their employees within 10 calendar days of the Notice to Proceed. For any subsequently awarded subcontract, completed security clearance packages for subcontractor workers shall be submitted in conjunction with the completed

SF-1413.

15BBNF26B60300001 Page 9 of 48

**A form package will be issued by the Administrative Contracting Officer or Contracting Officer's Representative (COR) at the institution upon contract award. Completed packages shall be submitted by the PRIME CONTRACTOR ONLY to obtain clearance for each prime and sub-contract employee. Security Clearance packages will NOT be accepted from sub-contractors. Upon clearance being obtained the contractor will be notified. Should a contract employee NOT be cleared to enter the facility for this project, the contractor will be notified immediately. The contractor will be responsible to submit another contract employee as soon as possible for clearance. Be advised, the Federal Bureau of Prisons cannot disclose why an individual does not pass the security clearance process, as it is a violation of law.**

FAO-0010 Assignment of Contract Administration Office and Functions

Pursuant to FAR 42.201 and 42.202, the assigned Contract Administration Office is listed in Block 26 of the Standard Form 1442 Back. This assignment carries with it the authority to perform all of the contract administration functions listed in FAR 42.302(a) and 42.302(b) to the extent that those functions apply to the contract.

The Contract Administration Office is required, however, to obtain written authorization from the Procuring Contracting Officer (PCO) to perform any function listed under 42.302(b). Specifically, the Administrative Contracting Officer (ACO) is required to obtain written authorization to perform the below referenced functions FOR CONSTRUCTION CONTRACT

AWARDS:

(1) Negotiate or negotiate and execute supplemental agreements incorporating contractor proposals resulting from change orders issued under the Changes clause. Before completing negotiations, coordinate any delivery schedule change with the contracting office.

(2) Negotiate prices and execute priced exhibits for unpriced orders issued by the contracting officer under basic ordering agreements.

(3) Negotiate or negotiate and execute supplemental agreements changing contract delivery schedules.

(4) Complete Contractor Performance Assessment Report System (CPARS) evaluations of contractor performance in accordance with FAR Subpart 42.15.

Should any other function under FAR Subpart 42.15 not listed above be required, the ACO is required to contact the PCO for authority.

FAO-0011 Schedule of Values

The Contractor shall prepare a Schedule of Values (SOV) for the project and submit to the Contracting Officer for approval prior to submitting the first application for payment. The SOV shall be correlated with the construction schedule.

The SOV shall be formatted per the Construction Specification Institute Master Format structure. The Contractor may propose an alternate organizational format to the Contracting Officer for approval.

(a) The SOV shall include:

(1) Project name, location, and contract number;

(2) Contractor’s name and address;

(3) Date of submittal.

15BBNF26B60300001 Page 10 of 48

(b) The SOV shall be arranged in a tabular form with separate columns to indicate the following for each item listed:

(1) Description of Work or Material;

(2) Related specification section, if applicable;

(3) Name of subcontractor, if applicable;

(4) Name of manufacturer or fabricator, if applicable;

(5) Name of supplier, if applicable;

(6) Change orders (modifications) that have affected value, if applicable;

(7) Dollar value;

(8) Percentage of Contract sum rounded to the nearest percent, adjusted to total 100 percent.

(c) The SOV shall breakdown the contract sum in sufficient detail to facilitate continued evaluation of applications for payment and progress reports. The contractor should separate principal subcontract amounts down into several line items.

(d) SOV amounts shall be rounded to the nearest whole dollar. The total of all SOV amounts shall equal the total contract amount.

(e) The contractor shall progress the percentage of completion, with the concurrence of the Contracting Officer’s Representative, for each value in conjunction with the preparation of each monthly application for payment. The progressed value percentages shall directly correlate to the calculated total amount due for each monthly progress payment.

(f) The SOV shall remain fixed for the duration of contract performance. Any revisions to the SOV must be requested in writing, with justification, for approval by the Contracting Officer.

