This document is a subcontract for the manufacture, inspection, and delivery of the Advanced Light Source Upgrade (ALS-U) Accumulator Ring to Storage Ring (ATS) and Storage Ring to Accumulator Ring (STA) transfer lines support structures.
The subcontract outlines the ordered items, pricing, payment terms, delivery schedule, shipping requirements, reports, and other administrative details. It incorporates the Statement of Work for the ALS-U ATS/STA Base Supports & Rafts, as well as other relevant documents. The subcontract is issued under Prime Contract No. DE-AC02-05CH11231 between the University of California and the U.S. Department of Energy for the management and operation of the Lawrence Berkeley National Laboratory. The subcontract requires the subcontractor to meet first article approval and other quality and environmental requirements before full production commences. The total fixed price for the ordered items is TBD.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Subcontract No. TBD Page 1
SUBCONTRACT
NO. TBD
The Regents of the University of California Lawrence Berkeley National Laboratory One Cyclotron Road Berkeley, CA 94720
Subcontractor:
VENDOR TBD
Attention: TBD
NOT A VALID VENDOR
Town/State/Country TBD Phone: TBD Fax: TBD E-Mail: TBD
University Procurement Representative:
Name: Martha Gamarano Grausz Title: Sr. Subcontracts Administrator Phone: (510) 486-6618 Fax: (510) 486-4380 E-Mail: MGGrausz@lbl.gov
Introduction This is a fixed price subcontract (hereinafter "Subcontract") for the manufacture, inspection, and delivery of the Advanced Light Source Upgrade (ALS-U) Accumulator Ring to Storage Ring (ATS) and Storage Ring to Accumulator Ring (STA) transfer lines support structures, as further described herein.
This Subcontract is between The Regents of the University of California, (hereinafter "University") and the party identified above as the "Subcontractor".
This Subcontract is issued under Prime Contract No. DE-AC02-05CH11231 between the University and the United States Government (hereinafter "U.S. Government"), represented by the Department of Energy (hereinafter "DOE") for the management and operation of the Lawrence Berkeley National Laboratory (hereinafter "LBNL") and the performance of certain research and development work.
Agreement The parties agree to perform their respective obligations in accordance with the terms, conditions, and provisions of the attached SCHEDULE OF ARTICLES and the documents referenced or incorporated therein, which together with this Signature Page shall collectively constitute the entire Agreement and shall supersede all prior negotiations, representations, or agreements, whether verbal or written.
VENDOR TBD
THE REGENTS OF THE
UNIVERSITY OF CALIFORNIA
By:
By:
Name:
Name:
Title:
Title:
Date:
Date:
Subcontract No. TBD Page 2
SCHEDULE OF ARTICLES
ARTICLE 1 – ORDERED ITEMS
A. Description
The Subcontractor shall furnish and deliver the following ordered item(s), in accordance with this Subcontract:
First Article Items (SOW Table 3-2)
Item
LBNL ID Description Quantity UOM Price Extended Amount
Delivery Schedule:
4 AL-1511-3285 Weldment, Base Support, Q2-B1, ATS
1.00 EA $TBD $TBD TBD
22 AL-1509-4380 ATS Raft 4, Weldment
1.00 EA $TBD $TBD TBD
Production Items (SOW Table 3-1/ Excludes Items 4 and 22) Base Supports
Item
LBNL ID Description Quantity UOM Price Extended Amount
Delivery Schedule:
1 AL-1354-0931 Support, Module #4, BPM 1, ATS
1.00 EA $TBD $TBD TBD
2 AL-1334-4020 Support, Module #5, Q1, ATS
1.00 EA $TBD $TBD TBD
3 AL-1504-7148 Adapter Plate, Module
#5, Q1, ATS
1.00 EA $TBD $TBD TBD
5 AL-1512-1171 Weldment, Bridge, Q4, ATS
1.00 EA $TBD $TBD TBD
6 AL-1507-8995 Support, Raft1 Base, Sector12
1.00 EA $TBD $TBD TBD
7 AL-1507-7378 Mini-raft Base Plate Weldment, ATS 11
Q7-Q9 (ATS Q7-Q9
Strut Baseplate)
1.00 EA $TBD $TBD TBD
8 AL-1505-6811 Vacuum Drift Support, ATS
1.00 EA $TBD $TBD TBD
9 AL-1613-2941 Diving Board, ATS Shield (TV camera shield diving board)
1.00 EA $TBD $TBD TBD
10 AL-1545-4931 Weldment, Base Support, M9-M10, Q5-B3, Q6-B4, STA
1.00 EA $TBD $TBD TBD
11 AL-1595-5383 Weldment, Base Support, M8, Q4-B2, STA
1.00 EA $TBD $TBD TBD
12 AL-1596-0512 Weldment, Pedestal, M6-M8, STA
1.00 EA $TBD $TBD TBD
Subcontract No. TBD Page 3
13 AL-1595-5168 Weldment, Base Support, M6, Q2-Q1, STA
1.00 EA $TBD $TBD TBD
14 AL-1550-0852 Weldment, Pedestal Support, Vacuum, STA
1.00 EA $TBD $TBD TBD
15 AL-1546-2606 Weldment, Pedestal Support, BPM, STA
1.00 EA $TBD $TBD TBD
16 AL-1595-3755 Mini-raft Base Plate Weldment, STA 12
Q7-Q9 (STA Q7-Q9
Strut Baseplate)
