2-Informal Bids - Attachments 1 thru 5.pdf
PDF 2 MB Posted
- Attached to
- Pleasant View Gardens Roof Top Units Replacement
- Solicitation number
- PUR-1504-25
- Issued by
- Baltimore City, Maryland
About this file
This document is a comprehensive set of contract attachments for the Housing Authority of Baltimore City (HABC), containing requirements for residential construction projects in Baltimore City County, Maryland. The attachments include insurance requirements, wage determination guidelines, labor standards, and Section 3 compliance provisions for contracts related to residential construction projects involving single-family homes and apartments up to four stories. The documentation covers contracts subject to Davis-Bacon Act standards and specifies wage rates, worker classifications, and labor hour benchmarks for various construction roles, with wage rates ranging from $13.81 for common laborers to $34.12 for carpet floor layers as of January 2025.
The contract attachments establish specific insurance requirements, mandating contractors maintain comprehensive coverage including Workers' Compensation, General Liability (minimum $1,000,000 per occurrence), Automobile Liability, and Professional Liability insurance. The documents also emphasize Section 3 requirements of the Housing and Urban Development Act, which mandate that 25% of total labor hours be worked by Section 3 workers, with 5% specifically targeted to HABC residents or local business concerns. Contractors must provide detailed compliance plans demonstrating their strategy for meeting these employment and economic opportunity goals, with potential consequences including contract termination and exclusion from future HABC business for non-compliance. The wage determinations are tied to Executive Orders 14026 and 13658, which establish minimum wage rates of $17.75 and $13.30 per hour respectively, depending on the contract's initiation date.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ARACHMENT1
Senlc,e CNCralJts - lnauranoe Regull'tlllelda
Insurance • The Contractor/SuppHer shall maintain for the entire duration of the proposed contract and until formally terminated by HABC, the required Insurance coverage as set forth below. All Insurance shall be procured from a company licensed to do business In the State of Maryland and placed with a carrier possessing an A.M. Best's Rating of B+VI or better. If the Contractor has a "claims-made" policy, then the following additional requirements apply: The policy must provide a "retroactive date· which must be on or before the execution date of the Contract; and the extended reporting period (Tall) may not be less than five years following the completion date of the contract. HABC may, at Its sole discretion, add, raise, waive or reduce In llmlts, any Insurance coverage required under this contract.
a.
b.
c.
Wllftfltt Cc-mrre .,_l'IIQII • Contactor/Suppller Including subcontractors shall obtain and maintain during the term of the contract, Worker's Compensation Insurance Including Employers Liability and shall apply and be In accordance with aN Maryland Statutory requirements.
fwd HeM!!r ts·,.... • Contractor/Supplier Including subcontractors shall obtain and maintain during the term of the contract, coverage for "bodily injury" (Including death, public liability & personal Injury) and 'property damage" with a Combined Single Limit In an amount not less than $1,000.000 per occ:urrence. The Certificate of Insurance for General Liability Insurance must name HABC as an additional Insured.
Alllomullle Ualfllty lnmNw • Contractor/Supplier Including subcontractors shall obtain and maintain during the term of the contract, coverage on all motor vehicles owned and non-owned, hired, leased or otherwise used In connection with this contract. This Insurance shall provide coverage for "bodlly Injury· (Including death) and "property damage• with a Combined Single Limit In an amount not less than $1,000,000 per occurrence and shall be In accordance with all Maryland Statutory requirements .
... Note: This applies If services rendered create a Pollution Hazard (example - disturb painted or tiled surfaces causing a lead paint or asbestos hazard, etc.)
d. Pollution LlablUtv lnsuranc:e • Contractor/Supplier Including subcontractors shall obtain and maintain during the term of the contract. Insurance covering hazardous material exposures, releases, damage and pollution resulting from construction, renovation, remodeling, testing, repair or demolition. This Insurance shall provide coverage for "bodily Injury• and "property damage· with a Combjned Single Limit In an amount not less than
1 000 000 per occurrence. The Certificate of Insurance must name HABC as an additional Insured .
... Note: This applies only to Professional Services rendered (example • Legal, Medical, Archilectural, Engineering, etc.)
e. PN111 ulpgl IJlllplNlw (Errors and Omissions) l11181'U01 - Contractor/Supplier Including subcontractors shall obtain and maintain Professional Uablllty/Malpractlce Insurance during the term of a professional services contract protecUng against claims for damages which may arise from operations under the contract. whether such operations be by the Contractor or by any employees, agents or representatives of the Contractor (Including subcontractors). Limits for this coverage shall not be less than $1 10001000 per occurrence.