FAO-0012 Progress Meetings

The Administrative Contracting Officer (ACO) shall conduct progress meetings at the project site on a monthly basis, or at intervals as determined by the ACO.

(a) At a minimum, the attendees shall include but is not limited to:

(1) FBOP: Administrative Contracting Officer, Contracting Officer’s Representative (COR), Facility Administr ator/Manager, Architect/Engineer (if applicable), Other Personnel (Executive Staff, Captain, Safety Manager, etc.).

(2) Contractor: Project Manager, Superintendent, and technical support disciplines as appropriate (Subcontractors, Manufacturers, Suppliers, etc.).

(b) The meeting should include, but is not limited to issues such as:

Administrative Contracting Officer:

(1) Old business from previous progress meeting(s);

(2) Status of modifications, certified payrolls, submittals, requests for information (RFI);

(3) Review of payments made to date and review/approve current payment request;

(4) Status of modification proposal requests;

(5) Discuss new business.

COR:

(1) Status of escort coverage;

15BBNF26B60300001 Page 11 of 48

(2) Review gate or sallyport entrance/exit issues;

(3) Discuss other delays contractor may be experiencing;

(4) Discuss performance/quality issues.

Contractor:

(1) Review/discuss updated progress schedule;

(2) Provide 30 day outlook;

(3) Discuss other issues affecting performance.

FAO-0013 Contract Closeout Procedures (for construction contracts exceeding SAT)

Contract Closeout must be completed within six (6) months of physical completion of the work.

Prior to payment of final invoice:

The contractor shall submit the following documents:

(1) Contractor’s Affidavit of Release of Liens (AIA Document G706A);

(2) Contractor’s Affidavit of Payment of Debts and Claims (AIA Document G706);

(3) All as-built drawings/shop drawings, if applicable;

(4) Contractor’s final invoice;

(5) Release of Claims (GSA Form 1142);

(6) Consent of Surety to Final Payment (AIA Document G707);

(7) Letter establishing warranty dates;

(8) Complete list of subcontractors with telephone numbers and points of contact;

(9) Guarantees and warranties;

(10) All balance and test reports;

(11) All operation/maintenance manuals;

(12) All permits and certifications.

AIA forms can be obtained from The American Institute of Architects at www.aiabookstore.com.

GSA forms can be obtained from the General Services Administration at www.gsa.gov (click on the “Forms Library” link).

FAO-0023 Payments under Fixed-Price Construction Contracts

a. Payment of price. The Government shall pay the Contractor the contract price as provided in this contract.

b. Progress payments. The Government shall make progress payments monthly as the work proceeds, or at more frequent intervals as determined by the Contracting Officer, on estimates of work accomplished which meets the standards of quality established under the contract, as approved by the Contracting Officer.

15BBNF26B60300001 Page 12 of 48

1. The Contractor’s request for progress payments shall include the following substantiation:

i. An itemization of the amounts requested, related to the various elements of work required by the contract covered by the payment requested.

ii. A listing of the amount included for work performed by each subcontractor under the contract.

iii. A listing of the total amount of each subcontract under the contract.

iv. A listing of the amounts previously paid to each such subcontractor under the contract.

v. Additional supporting data in a form and detail required by the Contracting Officer.

2. In the preparation of estimates, the Contracting Officer may authorize material delivered on the site and preparatory work done to be taken into consideration. Material delivered to the Contractor at locations other than the site also may be taken into consideration if-

i. Consideration is specifically authorized by this contract; and

ii. The Contractor furnishes satisfactory evidence that it has acquired title to such material and that the material will be used to perform this contract.

a. Contractor certification. Along with each request for progress payments, the Contractor shall furnish the following certification, or payment shall not be made: (However, if the Contractor elects to delete paragraph (c)

(4) from the certification, the certification is still acceptable.)