1.00 EA $TBD $TBD TBD
17 AL-1595-5256 STA Vacuum Drift Support
1.00 EA $TBD $TBD TBD
18 AL-1605-0942 Diving Board Shield, STA (TV camera shield diving board)
1.00 EA $TBD $TBD TBD
Rafts 19 AL-1506-9923 ATS Raft 1, Weldment
1.00 EA $TBD $TBD TBD
20 AL-1507-8666 ATS Raft 2, Weldment
1.00 EA $TBD $TBD TBD
21 AL-1507-8867 ATS Raft 3, Weldment
1.00 EA $TBD $TBD TBD
23 AL-1507-6856 ATS Mini-Raft Weldment
1.00 EA $TBD $TBD TBD
24 AL-1595-4641 STA Q1-Q2 Raft, Weldment
1.00 EA $TBD $TBD TBD
25 AL-1595-2510 STA Raft 1, Weldment
1.00 EA $TBD $TBD TBD
26 AL-1595-2395 STA Raft 2, Weldment
1.00 EA $TBD $TBD TBD
27 AL-1593-7670 STA Raft 3, Weldment
1.00 EA $TBD $TBD TBD
28 AL-1593-7618 STA Raft 4, Weldment
1.00 EA $TBD $TBD TBD
29 AL-1595-3075 STA Mini-Raft Weldment
1.00 EA $TBD $TBD TBD
Camera Supports and Shields
30 AL-1635-5911 Base Plate, SRM Camera Support
1.00 EA $TBD $TBD TBD
31 AL-1590-0850 Bracket, Camera Mount, ATS
1.00 EA $TBD $TBD TBD
32 AL-1590-0963 Bracket, Camera Mount, ATS
1.00 EA $TBD $TBD TBD
33 AL-1617-3590 Plate, Mounting, Camera Shield
Subcontract No. TBD Page 4
34 AL-1697-9998 Shield Camera-3, Plate 12.7mm (1/2"), STA
1.00 EA $TBD $TBD TBD
35 AL-1697-9999 Shield Camera-3, Round Bar 44.5mm
(1-3/4"), STA
1.00 EA $TBD $TBD TBD
36 AL-1697-5829 Shield CameraA-2, Plate 12.7mm (1/2"), STA
1.00 EA $TBD $TBD TBD
37 AL-1697-9676 Shield Camera-2, Round Bar 44.5mm
(1-3/4"), STA
1.00 EA $TBD $TBD TBD
38 AL-1698-0338 Shield Camera-1, Plate 12.7MM (1/2"), STA
1.00 EA $TBD $TBD TBD
39 AL-1698-0435 Shield Camera-1, Round Bar 44.5MM
(1-3/4"), STA
1.00 EA $TBD $TBD TBD
40 AL-1633-9142 Shield, Bottom Cover 1.00 EA $TBD $TBD TBD
41 AL-1633-7060 Plate, Bracket Shim 2.00 EA $TBD $TBD TBD
42 AL-1633-6312 Weldment, SMR Bracket, STA
2.00 EA $TBD $TBD TBD
43 AL-1633-7070 Support, Vert.
Mounting Post-2
1.00 EA $TBD $TBD TBD
44 AL-1635-5613 Support, Vert.
Mounting Post-1
1.00 EA $TBD $TBD TBD
45 AL-1635-5621 Support, Camera Mounting
1.00 EA $TBD $TBD TBD
46 AL-1697-9690 Support, Camera Shield Mounting, STA
TOTAL $TBD
The above delivery schedule identifies the date(s) by which the specified item(s) shall be delivered to the shipping address indicated in the article below entitled Shipping Requirements.
B. Acceptance Acceptance of the items described above is based upon successful completion of the acceptance criteria per the Statement of Work (SOW) AL-1692-2466 Titled Statement of Work for the ALS-U ATS/STA Base Supports & Rafts, Rev. A, dated 04/03/2024 incorporated into this Subcontract.
Subcontract No. TBD Page 5
C. Notice to Proceed The following documents shall be submitted to the University. Acceptable documents, as determined by the University, must be submitted and a Notice to Proceed must be issued before any work may commence, unless otherwise noted below.
1. Hold Point (HP) – The Subcontractor must not proceed beyond a hold point (HP) per the incorporated per the Statement of Work (SOW) AL-1692-2466 Titled Statement of Work for the ALS-U ATS/STA Base Supports & Rafts, Rev. A, dated 04/03/2024 Section 4.5 – Hold Points, without a formal written Notice to Proceed (NTP).
ARTICLE 2 – PRICE AND PAYMENT
A. Fixed Price
The Subcontractor shall furnish and deliver the ordered item(s) for the total fixed price of $TBD.
B. Sales or Use Tax
Items purchased by the University hereunder are treated as for resale, per the University's California State Resale Permit No. SR-CH 21-835970 for LBNL, and shall not be subject to any California or other State sales or use tax if shipped to California. Any items furnished hereunder for rentals or leases are subject to California State sales or use tax, and such tax is included in the fixed prices/rates stated herein.
The University of California State Resale Permit No. SR-CH 21-835970 for LBNL is available at:
http://procurement.lbl.gov/supplier-forms/.
C. Invoices
1. The Subcontractor shall email invoice(s) directly to the LBNL Accounts Payable Office at
APInvoice@lbl.gov, within thirty days of the acceptance of the item(s). The "subject" line of the email shall state the Subcontractor's name and the Subcontract number. If final invoices are not submitted within 180 days of acceptance, then any amounts paid by the University to that point will represent satisfaction in full by LBNL under this Subcontract and an Accord and Satisfaction. This means that LBNL will not be obligated to make any further payments under this Subcontract.
To avoid delays in processing and payment, Subcontractors should include only one attachment per email. Multiple invoices should be combined and attached as a single portable document format (PDF) or Microsoft Word or rich text format (RTF) file (up to 30 individual invoices per attachment) or emailed separately (one attachment per email).
Do not include icons/pictures in the email (logos, etc.) and ensure only one subcontract number is listed on the invoice.
2. If unable to submit an invoice by email, the Subcontractor may submit the invoice to the following address:
http://procurement.lbl.gov/supplier-forms/ mailto:APInvoice@lbl.gov
Subcontract No. TBD Page 6
Accounts Payable Office, Subcontract No. TBD One Cyclotron Road, M/S 971-AP Berkeley, CA 94720
3. Invoice(s) shall state: the Subcontract number; the Subcontractor (including business heading or logo); bill to address (same address as above); invoice date; unique invoice number; remittance address; sufficiently identify the items/services being invoiced; and identify any separately payable freight charges (with receipts if available) and taxes.
Invoice(s) in a spreadsheet format are not acceptable, but a spreadsheet can be used to support an invoice. The Subcontractor shall maintain records which support all invoiced amounts, and provide them to the University Procurement Representative upon request.