In addition to the above requirements to obtain and maintain Workers Compensation. General Uability, Automobile Liability, Pollution Liability and Professional Liability insurance, HABC ls to be named aa additional Insured on all pollcle• (where permissible). The Contractor/Supplier shall also agree to ,ave. defend. Indemnify and hold HABC, Ila offlcen, agents and employee., hannleu from any and all claims against HABC's officers, agents and employees which arise out of any action or omission of the Contract/Supplier or any of the Contract/Supplier officers, employees or agents, which are not covered pursuant ID the requirements of insurance in the a hove paragraphs. The agreement to hold HABC, its officers, agents and employees harmless shall not be limited to the level of liability insurance required under the provisions of this solicitation or contract, or of any document or instrument the provisions of this solicitation are or shall be made a part.
proof of Insurance, The Contractor/Supplier Including subcontractors shall furnish to HABC prior to start of contract, a certified copy of the policy or policies covering all work/services as required In the contract agreement evidencing that the Insurance required Is malntalned and in force for the entire duration of the contract agreement. The Contractor/Supplier including subcontractors must also notify HABC within 3Q days prior to any termination of the required Insurance. Any /apse In Insurance cowrage is caU§e for the immediate tennination of this contract.
II 111/s agraemenl Is wllh lhe Mayor and Clly Counc/1 of Sall/more (City) end/or rtte Srare of Maryland (St■t■J. HABC w111,ccept the Clly'.tlState's Se"•IMU11111Ce progr■m(sJ as 1ppl/ed to WOlflel'I Compenaallon. Commfldel Genetel Uabllify, Automoblle U.bllily. Pollution LJab/11/y, and ProleuSon■J UabiNty. Howe.,.,. II Is rqeed lhat /tie Cify'S/Slate's cow,age 1/m/U $hell re/feet 111d p,ovlde lJDl cornpllfl881ion for any end ,11 ios.s Mered as• ,.,un of the Ctty'�ate's perform1111C11 of lhls con/tact.
d t+acb.m c of 'l
"General Decision Number: MD20250061 01/03/2025
Superseded General Decision Number: MD20240061
State: Maryland
Construction Type: Residential
County: Baltimore City County in Maryland.
RESIDENTIAL CONSTRUCTION PROJECTS (consisting of single family homes and apartments up to and including 4 stories).
Note: Contracts subject to the Davis-Bacon Act are generally required to pay at least the applicable minimum wage rate required under Executive Order 14026 or Executive Order 13658.
Please note that these Executive Orders apply to covered contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but do not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.l(a)(l).
IIf the contract is entered linto on or after January 30, 12022, or the contract is !renewed or extended (e.g., an option is exercised) on or after January 30, 2022:
Executive Order 14026 generally applies to the contract.
The contractor must pay all covered workers at least $17.75 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in 2025.
I I I I I I I I I I I I
If the contract was awarded on . Executive Order 13658 I or between January 1, 2015 andl generally applies to the I January 29, 2022, and the I contract. I contract is not renewed or I, The contractor must pay alll extended on or after January I covered workers at least I 30, 2022: I $13.30 per hour (or the I
I applicable wage rate listed!
I on this wage determination, I I if it is higher) for all I I hours spent performing on I I that contract in 2025, I
________ I I
The applicable Executive Order minimum wage rate will be adjusted annually. If this contract is covered by one of the Executive Orders and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must still submit a conformance request.
Additional information on contractor requirements and worker protections under the Executive Orders is available at http://www.dol.gov/whd/govcontracts.
Modification Number
Publication Date 01/03/2025
CARP0251-007 05/01/2024
Rates
FLOOR LAYER: Carpet ............. $ 34.12
SUMD2012-021 06/25/2014
Rates
BRICKLAYER (Insulator Foam) ...... $ 21.60
CARPENTER, Excludes Drywall Hanging, and Metal Stud Installation ..................... $ 19.41
CEMENT MASON/CONCRETE FINISHER ... $ 18.92
DRYWALL HANGER AND METAL STUD
INSTALLER ........................ $ 16.36 **
ELECTRICIAN ...................... $ 22.59
IRONWORKER, ORNAMENTAL ........... $ 17.31 **
LABORER: Common or General, including brick mason tending and cement mason tending ......... $ 13.81 **
LABORER: Pipelayer .............. $ 16.19 **
OPERATOR:
Backhoe/Excavator/Trackhoe ....... $ 18.40
OPERATOR: Loader ................ $ 20. 25
Fringes
14.64
Fringes
0.00
3.11
0.00
0.62
0.81
0.00
0.00
2.15
4.42
2.06
PAINTER (Brush and Roller), Includes Drywall Finishing/Taping ................. $ 15.23 **
PLUMBER (HVAC Pipe
Installation Only) ............... $ 17 .60 *'
PLUMBER, Excludes HVAC Pipe Installation ..................... $ 20.48
ROOFER ........................... $ 26. 80
SHEET METAL WORKER (HVAC Duct Installation Only) ............... $ 18 .82
SPRINKLER FITTER (Fire Sprinklers) ...................... $ 26.06
0.70
0.00
0.00
0.00
1.20
6.52
WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
------------•----•z----=----a=---••----•=---=�---m--------------
** workers in this classification may be entitled to a higher minimum wage under Executive Order 14026 ($17.75) or 13658 ($13.30). Please see the Note at the top of the wage determination for more information. Please also note that the minimum wage requirements of Executive Order 14026 are not currently being enforced as to any contract or subcontract to which the states of Texas, Louisiana, or Mississippi, including their agencies, are a party.
Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.
Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at https://www.dol.gov/agencies/whd/government-contracts.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) {iii)).
The body of each wage determination lists the classifications and wage rates that have been found to be prevailing for the type(s) of construction and geographic area covered by the wage determination. The classifications are listed in alphabetical order under rate identifiers indicating whether the particular rate is a union rate (current union negotiated rate), a survey rate, a weighted union average rate, a state adopted rate, or a supplemental classification rate.
union Rate Identifiers
A four-letter identifier beginning with characters other than ""SU"", ""UAVG"", ?SA?, or ?SC? denotes that a union rate was prevailing for that classification in the survey. Example:
PLUM019B-005 07/01/2024. PLUM is an identifier of the union whose collectively bargained rate prevailed in the survey for this classification, which in this example would be Plumbers.
0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. The date, 07/01/2024 in the example, is the effective date of the most current negotiated rate.
Union prevailing wage rates are updated to reflect all changes over time that are reported to WHO in the rates in the collective bargaining agreement (CBA) governing the classification.
Union Average Rate Identifiers
The UAVG identifier indicates that no single rate prevailed for those classifications, but that 100% of the data reported for the classifications reflected union rates. EXAMPLE:
UAVG-OH-0010 01/01/2024. UAVG indicates that the rate is a weighted union average rate. OH indicates the State of Ohio.
The next number, 0010 in the example, is an internal number used in producing the wage determination. The date, 01/01/2024 in the example, indicates the date the wage determination was updated to reflect the most current union average rate.
A UAVG rate will be updated once a year, usually in January, to reflect a weighted average of the current rates in the collective bargaining agreements on which the rate is based.
Survey Rate Identifiers
The ""SU"" identifier indicates that either a single non-union rate prevailed (as defined in 29 CFR 1.2) for this classification in the survey or that the rate was derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As a weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SUFL2022-007 6/27/2024. SU indicates the rate is a single non-union prevailing rate or a weighted average of survey data for that classification. FL indicates the State of Florida. 2022 is the year of the survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. The date, 6/27/2024 in the example, indicates the survey completion date for the classifications and rates under that identifier.
?SU? wage rates typically remain in effect until a new survey is conducted. However, the Wage and Hour Division (WHD) has the discretion to update such rates under 29 CFR 1.6(c)(l).
State Adopted Rate Identifiers
The ""SA"" identifier indicates that the classifications and prevailing wage rates set by a state (or local) government were adopted under 29 C.F.R 1.3(g)-(h). Example: SAME2023-007 01/03/2024. SA reflects that the rates are state adopted. ME refers to the State of Maine. 2023 is the year during which the state completed the survey on which the listed classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination.
The date, 01/03/2024 in the example, reflects the date on which the classifications and rates under the ?SA? identifier took effect under state law in the state from which the rates were adopted.
WAGE DETERMINATION APPEALS PROCESS
1) Has there been an initial decision in the matter? This can be:
a) a survey underlying a wage deter•ination
b) an existing published wage determination
c) an initial WHO letter setting forth a position on a wage determination matter
d) an initial conformance (additional classification and rate) determination
On survey related matters, initial contact, including requests for summaries of surveys, should be directed to the WHD Branch of wage Surveys. Requests can be submitted via email to davisbaconinfo@dol.gov or by mail to:
Branch of Wage Surveys Wage and Hour Division u.s. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
Regarding any other wage determination matter such as conformance decisions, requests for initial decisions should be directed to the WHO Branch of Construction Wage Determinations.
Requests can be submitted via email to BCWD-Office@dol.gov or by mail to:
Branch of Construction Wage Determinations Wage and Hour Division u.s. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
2) If an initial decision has been issued, then any interested party (those affected by the action) that disagrees with the decision can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7).
Requests for review and reconsideration can be submitted via email to dba.reconsideration@dol.gov or by mail to:
Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
The request should be accompanied by a full statement of the interested party's position and any information (wage payment data, project description, area practice material, etc.) that the requester considers relevant to the issue.
3) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210.
END OF GENERAL DECISION"
Page 1 of 8 Form HUD-5370-EZ (1/2014)
U.S. Department of Housing and Urban Development Office of Public and Indian Housing OMB Approval No. 2577-0157 (exp. 1/31/2027)
General Contract Conditions for
Small Construction/Development
Contracts
See Page 7 for Burden Statement
Applicability. The following contract clauses are applicable and must be inserted into small construction/development contrac ts, greater than $2,000 but not more than $250,000.
1. Definitions
Terms used in this form are the same as defined in form HUD-5370
2. Prohibition Against Liens
The Contractor is prohibited from placing a lien on the PHA's property. This prohibition shall apply to all subcontractors at any tier and all materials suppliers. The only liens on the PHA's property shall be the Declaration of Trust or other liens approved by HUD.
3. Disputes
(a) Except for disputes arising under the Labor Standards clauses, all disputes arising under or relating to this contract, including any claims for damages for the alleged breach thereof which are not disposed of by agreement, shall be resolved under this clause.
