TECHNICAL SPECIFICATIONS SUMMARY
This document comprises the Technical Specifications (Part III) for the Borough of Stroudsburg's "2023 CDBG – Kraemer Avenue – Milling and Paving Project" located on Kraemer Avenue from North 2nd Street to North 3rd Street in Monroe County, Pennsylvania. The scope of work includes complete milling and paving operations consisting of mobilization and demobilization, maintenance and protection of traffic, milling to a depth of 1.5 inches from curb to curb, installation of tack coat, placement of 9.5mm Superpave wearing course WMA/HMA, and sealing of all joints at curbs, inlets, manholes, concrete edges, and existing pavement edges to provide water-tight seals. Sealed bids are due online via PennBid by 11:00 A.M. on March 31, 2026, at which time they will be publicly opened and read aloud at the office of the Borough Engineer, Peters Consultants, Inc., located at 2701 Columbia Boulevard, Bloomsburg, Pennsylvania 17815. No pre-bid walkthrough is scheduled for this project. The contract requires completion during appropriate weather conditions, with all roadway construction to be terminated by November 1st and not resumed before April 1st of the following year, except by written approval from the Engineer. Construction is prohibited during peak traffic hours exceeding 1,200 vehicles per lane per hour and during special local events.
The specifications require the contractor to include all mobilization and demobilization costs, dust control, erosion and sedimentation control, submittals including CPM schedules and shop drawings, color audio-video electrography documentation, temporary facilities and controls, and maintenance and protection of traffic within a lump sum bid price. The contractor must obtain and maintain PA One Call compliance, provide record drawings documenting as-built conditions, furnish maintenance and operating instruction manuals, maintain all existing utility services without interruption, and provide two-year maintenance bonds upon project completion. The project is funded through 2023 CDBG (Community Development Block Grant) and related state funding sources. All work must comply with PennDOT Publication 408 Specifications as last revised, Monroe County Conservation regulations, and Pennsylvania Act 38 regarding underground utilities. A 10% bid bond is required, along with comprehensive general liability insurance of $1,000,000 per occurrence and $2,000,000 annual aggregate, worker's compensation following Pennsylvania statutory requirements, and 100% performance and payment bonds.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 1-Part V.pdf | ||
| 4-Part IV.pdf | ||
| 3-Part II.pdf | ||
| 5-Part I.pdf | ||
| 2-Newspaper Ad - Updated.pdf | ||
| 5-Part III.pdf | ||
| 3-Part II.pdf | ||
| 7-Parking Garage Plans - Complete Set 9.23.25.pdf | ||
| 4-Part IV - NEW Wage Rates.pdf | ||
| 1-Part V.pdf | ||
| 6-Part I - Cover and Bid Form Updated 10.1.25.pdf |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PART III - TECHNICAL SPECIFICATIONS
01000-021626
PART III - CONTENTS
01010 Mobilization and Close-Out 1 - 4
01020 Maintenance and Protection of Traffic During Construction 1 - 2
01040 Dust Control 1
01050 Unforeseen Project Water Pollution Control (Soil Erosion) 1
01060 Submittals 1 - 5
01080 Special Requirements 1
01090 Color Audio - Video - Electrography 1 - 3
01100 Temporary Facilities and Controls 1 - 4
01170 Roadway Construction 1 - 3
01191 PA One Call 1
01195 Milling 1
01650 Delivery, Storage and Handling 1 - 2
NOTE: All Work under this Contract shall meet PennDOT, Publication 408 Specifications, as last revised, in addition to the Specifications attached herein
SECTION 01010
MOBILIZATION AND CLOSE-OUT
1. GENERAL
This Work shall consist of assembling all materials, workmen, storage yards and any other materials or facilities as required under this Contract or in reference to any Local, State or Federal regulations pertaining to this Project.
This item shall include the cost of required Insurance, Payment and Performance Bonds, Warranty
Bonds and/or any related initial and final expenses associated with this Project.
This item includes the cost of PA One Call compliance, Temporary Facilities and Controls, necessary Contractors Licenses and Permits (waived), any Agency Inspection Fees, Audio/Video
Record, Schedules, Cleaning and Final Restoration, Dust Control, CPM Schedule, Plan of
Operation and all other incidental items necessary to fully complete the Project, as would be normally expected for a Project of this nature in the location of Work, not covered by unit or lump sum price.
2. MATERIALS
A. Materials under this part of this Specification are limited to those required for
Mobilization for each Contractor but not intended for incorporation in the completed Contracts.
3. EXECUTION
A. All equipment required to diligently start the respective Contractors construction
Work shall be on the site in satisfactory operating condition. The physical construction facilities, personnel and equipment shall be set up and operating at the required efficiency to diligently pursue the Work. No mobilization / demobilization costs will be paid to relocate material or equipment.
4. CLEANING-UP
A. In addition to the requirements of the General Conditions and to the requirements for special cleaning in the various other sections of the Specifications, the
Contractor, except as noted, shall perform final cleaning as follows:
1. Dust, and if necessary wash, all adjacent vehicles and/or structures.
B. Final cleaning shall be performed after the Work is completed and immediately before turning the Work over to the Owner.
C. Cleaning materials shall be free from harmful abrasive and shall be acceptable to the Manufacturers of the materials on which they are used.
01010-021626
MOBILIZATION AND CLOSE OUT
D. Each Contractor shall remove all his field offices, storage facilities and any other materials or items that were used by him during construction and not incorporated into the Project. Leave these temporary service areas in a clean condition and repair or replace any damaged areas ready to be turned over to the Owner.