D. Payment Terms
All invoices except the final invoice shall be payable within 15 days of receipt, provided, however, that payments made thereafter shall not be subject to any penalty, interest, or late charges. Only those items/services identified in this Subcontract or a Subcontract Modification will be considered for payment. Payment amounts may be adjusted for any applicable credits, offsets, or withholds.
Full payment shall not be due until any final acceptance requirements of this Subcontract have been satisfied. For inquiries about the status of an invoice, call (510) 486-6954 or aphelp@lbl.gov.
ARTICLE 3 – SUBCONTRACT ADMINISTRATION
A. Notices, Requests, and Modifications The Subcontractor shall submit all notices and requests for approval by email to the University Procurement Representative indicated on the signature page or at the following mail address:
Attn: Martha Grausz One Cyclotron Road M/S 971-PROC
Only the University Procurement Representative is authorized to modify the terms, conditions, and requirements of this Subcontract, including any changes to the description of the work, and to issue any notices and approvals required by this Subcontract. Certain changes to this subcontract may be made only by the University Procurement Representative without subcontractor agreement or negotiation prior to the change. Such changes may include: changes of an administrative nature, directed changes pursuant to the clause incorporated herein entitled:
“CHANGES,” unilateral modifications authorized by clauses other than the Changes clause, and termination notices. Apart from the University Procurement Representative’s authority to issue unilateral changes, the parties may mutually agree to make changes in the work ordered, or modify any other term or condition of the subcontract, resulting in an amendment to the subcontract, but only by a written modification signed by the authorized representatives of both parties.
mailto:aphelp@lbl.gov
Subcontract No. TBD Page 7
B. Technical Representative
Technical Representative is the Technical Representative for this Subcontract. This individual is designated to monitor performance of the work and to interpret and clarify the technical requirements, but is not authorized to make changes to the work or to modify any of the terms and conditions of this Subcontract, including those related to the completion schedule or pricing.
Technical Representative TechRep@lbl.gov
(510) 486-XXXX
C. Closeout
The Subcontractor shall, as a condition of full payment, assist the University after the completion of the work in accomplishing the administrative closeout of this Subcontract, including, as necessary or required, the furnishing of documentation and reports, the disposition of property, the disclosure of any inventions, the execution of any required documents (including an Assignment and Release form if this form is an incorporated document), the performance of any audits, and the settlement of any interim or disallowed costs.
ARTICLE 4 – FURNISHED AND ACQUIRED PROPERTY
The University will not furnish any U.S. Government Property for use under this Subcontract. The Subcontractor is not authorized to acquire, fabricate, or provide any tangible personal property items for use under this Subcontract. The Subcontractor must not acquire tangible personal property for use under this Subcontract without the University Procurement Representative's advanced written approval via Subcontract modification. The Subcontractor is required to notify the University prior to purchasing any Subcontractor Acquired Property. The Subcontractor assumes the risk of not being reimbursed for property if approvals are not provided by the University in advance via Subcontract modification.
ARTICLE 5 – SHIPPING REQUIREMENTS
A. Shipping Terms The shipping terms are FOB Destination, freight prepaid and add. All shipments shall be shipped via the Subcontractor's vehicles or a licensed common carrier selected by the Subcontractor, at the University's expense.
B. Shipping Address All shipments shall be shipped to the following address:
Lawrence Berkeley National Laboratory For the U.S. Department of Energy One Cyclotron Road, Building 69
C. Shipping Point
Subcontract No. TBD Page 8
The shipping point is: TBD.
ARTICLE 6 – REPORTS
A. Type of Reports
The Subcontractor shall prepare and submit the following reports to the University:
1. Monthly Progress Reports Monthly progress reports shall be submitted by the fifth business day of each month. The progress reports may be informal letter summaries in a format approved by the University representatives. These reports shall contain a description of work performed during the report period and the work planned for the succeeding periods, and related financial information, including incurred and projected expenditures. They must also include an explanation for schedule changes, if applicable, as well as a list of completed quantities of key components throughout the production sequence
2. Reports and Meetings as identified within the Statement of Work
Meetings are to be scheduled and additional reports submitted as identified within the Statement of Work section 4.2. Reports shall be prepared and submitted in accordance with the instruction provided therein.
B. Submittal
Reports shall be separately submitted to the following recipients at the following email or mailing address:
Attention: [Intended Recipient; see below] One Cyclotron Rd., Mail Stop [see below]
Recipient Mail Stop Email Technical Representative TBD TBD@lbl.gov Martha G. Grausz 971-PROC mggrausz@lbl.gov
ARTICLE 7 – APPROVAL OF TECHNICAL DATA
If this Subcontract requires the Subcontractor to furnish any drawings, specifications, diagrams, layouts, schematics, descriptive literature, illustrations, schedules, performance or test data, or other technical data for approval by the University prior to Subcontractor performance, the approval of the data by the University shall not relieve the Subcontractor from responsibility for any errors or omissions in such data or from responsibility for complying with the requirements of this Subcontract, except as specified below.
Any work done prior to such approval shall be at the Subcontractor's risk.
Unless otherwise specified, the University requires a period of 10 working days from date of receipt to review and approve the data. If the University does not approve the data within the allotted time period, Subcontract No. TBD Page 9 the parties will establish a new time period for review and approval of the data and, if necessary, the delivery schedule or completion date will be equitably adjusted.
If the data includes any variations from the Subcontract requirements, the Subcontractor shall describe such variations in writing at the time of submission of the data. If the University approves any such variation(s), a change order to the Subcontract shall be issued by the University and, if appropriate, a bilateral modification to the Subcontract shall be negotiated.
ARTICLE 8 – PRELIMINARY INSPECTION
The University reserves the right to observe and witness all phases of the manufacturing of the items, including design, fabrication, assembly, testing, and inspection, conducted at the Subcontractor's facility or at any of its sub-tier subcontractors' facilities.
Preliminary in-process and source inspections may be performed at the Subcontractor's facility or at any of its sub-tier subcontractors' facilities. The inspection shall allow the University to verify that the Subcontractor has met the requirements of this Subcontract. Prior to University inspection, the Subcontractor shall perform a complete inspection and document the results. The Subcontractor shall present this documentation to the University at the time of the preliminary inspection. Such preliminary inspection does not waive the right of the University to inspect and accept or reject at the destination. The University reserves the right to subcontract with a qualified third party to conduct on its behalf any or all of the University inspections.
ARTICLE 9 – ENVIRONMENTALLY PREFERABLE PRODUCTS AND SERVICES
The Laboratory is subject to several interacting initiatives and federal and DOE requirements related to sustainability, including waste reduction, Recycled Content Products (EPA Designated Products), Biobased (BioPreferred®), energy efficient products (EnergyStar®), environmentally preferable and energy efficient electronics (EPEAT® and Federal Energy Management Program (FEMP) Designated Products), Non-Ozone Depleting Alternative Products (SNAP) and Water Efficient Plumbing Products (EPA Watersense®). The Laboratory also implements State of California requirements on packaging and electronic waste recycling.
The subcontractor must deliver products and services in compliance with this article which implements the requirements of DOE’s Sustainable Acquisition Program, as well as other federal- and state-mandated sustainability requirements.
In the performance of this Subcontract, the Subcontractor must specify, furnish, and use environmentally preferable products and services (i.e., products and services with a lesser or reduced effect on human health and the environment), to the maximum possible extent consistent with the Subcontract requirements herein, the General Provisions, and the intended end use of the products or services. The Laboratory generally considers the requirements practicable unless a specific program exception applies. Refer to SFTool.gov/Vendor Resources for links to sustainability resources and information on environmental programs the Laboratory and its suppliers/subcontractors are required to comply with, including exceptions.
https://sftool.gov/learn/about/652/vendor-resources#sftoolpages
Subcontract No. TBD Page 10
DOE Order 436.1.A. In addition to the above programs, DOE Order 436.1.A requires:
The subcontractor must maximize, to the extent feasible, the procurement of materials and operations with lower embodied emissions and alternatives to ozone-depleting substances and high global warming potential hydrofluorocarbons.
The subcontractor must minimize, to the extent feasible, the supply of products and services determined by the EPA to be contaminants of emerging concern (CEC), including pharmaceuticals and personal care products and CECs found therein. The subcontractor shall provide Safer Choice labeled products under this subcontract, as applicable. The subcontractor is encouraged to visit https://www.epa.gov/saferchoice for updated lists of qualifying products.
The subcontractor must minimize the supply of products with toxic and hazardous characteristics, and minimize the generation of toxic and hazardous waste, to the maximum extent practicable.
E-Waste Recycling Requirements. All recyclers of electronic equipment must be e-Steward certified by the Basel Action Network (BAN).
For any equipment removed by the subcontractor and scheduled to be refurbished or recycled, the subcontractor must attest that those actions will be handled by a refurbisher or recycler that is third-party certified to one of the known electronics recycling certification programs that is used in the United States, the Responsible Recycling Standard (R2) or the E-Stewards Standard.
Information on environmentally preferable products and services is also available at:
https://www.epa.gov/contracts/greening-government-procurement. State of California sustainable procurement information can be found at: https://ucop.edu/procurement-services/for-suppliers/sustainable-procurement/sustainable-procurement-training-resources.html
Questions regarding these sustainable acquisition requirements may be directed to the Laboratory Sustainable Procurement Representative (Business-Assurance-Sustainable@lbl.gov).
A. Packaging The subcontractor must minimize the supply of single use items including single-use plastic foodware (e.g., plates, cups, utensils, beverage bottles and bags).
The subcontractor must make good faith efforts to utilize smart-size packing; to customize box sizes in order to reduce packaging waste, and to minimize the number of shipments per order.
Recycling practices and methods should be used to minimize the adverse effects on the environment. The subcontractor must use every reasonable effort to use cardboard and paper-based packaging materials for shipments to the Laboratory.
Packaging Requirements All packaging must be compliant with the California Toxics in Packaging Prevention Act (California AB 455). and must meet all additional standards and requirements set forth in the UC Sustainable Practices Policy. In addition, the Laboratory requires that all packaging meet at least one of the criteria listed below:
• Uses bulk packaging;
• Uses reusable packaging (e.g. totes reused by delivery service for next delivery);
• Uses innovative packaging that reduces the weight of packaging, reduces packaging waste, or utilizes packaging that is a component of the product;
https://www.epa.gov/saferchoice https://www.epa.gov/contracts/greening-government-procurement https://ucop.edu/procurement-services/for-suppliers/sustainable-procurement/sustainable-procurement-training-resources.html https://ucop.edu/procurement-services/for-suppliers/sustainable-procurement/sustainable-procurement-training-resources.html mailto:Business-Assurance-Sustainable@lbl.gov
Subcontract No. TBD Page 11
• Maximizes recycled content and/or meets or exceeds the minimum post-consumer content level for packaging in the U.S. Environmental Protection Agency Comprehensive Procurement Guidelines;
• Uses locally recyclable or certified compostable material.
Foam packaging is prohibited as follows:
• Foam Ban – Food Service Packaging - The Laboratory does not allow packaging foam or expanded polystyrene (EPS) for takeaway containers or other food service items, in any University-owned or -operated food service facility.
• Foam Ban – Product Packaging - The Laboratory prohibits all subcontracted and non-subcontracted suppliers from selling or distributing packaging foam (other than that utilized for laboratory supply or medical packaging) to the Laboratory.
Packaging foam is defined as any open or closed cell, solidified, polymeric foam used for cushioning or packaging, including but not limited to: low-density polyethylene foam, polypropylene foam, polystyrene foam (i.e. EPS), polyurethane foam, polyethylene foam, polyvinyl chloride (PVC) foam, and microcellular foam. Not included in this ban are easily biodegradable, plant-based foams such as those derived from corn or mushrooms.
ARTICLE 10 – SYSTEM FOR AWARD MANAGEMENT (SAM)
By acceptance of this Subcontract, the Subcontractor certifies that it will be registered in the SAM database (http://www.sam.gov/) within 30 days of Subcontract award per Federal Acquisition Regulation (FAR) 52.204-7, System for Award Management, and acknowledges the requirement heretofore to maintain said registration in the database in accordance with FAR 52.204-13, System for Award Management Maintenance, during performance of this Subcontract. The Subcontractor is responsible for the accuracy and completeness of its data within the SAM database in accordance with the stated requirements. In any event, failure to complete the registration within the required timeframe or to maintain such registration throughout Subcontract performance is considered a breach of Subcontract.