(b) All claims by the Contractor shall be made in writing and submitted to the Contracting Officer for a written decision. A claim by the PHA against the Contractor shall be subject to a written decision by the Contracting Officer.
(c) The Contracting Officer shall, within 30 days after receipt of the request, decide the claim or notify the Contractor of the date by which the decision will be made.
(d) The Contracting Officer's decision shall be final unless the Contractor (1) appeals in writing to a higher level in the PHA in accordance with the PHA's policy and procedures, (2) refers the appeal to an independent mediator or arbitrator, or (3) files suit in a court of competent jurisdiction. Such appeal must be made within 30 days after receipt of the Contracting Officer's decision.
(e) The Contractor shall proceed diligently with performance of this contract, pending final resolution of any request for relief, claim, appeal, or action arising under or relating to the contract, and comply with any decision of the Contracting Officer.
4. Default
(a) If the Contractor refuses or fails to prosecute the work, or any separable part thereof, with the diligence that will insure its completion within the time specified in this contract, or any extension thereof, or fails to complete said work within this time, the Contracting Officer may, by written notice to the Contractor, terminate the right to proceed with the work (or separable part of the work) that has been delayed. In the event, the PHA may take over the work and complete it by contract or otherwise, and may take possession of and use any materials, equipment, and plant on the work site necessary for completing the work. The Contractor and its sureties shall be liable for any damage to the PHA resulting from the Contractor's refusal or failure to complete the work within the specified time, whether or not the Contractor's right to proceed with the work is terminated. This liability includes any increased costs incurred
(b) The Contractor's right to proceed shall not be terminated or the Contractor charged with damages under this clause if —
(1) The delay in completing the work arises from unforeseeable causes beyond the control and without the fault or negligence of the Contractor; and
(2) The Contractor, within 10 days from the beginning of such delay notifies the Contracting Officer in writing of the causes of delay. The Contracting Officer shall ascertain the facts and the extent of the delay. If, in the judgment of the Contracting Officer, the findings of Fact warrant such action, time for completing the work shall be extended by written modification to the contract The findings of the
Contracting Officer shall be reduced to a written decision which shall be subject to the provisions of the Disputes clause of this contract
(c) If, after termination of the Contractor's right to proceed, it is determined that the Contractor was not in default, or that the delay was excusable, the rights and obligation of the parties will be the same as if the termination had been for convenience of the PHA.
5. Termination for Convenience
(a) The Contracting Officer may terminate this contract in whole, or in part, whenever the Contracting Officer determines that such termination is in the best interest of the PHA. Any such termination shall be effected by delivery to the Contractor of a
Notice of Termination specifying the extent to which the performance of the work under the contract is terminated, and the date upon which such termination becomes effective.
(b) If the performance of the work is terminated, either in whole or in part, the PHA shall be liable to the Contractor for reasonable and proper costs resulting from such termination upon the receipt by the PHA of a properly presented claim setting out in detail: (1) the total cost of the work performed to date of termination less the total amount of contract payments made to the Contractor; (2) the cost (including reasonable profit) of settling and paying claims under subcontracts and material orders for work performed and materials and supplies delivered to the site, payment for which has not been made by the PHA to the Contractor or by the Contractor to the subcontractor or supplier; (3) the cost of preserving and protecting the work already performed until the PHA or assignee takes possession thereof or assumes responsibility therefore; (4) the actual or estimated cost of legal and accounting services reasonably necessary to prepare and present the termination claim to the
PHA; and (5) an amount constituting a reasonable profit on the value of the work performed by the Contractor.
(c) The Contracting Officer will act on the Contractor's claim within days (60 days unless otherwise indicated) of receipt of the Contractor's claim.
(d) Any disputes with regard to this clause are expressly made subject to the provisions of the Disputes clause of this contract
6. Insurance
(a) Before commencing work, the Contractor and each subcon-tractor shall furnish the PHA with certificates of insurance showing the following insurance is in force and will insure all operations under the Contract.
Form HUD-5370-EZ (1/2014)
(1) Workers' Compensation, in accordance with state or Territorial Workers' Compensation laws.
(2) Commercial General Liability with a combined single limit for bodily injury and property damage of not less than $ ________ [Contracting Officer insert amount] per occurrence to protect the Contractor and each subcontractor against claims for bodily injury or death and damage to the property of others. This shall cover the use of all equipment, hoists, and vehicles on the site(s) not covered by Automobile Liability under (3) below. If the Contractor has a "claims-made" policy, then the following additional requirements apply: the policy must provide a "retroactive date" which must be on or before the execution date of the Contract; and the extended reporting period may not be less than five years following the completion date of the Contract
(3) Automobile Liability on owned and non -owned motor vehicles used on the site(s) or in connection therewith for a combined single limit for bodily injury and property damage of not less than $ _____ [Contracting Officer insert amount] per occurrence.