I hereby certify, to the best of my knowledge and belief, that-

1. The amounts requested are only for performance in accordance with the specifications, terms, and conditions of the contract;

2. All payments due to subcontractors and suppliers from previous payments received under the contract have been made, and timely payments will be made from the proceeds of the payment covered by this certification, in accordance with subcontract agreements and the requirements of Chapter 39 of Title 31, United States Code;

3. This request for progress payments does not include any amounts which the prime contractor intends to withhold or retain from a subcontractor or supplier in accordance with the terms and conditions of the subcontract; and

4. This certification is not to be construed as final acceptance of a subcontractor’s performance.

__________________________________________________ (Name) __________________________________________________ (Title) __________________________________________________ (Date)

(d) Refund of unearned amounts. If the Contractor, after making a certified request for progress payments, discovers that a portion or all of such request constitutes a payment for performance by the Contractor that fails to conform to the specifications, terms, and conditions of this contract (hereinafter referred to as the "unearned amount"), the Contractor shall-

1. Notify the Contracting Officer of such performance deficiency; and

2. Be obligated to pay the Government an amount (computed by the Contracting Officer in the manner provided in paragraph (j) of this clause) equal to interest on the unearned amount from the 8th day after the date of receipt of the unearned amount until-

i. The date the Contractor notifies the Contracting Officer that the performance deficiency has been corrected; or

ii. The date the Contractor reduces the amount of any subsequent certified request for progress payments by an amount equal to the unearned amount.

(e) Retainage. If the Contracting Officer finds that satisfactory progress was achieved during any period for which a progress payment is to be made, the Contracting Officer shall authorize payment to be made in full. However, if satisfactory progress has not been made, the Contracting Officer may retain a maximum of 10 percent of the amount of the payment until satisfactory progress is achieved. When the work is substantially complete, the Contracting Officer may retain from previously withheld funds and future progress payments that amount the Contracting Officer considers adequate for protection of the Government and shall release to the Contractor all the remaining withheld funds. Also, on completion and acceptance of each separate building, public work, or other division of the contract, for which the price is stated separately in the contract, payment shall be made for the completed work without retention of a percentage.

15BBNF26B60300001 Page 13 of 48

(f) Title, liability, and reservation of rights. All material and work covered by progress payments made shall, at the time of payment, become the sole property of the Government, but this shall not be construed as-

1. Relieving the Contractor from the sole responsibility for all material and work upon which payments have been made or the restoration of any damaged work; or

2. Waiving the right of the Government to require the fulfillment of all of the terms of the contract.

(g) Reimbursement for bond premiums. In making these progress payments, the Government shall, upon request, reimburse the Contractor for the amount of premiums paid for performance and payment bonds (including coinsurance and reinsurance agreements, when applicable) after the Contractor has furnished evidence of full payment to the surety.

The retainage provisions in paragraph (e) of this clause shall not apply to that portion of progress payments attributable to bond premiums.

(h) Final payment. The Government shall pay the amount due the Contractor under this contract after-

1. Completion and acceptance of all work;

2. Presentation of a properly executed voucher; and

3. Presentation of release of all claims against the Government arising by virtue of this contract, other than claims, in stated amounts, that the Contractor has specifically excepted from the operation of the release. A release may also be required of the assignee if the Contractor’s claim to amounts payable under this contract has been assigned under the Assignment of Claims Act of1940 ( 31 U.S.C.3727 and 41 U.S.C. 6305).

(i) Limitation because of undefinitized work. Notwithstanding any provision of this contract, progress payments shall not exceed 80 percent on work accomplished on undefinitized contract actions. A "contract action" is any action resulting in a contract, as defined in FAR subpart 2.1, including contract modifications for additional supplies or services, but not including contract modifications that are within the scope and under the terms of the contract, such as contract modifications issued pursuant to the Changes clause, or funding and other administrative changes.