ARTICLE 11 – FIRST ARTICLE APPROVAL
A. The Subcontractor shall deliver to the University for testing the first articles AL-1511-3285 and, AL-1509-4380, within 20 calendar weeks from the ARO of this Subcontract.
B. The shipping documentation shall contain this Subcontract number and the item identification.
The characteristics that the first article must meet and the testing requirements are specified elsewhere in this Subcontract.
C. Within 10 business days after receiving the first articles, the University shall notify the Subcontractor, in writing, of the conditional approval, approval, or disapproval of the first article.
The notice of conditional approval or approval shall not relieve the Subcontractor from complying with all requirements of the specifications and all other terms and conditions of this Subcontract.
A notice of conditional approval shall state any further action required of the Subcontractor. A notice of disapproval shall cite reasons for the disapproval.
D. If the first article is disapproved, the Subcontractor, upon the University's request, shall submit an additional first article for testing. After each request, the Subcontractor shall make any necessary changes, modifications, or repairs to the first article or select another unit for first article testing.
All costs related to these tests are to be borne by the Subcontractor, including any and all costs for additional tests following a disapproval. The Subcontractor shall furnish any additional first article
Subcontract No. TBD Page 12 under the terms and conditions and within the time specified by the University. The University shall act on the first article within the time specified in paragraph C, above. The University reserves the right to require an equitable adjustment of the Subcontract price for any extension of the delivery schedule or for any additional costs to the University related to these tests.
E. If the Subcontractor fails to deliver any first article on time, or the University disapproves any first article, the Subcontractor shall be deemed to have failed to make delivery within the meaning of the termination for default provisions of this Subcontract.
F. If the University does not act within the time specified in paragraph C or D, above, the University shall, upon timely written request from the Subcontractor, equitably adjust the delivery or performance dates and/or the Subcontract price, and any other subcontractual term affected by the delay.
G. Before first article approval, the acquisition of materials or components for, or the commencement of production of, the balance of the Subcontract quantity is at the sole risk of the Subcontractor.
Before first article approval, the costs thereof shall not be allocable to this Subcontract for (1) progress payments, or (2) termination settlements if the Subcontract is terminated for the convenience of the University.
H. The Subcontractor shall produce both the first article and the production quantity at the same facility.
I. The Subcontractor shall remove and dispose of any first article from the University test facility at the Subcontractor’s expense if the first article is not included in the subcontract purchased quantity or is rejected by the University.
ARTICLE 12 – INCORPORATED DOCUMENTS
The following documents are hereby incorporated as a part of this Subcontract. The order of precedence for each document must be as specified in the Entire Agreement and Order of Precedence clause in the General Provisions. Any other documents not incorporated herein by specific reference are excluded from this Subcontract. The documents marked with an asterisk are available at http://procurement.lbl.gov/supplier-forms/.
• AL-1692-2466, Titled Statement of Work for the ALS-U ATS/STA Base Supports & Rafts, Rev.
A, dated 04/03/2024
• AL-1713-6747 Titled Document Reference List for ALS-U ATS/STA Base Supports and Rafts, Rev. A, dated 05/09/2024
• GENERAL PROVISIONS
The following General Provisions are incorporated by reference into this Subcontract and are available at: http://procurement.lbl.gov/welcome-to-procurement-property/become-a-supplier/general-provisions/.
A. General Provisions for Commercial Supplies & Services, dated 12/22/23
B. The clauses listed in the referenced General Provisions shall be applicable to this Subcontract, based on the value of the Subcontract, the status of the Subcontractor, or the nature and location of the Services, as indicated in the General Provisions.
http://procurement.lbl.gov/supplier-forms/ http://procurement.lbl.gov/welcome-to-procurement-property/become-a-supplier/general-provisions/
Subcontract No. TBD Page 13
(END OF SCHEDULE OF ARTICLES)