(b) Before commencing work, the Contractor shall furnish the PHA with a certificate of insurance evidencing that Builder's Risk
(fire and extended coverage) Insurance on all work in place and/or materials stored at the building site(s), including foundations and building equipment, is in force. The Builder's
Risk Insurance shall be for the benefit of the Contractor and the
PHA as their interests may appear and each shall be named in the policy or policies as an insured. The Contractor in installing equipment supplied by the PHA shall carry insurance on such equipment from the time the Contractor takes possession thereof until the Contract work is accepted by the PHA. The
Builder's Risk Insurance need not be carried on excavations, piers, footings, or foundations until such time as work on the superstructure is started. It need not be carried on landscape work. Policies shall furnish coverage at all times for the full cash value of all completed construction, as well as materials in place and/or stored at the site(s), whether or not partial payment has been made by the PHA. The Contractor may terminate this insurance on buildings as of the date taken over for occupancy by the PHA. The Contractor is not required to carry Builder's
Risk Insurance for modernization work which does not involve structural alterations or additions and where the PHA's existing fire and extended coverage policy can be endorsed to include such work.
(c) All insurance shall be carried with companies which are financially responsible and admitted to do business in the State in which the project is located. If any such insurance is due to expire during the construction period, the Contractor (including subcontractors, as applicable) shall not permit the coverage to lapse and shall furnish evidence of coverage to the Contracting Officer. All certificates of insurance, as evidence of coverage, shall provide that no coverage may be canceled or non-renewed by the insurance company until at least 30 days prior written notice has been given to the Contracting Officer.
7. Contract Modifications
(a) Only the Contracting Officer has authority to modify any term or condition of this contract. Any contract modification shall be authorized in writing.
(b) The Contracting Officer may modify the contract unilaterally
(1) pursuant to a specific authorization stated in a contract clause (e.g., Changes); or (2) for administrative matters which do not change the rights or responsibilities of the parties (e.g., change in the PHA address). All other contract modifications shall be in the form of supplemental agreements signed by the
Contractor and the Contracting Officer.
(c) When a proposed modification requires the approval of HUD prior to its issuance (e.g., a change order that exceeds the
PHA's approved threshold), such modification shall not be effective until the required approval is received by the PHA.
8. Changes
(a) The Contracting Officer may, at any time, without notice to the sureties, by written order designated or indicated to be a change order, make changes in the work within the general scope of the contract including changes:
(1) In the specifications (including drawings and designs);
(2) In the method or manner of performance of the work;
(3) PHA-furnished facilities, equipment, materials, services, or site; or,
(4) Directing the acceleration in the performance of the work (b) Any other written order or oral order (which, as used in this paragraph
(b), includes direction, instruction, interpretation, or determination) from the Contracting Officer that causes a change shall be treated as a change order under this clause; provided, that the Contractor gives the Contracting Officer written notice stating
(1) the date, circumstances and source of the order and (2) that the
Contractor regards the order as a change order.
(b) Except as provided in this clause, no order, statement or conduct of the Contracting Officer shall be treated as a change under this clause or entitle the Contractor to an equitable adjustment.
(c) Many change under this clause causes an increase or decrease in the Contractor's cost of, or the time required for the performance of any part of the work under this contract, whether or not changed by any such order, the Contracting Officer shall make an equitable adjustment and modify the contract in writing.
However, except for a adjustment based on defective specifications, no proposal for any change under paragraph (b) above shall be allowed for any costs incurred more than 20 days (5 days for oral orders) before the Contractor gives written notice as required. In the case of defective specifications for which the PHA is responsible, the equitable adjustment shall include any increased cost reasonably incurred by the Contractor in attempting to comply with the defective specifications.
(d) The Contractor must assert its right to an adjustment under this clause within 30 days after (1) receipt of a written change order under paragraph (a) of this clause, or (2) the fiunishing of a written notice under paragraph (b) of this clause, by submitting a written statement describing the general nature and the amount of the proposal. If the facts justify it, the Contracting Officer may extend the period for submission. The proposal may be included in the notice required under paragraph (b) above. No proposal by the Contractor for an equitable adjustment shall be allowed if asserted after final payment under this contract
(e) The Contractor's written proposal for equitable adjustment shall be submitted in the form of a lump sum proposal supported with an itemized breakdown of all increases and decreases in the contract in at least the following details:
(1) Direct Costs. Materials (list individual items, the quantity and unit cost of each, and the aggregate cost); Transporta-tion and delivery costs associated with materials; Labor breakdowns by hours or unit costs (identified with specific work to be performed); Construction equipment exclusively necessary for the change; Costs of preparation and/ or revision to shop drawings resulting from the change;
Worker's Compensation and Public Liability Insurance;
Employment taxes under FICA and FUTA; and, Bond Costs
- when size of change warrants revision.
(2) Indirect Costs. Indirect costs may include overhead, general and administrative expenses, and fringe benefits not normally treated as direct costs.
(3) Profit. The amount of profit shall be negotiated and may vary according to the nature, extent, and complexity of the work required by the change.
(f)The allowability of the direct and indirect costs shall be determined in accordance with the Contract Cost Principles and Procedures for Commercial Firms in Part 31 of the Federal Acquisition Regulation (48 CFR 1-31), as implemented by HUD Handbook 2210.18, in effect on the date of this contract. The Contractor shall not be allowed a profit on the profit received by any subcontractor.