(j) Interest computation on unearned amounts. In accordance with 31 U.S.C. 3903(c)(1), the amount payable under paragraph (d)(2) of this clause shall be-

1. Computed at the rate of average bond equivalent rates of 91-day Treasury bills auctioned at the most recent auction of such bills prior to the date the Contractor receives the unearned amount; and

2. Deducted from the next available payment to the Contractor.

15BBNF26B60300001 Page 14 of 48

Section 4 - Contract Clauses

Clauses By Reference

52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.acquisition.gov

Clause Title Fill-ins (if applicable)

52.203-6 Alt I Restrictions on Subcontractor Sales to the Government

(Jun 2020) - Alternate I (Nov 2021)

52.203-13 Contractor Code of Business Ethics and Conduct (Nov

2021)

52.203-17 Contractor Employee Whistleblower Rights (Nov 2023)

52.203-19 Prohibition on Requiring Certain Internal Confidentiality

Agreements or Statements (Jan 2017)

52.204-9 Personal Identity Verification of Contractor Personnel

(Jan 2011)

52.204-13 (DEV) System for Award Management-Maintenance (Oct 2018)

(DEVIATION NOV 2025)

52.204-14 (DEV) Service Contract Reporting Requirements (Oct 2016)

(DEVIATION NOV 2025)

52.209-6 (DEV) Protecting the Government's Interest When

Subcontracting with Contractors Debarred, Suspended, Proposed for Debarment, or Voluntarily Excluded (Jan

2025) (DEVIATION NOV 2025)

52.209-9 (DEV) Updates of Publicly Available Information Regarding

Responsibility Matters (Oct 2018) (DEVIATION NOV

2025)

52.209-10 (DEV) Prohibition on Contracting With Inverted Domestic

Corporations (Nov 2015) (DEVIATION NOV 2025)

15BBNF26B60300001 Page 15 of 48

Clause Title Fill-ins (if applicable)

52.211-12 Liquidated Damages-Construction (Sept 2000) (a): "$1,066.13"

52.212-4 (DEV) Terms and Conditions-Commercial Products and

Commercial Services (Nov 2023) (DEVIATION NOV

2025)

52.214-26 (DEV) Audit and Records--Sealed Bidding (Jun 2020)

(DEVIATION NOV 2025)

52.214-27 Price Reduction for Defective Certified Cost or Pricing

Data-Modifications-Sealed Bidding (Jun 2020)

52.214-28 (DEV) Subcontractor Certified Cost Or Pricing Data--

Modifications--Sealed Bidding (Jun 2020) (DEVIATION

NOV 2025)

52.219-6 (DEV) Notice of Total Small Business Set-Aside (Nov 2020)

(DEVIATION DEC 2025)

52.219-8 (DEV) Utilization of Small Business Concerns (Jan 2025)

(DEVIATION DEC 2025)

52.219-14 (DEV) Limitations on Subcontracting (Oct 2022) (DEVIATION

DEC 2025)

(f)(1) End of Base Term: "X"

52.219-28 (DEV) Postaward Small Business Program Rerepresentation

(Jan 2025) (DEVIATION DEC 2025)

(g)(1) NAICS Code: "238210"

52.222-1 (DEV) Notice to the Government of Labor Disputes (Feb 1997)

(DEVIATION DEC 2025)

52.222-3 (DEV) Convict Labor (June 2003) (DEVIATION DEC 2025)

52.222-4 (DEV) Contract Work Hours and Safety Standards--Overtime

Compensation (May 2018) (DEVIATION DEC 2025)

52.222-6 (DEV) Construction Wage Rate Requirements (Aug 2018)

(DEVIATION AUG 2025)

52.222-7 (DEV) Withholding of Funds (May 2014) (DEVIATION DEC

2025)

52.222-8 (DEV) Payrolls and Basic Records (Jul 2021) (DEVIATION

DEC 2025)

bop01431 Typewritten Text 52.212-4 is hereby tailored IAW FAR Dev 12.205(b)(1)(ii):

(b) Inspection/Acceptance IAW FAR Dev 52.246-12.

(d) Changes. IAW FAR Dev 52.243-4.

(i) Payment. Retain (i) payment, supplement with FAO-0023 Progress Payment.