5. FINAL RESTORATION
A. In addition to the requirements specified in the various Sections of these
Specifications each Contractor shall make final restoration of all areas disturbed by his temporary construction facilities such as, but not limited to, office and storage trailers.
B. In general, the Contractor shall repair all walks, roadways and any other areas damaged during construction, inside or outside the construction limits, to the satisfaction of the Engineer.
6. RECORD DRAWINGS
A. Contractor shall prepare one set of white prints for the purpose of recording as-built conditions. The As-Built “Record Drawings” shall be furnished, reviewed and approved prior to the release of the final payment.
B. These prints shall be marked "Record Drawings" and maintained at the Project Site.
Each Contractor shall record on the prints all deviations from the Contract
Drawings, at the time that such deviations are made.
1. All changes made in construction of the Project, as well as a complete record of the exact manner in which Work is installed, shall be recorded on the prints. Dimensions shall be included where necessary to accurately locate underground electrical feeds, piping, wyes and laterals and other items which shall be concealed in the finished Work and which may later be necessary to locate for service.
2. Record plans shall show all vertical and horizontal location of all under-ground facilities. Drawings shall indicate a profile showing the depths where rock was encountered and all other changes made to the Contract
Drawings. The Resident Project Representative shall provide the
Contractor with a sample Record Drawing at the time of construction.
C. A complete file of accepted field sketches, diagrams, and other changes as may become necessary during the progress of the Work shall also be maintained and attached to the set of marked-up prints.
D. At completion of the Work, the respective Contractor shall provide, for the information of the Engineer, each sheet of marked prints and all accepted field sketches and diagrams.
E. Before Final Application for Payment is processed, deliver “Record Drawings” in a clean and neat condition to the Engineer.
7. MAINTENANCE AND OPERATING INSTRUCTIONS
A. Prior to Final Application for Payment is processed, each Contractor or
Subcontractor shall provide final (up-dated) maintenance information for all material and equipment provided under the Contract. These instructions shall set forth all of the information necessary for the Owner to perform such maintenance and servicing as would ordinarily be done by the Owner.
B. Information shall be given in simple, non-technical language with sufficient diagrams and explanation to be readily understandable by the average layman.
Possible hazards shall be particularly pointed out with instructions cautioning against mistakes that might result in damage to materials or facility or in danger to personnel.
C. This information shall be assembled and bound in a hard cover brochure(s) or book(s). Brochure shall contain:
1. Maintenance instructions.
2. Manufacturer's literature marked to key with item numbers or code on Contract
Drawings, giving Manufacturer's material or equipment designation and list for replacement parts.
3. Name, address, and telephone number of installing Contractor or Subcontractor.
D. Submit manuals and operating instructions for all materials and facilities to the
Engineer in triplicate.
8. INSPECTION FEES
No Owner’s Representative inspection fees are to be paid by the Contractor.
9. INITIAL PAYMENT
A. Fifty percent (50%) of the price bid for Mobilization and Close-Out shall be payable to the respective Contractor whenever five percent (5%) of the Work of the Contract is completed. For the purposes of this item five percent (5%) of the Work shall be considered completed when the total of payments earned, exclusive of the amount bid for this item, as shown on the monthly certificates of the approximate quantities of Work done, prepared in conformance with the General Conditions shall exceed five percent (5%) of the total price bid for this Contract.
10. FINAL PAYMENT
A. The final fifty percent (50%) of the price Bid for Mobilization and Close-Out shall be payable to the respective Contractor when the following Work has been performed:
1. Completed all of the Work.
2. Clean-up and all final restoration of all disturbed areas related to the Contract.
3. Delivered all required documents enumerated in the Specifications including,
a. Required warranties and guarantees
b. Special bonds
c. Certificates from Manufacturers and Suppliers
d. Certificates from regulatory agencies and/or authorities
e. Maintenance and equipment instructions
4. Delivered, properly executed, the following:
a. Contractor's Affidavit
b. Statement of Surety Company (with Power of Attorney and
Statement of Surety's Financial Conditions)
c. Two Year Maintenance Bond (s) (with Power of Attorney and
Statement of Surety's Financial Conditions)
d. Contractor's Release
11. INSPECTOR'S FIELD OFFICE AND INSPECTION FACILITIES
A. No inspector's field office shall be required for this Project.
B. The Work shall, at all times, be made available for inspection by the Engineer, Resident Project Representative, Owner and all agencies having jurisdiction over the Work.
MOBILIZATION AND CLOSEOUT
SECTION 01040
DUST CONTROL
Maintain Dust Control necessary for the duration of the Project to avoid unstabilized areas.
Submit methods of Dust Control and plan of operation at the preconstruction conference for review and approval by the Engineer.
Methods of Dust Control shall include use of water, calcium chloride in all trenches, approved
Dust Control chemicals, vacuum sweeping and temporary bituminous paving and barricading
Work, as required. No oil is allowed for dust control nor is broom sweeping allowed.
Do not start Work until the Dust Control Plan, Schedule and operation methods have been reviewed and accepted.
Adequate water and/or vacuum shall be used during all cutting operations to prevent airborne dust.
The Engineer shall have the authority to order Dust Control Work to be completed by others if the
Contractor fails to correct inadequate Dust Control within 24 hours of notice and deductions from the Contractors payment shall be made to pay for dust control.
All Dust Control expense shall be included in the Mobilization/Demobilization lump sum bid price shown on the Bid Form, complete in place in accordance with the Contract Documents and good construction practice, including all materials, operation, workmanship and appurtenances for a complete job and shall NOT be paid separately under this Contract.