Equitable adjustments for deleted work shall include a credit for profit and may include a credit for indirect costs. On proposals covering both increases and decreases in the amount of the contract, the application of indirect costs and profit shall be on the net-change in direct costs for the Contractor or subcontractor performing the work
(g)The Contractor shall include in the proposal its request for time extension (if any), and shall include sufficient information and dates to demonstrate whether and to what extent the change will delay the completion of the contract in its entirety.
(h) The Contracting Officer shall act on proposals within 30 days after their receipt, or notify the Contractor of the date when such action will be taken.
(i) Failure to reach an agreement on any proposal shall be a dispute under the clause entitled Disputes herein. Nothing in this clause, however, shall excuse the Contractor from proceeding with the contract as changed.
(j) Except in an emergency endangering life or property, no change shall be made by the Contractor without a prior order from the
Contracting Officer.
9. Examination and Retention of Contractor's Records
The HA, HUD, or Comptroller General of the United States, or any of their duly authorized representatives shall, until three years after final payment under this contract, have access to and the right to examine any of the Contractor's directly pertinent books, documents, papers, or other records involving transactions related to this contract for the purpose of making audit, examination, excerpts, and transcriptions.
10. Rights in Data and Patent Rights (Ownership and Proprietary Interest)
The HA shall have exclusive ownership of, all proprietary interest in, and the right to full and exclusive possession of all information, materials, and documents discovered or produced by Contractor pursuant to the terms of this Contract, including but not limited to reports, memoranda or letters concerning the research and reporting tasks of this Contract.
11. Energy Efficiency
The Contractor shall comply with all mandatory standards and policies relating to energy efficiency which are contained in the energy conservation plan issued in compliance with the Energy Policy and Conservation Act (Pub.L. 94-163) for the State in which the work under this contract is performed.
12. Procurement of Recovered Materials
(a) In accordance with Section 6002 of the Solid Waste Disposal
Act, as amended by the Resource Conservation and Recovery Act, the Contractor shall procure items designated in guidelines of the Environmental Protection Agency (EPA) at 40 CFR Part
247 that contain the highest percentage of recovered materials practicable, consistent with maintaining a satisfactory level of competition. The Contractor shall procure items designated in the EPA guidelines that contain the highest percentage of recovered materials practicable unless the Contractor determines that such items: (1) are not reasonably available in a reasonable period of time; (2) fail to meet reasonable performance standards, which shall be determined on the basis of the guidelines of the National Institute of Standards and
Technology, if applicable to the item; or (3) are only available at an unreasonable price.
(b) Paragraph (a) of this clause shall apply to items purchased under this contract where: (1) the Contractor purchases in excess of $10,000 of the item under this contract; or (2) during the preceding Federal fiscal year, the Contractor: (i) purchased any amount of the items for use under a contract that was funded with Federal appropriations and was with a Federal agency or a State agency or agency of a political subdivision of a State; and (ii) purchased a total of in excess of $10,000 of the item both under and outside that contract
13. Training and Employment Opportunities for Residents in the
Project Area (Section 3, HUD Act of 1968; 24 CFR 75)
(a) The work to be performed under this contract is subject to the requirements of section 3 of the Housing and Urban
Development Act of 1968, as amended, 12 U.S.C. 1701u
(section 3). The purpose of section 3 is to ensure that employment and other economic opportunities generated by
HUD assistance or HUD-assisted projects covered by section 3, shall, to the greatest extent feasible, be directed to low- and very low-income persons, particularly persons who are recipients of HUD assistance for housing.
(b) The parties to this contract agree to comply with HUD's regulations in 24 CFR Part 75, which implement section 3. As evidenced by their execution of this contract, the parties to this contract certify that they are under no contractual or other impediment that would prevent them from complying with the
Part 75 regulations.
(c) The contractor agrees to send to each labor organization or representative of workers with which the contractor has a collective bargaining agreement or other understanding, if any, a notice advising the labor organization or workers' representative of the contractor's commitments under this section 3 clause, and will post copies of the notice in conspicuous places at the work site where both employees and applicants for training and employment positions can see the notice. The notice shall describe the section 3prioritization requirements, and shall state the minimum percentages of labor hour requirements established in the Benchmark Notice (FR-
6085-N-04).
Form HUD-5370-EZ (1/2014) Page 4 of 8
(d)The contractor agrees to include this section 3 clause in every subcontract subject to compliance with regulations in 24 CFR
Part 75, and agrees to take appropriate action, as provided in an applicable provision of the subcontract or in this section 3 clause, upon a finding that the subcontractor is in violation of the regulations in 24 CFR Part 75. The contractor will not subcontract with any subcontractor where the contractor has notice or knowledge that the subcontractor has been found in violation of the regulations in 24 CFR Part 75.
(e) .Noncompliance with HUD's regulations in 24 CFR Part 75 may result in sanctions, termination of this contract for default, and debarment or suspension from future HUD assisted contracts.