15BBNF26B60300001 Page 16 of 48

52.222-9 (DEV) Apprentices and Trainees (July 2005) (DEVIATION DEC

2025)

52.222-10 (DEV) Compliance with Copeland Act Requirements (Feb

1988) (DEVIATION DEC 2025)

52.222-11 (DEV) Subcontracts (Labor Standards) (May 2014)

(DEVIATION DEC 2025)

52.222-12 Contract Termination - Debarment (May 2014)

52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations (May 2014)

52.222-14 (DEV) Disputes Concerning Labor Standards (Feb 1988)

(DEVIATION DEC 2025)

52.222-15 Certification of Eligibility (May 2014)

52.222-19 (DEV) Child Labor-Cooperation with Authorities and Remedies

(Jan 2025) (DEVIATION MAR 2026)

52.222-35 (DEV) Equal Opportunity for Veterans (Jun 2020) (DEVIATION

DEC 2025)

52.222-36 (DEV) Equal Opportunity for Workers with Disabilities (Jun

2020) (DEVIATION DEC 2025)

52.222-37 (DEV) Employment Reports on Veterans (Jun 2020)

(DEVIATION DEC 2025)

52.222-40 Notification of Employee Rights Under the National

Labor Relations Act (Dec 2010)

52.222-50 (DEV) Combating Trafficking in Persons (Oct 2025)

(DEVIATION DEC 2025)

52.222-55 (DEV) Minimum Wages for Contractor Workers Under

Executive Order 14026 (Jan 2022) (DEVIATION DEC

2025)

52.222-62 (DEV) Paid Sick Leave Under Executive Order 13706 (Jan

2022) (DEVIATION DEC 2025)

52.222-90 Addressing DEI Discrimination by Federal Contractors

(APR 2026)

15BBNF26B60300001 Page 17 of 48

52.223-2 (DEV) Reporting of Biobased Products Under Service and

Construction Contracts (May 2024) (DEVIATION DEC

2025)

52.223-5 Pollution Prevention and Right-to-Know Information

(May 2024)

52.223-11 (DEV) Ozone-Depleting Substances (May 2024) (DEVIATION

DEC 2025)

52.223-23 (DEV) Sustainable Products (May 2024) (DEVIATION DEC

2025)

52.225-11 Alt I (DEV) Buy American-Construction Materials under Trade

Agreements (Nov 2023) - Alternate I (Nov 2023)

(DEVIATION DEC 2025)

52.226-8 Encouraging Contractor Policies To Ban Text

Messaging While Driving (May 2024)

52.227-1 Authorization and Consent (Jun 2020)

52.227-2 Notice and Assistance Regarding Patent and Copyright

Infringement (Jun 2020)

52.227-4 Patent Indemnity-Construction Contracts (Dec 2007)

52.228-2 Additional Bond Security (Oct 1997)

52.228-5 Insurance-Work on a Government Installation (Jan

1997)

52.228-11 Individual Surety-Pledge of Assets (Feb 2021)

52.228-14 Irrevocable Letter of Credit (Nov 2014)

52.228-15 Performance and Payment Bonds-Construction (Jun

2020)

52.229-12 (DEV) Tax on Certain Foreign Procurements (Feb 2021)

(DEVIATION AUG 2025)

52.232-23 Assignment of Claims (May 2014)

52.232-27 Prompt Payment for Construction Contracts (Jan 2017)

52.232-33 Payment by Electronic Funds Transfer-System for

Award Management (Oct 2018) bop01431 Typewritten Text List of expected materials:

"None"

15BBNF26B60300001 Page 18 of 48

52.232-40 Providing Accelerated Payments to Small Business

Subcontractors (Mar 2023)

52.233-3 (DEV) Protest after Award (Aug 1996) (DEVIATION NOV 2025)

52.233-4 (DEV) Applicable Law for Breach of Contract Claim (Oct 2004)

(DEVIATION NOV 2025)

52.236-2 (DEV) Differing Site Conditions (Apr 1984) (DEVIATION AUG

2025)

52.236-3 (DEV) Site Investigation and Conditions Affecting the Work

(Apr 1984) (DEVIATION AUG 2025)

52.236-5 (DEV) Material and Workmanship (Apr 1984) (DEVIATION

AUG 2025)

52.236-6 (DEV) Superintendence by the Contractor (Apr 1984)

(DEVIATION AUG 2025)

52.236-7 (DEV) Permits and Responsibilities (Nov 1991) (DEVIATION

AUG 2025)

52.236-8 (DEV) Other Contracts (Apr 1984) (DEVIATION AUG 2025)

52.236-9 (DEV) Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements (Apr 1984)

(DEVIATION AUG 2025)

52.236-10 (DEV) Operations and Storage Areas (Apr 1984) (DEVIATION

AUG 2025)

52.236-11 (DEV) Use and Possession Prior to Completion (Apr 1984)

(DEVIATION AUG 2025)

52.236-12 (DEV) Cleaning Up (Apr 1984) (DEVIATION AUG 2025)

52.236-13 (DEV) Accident Prevention (Nov 1991) (DEVIATION AUG

2025)

52.236-14 (DEV) Availability and Use of Utility Services (Apr 1984)

(DEVIATION AUG 2025)

52.236-15 (DEV) Schedules for Construction Contracts (Apr 1984)

(DEVIATION AUG 2025)

52.236-17 (DEV) Layout of Work (Apr 1984) (DEVIATION AUG 2025) bop01431 Typewritten Text See Specifications, page 82 Section 01 50 00 Temporary Facilities and Controls

15BBNF26B60300001 Page 19 of 48

52.236-21 Alt II (DEV) Specifications and Drawings for Construction (Feb 1997)

- Alternate II (Apr 1984) (DEVIATION AUG 2025)

(g) desired amount: "1"

52.240-91 (DEV) Security Prohibitions and Exclusions (DEVIATION NOV

2025)

52.240-92 Alt II (DEV) Security Requirements - Alternate II (DEVIATION NOV

2025)

52.240-93 (DEV) Basic Safeguarding of Covered Contractor Information

Systems (DEVIATION NOV 2025)

52.242-13 Bankruptcy (July 1995)

52.242-14 Suspension of Work (Apr 1984)

52.243-4 (DEV) Changes (June 2007) (DEVIATION JUL 2025)

52.246-12 Inspection of Construction (Aug 1996)

52.246-21 Warranty of Construction (Mar 1994)

52.248-3 Value Engineering-Construction (Oct 2025)

52.253-1 (DEV) Computer Generated Forms (Jan 1991) (DEVIATION

NOV 2025)

2852.222-70 Domestic Violence, Sexual Assault, and Stalking (DEC

2014)

Clauses By Full Text

52.252-6 Authorized Deviations in Clauses (Nov 2020)

(a) The use in this solicitation or contract of any Federal Acquisition Regulation (48 CFR Chapter 1) clause with an authorized deviation is indicated by the addition of "(DEVIATION)" after the date of the clause.

(b) The use in this solicitation or contract of any Justice Acquisition Regulation. [insert regulation name] (48 CFR Chapter

28) clause with an authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.

(End of clause)

2852.201-70 Contracting Officer's Representative (COR) (NOV 2020)

(a) Christian Edwards, Engineering Technician of FDC Honolulu , cedwards@bop.gov or 808-838-4200, extension 1703 , is hereby designated to act as Contracting Officer's Representative (COR) under contract titled Upgrade Fire Detection System , for the period of 161 calendar days (specify the performance period of the contract that the designation covers).

15BBNF26B60300001 Page 20 of 48

(b) Performance of work under this contract is subject to the technical direction of the COR identified above, or another representative designated in writing by the Contracting Officer. The term “technical direction” includes, without limitation, the following:

(i) Receiving all deliverables;

(ii) Inspecting and accepting the supplies or services provided in accordance with the terms and conditions of this contract;

(iii) Clarifying, directing, or redirecting the contract effort, including shifting work between work areas and locations, filling in details, or otherwise serving to accomplish the contractual statement of work to ensure the work is accomplished satisfactorily;

(iv) Evaluating performance of the Contractor; and

(v) Certifying all invoices/vouchers for acceptance of the supplies or services furnished for payment.

(c) The COR does not have the authority to issue direction that:

(i) Constitutes a change of assignment or work outside the contract specification/work statement/scope of work.

(ii) Constitutes a change as defined in the clause entitled “Changes” or other similar contract term.

(iii) Causes, in any manner, an increase or decrease in the contract price or the time required for contract performance;

(iv) Causes, in any manner, any change in a term, condition, or specification or the work statement/scope of work of the contract;

(v) Causes, in any manner, any change or commitment that affects price, quality, quantity, delivery, or other term or condition of the contract or that, in any way, directs the contractor or its subcontractors to operate in conflict with the contract terms and conditions;

(vi) Interferes with the contractor's right to perform under the terms and conditions of the contract;

(vii) Directs, supervises, or otherwise controls the actions of the Contractor's employees or a Subcontractor's employees.

(d) The Contractor shall proceed promptly with performance resulting from the technical direction of the COR. If, in the opinion of the Contractor, any direction by the COR or the designated representative falls outside the authority of (b) above and/or within the limitations of (c) above, the Contractor shall immediately notify the Contracting Officer.

(e) Failure of the Contractor and Contracting Officer to agree that technical direction is within the scope of the contract is a dispute that shall be subject to the “Disputes” clause and/or other similar contract term.

(f) COR authority is not re-delegable.

(End of Clause)

2852.223-70 Unsafe Conditions Due to the Presence of Hazardous Material (NOV 2020)

(a) “Unsafe condition” as used in this clause means the actual or potential exposure of Contractor or Government employees to a hazardous material.

(b) “Hazardous Material” as used in this clause includes any material defined as hazardous under the latest version of Federal Standard No. 313 (including revisions adopted during the term of the contract), any other potentially hazardous material requiring safety controls, or any other material or working condition designated as hazardous by the Contracting Officer's Representative (COR).

(c) The Occupational Safety and Health Administration (OSHA) is responsible for issuing and administering regulations that require Contractors to apprise its employees of all hazards to which they may be exposed in the course of their employment; proper conditions and precautions for safe use and exposure; and related symptoms and emergency treatment in the event of exposure.

(d) Prior to commencement of work, Contractors are required to inspect for and report to the Contracting Officer the presence of, or suspected presence of, any unsafe condition including asbestos or other hazardous materials or working conditions in areas in which they will be working.

(e) If during the performance of the work under this contract, the Contractor or any of its employees, or subcontractor employees, discovers the existence of an unsafe condition, the Contractor shall immediately notify the Contracting Officer, or designee (with written notice provided not later than three (3) working days thereafter), of the existence of an unsafe condition. Such notice shall include the Contractor's recommendations for the protection and the safety of Government, Contractor and subcontractor personnel and property that may be exposed to the unsafe condition.

(f) When the Government receives notice of an unsafe condition from the Contractor, the parties will agree on a course of action to mitigate the effects of that condition and, if necessary, the contract will be amended. Failure to agree on a course of action will constitute a dispute under the Disputes clause of this contract.

(g) Nothing contained in this clause shall relieve the Contractor or subcontractors from complying with applicable Federal, State, and local laws, codes, ordinances and regulations (including the obtaining of licenses and permits) in connection with hazardous material including but not limited to the use, disturbance, or disposal of such material.

(End of Clause)

DOJ-01 Whistleblower Information Distribution (Oct 2021)

15BBNF26B60300001 Page 21 of 48

Within 30 days of contract award, the contractor and its subcontractors must distribute the “Whistleblower Information for Employees of DOJ Contractors, Subcontractors, Grantees, or Sub-Grantees or Personal Services Contractors” (“Whistleblower Information”) document to their employees performing work in support of the products and services delivered under this contract (https://oig.justice.gov/sites/default/files/2020-04/NDAA-brochure.pdf).

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .