This is an Executive Summary document for Mansell Manor Phase I, a for-sale residential development project sponsored by Housing Assistance Management Enterprise (HAME), the nonprofit development affiliate of the Housing Authority of Salt Lake City (HASLC), located in Salt Lake City, Utah. The project proposes the development of forty-three (43) affordable, for-sale condominium units within a four-story residential building at approximately 1776 South West Temple. The development will primarily consist of two-bedroom homes designed to accommodate families and first-time homebuyers, utilizing a Community Land Trust (CLT) structure to preserve long-term affordability while enabling qualifying households to build equity through homeownership. The solicitation seeks qualified and experienced lenders to provide financing in two categories: construction financing for the development of the condominium units and individual homebuyer mortgage financing for qualified purchasers. Firms may submit proposals for either or both financing categories.

The project intends to demonstrate affordable homeownership opportunities through the CLT model, which restricts land ownership while allowing residents to own their units, thereby maintaining affordability in perpetuity. Supplemental project and financial documents available for download include the Mansell Manor I Project Overview and Financial Summary, HAME Real Estate Portfolio and Financial Information, and HASLC 2025 and 2024 Audited Financial Statements, providing prospective lenders with comprehensive information regarding the project's financial structure, organizational capacity, and historical performance. Pricing terms, specific funding amounts, response deadlines, and award timelines are not detailed in this executive summary document.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project Status Project Status Developer Fee Schedule Construction Documents at 90% Construction Loan Closing 10% Feb-26 117,273$

C of O 40% Aug-27 469,091$ Project Type 100% Units Sold 50% Feb-28 586,364$ For Sale Deferred Fee 0% FY -$

TOTAL 100% 1,172,729$

Ownership General Partner 100.00% Key Investment Metric

DSCR 0.00x Building & Site Information Debt Yield - Acreage (Approx.) 1.3 Total Building SF 56,547 Distribution Waterfall - Summary Site Density (units/acre) 34 Deferred Development Fee (Principal & Interest) -$ # of Units 43 General Partner -$ Rentable SF 45,740 sq.ft. Credit Investor - Limited Partner -$ # of Stories 4 Construction Type IIIA Elevator Served Yes Parking Type/Ratio 1

AMI # Units % 80%-120% 43 100%

Total 43 100%

For Rent For Sale Income Summary Escalation/Unit As-Stabilized Sales Income 0% -$ 12,900,016 Other Income 0% -$ -

Total Gross Income -$ 12,900,016$ Sales Commission 3% -$ 387,000$

Sources

Construction Per Unit Disposition Per Unit Construction Loan $ 11,844,560 $ 275,455 – – Net Sales Proceeds – – $ 12,900,016 $ 300,000

Total Sources $ 11,844,560 $ 275,455 $ 12,900,016 $ 300,000

Uses

Construction Per Unit Disposition Per Unit

Acquisition – – – – Hard Costs $ 9,255,750 $ 215,250 $ 9,255,750 $ 215,250 Soft Costs $ 1,162,866 $ 27,043 $ 1,162,866 $ 27,043 Construction Loan Costs $ 901,671 $ 20,969 $ 901,671 $ 20,969

Closing Costs/Sales Commissions $ 407,000 $ 9,465 $ 407,000 $ 9,465

Development Fee $ 117,273 $ 2,727 $ 1,172,729 $ 27,273

Total Uses $ 11,844,560 $ 275,455 $ 12,900,016 $ 300,000

(GAP)/SURPLUS - - - -

BACKGROUND

Housing Assistance Management Enterprise (“HAME”) is the nonprofit development affiliate of the Housing Authority of Salt Lake City (“HASLC”) and serves as HASLC’s development arm.

HASLC and HAME are advancing the development of Mansell Manor I, a new affordable homeownership community located at approximately 1776 South West Temple in Salt Lake City, Utah. The project represents the first phase of a larger, two-phase residential redevelopment intended to expand affordable housing opportunities and promote long-term neighborhood investment.

Mansell Manor I is anticipated to include forty-three (43) affordable, for-sale condominium units within a four-story residential building. The development will primarily consist of two-bedroom homes designed to accommodate families and first-time homebuyers. The project is intended to utilize a Community Land Trust (“CLT”) structure to preserve long-term affordability while providing qualifying households with opportunities to build equity through homeownership.

The development will incorporate a central landscaped courtyard, community gathering spaces, playground facilities, a dog park, and other outdoor amenities intended to foster neighborhood interaction and improve residents’ quality of life. The project will emphasize sustainable design principles, including all-electric residential units, water-efficient landscaping, and Enterprise Green Communities standards. Architectural design is underway, with construction anticipated to commence in the second quarter of 2027, subject to final approvals and financing, and completion currently projected in 2028.

Mansell Manor I is envisioned as the initial component of a broader neighborhood redevelopment that will ultimately include a second phase of affordable rental housing. Together, the two phases are intended to transform underutilized property into a residential community offering a range of housing opportunities, shared open space, and neighborhood amenities. Project financing is expected to incorporate public and private funding sources, together with other supplemental resources necessary to support affordable homeownership and long-term affordability.

Unit Mix by % - For Sale

SOURCE & USES

Mansell Manor Ph.1 (For Sale) November 24, 2026

OVERVIEW

PROJECT SUMMARY

OpportunitiesProject Takeaways

Insert Project Picture

Design Progress & Milestone Constr.

Pricing

Capital Costs Reduction

$300,000/Unit Avg.

Sales Price

$215,250/Unit Constr. Costs

– $ 5,000,000 $ 10,000,000 $ 15,000,000

Acquisition

Hard Costs

Soft Costs

Construction Loan Costs

Development Fee

USES

Uses Disposition Uses Construction

– $ 5,000,000 $ 10,000,000 $ 15,000,000

Construction Loan

Net Sales Proceeds

SO URCES

Sources Disposition Sources Construction