01040-021626
DUST CONTROL
SECTION 01050
UNFORESEEN PROJECT WATER POLLUTION CONTROL
(SOIL EROSION)
This Work is construction of temporary control measures, as ordered during the Contract life, to control water pollution and soil erosion meeting the requirements of PennDOT, Publication 408
Specifications, Section 845, as last revised and Monroe County (or other applicable) Conservation regulations.
When and as directed during construction, provide temporary pollution and erosion control measures to prevent or abate unforeseen conditions. All work shall be completed to prevent sedimentation from leaving the project area.
During the preconstruction conference or prior to the start of construction, submit an Erosion
Control Plan outlining the Schedules for accomplishing temporary and permanent erosion and water pollution control. Do not start Work until the Erosion Control Plan, Schedules, and operation methods have been reviewed and accepted.
This item shall be included in the Erosion and Sedimentation Control lump sum bid price shown on the Bid Form, complete in place, in accordance with the Contract Documents and good construction practice, including all materials, operation, workmanship and appurtenances for a complete job.
01050-021626
UNFORESEEN PROJECT WATER POLLUTION CONTROL
SECTION 01060
SUBMITTALS
The Contractor shall be responsible for preparing a CPM Schedule, Cash Flow Projection
Schedule, Plan of Operation and other submittals outlined in the Contract Documents for the entire
Project and shall include all Subcontract Schedules for the Work.
Each Contractor shall process the Shop Drawings required by his Contract to the Engineer and he shall be responsible for their timely submission in accordance with the Shop Drawing Schedule which is included in the overall progress or Work Schedule as described in item 3 of this Section.
Any proposed deviations/substitutions from that specified shall be clearly noted on the cover letter transmitting the Shop Drawing. Failure to note deviations/substitutions shall be cause for rejection of equipment, materials, etc., after installation.
All submissions shall be marked with the Specification section containing the item submitted for review.
Revised Shop Drawings submitted for review shall be marked "Resubmission".
"Or Equal" items for all equipment and materials shall be considered for approval.
2. SUBMITTAL PROCEDURES
All submittals shall be delivered to the Engineer for approval within 10 days of Notice to Proceed.
The Engineer shall screen the submittals to insure that they have been properly certified and identified by each Contractor. If they are submitted properly, the items shall be processed for review, acceptance and/or resubmission.
The processed submittals shall be returned to the Contractor within 20 days of receipt by the
Engineer.
3. SCHEDULE
The General Contractor shall prepare a CPM Schedule for the entire Project, showing the order in which each Contractor proposes to carry on his Work and salient features, including submission of Shop Drawings and samples and procurement of materials, to meet date of completion. The other Contractors shall be consulted in the preparation of this Schedule and shall signify their approval of the finished Schedule by their signature.
Each activity in the progress or Work Schedule shall be identified and a time for the performance of such activity indicated. Each activity shall be preceded by all Work that must be accomplished prior to that activity. All abbreviation, codes and/or symbols used shall be described in the
Schedule.
01060-021626
4. SUBMISSION
Submit four (4) copies of the CPM Schedule to the Engineer for review within fifteen (15) days after award of Contract. Weather related days shall be included in the CPM Schedule. Update and resubmit CPM Schedule monthly thereafter until completion of the Work. Updated CPM Schedule shall have completed activities removed or indicated as such. Whenever modifications are made to the Contract which add or delete activities and/or revise time of completion, CPM Schedule shall be revised and resubmitted to the Engineer within ten (10) days after such modification is authorized.
In the event that the Work is behind the CPM Schedule, the CPM Schedule shall be revised, through the use of overtime Work or by other means, to insure that the Work is completed within the Contract time. Under these circumstances, overtime Work shall be performed at no additional cost to the Owner.
5. SHOP DRAWINGS AND MANUALS
Shop Drawings are defined as drawings, diagrams, illustrations, Schedules, performance chart, brochures and other data prepared by each Contractor which illustrate how specific portions of the
Work shall be fabricated and/or installed.
Shop Drawings are not part of the Contract Documents, but are a supplementary means of communications to assist in the understanding of what each Contractor proposes to provide and to establish that whatever he intends to install either does or does not conform to the drawing and
Specifications.
In the instance of a request for a substituted item, each Contractor shall verify that it shall fit into the space allocated to the originally required item giving due regard to all other trade requirements.
Where modifications to the Contract Documents are proposed, the Contractor must clearly indicate such deviation in writing in his transmittal letter. If the modification and/or substitutions are agreed to by the Engineer, the Contract Documents shall be appropriately modified. However, when additional Work is required, the Contractor is advised that he must pay the Engineer for redesign to accommodate that revised substitution as well as pay other Contractor’s for extra Work required by them for the change. No increase in the Owner's construction cost shall be allowed.
6. CATALOG SHEETS
For standard manufactured items considered by the Engineer as not requiring special Shop
Drawings, each Contractor shall submit six (6) copies of Manufacturer's catalog sheets showing illustrated cuts of the items to be furnished, all details, sizes, dimensions, performance characteristics capacities and all other pertinent information.
The Engineer shall retain four (4) copies and return two (2) copies to the Contractor submitting the catalog sheets.
7. SHOP DRAWINGS
Each Contractor shall submit for review six (6) white prints of shop and working drawings of materials fabricated and/or supplied especially for his Contract, and of equipment and materials for which such drawings are specifically requested.
Prior to submitting drawings to the Engineer, the respective Contractor shall check thoroughly all such drawing to satisfy himself that the subject matter conforms to the plans and Specifications in all respects. Drawings which are correct shall be marked with the date, checker's name and certification of the Contractor's approval, and then shall be submitted to the Resident Project
Representative. Any Shop Drawings submitted without the respective Contractor's certification shall be returned without review.
The Engineer shall retain four (4) copies and return two (2) copies to the respective Contractor.
Shop Drawings shall show the principal dimensions, weight, structural and operating features, performance characteristics, space required, clearances, type and/or brand of finish or drawing.
When it is customary to do so, when the dimensions are of particular importance or when so specified, the drawings shall be certified by the Manufacturer or fabricator as correct for this
Contract.
When so specified or if considered by the Engineer to be acceptable, Manufacturer's
Specifications, catalog data, descriptive matter, illustrations, etc., may be submitted for review in place of shop and working drawings. In such case the requirements shall be specified for shop and working drawings, insofar as applicable.
Each Contractor shall be responsible for the prompt submission of all shop and working drawings in accordance with the Shop Drawing Schedule so that there shall be no delay to the Work due to the absence of such drawings.
No material shall be purchased or fabricated especially for this Contract until the required shop and working drawings have been submitted and reviewed as conforming to the Contract requirements.
All materials and Work involved in the construction shall then be as represented by said drawings.
The Engineer's review of shop and working drawings shall follow a general check made to ascertain conformance with the design concept and functional result of the Project and compliance with the information given in the Contract Documents. Each Contractor is responsible for details and accuracy, for conforming and correlating all quantities and dimensions at the job site; for information that pertains solely to the fabrication processes or to techniques of construction; and for coordination of the Work of all trades.
No Work shall be started or materials and equipment ordered until submittals are approved.
8. MANUALS
Each Contractor shall be responsible for initially submitting to the Engineer two (2) copies of all requested maintenance manuals with the Shop Drawing submittals. Six (6) complete sets of instructions, technical bulletins and other printed matter shall be furnished and delivered to the
9. FIELD DISTRIBUTION
Each Contractor shall be responsible for the required number of processed drawings or catalog cuts for field distribution to all necessary Contractors.
Each Contractor shall have the overall responsibility for coordinating the necessary information to properly coordinate the Work.
10. SUBMISSION OF SAMPLES
Unless otherwise specified, each Contractor shall provide samples in duplicate and identify each sample by an appropriate tag or label listing the name of the Project, the Owner, the Engineer and the Contractor and/or Subcontractor as well as the exact identification of the sample. Tag or label shall be large enough to provide a blank space for review stamps.
Samples of items submitted for destructive tests or for use in testing mixtures with other materials shall not be returned. Review of these items shall be given by letter.
When reviewed, one sample of each item, not submitted for destruction, shall be returned to the respective Contractor and shall be kept and maintained in good condition in the submitting
Contractor's office at the Project site for later use in comparison with material actually delivered for the Work. When samples of large fabricated items or of costly items are required, reviewed samples may be installed in the Work if the exact location of such samples is recorded on the
Engineer's Record Drawings.
11. CERTIFICATIONS AND TESTS
Two (2) copies of certifications and reports of tests when required under the various sections of the Specifications shall be submitted to the Engineer.
12. AS-BUILT PLANS
Contractor must submit one As-Built Plan from the field within 10 days of Substantial Completion.
Final Completion will not be approved until as built plans are submitted and approved by the
13. MEASUREMENT AND PAYMENT
Shop Drawings, submittals, samples, certifications and tests, CPM Schedule, and Plan of
Operation shall be included in the Mobilization/Demobilization lump sum bid price shown on the
Bid Form, complete in place, in accordance with the Contract Documents and good construction practice, including all materials, operation, workmanship and appurtenances for a complete job and shall NOT be paid separately under this Contract.
SECTION 01080
SPECIAL REQUIREMENTS
1. ADDITIONAL CONDITIONS OF THE CONTRACT
These Special Requirements are in addition to, or expansion of the responsibilities of each
Contractor noted in the General Conditions.
2. SURVEY OPERATIONS
The Owner shall provide "Reference Marks" for controlling horizontal alignment and "Bench
Marks" for controlling the vertical alignment for the entire length of the Project.
The Contractor shall provide "Offset Stakeout" as required for the construction of the Work. This
"Offset Stakeout" shall be provided as follows:
A. When the Contractor uses a Laser Beam for his construction, the above data shall be provided at 50 foot intervals.
B. When the Contractor uses any other method for his construction or when grades are
1.0 percent or less, the above data shall be provided at 25 foot intervals.
3. JOB CONFERENCES
Scheduled meetings shall be held at the site at a time mutually acceptable to the Owner, Engineer and Contractor. Unscheduled meetings may be arranged at the request of any party when deemed necessary for the proper execution of the Work.
Meetings shall be conducted by the Owner or his Representative and shall be attended by
Principals or their designated Representatives, of the Contractors and their major Subcontractors.
Instructions delivered or commitments made at these meetings shall be binding on all parties concerned.
4. EXISTING UTILITY SERVICE
The Contractor is specifically required to maintain "in-use" at all times, sanitary sewer lines, sewer laterals, water lines, gas lines, storm water connections, manholes and storm sewer inlets so that no public or private property is damaged, has service interrupted or is inconvenienced due to the construction. Contractor is solely responsible for damage to all utility lines, properly marked, as required by PA One Call and outside of the top and bottom exterior wall of pipe installed.
5. MEASUREMENT AND PAYMENT
Cost for the above Work shall be included in the Mobilization/Demobilization lump sum bid price shown on the Bid Form, complete in place, in accordance with the Contract Documents and good construction practices, including all materials, operation, workmanship and appurtenances for a complete job and shall NOT be paid separately under this Contract.
01080-021626
SPECIAL REQUIREMENTS
SECTION 01090
COLOR AUDIO-VIDEO ELECTROGRAPHY
A. Scope:
1. Description of Work
Provide all labor, materials and equipment to furnish color audio-video electrography including still pictures for the entire Project prior to the start of any construction Work.
Provide the Owner with two (2) copies of acceptable audio-video tapes of the total survey.
Work shall consist of, but not be limited to, the following:
a. At no time shall the Contractor be allowed to use any electrical circuits within a building structure in order to protect the electrical circuits from overloading.
b. All videotaping shall be done during regular business hours, unless otherwise specified by the Engineer.
c. The Contractor must enter and leave the Owner’s property in a professional and orderly workmanship-like manner.
2. Field Checks
The Contractor and the Engineer shall review the days taping and, if tapes are judged unsatisfactory, the subject Project area shall be re-taped.
3. Qualifications
a. Owner's Requirements:
The Owner may make such investigation as deemed necessary to determine the ability of the Contractor to perform the Work, and the Contractor shall furnish to the Owner all such information and data for this purpose as the
Owner may request, or modify such justification as submitted by the
Contractor of his ability to perform this Work as specified.
The Contractor shall notify the Engineer seven (7) calendar days prior to beginning of taping.
01090-021626
4. Submittals
The Contractor shall submit to the Engineer, prior to starting Work at his own expense, a sample 3/4 inch color video tape meeting the exact contract requirements. Videos may be taken with cell phones and E-mailed to the
Engineer or put on a thumb drive and delivered to the Engineer.
2. PRODUCTS
A. Equipment:
All equipment, accessories and materials to perform this service shall be furnished by the Contractor.
At the bottom of the video, periodic transparent alpha numeric information shall appear. This information shall consist of the name of the Project, name of the area covered, direction of travel, viewing side, etc.
B. Digital:
To preclude the possibility of tampering or editing in any manner, all video recordings must, by electronic means, display continuously and simultaneously generated transparent digital information to include the date and time of recording as well as the corresponding Engineering stationing numbers. The date information shall contain the month, day, and year, i.e., 06/15/2019, and shall be placed directly below the time information. The time information shall consist of hours, minutes and seconds separated by colons, i.e., 10:35:10. This transparent information shall appear on the extreme lower left-hand third of the screen.
3. REQUIREMENTS
A. Multi-Camera Requirements:
The audio-video tape shall consist of one (1) video and two (2) audio tracks, all of which must be recorded simultaneously. All tracks shall consist of original live recordings and thus shall not be copies of other audio or video recordings. Audio track 1 shall contain the narrative commentary of the electrographer recorded simultaneously with his fixed elevation video record of the zone of influence of construction. Audio track 2 shall contain the narrative commentary and evaluations of the ground level remote technician whose function shall be to provide a complete circumspection of any features not adequately visible to the electrographer and to describe in detail the extent of any unusual features encountered.
In order to maintain viewer orientation, transition from fixed camera overview to remote camera picture shall be by means of an electronic dissolve.
B. Lighting Requirements:
The color audio-video tape recording of surface features of the Project area located within the area of coverage of construction specified by the Engineer shall have the following minimum lighting:
1. In order to produce the proper detail and perspective, a minimum of 25,000 watts or 3400 Kelvin temperature lighting shall be required to fill the shadow area caused by all objects.
AREA TYPICALLY CHARACTERIZED BY AVE RATE MAX
High Density Kraemer Avenue from North 2nd Street to North 3rd Street 30 ft/min.
The Owner shall have the authority to designate what areas may be omitted or added for audio-video coverage.
The color audio-video tape recording of exterior surfaces of existing buildings and miscellaneous structures in the area of the Project as requested by the Engineer shall have the following tape coverage:
A. Taped coverage shall include all surface features located within the area of coverage of construction supported by appropriate audio description. Audio description shall be made simultaneously with video coverage. Building exterior coverage shall include, but not be limited to, all masonry features of the building such as walls, foundations or chimneys.
B. An electronic insert showing the exterior view of the Project being recorded shall be displayed in the upper right-hand corner of the television picture. This view shall be no larger than 20% of the picture area and must begin showing the address before the 360 degree pan. The electrographer shall pan and zoom in and out as to control sufficiently the clarity of objects being viewed and shall not exceed a rate of more than 2 inches per second on telephoto zoom.
C. All videotaping shall be done during regular business hours unless otherwise specified by the Owner.
4. MEASUREMENT AND PAYMENT
Color Audio-Video Electrography shall be included in the Mobilization/Demobilization lump sum bid price on the Bid Form, complete in place, in accordance with the Contract Documents and good construction practices for a complete job, including all materials, operation, workmanship and appurtenances for a complete job and shall NOT be paid separately under this Contract.
SECTION 01100
TEMPORARY FACILITIES AND CONTROLS
A. Scope:
The Contractor is referred to conditions and requirements given in various Sections of the
Specifications insofar as such documents affect the Work of this Section.
2. OCCUPYING PRIVATE LAND
Written consent from the Private Owner(s) shall be obtained by the Contractor prior to entering of/or occupying with men, tools, materials or equipment any land other than his property or that of the Owner for any purpose related to his performance of the Work on this Contract.
3. PROTECTION OF EXISTING UTILITIES
The Contractor shall conduct his operations and take all special precautions necessary to protect equipment, utility lines, roadways and subsurface, submerged and overhead facilities which are to remain in place and undisturbed by his operations under this Contract. The Contractor shall immediately notify the Owner of the facilities or areas which are disturbed, damaged or injured as a result of the Contractor's operations, and determine the proper method of replacing or repairing the affected facilities at least to the conditions which existed prior to the Contractor's operations.
The Contractor shall, at his own expense, replace, repair or restore the affected facilities or areas to their original condition or shall reimburse the Owner of said facilities or areas for such expenses as the said Owner may accrue in performing the Work, and the Contractor shall not be entitled to receive additional compensation under this Contract for such Work.
4. INTERFERENCE WITH/AND PROTECTION OF STREETS
The Contractor shall not close or obstruct any portion of a street, road or private way without obtaining permits therefore from the Owner. If any street or private way shall be rendered unsafe by the Contractor's operations, he shall make such repairs or provide such temporary ways or guards as shall be acceptable to the appropriate authority.
The Contractor shall assume full responsibility for the maintenance and restoration of those areas within the construction area and also those adjacent roadways on which equipment must operate to reach the construction area.
Street, roads, private ways and walks not closed shall be maintained passable by the Contractor at his expense, and the Contractor shall assume full responsibility for the adequacy and safety of provisions made.
The Contractor shall, 48 hours in advance of closing any street, notify the Owner, police and fire departments in writing, and notify County Emergency Response Agency, with a copy to the
01100-021626
He shall cooperate with the police department in the establishment of alternate routes and, at his own expense, shall provide adequate, plainly marked detour signs. The signs shall be as required by the Owner that has jurisdiction over the project.
For the proper control of traffic, the Contractor shall provide an adequate number of persons employed at his own expense.
Absolutely no equipment or material may be left within highway right-of-ways at the end of the working day.
The traffic control plan, prepared in accordance with PennDOT, Form 408 Specifications, as last revised, shall be adhered to during the construction Work in all project areas.
5. ACCESS
Provide suitable access for residents to their homes and for emergency vehicles and fire protection vehicles, such as temporary ramps between existing surfaces and excavated surfaces. Provide necessary temporary walks of timber or bituminous materials to ensure safe ingress and egress to homes. Provide adequate temporary street lighting for pedestrian safety during the construction stage. Suitably cover and mark all clean outs extending above the excavation in order to provide for pedestrian safety. Provide adequate signing for pedestrian and vehicular safety.
6. PROTECTION OF FACILITIES AND EQUIPMENT
Until final acceptance of the Work under this Contract, the Contractor shall continuously maintain adequate protection, of his Work and Work in progress from damage and shall protect from loss or damage Contractor-furnished machinery, equipment, materials and supplies being handled, including property considered for progress payments wherever located as well as other property of the Owner from loss or damage arising out of or in connection with the prosecution of his Work.
The Contractor shall make good any such loss or damage. The Contractor shall adequately protect adjacent private and public property as provided by law and the Contract Documents.
Since the Contractor shall not load or permit any part of any structure to be loaded with a weight that would endanger its safety, it shall be the Contractor's responsibility to verify the acceptable load carrying capacity of any structure his equipment or Work will affect.
The Contractor shall immediately report in writing, giving full details, to the Owner all accidents which arise out of or in connection with the performance of the Work, whether on or adjacent to the site, which cause death, serious personal injury or substantial property damage. In addition, the accident shall be reported immediately by telephone or messenger to the Engineer. If a claim is made or suit is filed by anyone against the Contractor on account of any accident, the Engineer shall be notified in writing with a copy to the Owner, giving full details of the claim.
The Contractor shall assume all risks of loss or damage of any kind to any vehicles, machinery, equipment, materials or supplies which he shall provide in doing the Work.
The Contractor shall conduct his Work in such a manner as to adequately protect property owned by others on or about the Owner's premises from damage by the construction operations.
No trimming or cutting of trees is allowed unless written authorization is granted by the applicable private property owner, Owner, and the Engineer. Any anticipated tree trimming or cutting shall be submitted to the Engineer in advance of reaching the subject area.
7. DUST CONTROL
During the progress of the Work, the Contractor shall conduct his operations and maintain the area of his activities so as to minimize the creation and dispersion of dust.
8. SANITARY
The Contractor shall provide, maintain and remove when no longer required, an adequate number of temporary, prefabricated, chemical-type toilets with proper enclosures for the use of workmen and women of all trades during construction. Locate toilets where directed.
The Contractor shall keep toilets clean and supplied with toilet paper, hand cleanser, and towels at all times and comply with all local and state health requirements and sanitary regulations.
9. WATER
The Contractor shall make necessary arrangements and supply all water required during entire construction period and provide suitable drinking water for all workers on the Project.
10. TEMPORARY WATER SUPPLY
In the event the water supply to a building or user will be disrupted for more than one hour, the
Contractor shall provide temporary water service to all such buildings or users.
11. ELECTRICITY
The Contractor shall make necessary arrangements and supply and pay for all temporary electric service and lighting required during the entire construction period. Temporary electric service shall be of sufficient capacity and characteristics to supply proper current for various types of construction tools, motors, welding machines, lights, heating plant, pumps and other items required.
Remove temporary service and lighting when no longer required.
12. FUEL, POWER, ETC. FOR TESTING
Unless otherwise specified, the Contractor shall pay for all potable water and electricity required for testing of installed Work. Fuel shall be provided by the Contractor. Labor and supervision required for making tests shall be provided by the Contractor for all the installed Work involved.
13. SECURITY
The Contractor shall provide and pay for an adequate level of security protection to protect the property and material of all Contractors from pilferage, removal or damage at all times.
14. OFFICES AND STORAGE
The Contractor shall, for his own use, provide and maintain such temporary office facilities as he may require and such watertight storage sheds with floors as may be required for storage of his materials which might be damaged by weather. The Contractor shall allocate suitable space for office and storage for each Subcontractor, subject to the acceptance of the Engineer.
Materials stored in the open at the Project site shall be stored on planks or other dunnage as necessary to keep materials from contact with the ground and shall be covered with tarpaulins for protection from weather.
All temporary offices and storage facilities shall be removed by their installer when no longer required.
15. UNDERGROUND FACILITIES
The Contractor shall meet all requirements of Pennsylvania Act 38, as last revised and related to underground utilities. Toll Free access number for PA One Call System is 1-800-242-1776.
16. MEASUREMENT AND PAYMENT
Cost for all work listed in this section shall be at the Mobilization/Demobilization lump sum bid price shown on the Bid Form, complete in place, in accordance with the Contract Documents and good construction practices, including all materials, operation, workmanship and appurtenances for a complete job and shall NOT be paid separately under this Contract.
SECTION 01170
ROADWAY CONSTRUCTION
No materials shall be placed on frozen or thawing subgrade material or during unfavorable weather conditions. Bituminous base and wearing courses shall not be placed when the air temperature is
40oF or lower. All roadway construction shall be terminated by November 1st and not resumed before April 1 of the following year except by written request to and approval from the Engineer.
All roadway construction unable to be completed before November 1st, except as noted above, shall be brought to a level of construction sufficient to withstand the winter months without serious deterioration as prescribed and/or approved by the Engineer.
No Work from 1200 hrs. on Thursday or Friday of a holiday weekend until 0700 hrs. on Monday or Tuesday of a holiday weekend.
No Work during a special local event, for example fairs.
The Contractors shall, at all times, provide watchmen, barricades, lights, warning signs, and take such other precautions to insure the safety of the public and property. The Contractor shall provide the Engineer with straight edges ten (10) feet in length to check any surface irregularities. The
Contractors shall maintain sufficient erosion and sediment control facilities in accordance with other sections of these Contract Documents, satisfactory to the Engineer, through all phases of roadway construction.
No Work during peak hours of traffic, where traffic exceeds 1,200 vehicles per lane per hour or a lower volume where traffic is controlled by signals.
The Contractors shall coordinate with the water and gas companies to adjust all valves during restoration work, as well as coordinating with the Borough to obtain the manhole adjustment rings.
Roadway construction shall be permitted in one of the following manners.
1.1 Complete Construction
Roadway construction shall be continuous in a workmanlike manner through all phases of construction to one hundred percent (100) completion.
01170-021626
2. NEW ROADWAY SURFACES
2.1 Superpave Wearing Course WMA/HMA 9.5 MM
The Superpave Wearing Course WMA/HMA 9.5 MM shall consist of a composition of materials and mixture meeting the PennDOT, Form 408 Specifications, Section 409, as last revised, warm-mixed or hot-mixed and warm-laid or hot-laid on the Superpave Base Course. PG-64-22 oil should be used to seal the surface, the ESAL count for the mixes should be 0.0-<0.3MIL and SRL
Designation L.
The Superpave Wearing Course WMA/HMA 9.5 MM shall be placed as designated on the bid sheet, compacted, with a self-powered asphalt paver to provide a compacted surface true to the line, grade, depth, and crown. The paver shall overlap all joints by two (2) to three (3) inches. Materials shall not be allowed to remain in the transporting vehicle for more than one-half (1/2) hour after reaching the Work area. All bituminous paving material shall be covered to prevent heat loss.
Immediately after placing, the mix shall be compacted with a ten (10) ton steel-wheeled tandem roller or steel three-wheeled roller. Intermediate rolling with a pneumatic-tired roller capable of applying sixty (60) PSI ground contact pressure shall be done after initial rolling.
Rolling shall be done with a ten (10) ton, two (2) or three (3) axle tandem roller. Rolling shall progress, parallel to the centerline of the roadway, from the sides to the center with overlapping of one-third (1/3) of the roller width on each successive pass. The drive wheel of the roller shall be positioned toward the un-compacted mix unless directed otherwise by the Engineer. Rolling shall continue until all surface irregularities are eliminated and the material meets the Marshall Plan density of at least ninety-five (95) percent. Areas inaccessible to the roller shall be thoroughly compacted by means of a vibratory plate compactor or a hand tamper. The rollers shall only pass over an unprotected transverse edge of the pavement when the present lift is discontinued and the mix is chilled.
Unless otherwise allowed, deliver, place, and compact 9.5mm paving mixtures during daylight hours. Ensure the mixture does not contain lumps of cold material. Deliver and place 9.5mm paving mixtures at the laying temperatures.
The surface of the 9.5mm compacted wearing course shall not vary by more than one quarter (1/4) inch from the lines, grades, and cross-sections as shown on the Plans and as directed by the
The wearing course adjacent to curbs, inlets, manholes, other structures, and previously laid bituminous material shall be sealed with warm or hot bituminous material identical to that used as the asphalt cement for the Superpave Wearing Course 9.5mm mix. The sealing material shall be applied by means of squeegees immediately after final rolling to fill the surface voids and provide a watertight joint. Care shall be taken to prevent spattering, with sealing material, surfaces that will not be in contact with the asphalt-aggregate mixture.
3. ROADWAY WIDENING AND REBUILDING
3.1 Superpave Wearing Course WMA/HMA 9.5 MM
See Item 2.4
In addition, areas of the existing roadway surface not requiring adjustments with a base course shall be prepared with a tack coat of eight hundredths (0.08) gallons per square yard of emulsified asphalt diluted one (1) part water to one (1) part emulsified asphalt. The water on the surface shall be allowed to evaporate before the wearing course is applied.
3.2 Sealing
All sawcuts and areas identified in 2.1 above shall be sealed with warm or hot bituminous material identical to that used as the asphalt cement for the Superpave Wearing Course WMA/HMA 9.5
MM mix.
4. MEASUREMENT AND PAYMENT
Payment for this item shall be included in each item of Work required, as shown on the Bid Form, complete in place in accordance with the Contract Documents and good construction practice, including all materials, operation, workmanship and appurtenances for a complete job and shall
NOT be paid separately under this Contract.
SECTION 01191
PA ONE CALL
The Contractor is required to notify Pennsylvania One Call System, Inc. 1-800-242-1776 three working days before excavation begins or as required by current regulations during the construction. Doing so will allow the utilities an opportunity to locate and mark their underground facilities in advance of the planned excavation.
Hand dig within the tolerance zone.
Protect and preserve these approximate markings until they are no longer required for safe proper excavation.
If the markings of facilities are destroyed or removed before excavation commences or is completed, the excavator must re-notify PA One Call System, Inc. and the company locator should remark the location within two working days of the notice.
Maintain a reasonable clearance between any subsurface utility facility and the cutting edge or point of powered equipment, to the limits as required by current law or regulations.
Marking indicates only the approximate location of buried lines. Hand-dig test holes in a careful and prudent manner to determine the precise location of underground utility lines. Upon hand digging, if you are still unable to determine the exact location of the lines, call PA One Call System, Inc. or the utility company for assistance prior to any excavation.
If you must expose a utility line, state law requires you to protect and support the line while working on site. Ask the company locator for help and advise when you are near underground facilities.
01191-021626
PA ONE CALL
SECTION 01195
MILLING
This Work consists of milling of an existing bituminous pavement and other materials, with specified equipment, to the depth indicated on the bidding sheet, as required for installation of proposed materials to proposed elevations and grades.
Mill and overlay the same day or use rough road signs and use 3.1 tapers at manholes, inlets, etc.
2. CONSTRUCTION
A. Equipment:
Use a milling machine designed and built for this type of Work. Provide a machine with an effective automatic grade and slope control system and has the capacity to mill pavement.
B. Milling Operations:
Mill so the finished surface is free from gouges, grooves, and ridges and is in accordance with the surface tolerance requirements of Penn DOT Pub 408
Specifications, Section 401.3(k), or as directed by the Engineer. Pick up and move milled material immediately after the milling operations. Use care to remove the existing bituminous material around all utility facilities within the Work areas.
Repair or replace, to the satisfaction of the utility Owner, utility facilities which are damaged by the milling operation. Control the rate of milling to avoid tearing of the mat, resulting in chunky and non-uniformly milled material. Separate oversize and chunky milled material, as directed. Keep the milled pavement surface free of all loose materials and dust.
C. Disposition of Milled Material:
Satisfactorily dispose of the milled material at a PA Department of Environmental
Protection approved Site.
3. MEASUREMENT AND PAYMENT
Payment for this item shall be included in each item of Work required, as shown on the Bid Form, complete in place in accordance with the Contract Documents and good construction practice, including all materials, operation, workmanship and appurtenances for a complete job and shall
NOT be paid separately under this Contract.
01195-021626
MILLING
SECTION 01650
DELIVERY, STORAGE AND HANDLING
A. Summary
1. Protect products scheduled for use in the Work by means including, but not necessarily limited to, those described in this Section.
2. Related Work:
a. Documents affecting Work of this Section include, but are not necessarily limited to, General Conditions, Supplementary
Conditions, and sections in these Specifications.
b. Additional procedures also may be prescribed in other sections of these Specifications.
2. QUALITY ASSURANCE
A. Include within the Contractor’s quality assurance program such procedures as are required to assure full protection of Work and materials.
3. MANUFACTURERS RECOMMENDATIONS
A. Except as otherwise approved by the Engineer, determine and comply with the
Manufacturers recommendations on product handling, storage, and protection.
4. PACKAGING
A. Deliver products to the job Site in their Manufacturer’s original container, with labels intact and legible.
1. Maintain packaged materials with seals unbroken and labels intact until time of use.
2. Promptly remove damaged material and unsuitable items from the job Site, and promptly replace with material meeting the specified requirements, at no additional cost to the Owner.
B. The Engineer may reject as non-complying such material and products that do not bear identification satisfactory to the Engineer as to Manufacturer, grade, quality, and other pertinent information.
01650-021626
DELIVERY, STORAGE & HANDLING
5. PROTECTION
A. Protect finished surfaces from damage.
B. Maintain finished surfaces clean, unmarred, and suitably protected until accepted by the Owner.
6. REPAIRS AND REPLACEMENTS
A. In event of damage, promptly make replacements and repairs to the approval of the
Engineer at no additional cost to the Owner.
B. Additional time required to secure replacements and to make repairs shall not be considered by the Engineer to justify an extension in the Contract Time for completion.
7. MEASUREMENT AND PAYMENT
This item shall be included in the Mobilization/Demobilization lump sum bid price shown on the Bid Form, complete in place, in accordance with the Contract Documents and good construction practice,…