(f) Contracts, subcontracts, grants, or subgrants subject to
Section 7(b) of the Indian Self-Determination and Education
Assistance Act (25 U.S.C. 5307(b)) or subject to tribal preference requirements as authorized under 101(k) of the Native American Housing Assistance and Self-Determination
Act (25 U.S.C. 4111(k)) must provide preferences in employment, training, and business opportunities to Indians and Indian organizations, and are therefore not subject to the requirements of 24 CFR Part 75.
14. Labor Standards - Davis-Bacon and Related
If the total amount of this contract exceeds $2,000, the Federal labor standards set forth in the clause below shall apply to the development or construction work to be performed under the contract.
(1) Minimum wages—(i) Wage rates and fringe benefits.
All laborers and mechanics employed or working upon the site of the work (or otherwise working in construction or development of the project under a development statute), will be paid unconditionally and not less often than once a week, and without subsequent deduction or rebate on any account (except such payroll deductions as are permitted by regulations issued by the Secretary of Labor under the Copeland Act (29 CFR part 3)), the full amount of basic hourly wages and bona fide fringe benefits (or cash equivalents thereof) due at time of payment computed at rates not less than those contained in the wage determination of the Secretary of Labor which is attached hereto and made a part hereof, regardless of any contractual relationship which may be alleged to exist between the contractor and such laborers and mechanics. As provided in 29 CFR 5.5(d) and (e), the appropriate wage determinations are effective by operation of law even if they have not been attached to the contract. Contributions made or costs reasonably anticipated for bona fide fringe benefits under the Davis-Bacon Act (40 U.S.C. 3141(2)(B)) on behalf of laborers or mechanics are considered wages paid to such laborers or mechanics, subject to the provisions of paragraph (a)(1)(v) of these contract clauses; also, regular contributions made or costs incurred for more than a weekly period (but not less often than quarterly) under plans, funds, or programs which cover the particular weekly period, are deemed to be constructively made or incurred during such weekly period. Such laborers and mechanics must be paid the appropriate wage rate and fringe benefits on the wage determination for the classifications(s) of work actually performed, without regard to skill, except as provided in 29 CFR 5.5 (a)(4). Laborers or mechanics performing work in more than one classification may be compensated at the rate specified for each classification for the time actually worked therein: Provided, That the employer's payroll records accurately set forth the time spent in each classification in which work is performed. The wage
The Administrator, or an authorized representative, will issue a determination within 30 days of receipt and so advise the contracting officer or will notify the contracting officer within the 30–day period that additional time is necessary.
(E) The contracting officer must promptly notify the contractor of the action taken by the Wage and Hour Division under 29 CFR 5.5 (a)(1)(iii)(C) and (D). The contractor must furnish a written copy of such determination to each affected worker or it must be posted as a part of the wage determination. The wage rate (including fringe benefits where appropriate) determined pursuant to 29 CFR 5.5 (a) (1)(iii)(C) or (D) must be paid to all workers performing work in the classification under this contract from the first day on which work is performed in the classification.
(iv) Fringe benefits not expressed as an hourly rate. Whenever the minimum wage rate prescribed in the contract for a class of laborers or mechanics includes a fringe benefit which is not expressed as an hourly rate, the contractor may either pay the benefit as stated in the wage determination or may pay another bona fide fringe benefit or an hourly cash equivalent thereof.
(v) Unfunded plans. If the contractor does not make payments to a trustee or other third person, the contractor may consider as part of the wages of any laborer or mechanic the amount of any costs reasonably anticipated in providing bona fide fringe benefits under a plan or program, Provided, That the Secretary of Labor has found, upon the written request of the contractor, in accordance with the criteria set forth in 29 CFR 5.28, that the applicable standards of the Davis-Bacon Act have been met. The Secretary of Labor may require the contractor to set aside in a separate account assets for the meeting of obligations under the plan or program.
(vi) Interest. In the event of a failure to pay all or part of the wages required by the contract, the contractor will be required to pay interest on any underpayment of wages.
(2) Withholding—(i) Withholding requirements. The [write in name of Federal agency or the recipient of Federal assistance] may, upon its own action, or must, upon written request of an authorized representative of the Department of Labor, withhold or cause to be withheld from the contractor so much of the accrued payments or advances as may be considered necessary to satisfy the liabilities of the prime contractor or any subcontractor for the full amount of wages and monetary relief, including interest, required by the clauses set forth in 29 CFR 5.5(a) for violations of this contract, or to satisfy any such liabilities required by any other Federal contract, or federally assisted contract subject to Davis-Bacon labor standards, that is held by the same prime contractor (as defined in 29 CFR 5.2).
The necessary funds may be withheld from the contractor under this contract, any other Federal contract with the same prime contractor, or any other federally assisted contract that is subject to Davis- Bacon labor standards requirements and is held by the same prime contractor, regardless of whether the other contract was awarded or assisted by the same agency, and such funds may be used to satisfy the contractor liability for which the funds were withheld. In the event of a contractor’s failure to pay any laborer or mechanic, including any apprentice or helper working on the site of the work (or otherwise working in construction or development of the project under a development statute) all or part of the wages required by the contract , or upon the contractor’s failure to submit the required records as discussed in 29 CFR 5.5(a)(3)(iv), the [Agency] may on its own initiative and after written notice to the contractor, sponsor, applicant, owner, or other entity, as the case may be, take such action as may be necessary to cause the suspension of any further payment, Form HUD-5370-EZ (1/2014) Page 5 of 8 advance, or guarantee of funds until such violations have ceased.
(ii) Priority to withheld funds. The Department has priority to funds withheld or to be withheld in accordance with 29 CFR 5.5 (a)(2)(i) or (b)(3)(i), or both, over claims to those funds by:
(A) A contractor’s surety(ies), including without limitation performance bond sureties and payment bond sureties;
(B)A contracting agency for its reprocurement costs;
(C)A trustee(s) (either a court-appointed trustee or a U.S.
trustee, or both) in bankruptcy of a contractor, or a contractor’s bankruptcy estate;
(D)A contractor’s assignee(s);
(E)A contractor’s successor(s); or (F)A claim asserted under the Prompt Payment Act, 31 U.S.C. 3901-3907. (3) Records and certified payrolls—(i) Basic record requirements—(A) Length of record retention. All regular payrolls and other basic records must be maintained by the contractor and any subcontractor during the course of the work and preserved for all laborers and mechanic s working at the site of the work (or otherwise working in construction or development of the project under a develop-ment statute) for a period of at least 3 years after all the work on the prime contract is completed.
(B)Information required. Such records must contain the name; Social Security number; last known address, telephone number, and email address of each such worker; each worker’s correct classification(s) of work actually performed; hourly rates of wages paid (including rates of contributions or costs anticipated for bona fide fringe benefits or cash equivalents thereof of the types described in 40 U.S.C. 3141(2)(B) of the Davis-Bacon Act); daily and weekly number of hours actually worked in total and on each covered contract; deductions made ; and actual wages paid.
(C)Additional records relating to fringe benefits. Whenever the Secretary of Labor has found under 29 CFR 5.5(a)(1)(v) that the wages of any laborer or mechanic include the amount of any costs reasonably anticipated in providing benefits under a plan or program described in 40 U.S.C. 3141(2)(B) of the Davis-Bacon Act, the contractor must maintain records which show that the commitment to provide such benefits is enforceable, that the plan or program is financially responsible, and that the plan or program has been communicated in writing to the laborers or mechanics affected, and records which show the costs anticipated or the actual cost incurred in providing such benefits.
(D) Additional records relating to apprenticeship. Contractors with apprentices working under approved programs must maintain written evidence of the registration of apprenticeship programs, the registration of the apprentices, and the ratios and wage rates prescribed in the applicable programs.
(ii) Certified payroll requirements—(A) Frequency and method of submission. The contractor or subcontractor must submit weekly, for each week in which any DBA- or Related Acts-covered work is performed, certified payrolls to the [write in name of appropriate Federal agency] if the agency is a party to the contract, but if the agency is not such a party, the the case may be, that maintains such records, for transmission to the [write in name of agency]. The prime contractor is responsible for the submission of all certified payrolls by all subcontractors. A contracting agency or prime contractor may permit or require contractors to submit certified payrolls through an electronic system, as long as the electronic system requires a legally valid electronic signature; the system allows the contractor, the contracting agency, and the Department of Labor to access the certified payrolls upon request for at least 3 years after the work on the prime contract has been completed; and the contracting agency or prime contractor permits other methods of submission in situations where the contractor is unable or limited in its ability to use or access the electronic system.
(B)Information required. The certified payrolls submitted must set out accurately and completely all of the information required to be maintained under 29 CFR 5.5(a)(3)(i)(B), except that full Social Security numbers and last known addresses, telephone numbers, and email addresses must not be included on weekly transmittals.
Instead, the certified payrolls need only include an individually identifying number for each worker (e.g., the last four digits of the worker’s Social Security number). The required weekly certified payroll information may be submitted using Optional Form WH- 347 or in any other format desired. Optional Form WH-347 is available for this purpose from the Wage and Hour Division Web site at https://www.dol.gov/sites/dolgov/files/WHD/legacy/files/wh347.pdf or its successor website. It is not a violation of this section for a prime contractor to require a subcontractor to provide full Social Security numbers and last known addresses, telephone numbers, and email addresses to the prime contractor for its own records, without weekly submission by the subcontractor to the sponsoring government agency (or the applicant, sponsor, owner, or other entity, as the case may be, that maintains such records).
(C)Statement of Compliance. Each certified payroll submitted must be accompanied by a “Statement of Compliance,” signed by the contractor or subcontractor, or the contractor’s or subcontractor’s agent who pays or supervises the payment of the persons working on the contract, and must certify the following:
(1) That the certified payroll for the payroll period contains the information required to be provided under 29 CFR 5.5(a)(3)(ii), the appropriate information and basic records are being maintained under 29 CFR 5.5 (a)(3)(i), and such information and records are correct and complete;
(2) That each laborer or mechanic (including each helper and apprentice) working on the contract during the payroll period has been paid the full weekly wages earned, without rebate, either directly or indirectly, and that no deductions…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .